By
formerfed
on Monday, April 02, 2001 - 09:36 am:
Bob just posted this to the site. It's B-286979, and concerns
an appeal of an agency level decision. It's interesting in that
the agency level decision (Army - AMC) displayed some rather
poor rational, which cited the CO as wrong. Fortunately, GAO
didn't buy into it.
http://www.wifcon.com/cgdedbelowcost.htm
Any thoughts?
By
ex-fed
on Monday, April 02, 2001 - 10:42 am:
The Army demonstrated inability to think clearly and got into
very faulty mixing of "apples and oranges." It did so
by equating "NSP" with "$0.00" and tangible
deliverable CLINS with work required to deliver them in a FFP.
In the latter case one has to wonder at the logic of including
contractor's labor as a CLIN in such a contract. It really makes
no sense whatever. An analogy might be to require the retailer
to disclose and separately bill the store manager's
"cost" when one buys a television or an office
software package. On the surface it appears to be a FFP for a
"thing" in which the buyer became confused and tried
to impost cost contract like insight into component costs.
I expect all involved will get performance awards later this
year.
By
Linda
Koone on Monday, April 02, 2001 - 11:26 am:
Formerfed:
You beat me to the draw on this one. I thought it was an
interesting decision too.
I agree with the GAO decision that was primarily based on the
concept that "NSP" and a price of $0.00 are two
separate concepts.
What I question, and what wasn't raised, was whether the CO's
discussions produced the desired outcome of discussions, which
is to ensure that the Govt obtains the best value. I believe
that letters can be used during discussions as a means of
beginning a dialogue. I can't help thinking, however, that if
actual verbal exchanges occurred, the CO might have reconsidered
having a line item for the Program Manager; or alternately, the
company that entered NSP may have learned that there would be an
acceptable way to meet the requirements of the solicitation and
still not directly charge for Program Manager hours.
By
Kennedy How
on Monday, April 02, 2001 - 01:20 pm:
It appears to me that it could be somebody wanting to see the
costs involved with performing on the contract other than for
the hardware being ordered. Maybe somebody directed them to
separately price the labor.
I remember Congress directing us in the past to compete
technical support contracts, which normally went to the systems
developer. And, if a competetor won that contract, look out!
We've also broken out Warranty costs as a separate line item. In
that case, somebody wanted to see exactly how much something
like that costs for a armored combat vehicle.
As a contract specialist, I tend to find it difficult to believe
that a separately priced line item requirement was included on a
whim. Usually, it's in response to the desires of somebody
higher up. Maybe it was the result of an audit or DoDIG ding for
NOT breaking it out!
Kennedy
By
ex-fed
on Monday, April 02, 2001 - 03:20 pm:
Then it appears the contract was the wrong type. End price,
with contractor taking the risk is the point of this type. Data
collection is not the point. Being curious about internal cost
is not the point.
If I'm shopping for the best fixed price on a car, TV,
installing a toilet, or obtaining an office software package I
am mixing apples and oranges if my interest extends to the
vendor's internal cost of delivering that package. I've no
business getting curious about summer AC cost, the manager's
office decor, or how much anyone makes. Do I get item X with my
required material terms (return policy, warranty, and such) and
nothing more. Checklist. Done deal. If I'm wasting my time on
quibbling about "your sofa is too fancy for a plumber"
I'm stupid.
I'd love to hear an rational explanation of why someone should
insist a contract is an "apple" while requiring
"orange like" terms. If driven by a legitimate need
then put in a CLIN with the right type. Complicating a
"simple" contract with complexities of another type is
just useless work and a recipe for trouble. Selection of FFP
offers should not involve such effort. So now they got it -- and
15 minutes of fame and publicity.
If higher authority is doing this then they need their
performance evaluated! Muddled thinking is muddled thinking
regardless of grade level.
By
Eric
Ottinger on Tuesday, April 10, 2001 - 07:20 pm:
Former Fed and All,
I think the court got the issue, regarding NSP and $0.00, right.
An NSP item is directly linked to other specific CLIN(s). There
is no link with the $0.00.
"On the contrary, while an entry of NSP, by its terms,
means that the item in question is "not separately
priced" and therefore suggests that it may not be orderable
separate from other CLINs, an entry of $0.00 does not raise any
such question about the offeror's intent to provide the CLIN
without a separate purchase of another CLIN."
Initially, I thought the Court was missing the subtext. The only
way that the offeror could be proposing $0.00 for the Program
Manager category would be a situation where the Program Manager
was normally charged to indirect. But this point is addressed at
the end of the opinion.
A similar "level playing field" issue arises when some
offerors charge secretaries (administrative assistants, graphics
support, etc.) direct and other offerors charge indirect.
I think the key is the availability of this (or these) person(s).
If the program manager is a person with a name and a face, that
should go a long way toward answering the question. However, I
would want written assurances regarding this person's
availability.
