By anonymous6-8 on Friday, June
21, 2002 - 11:23 am:
Vern,
Thanks for the summary in your June 20 11:30 pm post. My reading
of the cases and discussions on the subject written by lawyers
leads me to pretty much the same conclusion, with one exception.
That exception is that "operation of law" is slightly more
broadly defined than that being used by others in this
particular discussion. Some of my posts demonstrate that
conclusion. For example, it certainly appears that if Jane Doe
inherits her father's interest in a contracting company a
government demand for novation will probably fail.
Many of the lawyers point out that results are not entirely
predictable. Courts do draw differing conclusions on evidence
and law. They seem entirely together, perhaps for ulterior
motives, in that no entity holding judicially ordered possession
of an interest with such contracts should rush into a novation
agreement. The Executive's ability to take action is now
contingent on the court's rulings.
In the specific case of bankruptcy the code dealing with the
matter itself wedges opens a door for the government to argue
its ability to affirm or deny acceptance; however, the courts
are split in how they apply that wedge. Firms were even advised
to examine their structure for the possibility of filing in
geographical areas where courts applying the "actual test" vice
the "hypothetical test" on assignment.
I cannot and should not give legal advice. My reading on the
subject tells me that if I were ever faced with a novation
demand when in possession of a court ordered transfer of such
interests my first response would be to see my lawyers. My
feeling, from reading the record so far, is their answer to the
contracting officers would simply be "No. Here is the court
ruling. Accept it or see us before the court that has already
effected the transfer." Why? Because, despite disclaimers at the
legal firm sites, I find a number of papers advising companies
not to simply accept demands for novation agreements before
seeking legal advice as such demands are often without merit. I
have also read a number of cases not cited here that support the
view that the government will most probably fail in overturning
such rulings.
The webmaster apparently decided your advice to me and my reply
were too personal. I, unlike some, can see the uselessness of
argument against a tide. I therefore do not plan to answer any
more of the somewhat random arguments against what appears to me
to be quite clear from the legal sources readily available.
Personally I see no real reason to proceed further into Part 3
of an already long discussion. Some people can learn from others
what "hot" means, some have to stick their hands into fire.
Perhaps these individuals will have an opportunity to learn
directly from a judge. Others need to recognize they are outside
FAR territory whenever there is court action on these matters
and go straight to legal. Let legal work the problem where there
are any questions of whether the government should recognize or
not recognize continuation of the contract. Contracting officers
should not rush in where lawyers tread with caution and due
preparation.
By Eric Ottinger on Monday,
June 24, 2002 - 06:50 pm:
On the topic of legal advice—
If I were pretending to be one of these genuine expert types, I
would tell you that I photocopied FAR 42.1204 to my left
temporal lobe sometime back in 1990, which is the last time I
encountered a novation, and somehow neglected to update it for
FAC 97-3. I was just citing the explicit direction in the FAR.
And why would Vern or anyone think that constituted “legal
advice.”
The truth is much simpler. My only intention was to direct
Denise to a section in the FAR. The title for this section is
“Novation and Change of Name Agreements.” This was clearly more
than a change of name. So I said, “You need a novation.” This
was the outer limit of the thought or intention that I put into
that response.
If I had given a very general piece of good advice like, “Denise
should eat a variety of fruits, nuts and vegetables to stay
healthy.” John or Vern or might reply, “What makes you think you
are qualified to be a nutritionist. Denise might eat a peanut,
and she might be allergic, and she might die.”
I trust that only extremely literal minded people would think
that I was giving Denise legal advice. Actually, I assumed she
would read between the lines in the FAR and realize that the
first thing she should do is to talk this over with her agency
general counsel. If the FAR isn’t so explicit, the “One Book”
is.
(By the way-- The biggest jump to a conclusion in this whole
thread is the assumption that Denise is going to be the
contracting person responsible for the novation. If there is an
ACO, the ACO will do the novation. If there is more than one
contracting officer, the contracting officer with the largest
remaining dollar balance will do the novation. A novation is
typically a team effort with agency counsel giving legal
guidance and several contracting offices doing the legwork.)
Vern has switched from Denise’ side of the table to the
contractor’s side. And the “simple truth” argument has
disintegrated. But let’s let that rest for a minute, while I
demonstrate that I actually agree with some folks more than they
think.
John didn’t indicate any knowledge of the FAC 97-3. Hence, I
infer that John was critiquing the FAR as it stood before FAC
97-3, when the FAR did not, in any way, acknowledge a transfer
“by operation of law.” In 1995 the American Bar Association
recommended certain modifications to the FAR to acknowledge
assignment by operation of law. These recommendations were
eventually incorporated in FAC 97-3. Hence, John’s critique of
the FAR as it stood before FAC 97-3 is almost certainly correct.
Ditto professor Cibinic and, to a large degree, Ms. Manos.
On the other hand, the fact that none of us was aware of FAC
97-3 until Ms. Manos brought it to our attention, demonstrates
that all of us were essentially clueless.
Anonymous6-8 got bent out of shape arguing that I might
antagonize a federal judge. In my experience contracting
officers don’t talk to federal judges, unless they are giving
testimony. Agency counsel does that. I am sure that agency
counsel talks very politely when they talk to judges. But that
was my advice to Denise at the outset. She should get legal help
from agency lawyers, not chat rooms.
Since there seems to be some confusion –
I don’t disagree that a contractor might refuse to sign a
standard novation agreement. I am sure that if ITT had it to do
over again, ITT would think twice before signing the agreement
that they signed. (Whether they would have done better with no
agreement at all is a somewhat different issue. They had some
400 contracts, and I expect they wished to be paid.) I
understand what Ms. Manos is saying, but I would characterize
her approach as a hardball negotiating tactic. It is certainly
no reason to revise the FAR
Eric
By Vern Edwards on Monday, June
24, 2002 - 08:45 pm:
FAR Subpart 42.12 should be changed in at least the following
ways:
First, FAR should be changed to clarify the differences among
novations, assignments, and delegations, based on ordinary
common law usage. FAR should use the term novation for transfers
in which a new contractor takes over performance and the
original contractor is discharged, either through negotiation or
by operation of law.
Second, FAR should be changed to clarify the requirements of 41
U.S.C. § 15 as interpreted by the boards of contract appeals and
the U.S. Court of Federal Claims. At the very least, FAR should
mention that (a) the boards and the Court have held that 41
U.S.C. § 15 does not apply when a contract has been transferred
by operation of law, (b) that the government's approval is not
required for such transfers, and (c) that contractors need
neither seek the government's approval nor sign a novation
agreement with respect to such transfers. At present, FAR §
42.1204(b) is not adequate in that regard.
Third, FAR should be changed to advise contracting officers
about the government's options when a contract has been
transferred by operation of law and about what factors to
consider when weighing those options.
Fourth, FAR should be changed to advise contracting officers
about how to officially recognize transfers that have been
effected by operation of law, when the government decides not to
terminate the contract for convenience.
By Eric Ottinger on Tuesday,
June 25, 2002 - 09:40 pm:
For those who prefer logic to bombast--
Both the Toftco court and Ms. Manos thought the ITT Gilfillan
case was pertinent to the discussion. Maybe Vern walked into the
wrong discussion.
ITT Gilfillan puts Vern et. al. on the horns of a classic
dilemma. If in fact the transfer did take place by operation of
law, we have two courts stating that the government can still
negotiate a novation agreement and the agreement will be
enforced. If, as Vern seems to think, the ITT Gilfillan court
didn’t decide “operation of law” and effectively determined that
there was some doubt about whether the transfer was by operation
of law or not, then we have to conclude that there is an element
of doubt regarding every “transfer by operation of law.” The ITT
Gilfillan transfer fits the ABA approved operation of law
criteria to a “t”, as John immediately understood. If this isn’t
transfer by operation of law, nothing is.
Clearly the Tuftco court and Ms. Manos are not in any doubt
about whether the transfer was in operation of law. And I don’t
think the ITT Gilfillan court was either.
ITT Gilfillan says something interesting about the relationship
between case law, statutes and regulations. I presume that as
much as courts honor stare decisis there is always a possibility
(however small) that a subsequent court will decide that the
dissenting opinion had a better argument. And any juris doctor
who wishes to enlighten us on this issue is invited to do so.
