HOME  |  CONTENTS  |  DISCUSSIONS  |  BLOG  |  QUICK-KITs|  STATES

Google

       Search WWW Search wifcon.com

To Contents

Escalation of Labor Rates Subject to Service Contract Act
By RAM on Thursday, July 11, 2002 - 06:06 pm:

I need help on settling a topic of debate regarding the allowance of an escalation applied to direct labor which is subject to the SCA. The example: solicitation for fixed-price contract with base and option years - includes FAR 52.222-43. Proposals include direct labor that is subject to SCA. Offerors apply an escalation rate (straight %) to this direct labor cost in the out-years.

Question: Is this a deficiency that must be corrected through discussions?

My opinion: This is a deficiency that will require the need for discussions.

My Logic: (which can be unique )Based on my reading of the FAR clause, an offeror that does this is building in a contingency that the clause already provides a remedy for. I also relied on some guidance from a cost&pricing guidebook. To be fair, the guidebook, while clearly stating building in the contingency is not permissible, does give the impression that if higher rates are proposed for out-years and the successive wage determination rates are lower, then a modification can be done to reduce the contract cost by the appropriate amount. My thought is that if it is identified during the evaluation phase - and it will have to be dealt with either sooner or later - why not sooner.

The opposing argument has two questions: 1) Why shouldn't the offeror be allowed to escalate labor rates subject to SCA by a reasonable escalation factor? And, 2)If it really isn't allowed, and evaluation doesn't turn up any other deficiencies, can award without discussions be made by identifying this problem as weakness that will be resolved by modification to the contract when the option is exercised (if necessary)?

Opposing Logic: We get pay raises every year. Why shouldn't the offeror's personnel? If offeror's rates (or escalation factor) are determined reasonable and end result is that out-year rates are higher than successive year(s) wage determination rates that should be okay. Contractor should not have to eat the difference out of his profit by only being allowed the amount of the successive wage rate.

By Vern Edwards on Thursday, July 11, 2002 - 08:55 pm:

RAM:

There is some GAO case law on the SCA-FLSA price adjustment clause. I just scanned it; I didn't read it closely; but it does not appear to answer your question.

I don't think that the offeror's escalation of option year prices constitutes a deficiency, unless it violates some instruction in the RFP. There is no standard, SCA-related FAR solicitation provision that prohibits offerors from escalating option year prices. The SCA specifies only minimum wages and fringes; it does not limit the contractor to the wages and fringes in the wage determination. There is no rule that says the offeror cannot simply decide to charge you more in the option years. The only effect of the offeror's escalated pricing will be that if a new wage determination increases wages and fringes, but does not increase them to levels higher than those proposed, then the contractor will not be entitled to a price adjustment due to higher SCA wages and fringes. I think that's it.

I wonder whether the offeror escalated the option year prices by mistake, not realizing that the SCA-FLSA price adjustment clause already provides for an increase due to a new wage determination. If you have some reason to think that the offeror has made a mistake, then you must put the offeror on notice.


By joel hoffman on Thursday, July 11, 2002 - 11:32 pm:

From your description of the scenario, it appears that the Offeror intends to pay the SCA minimums for the base period, then incorporate an escalation factor for out-year prices. I recommend discussing this with the offeror. Find out if its intent is to continue paying the SCA minimums in the out-years.

If so, I'd point out that the contract provides a mechanism to protect the contractor from escalting SCA rates in the future. I'd also not count on a credit, if the escalated out-year prices outstrip increases in the SCA wage determinations. Credits are voluntary, on the part of the Contractor, at least for Davis-Bacon adjustments, and the FAR states that SCA adjustments for option years are handled similarly. The Contractor could pocket the difference.

If the Contractor intends to pay SCA minimums in the out-years, I believe that I'd indicate to the Offeror that the Government doesn't agree with its pricing scheme for the out-years, because it only benefits the Contractor.

Again - the above is based on the impression that the Offeror intends to pay its employees the minimum SCA wage rates. If that isn't the case, the Offeror's pricing approach may be valid. happy sails! joel


By RAM on Friday, July 12, 2002 - 09:30 am:

Joel - Vern - thanks for the advice. I guess the scenario in the guidebook threw me off - maybe I will throw away the guidebook.