Even if the Program Manager is charged direct, you will usually
find that a person at that level is expected to put in some
hours supporting indirect company headquarters cost objectives.
Examples would include recruiting, proposal preparation and long
range planning. If the Program Manager's direct hours in support
of the Army contract are not revenue enhancing, there will be a
powerful temptation to use this person as much as possible for
indirect "other duties as assigned" and shift his/her
responsibilities to other high level direct charge categories.
There are good reasons to be concerned about performance risk.
Arguably, the multiple award ID/IQ arrangement would answer this
concern. Ongoing competition should keep GTSI honest. The actual
Task Orders should be completion, if possible, rather than level
of effort.
My initial thought was that we should be careful about casting
any aspersions on the PCO. It takes a team effort with help from
Management and Legal (and, in this case, Higher Headquarters) to
really screw things up.
You or I might not entirely agree with this risk assessment in
the finding signed by the SSA. But, unless the risk assessment
is utterly unreasonable (which it isn't) this issue should be
protest proof.
"Based on this review, the selection authority made
findings of possible risk associated with accepting GTSI's
decision to price program management at $0.00. In these
findings, at 15, the selection authority determined that there
was no unacceptable risk to the government in the approach
because:
(a) GTSI's letter dated 14 June 2000 has assured the Government
that Program Management hours will be included as required in
individual delivery orders and that they will utilize
individuals with the requisite qualifications as stated in the
RFP. …"
Not to quibble, but if this were strictly hardware and not
services, it should be a "Delivery Order" contract,
not a "Task Order" contract. In any case, there is
clearly an element of services included in "servers,
workstations, accessories, and support."
Eric
By
formerfed
on Wednesday, April 11, 2001 - 07:53 am:
Eric,
I think the CO and SSO used proper logic. GAO agreed. The part I
thought was awful is AMC's interim decision supporting the
protest and, in essence, saying the CO erred. I wonder where
AMC's head (along with their lawyers) was when they sustained
the protest, causing this to go to GAO.
By
Kennedy How
on Wednesday, April 11, 2001 - 01:06 pm:
I remember having this kind of discussion with my colleagues
a few years back on the issue of direct/indirect contracts
support. I was more in favor of direct charging, where I could
hook a name to a position, and pay for that position over the
life of the program. I had some friends who were seeing more of
the opposite. That is, charging those sorts of administrative
functions to indirects. Maybe it was due to cost cutting. Or
budget constraints. Or, because it was just plain difficult to
slot a direct charge person there because he didn't exist, and
he wouldn't until they got the contract. On the other hand, if
there was already an office tasked to do that stuff, and they
were being allocated on an "as required" basis, then
maybe being charged as an indirect is proper. Having a Program
Manager being charged both direct and indirect causes problems,
in my view.
But, I do remember thinking back then that we were heading back
to the gigantic indirect pools of old, before we decided to get
more specific, and started requesting that people be direct
charged.
Kennedy
By
ex-fed
on Wednesday, April 11, 2001 - 07:23 pm:
All:
How about clarifying the rationale for such detail on who does
what at what cost on a FFP contract, the type at issue in this
case.
Why are you really interested?
Why are you even justified in looking into this level of detail
within a private company that has already said we will deliver
this at this price?
Within the price envelope for a clearly stated product or
service, presumably the focus of the decision, what business is
it of yours what the required PM cost as long as the PM function
is met?
To me this clearly is something that needs a strong reason to
do, not a reason not to do. It is involving the government
inappropriately at a level it has no need to enter at some cost
to itself and the contractor. It has both cost and
"political" ramifications.
Finally, if the need for such insight into the contractor's
internal cost structure is for some legitimate reason, aside
from meddlesome curiosity, firmly established why stay with this
contract type?
By
Anonymous
on Thursday, April 12, 2001 - 08:11 am:
All:
I think that the explanation for the pricing scheme is in the
first paragraph of the Background section of the decision.
CECOM intended for this contract to be available to all Federal
agencies, worldwide, to order IT supplies or services as needed.
This was to be a GWACS-type contract. That's why CECOM had such
a complicated CLIN/SLIN schedule and required the offerors to
provide separate pricing and agree to separate ordering. The
contract was designed to allow any agency to buy virtually any
kind of IT supplies or services from the contractors. The CLIN/SLIN
pricing scheme facilitated that objective. ex-fed, the agency
wasn't being nosey about costs, it was establishing a catalog of
supplies and services and their associated prices. As mentioned
in the decision, the contractor was aware that it might have to
provide program manager services at an hourly rate or price of
$0.00 in response to a task order.