Let’s be exact. The Court of Claims did not decide the issue on
some other grounds. It is clear that the Court is making a point
of very explicitly not considering the case law precedents
regarding “operation of law” and the Anti-Assignment Acts.
The relevant section of the case is not too long, and as Vern
says, we can all read.
Incidentally, this case should make it perfectly clear why it
would be plain foolish for the FAR to specifically reference a
problematic concept like “operation of law,” notwithstanding
much tendentious carping earlier in this thread.
ITT Gilfillan, Inc. and International Telephone and Telegraph
Corporation v. The United States., In the United States Court of
Claims. No. 356-68. Decided , January 18, 1973 200 CtCl 367 471
F2d 1382 ,
“Previously before the Armed Services Board of Contract
[Appeals] In its first claim for relief (count I of plaintiff’s
petition), plaintiff contends (1) that the novation agreement
lacked consideration and was therefore a nullity, and (2) …”
“That the novation agreement lacked consideration and therefore
is of no effect is urged on the premise that the transfer of the
contracts took place by operation of law, as the result of a
corporate merger. If the transfer was by operation of law, the
plaintiff argues, then there was no need to enter into a
novation agreement. The Government’s consent to the transfer
was, it says, not required. In support of this argument the
plaintiff points to an administrative decision made by the IRS
in response to questions concerning plaintiff’s tax liability as
the result of its taking over the assets of Gilfillan
Corporation. The plaintiff also argues that the instant case
does not present the evils intended to be dealt with in the
anti-assignment statutes. See 31 U. S. C.§203, and 41 U. S.
C.§15 (1964).”
“The defendant argues that what has taken place is a complete
corporate reorganization, the costs of which are specifically
barred by the Cost Principles which control Cost Reimbursement
Contracts, 32 C. F. R.§15.205-23 (1960, Supp.) and that the
antiassignment statutes were intended, among other things, to
prohibit incurrence of extra costs to do the same job which
might result from the assignment of contracts.”
“From the defendant’s point of view, since the transfer would
have been barred by statute, without the signing of the novation
agreement, there was adequate consideration on the part of the
Government, and the novation agreement should be given effect.”
“In dealing with the question of consideration it is not
necessary to examine the character of the acquisition of
Gilfillan Corporation by ITT Corporation, as the Board did, to
determine if the transfer was a “reorganization” or not. It is
clear that at the time of the acquisition the defendant believed
and claimed in good faith that the transfer of the contracts in
question, even by reorganization, was barred by the
antiassignment statutes unless consented to by novation. ASPR
1-1602. THERE IS NOTHING IN THE TEXT OF THE STATUTES OR THE
REGULATION TO ESTABLISH THAT A TRANSFER INCIDENT TO A
REORGANIZATION WAS SPECIFICALLY EXCEPTED. As a result of the
parties signing the novation agreement the defendant refrained
from asserting its position. It has been held by this court that
such a compromise leading to forbearance is in itself
consideration. …”
“… In holding that the compromise agreement was supported by
consideration the court quoting from 1 Williston, Contracts (3rd
Ed.)§128, fn. 18, stated at page 1088, 354 F. 2d 268:”
“’***** it is settled law that a compromise “is supported by
sufficient consideration when there is a bona fide claim which
is ***** disputed or doubtful, the real consideration to each
party being, not the sacrifice of the right, but the settlement
of the dispute.” (Cites omitted.)’”
“Likewise in the case of State of Oklahoma v. United States, 146
Ct. Cl. 185, 173 F. Supp. 349 (1959), this court held
forbearance on the part of state officials in asserting legal
claims for damages to be adequate consideration to support a
promise by the Government to pay certain sums of money.”
“It is obviously unlikely that ITT Corporation would have been
interested in a “merger” without acquiring an uncontested right
for its subsidiary to take over the contracts. Assertion by the
Government of its bona fide [i.e. good faith] claim that the
transfer was barred by the anti-assignment statutes would have
put the whole transaction in jeopardy. Defendant’s forbearance
in asserting a bar against the transfer resulted from the
parties entering into the novation agreement, in the form
defendant had prescribed for such circumstances. SUCH
FORBEARANCE, UNDER THE CIRCUMSTANCES IS SUFFICIENT CONSIDERATION
TO SUPPORT THE COMPROMISE THEREBY REACHED.”
Eric
By Vern Edwards on Wednesday,
June 26, 2002 - 07:57 am:
I don't know what Eric's last post was about.
The discussion is over. I'm happy to conclude my participation
by saying that the FAR coverage of novation is inadequate and
ought to be revised in the ways that I suggested on June 24.
By Anon2U on Wednesday, June
26, 2002 - 04:37 pm:
I agree with Vern entirely. The FAR needs to say what is
intended and not beat around the bush about it.
By Eric Ottinger on Wednesday, June 26, 2002 - 10:11 pm:
FAC 97-3 revised the FAR to incorporate recommendations by the
American Bar Association with regard to novations and operation
of law. I expect the American Bar Association understands
novations and operation of law.
At the bottom line, much of this discussion doesn’t matter.
We all have to acknowledge the clear direction in the FAR and
agency guidance like the DCMA “One Book.” The novation process
is a team effort involving several contracting officers and
agency counsel. The idea that a single contracting person can
unilaterally choose to NOT go through the novation process is
unlikely, improper and illogical. The purpose of the novation
process is clearly to identify and address issues where it is
necessary to protect the interest of the government.
The government can withhold consent to obtain negotiating
leverage for the purpose of assuring that the government’s
legitimate interests are protected, or the government can just
as easily terminate. Both consent or potential termination can
be used by the government as negotiating leverage to 1) assure
mitigation of an organizational conflict of interest, 2) protect
progress payment inventories, 3) assure compliance with CAS, 4)
protect the government’s interest regarding overfunded pension
liability, 5) ensure environmental protection, 6) ensure that
the cost of the contract will not increase (or not increase
unreasonably), etc. THE FACT THAT CONSENT AND TERMINATION ARE
ESSENTIALLY EQUIVALENT MAKES THE WHOLE ARGUMENT ABOUT WHEN AND
HOW CONSENT MAY OCCUR AUTOMATICALLY A MOOT AND POINTLESS
ARGUMENT.
The contractor’s willingness to accede to such requests is
probably more a question of maintaining good relations with the
customer than the contractor’s exact legal rights under a
particular contract. Keep in mind that the novation process
addresses all of the contractor’s contracts, not just a single
contract.
As for case law, it is the dog that doesn’t bark which is most
telling. Almost all of the case law cited in this thread applies
to physically complete contracts and claims. Case law regarding
ongoing executory contracts is sparse and the government usually
wins.
The significance of ITT Gilfillan is that it may be appropriate
to negotiate a novation agreement, even if strictly speaking, it
is not required. And the agreement will be enforceable, even if
the transfer takes place by operation of law. Whether Ottinger
believes this or not doesn’t matter. Acknowledged experts like
Ms. Manos and the Court of Claims have made this point. As Casey
Stengel said, “You can look it up.”
Eric
By Vern Edwards on Thursday,
June 27, 2002 - 07:53 am:
The significance of ITT Gilfillan is that contractors should
beware signing government-proposed novation agreements when a
transfer has already been effected by operation of law. ITT
Gilfillan learned that lesson the hard way.
As Virgil (or somebody else) said, "Beware of Greeks bearing
gifts."
By Roy on Thursday, June 27,
2002 - 09:10 am:
I agree with Eric. The regulatory requirements in the FAR while
not perfect, are clear to me.
I questioned all of this case law that has been brought up in
this thread before, as to its relevance as compared to
compliance with the specific requirements in the FAR. The
implications in this thread that a third party can be forced
upon the Government to complete performance of a contract,
whether the Government likes it or not, is very puzzling to me.
Seems as there was not much resistance or arguments from the
legal folks during the rule making process that resulted in the
language changes included in FAC 97-03. The only real change I
could find that was made by that Circular was the addition of a
paragraph that addressed situations where there is a change in
ownership as a result of a stock purchase. It was emphasized
however that even in those situations there may be issues that
should be addressed in an agreement between the contractor and
the Government.