By Vern Edwards on Friday, July 12, 2002 - 09:58 am:

Ram:

Don't throw it way! What's the name of the guidebook?


By RAM on Friday, July 12, 2002 - 03:40 pm:

Vern:

It is an old FORSCOM guidebook. Exact title is FORSCOM Handbook for Cost and Price Analysis - FY00 - Forces Command DCS for Logistics. Mind you, I am no longer at a FORSCOM installation but had it handy and thought it would still be useful.


By Vern Edwards on Friday, July 12, 2002 - 03:50 pm:

RAM:

I think you're talking about FORSCOM PAM 715-10, Nov 91. Right? Rescinded in February 2000.


By RAM on Friday, July 12, 2002 - 04:57 pm:

Vern:

I don't believe that is correct. If you go to the following web address you can access this handbook: http://www.forscom.army.mil/contract/policy.htm

The guidance that got me going on this issue starts about the middle of page 59 and runs through page 60.


By Vern Edwards on Friday, July 12, 2002 - 05:23 pm:

RAM:

Thanks.

I looked at the FORSCOM handbook and it is pretty unequivocal:

"Offerors must propose Non-Exempt labor based on the wage determinations in the solicitation. That is, the offerors must propose at least the minimum wage; they may initially propose wages higher than the stated minimums. Under fixed price contracts, offerors cannot propose higher Non-Exempt wages in the out years. FAR considers this an unwarranted contingency based on the fact that the contract provides a mechanism for wage adjustments in the out years. Under cost-reimbursement contracts, contractors are not restricted from proposing higher out year wages."

Italics added.

I could not find any support in FAR Subpart 22.10 for the idea that offerors cannot propose higher wages and fringes in the option years. The closest thing that I could find that could be said to support the statement is the second paragraph in the SCA-FLSA price adjustment clause, FAR § 52.222-43, which says:

"The Contractor warrants that the prices in this contract do not include any allowance for any contingency to cover increased costs for which adjustment is provided under this clause."

Now let's suppose that the wage determination for the first year of performance specifies combined wages and fringes of $15.00 per hour. The FORSCOM handbook seems to say that an offeror could propose $17.00 for the first year (higher than the wage determination, in order to establish and maintain a top-notch workforce), but must propose no more than $15.00 for the options years. That doesn't make sense to me. What if the wage determination for the first option raises the rate from $15.00 to $15.75, a five percent increase, but lower than the $17.00 paid during the first year? Does the contractor have to make a choice between cutting the workers' wages and fringes or taking a reduction in profit or even a loss?

What am I missing? I must be missing something.


By Anonymous on Friday, July 12, 2002 - 05:32 pm:

Vern & RAM:

I'm a contractor who just submitted an SCA bid for a Navy contract that had FAR 52.222-43. This isn't my first SCA bid, and I have seen evaluators handle it differently, much to my consternation. I suspect it doesn't help much that so many contractors don't understand SCA, especially in T&M contracts. Here's my take:

No escalation following FAR 52.222-43 means Direct Labor (DL) and the stipulated Health & Welfare (H&W) cannot be escalated at all. BUT, DL & H&W do not exist alone in the pricing structure. Overhead still escalates. Fringe not covered by the H&W allowance escalates. G&A escalates. So, I don't touch DL or H&W, but all else--especially in a multi-year risky T&M bid-- must be escalated.

The reason is simple. As a contractor, the only adjustments I can expect to see when a new DoL Wage Determination is issued is a penny-for-penny increase in the DL and a penny-for-penny increase for H&W. Therefore, I MUST be allowed to escalate other expenses not covered by DL and H&W. As an evaluator, you may very well see what appears to be escalation because the burdened labor goes up from year-to-year, but it may be due to the non-DL and non-H&W factors.


By joel hoffman on Friday, July 12, 2002 - 05:58 pm:

Anon, that makes perfect sense and is something that can be reasonably clarified during discussions.