This was yet another entreprenuerial endeavor by a Government
agency seeking to compete with GSA. I'll bet that CECOM is to
receive compensation from agencies that use its contracts. The
REALLY interesting question that this decision raises for me is
whether agencies should be allowed to engage in these kinds of
entreprenuerial endeavors. Otherwise, the decision is
interesting mainly because of the enjoyment one gets from seeing
the smarty-pants AMC Headquarters lawyer(s) getting put down by
GAO. As the GAO pointed out, the difference between NSP and
$0.00 was established some time ago.
By
ex-fed
on Thursday, April 12, 2001 - 12:00 pm:
Let me get this straight. There will be a menu of options
forming a program of different composition and flavor for
various ordering agencies. Some will order the program with and
some without a program manager. Interesting.
I would think the management function was a necessity to some
degree regardless of whether the full or partial menu was
ordered. "I'll have the Caesar salad, surf and turf, baked
potato, asparagus without management please." The logic
still escapes me.
On a FFP it would seem to me the sensible thing is to include
"management" among the non-directs with every order
paying a share according to consumption. Even varied CLIN
difficulty levels could be covered by varied rates on the
deliverable CLINS. That avoids violation of the KISS principle
-- one FFP objective I believe.
By
formerfed
on Thursday, April 12, 2001 - 01:03 pm:
Anon,
You brought up a subject that always puzzles me. So many
agencies are establishing government-wide contracts and charge
fees for their use. However, most of these agencies can't do
much (or shouldn't be doing much) with the fees. Unless they
have special authorization, such as franchise authority or a
working capital/revolving fund, they can only charge for
reimbursement of their actual costs. So what's the point of all
the extra work? If you want to do something entertaining, ask an
IT marketing rep what contracts are available for you to order
their products from. Some companies can come up with five or
more.
The next issue of AMC's legal newsletter "AMC Command
Counsel Newsletter" will be interesting. Bob has a link to
it. Let's watch and read the lawyer's side of this.
By
ex-fed
on Thursday, April 12, 2001 - 11:03 pm:
Formerfed,
One might wonder about the result if the total potential value
and total deliverable payload of all those government wide
contracts were calculated and then compare against a realistic
estimate of need. Might we expect another fun story on the
evening news?
Even more interesting might be a real analysis of exactly what
differs in cost and terms for very closely comparable or even
exact items in the various contracts.
There may really be entirely too many cooks in this kitchen.
By
bob
antonio on Friday, April 13, 2001 - 05:24 am:
Ex-fed:
If I remember correctly, before the GWAC program started, the
Director of the Ofice of Management and Budget was required to
certify that this was a cost-saving program.
However, I remember posting a note to Director Raines and
Administrator (forgot his name already) on an old forum that I
could show the government paying several different prices for
the same item. Additionally, I feel that I can show a better
price for the same item on a state or local contract.
Several years ago, on the Dell.com site, they included a
separate area for government buys. If only, I had access to the
prices paid for items on those contracts.
I have three current projects that will take me into 2002--most
notably my eternal effort to do an article on the Adarand cases.
However, GWACS, MACS, GSA schedules, etc. are dear to my heart.
I would be pleased to post an article on this site dealing with
an in-depth analysis of these programs.
Next month, the House Small Business Committee (I think that is
the one) will begin its attack on the government competing with
industry. I feel confident that the General Services
Administration will be a major topic in those hearings. They
have already been criticized for competing with private industry
with GSA Advantage. If they receive criticism for a progam that
is quite old and precedes any industry competition, I would
suspect that all the GWAC and MAC programs could be included in
the criticism.
By
formerfed
on Friday, April 13, 2001 - 08:23 am:
Bob,
GSA Schedules are also dear to my heart. It's difficult to come
up with a contractual vehicle that has so many good and bad
features at the same time. However, the negative points are so
easily overcome if government buyers just used the same
approaches to purchasing as they do in making personal buying
decisions.
Buying a car is a good example. Very few people pay sticker
price, but that's close to what GSA prices are. Getting better
is so easy. All one usually has to do is ask a few questions and
play some games with the salesperson, just like with the car
dealer. Most every item is available through several different
GSA vendors. It's so easy to prepare an RFQ and fax to several.
The buyer needs to let the company know they are seeking
competitive quotes as well.
I don't think the program is broke - it certainly saves a lot in
administrative time and expense. The problem seems to be in the
use. I don't know what the solution is. There are many
unskilled, untrained, and unmotivated people doing purchasing.
Also, there are good people in the 1102 ranks that are capable
and qualified, but it's overkill to use GS-13's (even though
many GSA orders run into several hundred thousand dollars). The
acquisition workforce has been so depleted at many agencies,
that there aren't enough people to do the proper job. Too many
orders are just processed by "rubber stamping" what's
on the requsition. If you want to do an interesting study, ask
some vendors what received orders look like. There are horror
stories galore that demonstrate that no thinking or effort went
into the order at all.