For those folks that would like to be flies on the wall in court
rooms, and have declared that the specific requirements in the
FAR are irrelavant and that we should instead follow what is
declared in all these court decisions, I say they don't
understand the Federal Procurement process. I believe that most
Contracting Officers keep up with court decisions that impact
the procurement process, but I also believe that most
Contracting Officers follow the FAR rather than attempt to
figure out complicated conclusions made in court decisions. Most
will also follow the advise of General Counsel, when their
opinions are sought out.
Maybe there is room for more clarifications to the language in
the FAR. However, I disagree with my hero (Vern) in this regard.
Termination for Default is also an option.
Roy
By Eric Ottinger on Thursday,
June 27, 2002 - 07:02 pm:
Roy,
Thanks. I am glad that at least one person is still paying
attention.
Now that John, Vern and I all seem to agree that ITT Gilfillan
fits FAR 42.1204(b) (as recommended by the ABA and incorporated
by FAR 97-3), we can all agree that the current FAR would not
require ITT to sign a “novation” agreement per se.
To determine whether the government should negotiate, and
whether the contractor should sign any agreement, requires that
we go through the whole information gathering process described
in the FAR and look at all of the contracts and all of the
issues. Presumably, the contractor will be doing a similar
analysis.
Take a look at the specific issues referenced under FAR
42.1204(b). In the short term a contractor may be able to gain
or protect some financial advantage on a particular contract. In
the long run the contractor would tar itself as a contractor
with a bad attitude with regard to “long-term incentive
compensation plans, cost accounting standards noncompliances,
environmental cleanup costs, and final overhead costs” etc. That
is a good way to antagonize the customer, win a battle and lose
the war.
There may be instances of assignment by operation of law outside
of the ABA approved criteria in FAR 42.1204(b) (very similar to
the criteria which Ms. Manos finds “boards and courts” [have]
“generally held to be outside the prohibition of the
Anti-Assignment Act.”) But I don’t understand why anyone wants
the FAR to recognize legal theory which is obviously in a gray
area. Let the contractor make his case, and let agency counsel
deal with it.
Eric
By Vern Edwards on Friday, June
28, 2002 - 09:33 am:
Eric:
When you talk about "bad attitude" and antagonizing the
customer, are you suggesting that an agency should consider a
contractor's refusal to sign a novation agreement to be an
instance of poor past performance? Do you think that agencies
should consider this in source selections?
Please, don't dodge the question by changing the subject.
Roy:
Eric now agrees with me that, in his own words: "There may be
instances of assignment by operation of law outside of the ABA
approved criteria in FAR 42.1204(b)." He also agrees that under
such circumstances a contractor would not have to sign a
novation agreement. These are the points that I have been making
all along. See my remarks of June 30 at 11:30 p.m. Since Eric
now agrees with me about this, and you agree with him, do you
also now agree with me?
Vern
By Eric Ottinger on Friday,
June 28, 2002 - 10:09 am:
Vern,
My point is that neither party really wants to kill the
contract. Hence, the hypothetical ability to do so is at best a
bargaining tool in the real world.
In the real world a customer that gets conspicuously ripped off
is going to be reluctant to continue the relationship. A
contractor that weaseled out of its commitments with regard to
environmental cleanup costs is probably going to leave the
customer with a very bad taste in the mouth.
By the same token, a contractor that sticks the government
customer with exorbitant overhead rates and serious CAS
noncompliances is going to have a hard time convincing the
government that costs are going to be reasonable and properly
accounted for on subsequent contracts. This is most likely to
play as a realism issue in a source selection.
“I know what you are promising, but why should I believe it in
light of what you just did to me.”
I don’t agree that a “contractor would not have to sign a
novation agreement” for “operation of law” in a gray area
outside of the ABA recommended exception in the FAR. The
contractor would have to go to court, and the contractor would
probably lose.
By the way, I am trying to be polite. But it is nice to see that
you are back to normal. I doubt I have dodged anything.
Eric
By Roy on Friday, June 28, 2002 - 10:57 am:
Vern,
From reading Eric's post, I don't believe he concluded that a
novation agreement would be unnecessary in those "gray" areas he
alludes to. It's obvious that the FAR does not recognize them as
exceptions. The one exception cited in the FAR was riddled with
very specific criteria; i.e., "with no legal change in the
contracting party, and where that contracting party remains in
control of the assets and is the party performing the contract".
My biggest problem throughout these discussions as been with the
positions by some that any third party through this thing called
"assignment by operation of law" can assume the role of
contractor and continue performance of work under a government
contract. It has been suggested that procurement officials
through their FAR procedures had better not hinder this party in
any way or face the wrath of the judiciary branch. Can you
imagine one of these third parties involved in a transfer "by
operation of law" taking over a contract that involves special
nuclear materials and requiring security clearances, etc. What
if the "contractor by operation of law" was not able to meet the
security requirements. I don't see how it would be possible for
the Government to allow this party to perform.
I believe the FAR covers the process of recognization of a
"successor in interest" properly in a way that protects the
Governments interest when these situations arise. I think that
if we start interjecting these gray areas into the language in
the FAR, the process could get very confusing.
I will let Eric speak for himself regarding the conclusions you
made.
Thanks Roy
By Roy on Friday, June 28, 2002
- 11:10 am:
Vern,
I was playing around with drafting a response to you earlier and
did not know about Eric's response at 10:09.
It seems as if I was correct about Eric's position on the gray
areas.
Roy
By Vern Edwards on Friday, June
28, 2002 - 11:24 am:
Eric:
I don't know what you mean by "back to normal"; I haven't
changed. But putting that aside, you did not answer the
question. Is your answer yes or no?
Let me lay it out for you: If a contract has been transferred by
operation of law (no "gray area"), and the government and the
new contractor disagree over an accounting issue that affects
contract costs, and the contractor refuses to sign the
government's proposed novation agreement, should the government
consider the contractor's refusal to be evidence of a "bad
attitude" and antagonistic, and rate the new contractor's past
performance negatively? What's your answer: yes or no?
I'm don't plan to argue with you about your answer, but I do
want to know where you stand, since you seem to consider this to
be a matter of customer relations. When you said that the
contractor might "win a battle and lose the war" you seemed to
suggest that the government should retaliate against the
contractor for its victory by denying it future contracts. I
thought you might want to clarify your remarks.
So what's your answer: yes or no?
By Vern Edwards on Friday, June
28, 2002 - 11:56 am:
Roy:
My problem with Eric's "gray area" comment is that I don't know
what he's talking about. What does he mean by "gray area"?
What's gray?
By "gray area" does Eric mean that the courts are not sure what
kinds of transfers are transfers by operation of law? If that is
what he means, then I'm not sure that he's right. It may be that
lawyers and judges know what transfers are by operation of law,
even if we here at Wifcon don't know. I didn't see anything in
my case law readings to indicate that the courts are uncertain
in that regard.
Or, by "gray area" does Eric mean that it's unclear what the
novation rule is when a transfer has been made by operation of
law? If that's what he means by "gray area," then I disagree. I
have read enough to be confident that the courts and the boards
of contract appeals consider it to be well-established that (a)
41 U.S.C. § 15 does not apply to transfers that have been
effected by operation of law, (b) government assent to such
transfers is not required, FAR Subpart 42.12 notwithstanding,
and (c) a contractor is not required to sign a novation
agreement when a transfer has been effected by operation of law.
But, Roy, I respect your disagreement with me and I accept it,
even if I don't understand it.
Vern
By Eric Ottinger on Friday,
June 28, 2002 - 10:01 pm:
Roy,
Exactly.
I started out asking why we were giving legal advice. Now I am
asking why we think we know more about novations than the
American Bar Association.
A transfer that conforms to FAR 42.1204(b) is clearly by
operation of law, and the agreement (if any is required) should
not be a novation agreement.
Outside of that, the contractor would have to convince my agency
counsel or take me to court.
At this point Vern and I probably agree about the meaning of
“operation of law.” It is something that happens so
automatically that even the court doesn’t have any discretion.
THERE IS NO SIMPLE OPERATION OF LAW EXCEPTION TO THE
ANTI-ASSIGNMENT ACT. There are a specific number of judicially
recognized exceptions under the “operation of law” heading.