Vern, I think that the FORSCOM guidance is simply not well verbalized. It might be referring to the FAR 52.222-43 restriction on not escalating wages to cover adjustments, otherwise provided for in the SCA mechanism. happy sails! joel


By Vern Edwards on Friday, July 12, 2002 - 08:22 pm:

Anonymous of 5:32pm:

You say: "No escalation following FAR 52.222-43 means Direct Labor (DL) and the stipulated Health & Welfare (H&W) cannot be escalated at all."

Are you saying that an offeror is not allowed to propose higher prices for option years based on higher wages and fringes than the base year wage determination? If so, since SCA-FLSA price adjustments are limited to the increases caused by the the new wage determination, wouldn't that effectively make the option year SCA wages and fringes maximums instead of minimums?

Joel:

Yeah, I guess it could mean that. You know, I've read that clause maybe a hundred times and never really thought clearly about what paragraph (b) meant. Now I'm wondering about the practical effect of that "warrants" language. It probably doesn't become an issue very often because most offerors don't propose wages and fringes that are higher than the minimums specified in the wage determination. The practical effect of the SCA is that the Department of Labor specifies the wages that will be paid, not just the minimum that must be paid.


By Anon2U on Sunday, July 14, 2002 - 06:52 pm:

The SCA sometimes hurts labor rather than helping it as intended. The wages are too low in many cases and don't take into account spot shortages of certain career fields such as security personnel after 9/11.

We have contracts where the competition was so fierce that anyone proposing wages higher than the SCA minimums would have been eliminated due to high price. But once the contract is awarded, the contractor has a hard time keeping the good personnel who jump to higher paying commercial contracts. The SCA wages are a middle average - a good wage for mediocre workers, bad wage for good workers.

This puts the contracting officer and source selection authority into a bad position too. In a best value you can select a higher price but how are you to know at time of award if the proposed SCA wage will be detrimental. If you select based on higher wages, a protest is almost sure to follow. After all, how can proposing Department of Labor wage rates make the proposal a bad value.

Union contracts complicate things even more because wages are allowed to drop from Union pay the first year to wage determination the second. It is not likely because a new union contract will probably be negotiated during the first year, however, they could bid that way, and did on one of my contracts. They ended up $15M cheaper because of it. We solved that problem with a GAO suggestion that we follow Department of Justice's practice of dictating the current union wages for all the out years. While this does not allow for a company to "buy in" on wages, it does eliminate the labor turmoil and high performance risk of wages cut by 33% after the first year.


By jimso on Thursday, October 10, 2002 - 11:56 am:

Move on down to par (c) which addresses G&A, overhead and profit. When taken in conjunction with the "warrant" in (b), I believe that any escalation of outyear rates is a violation of this clause and could be used to seek reductions from the contractor if rates have been escalated in the out years. This is an example of a clause that is a pricing clause as opposed to an accounting/allocation clause. The logic was that a contractors costs do not increase just because of a labor rate increase and therefore, the contractor is not entitled to additional G&A, overhead and profit, only the incremental costs of the labor and fringe. The clause ignores the allocation of burdens based on dollars as required by CAS 402 and therefore penalizes the contractor in labor rates for outyears. If the contract is the only one the company has, the pricing rule is probably true. If the contractor has several contracts of mixed types, escalation of rates will eventually erode his profit on the contract to nothing when adjustments are made under 52.222-43.

Several years ago I attempted to bring this to the attention of the Service Contracts Association but their then legislative analyst was not interested in exploring a clarification or change to the clause.

I think there is need of a FAR case to clarify this. Also one to clarify the "fee" limitation on A&E contracts.


By joel hoffman on Friday, October 11, 2002 - 10:32 pm:

jimso, I assume that you are referring to the ambiguity in the use of the term "fee", on A-E contracts. Yes, the term "fee" can be read as the entire charge for the design or it could be interpreted as the markup on costs - profit?, G&A and profit? A "design fee" is different than a "fee" or "profit allowance". There are also varying interpretations of what is excluded from design costs - surveys, reports, drafting, etc.! happy sails! joel

ABOUT  l CONTACT