By
Anon
Zed on Friday, April 13, 2001 - 08:56 am:
Two observations in response to formerfed's last message:
First, I am convinced that the problems described by formerfed
reflect a larger problem with government in general. A headline
in today's New York Times says that due to personnel cuts the
IRS is no longer enforcing the tax code and that
"millions" who have not paid their taxes are being
left alone. Cuts in civil service staffing levels, competence
problems, recruiting problems, and poorly managed
contracting-out are undermining Government competence.
Second, and more to the point of this discussion, the problems
discussed in the more recent messages in this thread reflect
that fact that agencies do not feel that they can "get on
contract" quickly enough under the rules in FAR Part 6 and
FAR Part 15. The proliferation of schedule contracts and GWACs
and MAC contracts for services, and task order contracts in
general, reflect attempts to speed up the contract formation
process. They are officially-sanctioned ways around what is
perceived by many to be a CICA-Part 15 roadblock to management
effectiveness in this era of contracted-out government. What
worries me is that no one is systematically studying the effect
that these policies and procedures are having on what Steve
Kelman called "the quality of Government performance."
Please, do not misconstrue what I've said to mean that I am a
CICA advocate, an opponent of acquisition reform, or a
Cassandra. But I do wonder if we are in a state of free market
anarchy in government acquisition and, if we are, whether it
will produce good or bad results in the long run.
By
formerfed
on Friday, April 13, 2001 - 09:34 am:
Anon Zed,
Good points. Personally I see many good things done over the
past several years. The problem is too many of the workforce are
ill equipped are use the tools. Consequently abuses, mistakes,
and just plain exercise of poor judgement are common.
Let me state it differently. Most agree the old (pre-acquisition
reform) process didn't get the job done. Now many tools are
available to reduce lead times, select the best vendor, and
management the acquisition process better. However, embedded in
it is the responsibility to plan and exercise prudent judgment.
If a CO can get the right products/services quicker and easier,
while still economical, so much the better. However, that CO is
expected to use good judgement and the audit trail should show
taxpayers benefited from the initiative, insight, and overall
actions taken. A few might look at getting around roadblocks,
but a good CO leaves a track record showing good things - a
procurement that used to take years was done in months, the
result was achieved by two people instead of 20, the business
deal is a good one, and industry didn't spend a fortune to
participate.
The problem is not many CO's can carry this out. For starters,
they need to earn the trust and respect of the programs they
support. This ensures they are brought in on the acquisition at
the earliest stages to help formulate the strategy. Next, they
need to be able to communicate with industry in conducting
market research. Then they need the savy and knowledge to apply
the wide variety of tools. Finally they need to use sound
judgment and let the results speak for themselves.
But what we have are too many people lacking these skills and
knowledge. That's why orders on GSA are placed at inflated
prices, why orders are competed when appropriate, why program
offices use GWAS and other means to avoid competition, and on
and on.
Well, when I'm elected President, I'll get everything straight.
By
ex-fed
on Friday, April 13, 2001 - 11:01 am:
Increased freedom requires increased responsibility. We don't
give freedom to five year olds. Now we see reform offering
increased freedom and personnel policies driving a workforce
less able to perform even under the old, more restrictive rules.
Do it faster with less under these circumstances means
something. It means do it poorly. I think the real "tax
cut" could come from more sensible and responsible
management of government spending in acquisition, particularly
as more and more of the work expected is done through contracts.
On the other hand, the combination of money in politics and the
intensive lobbying interest by contractors combined with
disinterest among ordinary citizens almost gurantees nothing
will really be fixed.
As a businessman I'd love to have one of my largest, most
powerful customers fragmented into little buying groups who
can't be bothered to compare the prices I'm charging. I'll let
the fools pay while I grin all the way to the bank. I'll also
spend a few bucks up in the CEO's office and take the Board out
for a few lunches so I can explain how wasteful it would be to
pay more attention. Let the market decide. Give them freedom and
they will make the right choice in a free market composed of
their many branches and my shop. Oh yeah!
By
ex-fed
on Friday, April 13, 2001 - 11:06 am:
By the way, is anyone taking on those questions I asked up
above? Why am I not being blasted for just not understanding the
fine points of the original issue?
Did or did not the Army lose sight of KISS in this effort to
load up a FFP vehicle with cost like insight?
By
Kennedy How
on Friday, April 13, 2001 - 12:13 pm:
Formerfed,
If you are referring to the issue of "Dinner without
management, please", then I would say that depending on
what a particular customer wants, they might want to do it all
themselves, without a program manager type, or maybe they want a
"one stop shopping" approach to include all of the
admin stuff necessary to get what they want up and running.
I'm taking the approach that the program manager isn't somebody
managing this contract program, but somebody who's doing some
kind of integration work for the customer. A service, in other
words. I can't really see a program manager who manages a GWAC
in it's entirety to be paid on one order and not on another.