As simple as the “operation of law” concept may be, courts and
boards disagree about the application to specific situations.
That is what I mean by “gray areas.”
For instance, one of the judicially recognized exceptions is
death. If the contractor gets hit by a bus, the transfer takes
place in a very automatic fashion.
Chapter 7 bankruptcy is the way corporations die. Nobody is
questioning that the transfer from the contractor to the trustee
is automatic, “by operation of law.”
Chapter 11 is a different matter because the corporation is
hoping to have a near death experience and live to talk about
it.
After that, we have mergers and other forms of restructuring.
That is a topic more than adequately addressed by Ms. Manos, the
ABA and FAR 42.1204(b).
The answer to Vern’s question is as follows. If the successor in
interest contractor has a CAS non-compliance issue, the CAS
issue would be an issue for all of the contractor’s contracts,
not just the contracts which are being transferred. The ACO
would note the CAS non-compliance during the information
gathering phase of the novation process. Even if the transfer is
by “operation of law” (i.e. FAR 42.1204(b)) the ACO would
attempt to resolve the CAS noncompliance issue by negotiation,
as the FAR clearly directs.
If a PCO wishes to award a new contract to the successor in
interest contractor, the PCO would call the ACO to determine if
there are any CAS noncompliances. (Every standard negotiation
clearance format has a block which must be completed with this
information.) If the ACO indicates a noncompliance, the PCO has
to take this into account. The PCO will consider the seriousness
of the noncompliance, the credibility of the ACO’s argument and
the likelihood that the issue will eventually be resolved in a
satisfactory manner.
(With large contractors, CAS issues are like sniffles for
children attending day care. That is-- This must be taken into
account, but the condition is more or less constant.)
In short, given the normal sequence of events, there is no way
that a CAS noncompliance will not have some impact on a
selection decision. On the other hand, nobody has been debarred
for a CAS noncompliance. We frequently make awards in spite of
these negative indicators.
You can plug “environmental cleanup costs” or “exorbitant
overhead rates” into the above equation and get essentially the
same answer.
I have a war story regarding a novation which I would love to
work into this discussion at some point. After our legal counsel
had given us the legally correct answer, I asked how long the
novation would require. The shortest possible time was three
months. I protested that we would have a crisis within two
weeks. Counsel slowly intoned, “Process, process.” That is the
correct answer to Vern’s “yes” or “no” question.
Maybe it would be best to ask Vern a question.
Vern,
Since these issues cut across all of the firm’s contracts, why
do you think this is a “past” performance issue?
To put it another way-- If the contractor fixes the CAS
noncompliance, funds the environmental cleanup and cuts out the
unreasonable overhead costs; of course, I will be happy to do
business with the contractor.
If he doesn’t, we still have a problem. “Retaliation” has
nothing to do with it.
Eric
By Eric Ottinger on Saturday,
June 29, 2002 - 08:30 am:
Vern,
We have already discussed gray areas in this thread.
I think the application of claims related precedents to
executory contracts is about a gray as you can get. But I can’t
find enough relevant cases to even begin to sort that out. In
fact if anyone has a simple, “Somebody wants to assign an
executory contract to a government customer, and the government
objects, and the contract is assigned anyway (or not assigned
and the government is sued)” I would love to read that case.
The few accessible executory contract cases generally have a
counterintuitive “man bites dog” character to them. For
instance, Johnson Controls tries to walk off with $56 million of
overfunded pension costs. The successor in interest contractor
cites the Anti-Assignment Act to deny the government privity of
contract. The government never explicitly consented to the
assignment, but the government’s “knowledge, assent, and action
consistent with the terms of the assignment” would do just as
well as a formal novation. The government still has privity of
contract.
(Note that the government can consent “by operation of law,” by
acting oblivious and doing nothing for some unspecified period
of time. Does anyone want to argue that this is a clear, simple
rule, which should be endorsed by the FAR?)
Per the Court of Federal Claims, “These circumstances [i.e.
similar to FAR 42.1204(b)] resemble closely the instances in
which courts have recognized a transfer by operation of law…” If
the Court of Claims uses squishy language like “resemble
closely,” Ottinger is not going posit any “simple” black and
white rule.
Per Ms. Manos, “…the boards and courts have largely ignored the
form of the transaction and focused instead on how the
transaction affects the and liabilities of the parties.” (I
don’t really speak this legalese, but “form” sounds like “simple
answer,” and “rights and liabilities of the parties” sounds
highly judgmental.)
Some courts (or boards) cite a “categorical” rule. Others, go
back and apply the generally agreed purposes of the law to the
specific circumstances of the case. There is disagreement
regarding voluntary vs. involuntary. (Vern initially cited
Mancon as support for a simple rule. But it turns out Mancon is
highly controversial.)
In short, this is not simple.
Eric
By: Vern Edwards on Saturday,
June 29, 2002 - 12:52 pm
Eric:
First, you have just said: "A transfer that conforms to FAR
42.1204(b) is clearly by operation of law...." Italics added.
That is incorrect, because FAR § 42.1204(b) is not about
transfers (assignments or delegations), whether by operation of
law or otherwise. Rather, it is about situations in which there
has been a change of corporate ownership, but no transfer of
contractual responsibility. It says, in pertinent part:
"A novation agreement is unnecessary when there is a change in
the ownership of a contractor as a result of a stock purchase,
with no legal change in the contracting party, and when that
contracting party remains in control of the assets and is the
party performing the contract."
Underlining added. [Note that FAR § 42.1204(b) does not apply to
changes in the ownership of proprietorships or general
partnerships, apparently since such a change of ownership would
be a change of contracting party.]
In short, FAR § 42.1204(b) says that you don't need a novation
agreement when there is not going to be a transfer of
contractual rights and obligations. It does not say that you
don't need a novation agreement when there has been a transfer
by operation of law. It's the very fact that FAR does not
acknowledge the operation of law exception to 41 U.S.C. § 15
that sparked this conversation in the first place.
Second, on June 24 at 6:50 p.m., you said: "In 1995 the American
Bar Association recommended certain modifications to the FAR to
acknowledge assignment by operation of law. These
recommendations were eventually incorporated in FAC 97-3."
Italics added. Then, on June 26 at 10:11 p.m., you said: "FAC
97-3 revised the FAR to incorporate recommendations by the
American Bar Association with regard to novations and operation
of law." Italics added. You rely heavily on these assertions
about the ABA, but you err in doing so.
According to the proposed rule that preceded FAC 97-03
(published at 61 FR 43294 on Aug. 21, 1996), the ABA asked the
FAR Council to revise FAR Subpart 42.12. Neither the proposed
rule nor FAC 97-03 describe the ABA's request in any detail or
mention any recommendations. The background statement that
accompanied the proposed rule says, in its entirety:
"This proposed rule is in response to an October 2, 1995,
request from the American Bar Association to revise FAR Subpart
42.12. The purpose of the change is to facilitate the process of
novating contracts and provide guidelines for contracting
officers while preserving the Government's interests in business
combinations affecting contracts."
FAC 97-03, the final rule (published at 62 FR 64934 on Dec. 9,
1997), does not mention the ABA at all. The phrase operation of
law does not appear in the proposed rule, FAC 97-03, FAR Subpart
42.12, or anywhere else in FAR Part 42 for that matter.
In her article in the Public Contract Law Journal, Ms Manos
reported that the ABA asked the FAR Council "to revise the
current procedures for obtaining a novation agreement to resolve
the business uncertainty and administrative problems inherent in
the current [pre-FAC 97-03] procedures." She did not say what
the specific recommendations were or whether they had anything
to do with the operation of law exception to the application of
41 U.S.C. § 15. Nor did she say that the 1996 proposed change to
FAR § 42.1204(b) recognizes the operation of law exception.
We have been talking about situations in which contractual
rights and obligations have been transferred from one party to
another by operation of law. FAR § 42.1204(b) clearly doesn't
address such transfers and thus is not pertinent to the topic.
Third, you just said: "Note that the government can consent 'by
operation of law,' by acting oblivious and doing nothing for
some unspecified period of time." I think that you are confusing
transfers by operation of law with transfers by government
"recognition," waiver, or implied approval and without a formal
novation agreement.
Transfers resulting from government recognition, waiver, or
implied approval are considered voluntary, not by operation of
law. See: Tuftco Corporation v. United States, 614 F.2d 740, 222
Ct. Cl. 277 (1980), which distinguishes transfers by operation
of law from those resulting from recognition without a formal
novation agreement. See, also, Prof. Cibinic's article, which I
previously cited, and which notes the distinction between
transfers by operation of law and transfers by government waiver
or implied approval. Ms Manos discussed this subject briefly, as
well.
Finally, you shouted, "THERE IS NO SIMPLE OPERATION OF LAW
EXCEPTION TO THE ANTI-ASSIGNMENT ACT. There are a specific
number of judicially recognized exceptions under the 'operation
of law' heading." Forgive me, Eric, but I do not understand your
point, or why you shouted it.
Perhaps there is no simple answer to the question of what kinds
of transfers are transfers by operation of law, but it's
certainly simple that a transfer effected by operation of law is
exempt from the anti-assignment acts, the courts and boards have
been very clear about that.
Think of it this way-- All of the various kinds of transfers
(assignments and delegations) can be divided into two
categories: (a) transfers by operation of law and (b) transfers
not by operation of law. You and I may not know which of all the
various kinds of transfers fall into the operation of law
category (I certainly don't, although Tuftco identifies at least
some of them), but I know that those which do fall into the
operation of law category are exempt from 41 U.S.C. § 15.
So, if by "gray area" you mean that the courts and boards are
unsure about which kinds of transfers are transfers by operation
of law, then perhaps you are right. But that's a different issue
than the one that we have been discussing. On the other hand, if
you mean that there is a "gray area" within the operation of law
category, some undefined subset of transfers by operation of law
that are not exempt, then I don't understand how you reached
that conclusion. The Broadlake decision mentioned by Ms Manos
seems to be a rather clearly defined exception that would not
establish the existence of a "gray area."
You dodged my question.
By Vern Edwards on Sunday, June
30, 2002 - 05:14 pm:
On June 29 at 8:30 a.m., Eric asked for an example of a case in
which the government objected to the assignment of an executory
contract and the contract is assigned anyway. Healy Tibbits
Builders, Inc., ASBCA No. 45269, 94-1 BCA 26,409 is such a case.
Before I go any further, let me explain what executory contract
means. Black’s Law Dictionary, 7th ed., defines executory
contract as follows:
"A contract that remains wholly unperformed or for which there
remains something still to be done on both sides, often as a
component of a larger transaction and sometimes memorialized by
an informal letter agreement, by a memorandum, or oral
agreement."
See, too, In re TechDyn Systems Corp., 235 B.R. 857 (1999), in
which a bankruptcy court discussed the concept of executory
contract as follows:
"Congress has not chosen to define the term "executory
contracts," but most courts have adopted the classic definition
first articulated by professor Vern Countryman: "A contract
under which the obligations of both the bankrupt and the other
party to the contract are so far unperformed that the failure of
either to complete the performance would constitute a material
breach excusing the performance of the other." Vern Countryman,
"Executory Contracts in Bankruptcy: Part I," 57 Minn.L.Rev. 439
(1973). See Lubrizol Enterprises, Inc. v. Richmond Metal
Finishers, Inc., 756 F.2d 1043, 1045 (4th Cir.1985) ("a contract
is executory if performance is due to some extent on both
sides.").
In short, an executory contract is one under which each party
still owes some duty to the other.
Now, here’s what happened in Healy Tibbits Builders, Inc.:
On June 5, 1989, Healy Tibbits Construction Co. (HTC) bid on a
Navy construction contract.
On August 7, the Navy notified HTC that it was the low bidder
and requested responsibility information.
On August 14, HTC filed for bankruptcy under Chapter 11 due to
the insolvency of its parent company. However, HTC continued to
pursue the Navy contract and told the Navy that its performance
would be funded, bonded and backed by a company named Weeks
Marine, Inc. (Weeks).
On September 12, HTC became debtor-in-possession under Chapter
11, and it negotiated a deal with Weeks through which Weeks
would acquire all of HTC’s contracts. HTC agreed to continue
performance of the contracts until the deal was approved by the
bankruptcy court. On September 13, HTC and Weeks submitted the
deal to the bankruptcy court for approval. Meanwhile, the Navy
continued to investigate HTC’s responsibility, and discussed the
matter with both HTC and Weeks.
On September 14, HTC and Weeks gave the Navy a copy of the deal
they had submitted to the bankruptcy court.
On September 26, the Navy determined that HTC was responsible
and awarded HTC the contract.
On October 11, HTC and Weeks amended their deal to include an
"inactive affiliate" of Weeks named Deepwater Construction Co.
(Deepwater). On that same date, the bankruptcy court approved
the deal between HTC, Weeks and Deepwater and the assignment of
HTC’s "executory contracts" to either Weeks or Deepwater, which
would be jointly and severally liable for performance.
On October 13, more than two weeks after contract award, HTC and
Deepwater entered into an agreement through which Deepwater
became the owner of HTC. The management, employees and capital
assets of HTC remained intact under Deepwater’s ownership. HTC
agreed to continue performing the Navy contract until Deepwater
could obtain necessary licensing, at which time the contracts
would be transferred to Deepwater.
On October 19, Deepwater changed its name to Healy Tibbits
Builders, Inc. (which the ASBCA abbreviated as "HTB," but which
I’ll abbreviate as "HTB-Deepwater" to avoid confusion with HTC).
From November 1989 to March 1991, invoices were submitted to the
Navy in the name of HTC. The HTC project manager became an HTB-Deepwater
employee, but continued to manage the Navy project. The Navy
addressed contract correspondence to both HTC and to HTB-Deepwater,
and received correspondence from both. By August 1990, the
construction work was sufficiently complete to permit beneficial
occupancy by the Navy.
On March 3, 1991, the Navy contract specialist sent a novation
agreement to HTB-Deepwater with copies of the FAR provisions
about novation. HTB-Deepwater’s lawyer objected to a novation on
grounds that it would be too costly. The parties never signed a
novation agreement.
On March 12, HTB-Deepwater sent the government a claim for
equitable adjustments. The parties then began to wait for DCAA's
audit of the claim, which took a while. In the meantime, the
deducted 115 days worth of liquidated damages at $1,050 per day.
In April 1992, the Navy raised the issue of the identity of the
contractor for the first time.
On September 24, the Navy denied HTB-Deepwater’s claim, and on
October 30, HTB-Deepwater appealed to the ASBCA.
The Navy asked the ASBCA to dismiss the appeal, asserting that
HTB-Deepwater was not the contractor and had no right to appeal.
The ASBCA described the Navy's position as follows:
"Essentially, the Government contends that the party contracting
with the Government was Healy Tibbits Construction Co. [HTC],
which continued to be the entity represented throughout contract
performance as the contractor. Thus, the Government at no time
had a contract with Healy Tibbits Builders, Inc. [HTB-Deepwater],
no privity exists, and appellant has no standing to bring the
appeal. Morever [sic], if, at some time during performance, the
contract was assigned to HTB, the Government was not informed
and any purported assignment is asserted to be contrary to the
anti-assignment statutes, 31 U.S.C. § 3721 (formerly § 203) and
41 U.S.C. § 15."
The court denied the Navy’s motion to dismiss the appeal,
saying: "It is now well established that assignments which occur
by operation of law are excepted from the provisions of the
anti-assignment statutes, and that assignments incident to
court-ordered bankruptcy proceedings constitute such assignments
by operation of law. See, e.g., Goodman v. Niblack, 102 U.S.
556, 26 L.Ed. 229 (1880); Keydata Corp. v. United States, 205
Ct. Cl. 467 (1974); Broadlake Partners, GSBCA 10713, 92-1 BCA ¶
24,699. As these cases illustrate, in determining whether the
anti-assignment statutes apply the threshold [sic] question is
whether the assignment is susceptible to the evils against which
the anti-assignment statutes were enacted; here, it is not.
Accordingly, we find the assignment here in issue, being one by
operation of law, to be excepted from the anti-assignment
statutes."
Italics added.