He's responsible for this "program", you have to pay
him. Thus, he might be a service rep.
On my EDI contract, I have a program manager who does all the
coordination on his (contractor) side of the house. Sometimes, a
deliverable to us is deemed to be useful to some other agency,
who contacts us for more info. We've offered him up to that
agency to help them integrate our application into whatever it
is they want to have accomplished; but that agency MIPRs us the
money to pay for his time, we don't pay for it. Or, we can hand
the entire app over to them (it's owned by the Government) to do
what they will, they don't get any of my PM's expertise. Plus,
we don't do any further work on THEIR version of the
application, and we don't warrant/support any changes they make.
Kennedy
By
formerfed
on Friday, April 13, 2001 - 01:33 pm:
Ex-fed,
Without the benefit of seeing the solicitation, my guess is the
KISS principle is violated because the Army tried to be too many
things to too many people. From looking at the protest decision,
I get the impression the procurement is overly broad for one
single action. For starters, the scope is government-wide and
world-wide. Then it includes a broad array of products and
services: servers, workstations, operating systems, compilers,
engineering support, LANs and WANS, maintenance, leasing,
consumables, etc. Then, as an indication oh how complicated this
all is, there are 15 CLINS for program management support.
Again, another assumption, the Army should have talked with
industry before this went out, or at least have considerable
prior experience when they developed their CLIN structure.
You point makes sense to me, but I wonder how many of the
offerors might balk about living with that kind of arrangement
for world-wide support over several years. What I think we see
is the Army attempting to do the best they can with an overly
ambitious IDIQ contract. Maybe this was the simplest they could
devise.
By
ex-fed
on Friday, April 13, 2001 - 10:36 pm:
I'll agree the solicitation is needed for a definitive
conclusion. The comments "Federal Data Corporation (FDC)
and PRC, Inc., learned for the first time that GTSI entered
"$0.00" for certain CLINs that required hourly, daily,
weekly, monthly, and yearly rates for a program manager"
and "we note for the record that during the course of this
protest GTSI reaffirmed its intent to provide program manager
services for $0.00, even if the services are ordered
separately" don't sound to me as if some sort of
"service rep" to me. I guess Occam's Razor is my view.
Why would the decision keep referring to "program
manager" -- a rather clearly defined position -- when what
is really meant is "service rep" -- another well
recognized position.
Without further evidence, I believe they are talking about a
contractor's PM who will manage all the things such a person
would normally do and in the framework of a FFP contract. The
purpose of such a contract is a quite direct. In basic form
isn't it "I require (this) at this time under these terms.
You state you will comply, any reservations and a price. I don't
want any further bother or involvement beyond taking
delivery."
Now someone wants to "get involved" to see what is
going on in the process -- not just the result. In some ways it
really is like "I'll have your $9.95 chicken dish and oh,
by the way, I do need a receipt and I also want you to allocate
the restaurant manager's cost for its preparation separately on
my bill."
We all know of cases where such insight may be necessary, but
this seems wrong place, wrong type. As for "too many things
to too many people," Amen. The disease seems rampant.
By
Rob
Bristow on Monday, April 23, 2001 - 11:16 am:
I commend the Army's KO for trying to get the best deal for
the taxpayers. Without engaging in the usual banter about cost
and pricing data or how CLINs are set up, it is obvious that the
KO was on the right track.
All too often federal consumers are paying prices using
BankCards, GSA, GWACs, and so on without analyzing what they are
paying let alone planning and adequately developing requirements
all driven by the PM office addiction to acquisition self-
gratification.
Poorly developed requirements continues to be the most
significant shortfall not cycle times (or development of Section
B) by the local contracting officer. Deidre Lee makes an
excellent point about GSA when she states we can now buy the
wrong things faster.
By
ex-fed
on Friday, April 27, 2001 - 11:45 pm:
Rob, how can you commend the KO for mistaking the principle
of the matter? The decision involves "award of a
fixed-price ID/IQ task order contract" and not a cost
type contract. The contract involved is not a type in which the
government should be interested in the individual components of
the total cost. If that is required, another type applies.
In reality it demonstrates a government meddling in places it
has no business. I agree with your comment on requirements, but
the requirement has been established to be something obtainable
by fixed price. If that is an "economy sedan"
delivered at fixed price (all risk on contractor) the
contractor's broken down cost are neither the government's
business or concern assuming the homework has been done and the
offered prices are within industry standards to other customers.
Driving a hard bargin is the KO's business. Monitoring
components in fixed price contracts isn't. If one can make an
argument they are, then another contract type is also arguable
and probably should be picked. Misplaced diligence is not
commendable.
By
Anon
Zed on Saturday, April 28, 2001 - 10:18 am:
ex-fed:
You seem to think that the inclusion of a line item for
"program manager" reflects a misplaced concern about
contractor costs. That's not correct. On April 12 at 08:11 am,
"Anonymous" explained that this was to be a GWACs-type
task order contract, available to many users.