The ASBCA also held that the Navy had, in any event, effectively
waived the provisions of the anti-assignment act.
So, in Healy Tibbits Builders, Inc. we have a case in which a
bankruptcy court assigned an executory contract from one
contractor (HTC) to a new legal entity (HTB-Deepwater), the Navy
claimed ignorance of the assignment and objected to it while the
contract remained executory (the construction work was only
substantially complete), and the ASBCA held that the contract
had been assigned by operation of law.
I have Key-Cited the case and could find no further reference to
it. Apparently, the parties settled after the ASBCA denied the
Navy's motion to dismiss.
By Eric Ottinger on Monday,
July 01, 2002 - 10:25 pm:
Vern,
You have a fundamental problem. The ABA recommended changes to
the FAR to improve the coverage of novations. Substantial
changes were made to FAR 42.1204, including new language
explicitly intended to clarify when a novation would be
required. Nobody is arguing that the ABA does not understand
“operation of law.”
So we are still left asking how Vern and John know so much about
“operation of law” and the American Bar Association doesn’t know
or doesn’t care.
Regarding your first and second point, it was Ms. Manos who tied
her analysis of what the courts and boards have “focused” on to
the ABA recommended changes and FAR 42.1204(b).
“In analyzing the various types of corporate restructuring, the
boards and courts have largely ignored the form of the
transaction and focused instead on how the transaction affects
the rights and liabilities of the parties. When (1) the
transferred contract continues to be performed by the same
employees under the same management, (2) the contractor remains
intact as a separate entity, and (3) the financial condition of
the contractor does not change, the transfer is generally held
to be outside the prohibition of the Anti-Assignment Act. 12
Consistent with this analysis, the proposed revisions to FAR
42.1204 would expressly recognize that “’[a] novation agreement
is unnecessary when there is a change in the ownership of the
contractor as a result of a stock purchase, with no legal change
in the contracting party, and where that party remains in
control of the assets and is the party performing the contract.’
13”
“13. 61 Fed. Reg. 43,294, 43,295 (1996) (to be codified at 48
C.F.R. pt. 42) (Proposed Aug. 21, 1996).”
In short, Ms. Manos links “remaining intact as a separate
entity” with “no legal change in the contracting party” with the
ABA recommended changes to the FAR.
(Ms. Manos and the ABA also recommended that the FAR be revised
to allow the contractor to submit documents before the novation
rather than being required to transfer first and risk having the
government disapprove the transfer. This obviously makes sense,
but it has no relevance to our discussion.)
Per Ms. Manos, “the Claims Court found a novation agreement …
enforceable, even though Government consent to the transfer—and
thus the novation agreement—were unnecessary because the
transfer occurred by operation of law.” As, I believe, John
immediately recognized, ITT Gilfillan fits FAR 42.1204(b)
perfectly.
I will concede your third point with the caveat that it doesn’t
really make any difference. Forbearance seems to fit the
“operation of law” definitions that I provided earlier. (That
is— “a change or transfer which occurs automatically due to
existing laws and not an agreement or court order.”) However, I
can’t find any case or authority explicitly equating forbearance
with operation of law.
This does not help your argument very much, because it becomes
apparent that once you take the waiver or forbearance (i.e.
“impliedly recognized”) exception out of the equation,
everything else which Ms. Manos considers to be consistent with
her analysis of what courts and boards have “generally held to
be outside of the prohibition of the Anti-Assignment Act”, has
been addressed by FAR 42.1204(b).
As for your fourth point, you blame me for shouting then ignore
what I have to say. There is only a very short list of generally
recognized judicial exceptions under the operation of law
heading.
If you really feel that the FAR has failed to recognize one of
these exceptions, you need to be more specific. Earlier in this
thread you reduced your argument to a tautology. “If operation
of law occurs automatically, by golly, it must occur so
automatically that it is done and over with before the
government can consent or refuse to consent.” I don’t disagree
and I don’t think the statement is meaningful.
What specific circumstances do you have in mind outside of FAR
42.1204(b) and what authority do you have to back up your
argument?
Regarding Healy Tibbits—
I asked for a contract where the government explicitly objected
to the assignment at the time the transfer occurs.
“’Somebody wants to assign an executory contract to a government
customer, and the government objects [at the time of the
transfer], and the contract is assigned anyway (or not assigned
and the government is sued)’ I would love to read that case.”
Here, you gave me a case where the government refused to
acknowledge a claim, long after the transfer had taken place.
Since it was 1993 by the time that the ASBCA decided this case,
I doubt very much that the contract was executory at the time
the case was decided.
The government sent a novation agreement over for signature and
then let the matter ride when the contractor refused to sign the
novation agreement.
There are several cases where the transfer occurs during the
executory phase of the contract, but the litigation doesn’t
occur until many months after. I am aware of these cases, but
they don’t demonstrate anything other than the fact that the
courts and boards are reluctant to let the government use either
of the anti-assignment acts to prevent the successor-in-interest
contractor from pursuing an otherwise legitimate claim.
The reference to a Court “Order” is a red herring. The debtor in
possession sold the firm, which puts this case solidly under
42.1204(b), the court merely approved the sale.
Eric
By Vern Edwards on Tuesday,
July 02, 2002 - 01:13 am:
Eric:
Your post is largely unresponsive to my comments.
The ABA's recommendations, whatever they may have been, have no
bearing on this discussion. As far as I have been able to
determine, the ABA recommended nothing to the FAR Council about
the operation of law exception to 41 U.S.C. § 15.
You say: "So we are still left asking how Vern and John know so
much about 'operation of law' and the American Bar Association
doesn’t know or doesn’t care." Eric, what's that comment about?
John hasn't said anything about the ABA and I have simply spoken
the truth about what is known to us of the ABA's request and
recommendations. I don't know what the ABA recommended. How do
you know what the ABA recommended? Have you seen the ABA's
October 2, 1995 letter?
The Government Contractor discussed the ABA's recommendations in
contemporaneous articles published on July 27, 1994 and August
28, 1996. Neither article mentions any ABA comment or
recommendation about the operation of law exception. See: "DOD
Declines to Issue Policy Guidance on Novation Process," 29
Government Contractor ¶ 390, and "FAR Council Proposes to Ease
Novation Requirements," 33 Government Contractor ¶ 416.
How on earth do you link FAR § 42.1204(b) with the operation of
law exception to 41 U.S.C. § 15? A novation either replaces an
old agreement with a new one or one party with another. See the
entry in Black's Law Dictionary, 7th ed. and in The Government
Contracts Reference Book, 2d ed. Since a corporation is a legal
entity separate from its ownership, a mere change in ownership
does not require a novation. FAR § 42.1204(b) simply recognizes
that there is no need for a novation agreement if the
contracting parties remain unchanged. FAR § 42.1204(b) has
nothing to do with transfers of obligation from one party to
another by operation of law. It's as simple as that.
You have no basis for claiming that the ABA's recommendations
had anything to do with the operation of law exception. And even
if they did, FAR § 42.1204(b) does not address that exception.
The fact is that you don't know what the ABA recommended and
nothing in Ms Manos's article supports your contentions in that
regard.
Eric, what is your position at this point? As the ASBCA said:
"It is now well established that assignments which occur by
operation of law are excepted from the provisions of the
anti-assignment statutes[.]" What is it about that statement
that is gray to you? What don't you understand? The boards and
the courts have identified several specific examples of what
kinds of transfers constitute transfers by operation of law.
Again, what is gray to you?
My position is simple:
(a) The boards and courts consider it well-established that 41
U.S.C. § 15 does not apply to changes of contractor that are
effected by operation of law.
(b) When a contract has been transfered from one contractor to
another by operation of law, Government approval is not required
and refusal by either the old or the new contractor to sign a
novation agreement under such circumstances would not be grounds
for termination for default.
(c) FAR does not address transfers by operation of law in any
way. FAR § 42.1204 addresses only changes of corporate
ownership, and not changes in the contractor.
(d) In light of the case law, and the continuing confusion and
litigation associated with transfers by operation of law, the
FAR Council ought to revise FAR Subpart 42.12 to provide
contracting officers with guidance about the operation of law
exception and about the government's options when a contract has
been transferred by operation of law.