The key to understanding such task order contracts is to
recognize that they allow agencies to buy services while
deferring specification of individual tasks until an order is
placed. Since specification is deferred, you cannot price the
tasks at the time of contract award. However, statute and
regulation require that Government contracts include prices of
some kind. Thus, it is standard practice to include line items
for different labor categories in such contracts -- including
program manager. Such labor category pricing lets users of the
contract negotiate task order prices without starting entirely
from scratch. The labor category prices serve as price ceilings
for future task order proposals and satisfy the statutory and
regulatory pricing requirement.
The Army's contract does not violate the KISS principle when you
consider the Army's objective, which was to establish a contract
that included a catalog of task component prices from which
agencies could assemble a total task order price. One such task
component might be a program manager.
While the wisdom of the wide-spread use of these GWAC-type
contracts is a matter for debate, I think that your criticism of
KO "meddling" is misplaced in this instance.
By
ex-fed
on Saturday, April 28, 2001 - 01:47 pm:
Anon Zed:
I fully understand the concept here of the GWAC-type allowing
agencies to order off a menu. My problem with this issue deals
directly with the menu item of with or without PM. Perhaps I'm
not thinking in terms of some sort of "special" PM
these people had in mind, but I have a real difficulty in
picturing contract activity without management.
Degrees of management are an issue. For example, what is my
loading of "management" when I simply browse the
aisles of a discount store and take items through checkout? It
is probably at about the same low level as that of my ordering
from a catalog. In both cases my share of management is really
an overhead type thing. It is background, but management is
there and part of the fixed price I pay supports that
management. The management support level is very likely to
increase when I'm not putting an item in the cart and am getting
a service. Still, in a fixed price world it is included in the
service price.
Now, I have a real problem in the store or with the catalog
sales. I call for management to settle the problem. I take the
manager's time and perhaps cause management to increase their
work level. Whether TV in a cart or problematic haircut I still
pay the fixed price.
I can only go by what is in B-286979: "GTSI's contract was
awarded pursuant to request for proposals (RFP) No.
DAAB07-00-R-H254, issued by the Army's
Communications-Electronics Command (CECOM), for
commercial-off-the-shelf servers, workstations, operating
systems, compilers, software applications, peripherals, local
and wide area networking, engineering and support services,
managed environment support, maintenance, system upgrades,
training, leasing, documentation, and consumables to meet
world-wide requirements of the U.S. government." It is
described as "fixed-price ID/IQ task order."
Of the described categories "commercial-off-the-shelf
servers, workstations, operating systems, compilers, software
applications, peripherals" and "leasing,
documentation, and consumables" appear to be items from
that store shelf or catalog requiring a low, background level of
management. The "local and wide area networking,
engineering and support services, managed environment support,
maintenance, system upgrades, training" are more in the
service area and are likely to include more intensive
management.
KISS would seem to indicate that for this fixed price contract
the line items should be category based with the differing
management loading included in the fixed price for the specific
category. Thus everyone pays an appropriate share of management,
that I hope is required and given in all cases, depending on the
management loading of the service. The pricing and selection is
straightforward by comparing item cost to item cost and service
cost to service cost. Just as the cost of a TV includes store
management, the cost of "servers, workstations, operating
systems, compilers, software applications, peripherals"
would be low and selection would be on the comparative cost of
these items. The same with the higher management loading
required for categories aligned with "engineering and
support services."
One thus compares an hour of engineering and support services
with an hour of engineering and support services period instead
of the oddity of an hour of managed services or with unmanaged
service! The fact that all the contractors came in with either
"NSP" or "$0.00" indicates to me the
contractors understood this and the Army was confused. Perhaps
GAO should look more closely into that interesting idea of
unmanaged services!
Category pricing to include management also makes it absolutely
clear that management risk is on the contractor and not some
separately priced item included for fun and games. More
intensive "management" tends to be caused by
mismanagement. Really good management is nearly invisible and is
hidden behind operational excellence. The message to the
contractor is to make your price competitive in each category by
managing your management costs. The message is "You are at
risk if your poor service demands considerable and unforeseen
management attention" and, as in the store above, that
extra demand on the manager's time may have just taken the
profit out of that fixed price item.
I maintain that the described RFP violated basic principles and
KISS.
By
Anon
Zed on Saturday, April 28, 2001 - 04:18 pm:
ex-fed:
Given the wide variety of projects that are likely to be
performed under orders issued against a GWACs-type contract, I
think it would be difficult to treat project management as an
overhead cost allocated to service categories, because some
tasks will require more management than others. Not all
"engineering support" projects are the same or require
the same ratio of management to labor.
Unless all tasks within a service category are expected to be of
the same level of complexity and difficulty and thus require the
same ratio of management to labor, labor category pricing is
usually simpler and more flexible than service category pricing.