Which of those points do you disagree with?
Finally, you quoted me as saying: "If operation of law occurs
automatically, by golly, it must occur so automatically that it
is done and over with before the government can consent or
refuse to consent." You put that statement in quotation marks.
When did I say that? Please cite the date and time of the post.
Please don't deliberately misquote people or attribute your
statements to another person, it's unethical. If you're going to
put a statement in quotation marks, please quote and attribute
accurately.
And don't misquote yourself, either. When you asked for an
example case you didn't say at the time of the transfer, and
it's disingenuous to put corrective phrases in brackets.
By Vern Edwards on Tuesday,
July 02, 2002 - 01:16 am:
Eric:
P.S. You're still dodging my question.
By Eric Ottinger on Tuesday,
July 02, 2002 - 09:57 pm:
Roy and all,
Let’s look at a list of these judicially recognized exceptions
to the anti-assignment acts.
“[T]he courts have held the following assignments or transfers
to be by ‘operation of law, and exempt from the relevant
statutory provision: transfers by intestate succession or
testamentary disposition, Erwin v. United States, 97 U.S. 392
(1878); by consolidation or merger to the successor of a
claimant corporation, Seaboard Air Line Ry. Co. v. United
States, 256 U.S. 655 (1921); by judicial sale, Western Pacific
R. Co. v. United States, 268 U.S. 271 (1925); by subrogation to
an insurer, United States v. Aetna Casualty & Surety Co., [338
U.S. 366 (1949)]; by statutory provision to a trustee in
bankruptcy, McKay v. United States, 27 Ct. Cl. 422 (1892) . . .
and by voluntary assignment of all the assets of an insolvent
debtor for the benefit of creditors, Goodman v. Niblack [102
U.S. 556) (1880) .”
What do we have? We have –
Death (i.e. intestate succession and testamentary disposition)
Corporate death (i.e. “judicial sale” (strictly claims and
Assignment of Claims Act), “by statutory provision to a trustee
in bankruptcy,” and “voluntary assignment of all of the
assets.”)
The condition of remaining intact and being swallowed whole.
(i.e. “by consolidation or merger to the successor of a claimant
corporation”)
And, “subrogation to an insurer.” (If you don’t already
understand this one, don’t worry about it. The insurance company
is not going to perform the contract. This is strictly claims.)
That leaves a vast number of scenarios where the firm sells off
parts of the business and the contracts that go with them. These
are clearly outside of the “generally held” criteria set forth
by Ms. Manos and the similar criteria referenced in the Court of
Federal Claims in the Johnson Controls case.
If this discussion is going to go forward in some meaningful
way, someone needs to identify one or more other specific
judicially recognized “operation of law” exceptions to the
Anti-Assignment Act.
Eric
By Vern Edwards on Tuesday,
July 02, 2002 - 11:36 pm:
Eric:
You said: "If this discussion is going to go forward in some
meaningful way, someone needs to identify one or more other
specific judicially recognized 'operation of law' exceptions to
the Anti-Assignment Act."
No one needs to do any such thing. Just one
judicially-recognized exception is enough to prove my point.
As I said on June 29 at 12:52 p.m., transfers can be categorized
in two ways: (a) those that are effected by operation of law,
and (b) those that are not. I do not claim that all transfers
are by operation of law. I only claim that transfers by
operation of law do not fall under 41 U.S.C. § 15 and that
government consent to them is not required, no matter what the
FAR says.
Various courts have included the following kinds of transfers as
by operation of law:
1. the passage of claims to heirs and devisees;
2. transfers made incident to proceedings in bankruptcy or
receivership;
3. tranfers by succession of one business entity for another;
4. assignments made by judicial sale or order; and
5. assignments produced by operation of the law of subrogation.
According to the U.S. Court of Claims in Keydata Corp. v. U.S.,
504 F.2d 1115 (1974): "These classes of assignments are all
thought to be outside the statute's scope because none of them
threatens the dangers Congress sought to avoid by enacting the
prohibition." Most of those same exceptions were mentioned by
the U.S. Supreme Court in Seaboard Air Line Railway v. United
States, 256 U.S. 655 (1921).
In Johnson Controls World Services, Inc. v. United States, 44
Fed. Cl. 334 (1999), the U.S. Court of Federal Claims, the
successor to the U.S. Court of Claims, said: "Transfers by
operation of law include corporate mergers, consolidations, and
reorganizations."
I do not understand all of the listed exceptions, and for all I
know, the list is not all-inclusive.
My point is that transfers by operation of law do not fall under
the anti-assignment statute, 41 U.S.C. § 15, and thus do not
require government approval or consent. When a contract has been
transferred by operation of law, neither the old contractor nor
the new contractor is required to sign a novation agreement.
Under such circumstances, while a novation agreement may be
administratively expedient, whether it is in the best interests
of both of the parties, or not, depends on what it says.
FAR does not reflect this simple legal reality and, therefore,
ought to be revised to provide better guidance to contracting
officers.
Now, if you want to continue this discussion, please tell us
which of my four July 2 position points you disagree with. And
please tell us your answer to my question of June 28 at 11:24
a.m. Yes or no?
By Eric Ottinger on Monday,
July 08, 2002 - 08:18 pm:
Roy and all,
Let’s sort this out.
There really are only a small number of possibilities for
mergers and consolidations.
Death is simple and self-evident. Nobody is going to question
that death represents an automatic transfer.
Corporate death is somewhat more problematical. The standard
list mentions only the transfer to the trustee. As for a
transfer to the debtor in possession, different courts have
different opinions.
For bankruptcy a transfer to a third party would not appear to
fit the definition for “operation of law.” An automatic transfer
to a third party by a trustee would appear to be prohibited by
the plain language of Section 365(c)(1)(A), although at least
one judge has another opinion. In any case, the transfer can’t
be all that automatic if there is more than one third party to
choose from. And no one has cited any case or any other
authority to support the idea that a transfer resulting from a
bankruptcy, other than the transfer to the trustee or the debtor
in possession, is by “operation of law.”
Partial transfers don’t fit because courts have generally held
that the contractor must remain intact as a separate entity for
the transfer to be “by operation of law.”
That leaves a transfer of all of the assets or all of the stock.
The ASBCA considers a transfer of all of the assets to be a
“voluntary” transfer, and not “operation of law.”
This leaves the purchase of all of the stock (i.e. FAR
42.1204(b)).
Here is the ASBCA on the asset vs. stock issue.
Siracusa Moving & Storage, ASBCA No. 51433, Dated: 7 July 1999
“The Anti-Assignment Act generally prohibits transfer of
Government contracts from a contractor to a third party. The
Board recognizes an exception to this prohibition for transfers
that occur involuntarily or “by operation of law.” However, we
have long held that “[t]he assignment of Government contracts as
an incident to the sale of the assets of a business is not an
involuntary assignment or transfer by operation of law and hence
is barred by the statute.” Mancon Liquidating Corp., ASBCA No.
18304, 74-1 BCA 10,470 at 49512. Thus, the “operation of law”
exception is inapplicable to this case. Accordingly, we find
that the attempted transfer of Collings’ contract to Siracusa is
invalid and barred by the Anti-Assignment Act. 41 U.S.C. § 15.”
For those who are curious about the legalese, here are the legal
dictionary definitions. The definition of "testamentary
disposition" is courtesy of Everybody's Legal Dictionary. All of
the other definitions are courtesy of Merriam-Webster.
Keep in mind that almost all of the novation case law relates to
claims rather than ongoing "executory" contracts. There is no
need to strain trying to imagine how someone might buy an
ongoing government contract at a bankruptcy sale.
”1. the passage of claims to heirs and devisees;
2. transfers made incident to proceedings in bankruptcy or
receivership;
3. tranfers by succession of one business entity for another;
4. assignments made by judicial sale or order; and
5. assignments produced by operation of the law of subrogation.”
Death:
intestate succession: “the transmission of property or property
interests of a decedent as provided by statute as distinguished
from the transfer in accordance with the decedent's will
also
the operation of such statutory provisions in transmitting
intestate property ”
testamentary disposition: “Leaving property in a will.”