While I am an advocate of simplicity, I don't think the KO
violated any "basic principles," including KISS. At
least, I don't see anything in the information that we have
about the procurement that justifies your opinion in that
regard.
You're entitled to your opinion, of course, so I won't debate it
with you further.
By
ex-fed
on Saturday, April 28, 2001 - 05:13 pm:
I understand your point, but I cannot understand how a fixed
price management CLIN evaluated at the initial proposal stage
quite meets the problem of high "complexity and
difficulty" requiring varying ratios of management to labor
either. I am assuming the rate would apply to varying hours
proposed for each task. While it allows some of the variance, it
does not seem to work well as a complex support situation will
quite likely take a higher paid manager. Again, my preference
would be to class those support elements (Eng. Support I, II,
III, etc.) and price them according to complexity.
If this was for mundane IT support I see no need for the
complexity of what was done. If for more complex support the
type chosen for the support CLINs seems ill advised.
Likewise, I agree to disagree in the absence of more
information.
By
Anonymous
on Sunday, April 29, 2001 - 09:24 pm:
Ex Fed,
Are you aware that the CLINS were for "program
managers" priced on an hourly, daily, and weekly basis and
not a fixed-price CLIN for "management"?
By
ex-fed
on Monday, April 30, 2001 - 03:51 pm:
Yes, I read the decision and I am aware of how the contract
was structured as far as the decision reveals. I find it odd to
bizzare. I would still welcome explanation of what logic
underlies "unmanaged," "part managed" or
"fully managed" at the selection of the buyer in an
overall fixed price situation. I question the logic of the
contract as presented, but then there seem to be no few ill
conceived efforts running about.
In fair warning, it is going to be difficult to convince me,
just as it would be to have me approve of "Hi, we want 24/7
network support with one hour a week of it managed." My
response would be "What have you been smoking? Go back and
form an acceptable plan."
Good management is essential to an efficient and cost effective
contractro program. The very idea of a program without
management strikes me as poor business judgement. I readily
agree some things take less management than others. Parsing the
effort by management intensity therefore makes sense if
management intensity is a cost driver in the fixed price
categories. For fun, let's start some CLINS for
"schedule."
"I'll have six servers, sixty workstations, these COTS
software packages and the network support, please."
"Fine, do you want them with or without schedule?"
"I'm cutting costs so I'll have them without management and
without schedule."
"Schedule" costs. In fact it is a key to
"management." Simple delivery is less costly to
schedule than complex IT support service working around
government operating schedules. Optional, separately priced
schedule CLINS have the same ring of illogic. That is the core
of this issue.
By
Kennedy How
on Tuesday, May 01, 2001 - 12:25 pm:
This may sound like it's directed to Ex-Fed, but it's
probably to anybody out there who's familiar with the case, but,
do we really know, or have we determined exactly what the SOW
says with respect to the "Program Manager"? Have we
determined just what part of the contract SOW this falls under?
Does anybody know just how wide and "menu driven" this
contract really is?
I still believe that the Program Manager may be a term coined to
cover somebody who is tasked to assist in the integrating the
hardware for a customer. This person is distinct from the
Program Manager who is the overall manager of the Contract
itself.
Using Ex-Fed's example, if an agency wants all the servers,
workstations, and COTS stuff delivered to their receiving dock
on a certain date, they should be allowed to do that. They don't
need to pay for some "Program Manager" to help them
integrate all this stuff into their facility. They may have
already bought some of this stuff previously, and have the
integration expertise to do it "in house". On the
other hand, if the customer was computer illiterate, and is not
techincally able to do this, so buying contractor expertise is a
valid option for them.
This is not to say that the overheads for the management of the
GWAC isn't being covered; I believe it is. Every participant is
being charged their share, as I understand it.
Kennedy
By
Eric
Ottinger on Tuesday, May 01, 2001 - 12:53 pm:
Kennedy,
I think "Program Manager" simply means
"supervisor" in this context.
Ex-fed,
I guess "unmanaged" refers to a situation where the
contractor sends one or two repairmen and they manage
themselves. Nevertheless, I agree that this is all very odd.
Eric
By
ex-fed
on Tuesday, May 01, 2001 - 01:06 pm:
Kennedy, I understand your point and agree that we don't know
exactly what this "Program Manager" really was in
terms of exact function.
A part of my point is that program management, in the
conventional usage, is required even for delivery of items to
the dock. That is associated with what I'll admit is a somewhat
purist view of fixed price contracting in which a vendor agrees
to sell an item or service at a fixed price on essentially
commercial terms. I qualify the "essentially
commercial" in that there may be special agreements, but
there will not be unusually complex "oversight" or
other terms. This places it close to what happens between
customer and K-Mart, an auto dealership, an airline, or perhaps
even a lawyer: you provide "x" at this unit price and
I'll transfer the cash.