Corporate Death:
judicial sale: “a sale of property conducted by an authorized
official by order of a court
See also forced sale”
assignment for the benefit of creditors: “assignment of property
by a debtor to an assignee to be held in trust and used to pay
off the debtor's debts”
The condition of remaining intact (or not) and being swallowed
whole:
merger: “absorption by one corporation of another
also
any of various methods of combining two or more organizations
(as business concerns)
compare consolidate”
consolidate: “to combine (two or more corporations) to form one
new corporation
compare merger”
Irrelevant:
subrogation: “a doctrine holding that when an insurance company
pays an insured's claim of loss due to another's tort the
insurer succeeds to the insured's rights (as the right to sue
for damages) against the tortfeasor”
What was this all about. I think this was a potentially
interesting thread which was sidetracked by an effort to
demonstrate that there must be something wrong with the FAR.
There probably was something wrong with the FAR ten years ago.
Subsequently, the ABA made recommendations and the FAR was
revised.
It appears that the FAR is right in line with the ABA
recommendations, and right in line with the case law as it
stands today.
Vern,
I didn’t know that it was such bad manners to put quotation
marks on, when the quote is self-evidently meant to be
ridiculous. The reader will note that I made up the “by golly”
quote and you may have my apology. Your argument is still a
tautology.
Eric
By Vern Edwards on Monday, July
08, 2002 - 09:46 pm:
Eric:
Since you're obviously not going to answer my questions, I
consider our discussion to be ended.
On to the next topic.
Vern
By Eric Ottinger on Wednesday,
July 10, 2002 - 10:14 pm:
Roy and all,
Google turned up a few interesting hits.
Here is a bit of the DLA directives. Note the imperative to
notify agency counsel at the start of the process. If we had all
agreed on this point at the start of the thread, this would have
been a much shorter thread.
I will express a bit of skepticism on one point. “Corporate
reorganization” is no doubt a “rapidly changing” and “complex
field.” However, novation law is not moving all that rapidly.
Cases cited typically go back to 1929 or the 19th century. It
isn’t the fast moving character that makes this treacherous for
a layman, it is the need to do research in a large legal
library.
http://131.70.202.82/dynaweb/dlaps/dladir/@Generic__BookTextView/23759
Here is the ABA view circa 1996.
“The Section believes the proposed amendments to FAR Subpart
42.12 represent a substantial improvement to the current
regulations by providing contracting officers with guidelines on
utilization of novation agreements and flexibility to
accommodate transactions, while preserving the Government's
legitimate interests in business combinations affecting its
contracts.”
http://www.abanet.org/contract/federal/regscomm/transactions_002.html
This “white paper” is a roundtable discussion on the topic of
novations. Some of the comments are intriguing in light of the
discussion in this thread. “Operation of law” is characterized
as a “magic umbrella.” And, “The courts have essentially split
on whether a transfer through bankruptcy is inside the
assignment provisions.” (Is this the In re West controversy or
other issues?)
www.grantthornton.com/downloads/17089_17089.doc
The following is a fairly comprehensive article on the topic
posted at a law firm site.
http://www.wrf.com/db30/cgi-bin/pubs/critcl_thnkng(web).pdf
The redoubtable Carl Peckinpaugh weighed in on this topic in
Federal Computer Week in 1996, before FAC 97-3.
http://www.fcw.com/fcw/articles/1996/FCW_060396_348.asp
“In general, a government contractor may not transfer its rights
under a contract without prior approval from the responsible
contracting officer. However, the contracting officer must
consent when the transfer is "by operation of law." This
includes situations in which the entire business entity changes
hands, either through a stock transfer or a transfer of the
complete assets of the company. It may also include transfers of
the complete assets of the unit responsible for the government
contract.”…
”In contrast to the clearly improper transfers to which the act
was addressed, certain transfers do not involve the potential
for abuse. The courts and other authorities have recognized that
transfers by operation of law are not prohibited by the
statute.”
”Some authorities have suggested that this rule extends to
transfers of an entire business unit that is responsible for a
government contract, even though it is not a separate corporate
entity (see, e.g., 9 Comp. Gen. 72 (1929)). However, there is
little precedent on this point.”
”Under Federal Acquisition Regulation Subpart 42.12, the parties
are required to obtain government approval for all contract
transfers, including those by operation of law. However, the
government has no right to disapprove transactions that are
outside the prohibitions of the Anti-Assignment Act.”
It is clear that in 1996 Mr. Pechinpaugh took a more expansive
view of “operation of law” than the ASBCA and the current FAR.
Just for clarity-- I don’t believe that it is the FAR’s job to
override the ASBCA. In fact, that would be highly inappropriate.
The FAR should reflect settled case law. If an appeals court or
the Supreme Court should reverse the ASBCA, the FAR should be
revised accordingly.
Since the case law recognizes a short list of judicially
recognized exceptions under the “operation of law” heading, the
FAR should reflect the specific judicially recognized
exception(s), which is what you see in FAR 42.1204(b).
Eric
By Eric Ottinger on Thursday,
August 22, 2002 - 08:18 pm:
When I asked, “Keeping in mind that Denise’s contractor is in
Chapter 11 bankruptcy, am I correct if I say that in view of In
re West, a transfer to either the debtor in possession or a
transfer to a third party is not a transfer by “operation of
law,” I honestly expected that the answer would be, “Yes, it was
now clear that there was no way that Denise’ contract would be
assigned to a third party contractor without government
consent.” I am still waiting for that reply.
Here are two articles by government lawyers to make the point
perfectly clear.
This is the first “A Lawyer’s View” article, which makes it
something of a collectible.
http://www.contracts.ogc.doc.gov/cld/LV/Bnkrpty.pdf
I would note that there is more controversy, than this article
would leave you to believe, regarding the debtor in possession.
Here is the DOJ position. See Para F.2.(c).
http://www.usdoj.gov/usao/eousa/foia_reading_room/usam/title4/civ00060.htm
In government contracting law, the line of cases following In re
West seems to have died out in 1994. However, this issue appears
to be a hot topic in intellectual property law.
Journal of Internet Law
“The Code recognizes that a reorganizing debtor must have the
ability to hold third parties to existing contractual
obligations where beneficial to the estate, and even transfer
the contractual obligations to third parties. Section 365 grants
the debtor the ability to assume and assign such executory
contracts. The debtor's ability to assume and assign a contract
is not absolute. The Code recognizes that in some circumstances
allowing a debtor to assign a contract to a third party creates
too great an imposition on the other party to the contract.
Rather than define the specific instances when a contract may
not be assigned, Section 365(c)(l)(A) of the Code restricts
assignment when nonbankruptcy laws (but not contractual terms)
excuse the nondebtor party to the contract from accepting
performance from an assignee.28 Thus, the Code looks to other
law, either statutory or judicial, to determine when forced
assignment of contract rights is too unfair to the nondebtor
party to be allowed.”
http://www.gcwf.com/articles/journal/jil_oct00_1.html
Good discussion of catapult case --
http://www.cov.com/publications/222.pdf
http://www.icemiller.com/newsltr/cauapr99.htm
In re West logic applied to intellectual property.
http://www.flhlaw.com/news/May1999.htm
Various relevant cases --
http://caselaw.lp.findlaw.com/scripts/getcase.pl?navby=search&case=/data2/circs/9th/9716707.html
http://contracts.corporate.findlaw.com/agreements/geocities/informix.lic.1998.06.30.html
http://caselaw.lp.findlaw.com/scripts/getcase.pl?navby=search&case=/data2/circs/9th/9416960.html
http://caselaw.lp.findlaw.com/scripts/getcase.pl?navby=search&case=/data2/circs/9th/9556527.html
http://www.law.emory.edu/caselaw/1ca/jan97/96-2028.01a.html
http://www.kentlaw.edu/7circuit/1993/92-3902.html
http://caselaw.lp.findlaw.com/scripts/getcase.pl?navby=search&case=/data2/circs/9th/9416960.html
I found this article on the failures of textualism entertaining
in light of some of our past dialogues in this forum. Judge
Learned Hand is quoted, “it is one of the surest indexes of a
mature and developed jurisprudence not to make a fortress out of
the dictionary.”
http://law.vanderbilt.edu/lawreview/vol533/bussel.pdf
Eric
|