In all those situations "management" takes place to
some degree. One does not go to the airline counter and ask how
much the ticket will be "without management." If
management cost and luxury drives one airline's cost too far out
of line with the others competition is supposed to act to bring
sanity. We deal with these real world "fixed price
contracting" matters at the rolled up price level.
Government entirely too often starts mixing and matching without
sound logic. My issue here is that if this is an all fixed price
contract the airline model should be followed. Compare on the
"ticket price" and stay out of the details except for
the service provided. If there is sound reason to deviate, go to
charter and negotiate (at least on the CLIN level in these
contracts). Don't get wrapped around the axle trying to buy a
regular ticket with management carved out separately and
"with" or "without" options. It complicates
the simple model in a weird way.
I cannot know without the SOW, but this has fingerprints of a
mixed concept mess. There was probably no reason the contract
could not have been structured to include the PM, whatever they
were doing, in tailored task descriptions to keep it simple. For
example, "network support with on-site manager" vice
"network support with off-site manager" - my view of
"network support without manager" is already clearly
skeptical.
The very fact this came to our attention as it did indicates
things were fouled up to some degree. If they didn't mean PM in
the usual sense they apparently didn't make that clear to the
contractors either. My gut feeling from the facts in the
decision is that they ventured into a poorly thought out means
of offering choice, began mixing fixed price concepts with
others, got unexpected results (NSP/$0.00), picked out one to
challenge for some reason and came to our attention. When the
concept has logic holes things tend to come apart. It is worth
time doing self challenge to close such holes before going on
the street. Rarely will every hole be closed, but damage is
less.
By
Anonymous
on Tuesday, May 01, 2001 - 03:01 pm:
You guys seem to be assuming that services procured under the
contract were to be provided only in conjunction with a hardware
purchase. But that is not necessarily the case. Under a GWACs
type contract it's possible that services could be procured
separately.
By
ex-fed
on Tuesday, May 01, 2001 - 08:13 pm:
How did you reach that assumption? I've certainly made no
such assumption and have not been struck by anyone else doing
so.
By
Anonymous
on Tuesday, May 01, 2001 - 08:48 pm:
Well, I'm not sure how I reached that assumption.
I'm also not sure what the heck you're talking about.
The program manager line item is there just to establish a
resource price. It enables the parties to price the cost of
project management for each task, as required. Some tasks may
need more project management than others and including a line
item for project managers on an hourly, daily and weekly basis
lets the parties determine and price the management requirements
for each task on an ad hoc basis. On a IDIQ task order contract
the hourly rate for a labor category usually reflects the
general nature of the work that type of person does and
qualifications requirements in the contract, but it does not
reflect any specific job, and the person in that labor category
may be paid more or less than another person in that same labor
category working on a different project.
The pricing arrangement in the contract described in the case is
standard practice on such contracts. In fact, that pricing
arrangement has been in use for at least forty years. I'm really
mystified by your reaction to it, especially the part about it
being "odd" and "bizarre." It's nothing of
the kind.
And what is the business about "unmanaged"? Where did
that idea come from? I have read this entire thread and the case
in question and I simply cannot understand where that line of
thinking comes from, and I have tried hard to understand,
thinking that I've been missing something. Now I think that you
misunderstand this kind of contract, which, based on the
description in the GAO decision is just about as common as dirt
these days.
Forgive me for sounding frustrated. I don't mean to be rude. But
I just don't understand why you are so bothered.
By
anon4
on Wednesday, May 02, 2001 - 08:13 am:
Anonymous,
I don't know that I would agree that pricing Program Manager
support with a $0.00 hourly rate is a standard practice. I have
worked in procurement for 17-18 years (Army (Army Materiel
Command), Navy (NAVFAC and NAVSEA) Army Corp of Engineers and
two civilian agencies)and have not seen it as a common practice.
Although I don't know that I am adverse to it not being priced
and included in the burdened rate. I do agree with the decision
rendered in this case and see some logic in accepting the $0.00
CLIN price.
By
Eric
Ottinger on Wednesday, May 02, 2001 - 09:15 am:
Anon4,
The court said that it was acceptable propose to lower than a
realistic cost. This is true. However, I would not take that
logic all the way to zero.
In any case, the offeror didn’t really propose zero. The
offeror included the “Program Manager” cost as 13 percentage
points of overhead applied to the other rates.
Bidding zero is not a standard practice. However, it is not
uncommon to include supervision in overhead. I don’t think
this is a particularly complicated issue. The “Program
Manager” is the on-site supervisor. The PCO wanted an
assurance that this person would show up for work at the site,
even though this person was being charged indirect rather than
direct. The PCO got these assurances.
In any case, in a multiple award situation, the offeror would be
foolish to antagonize the customer by not providing the promised
on-site supervision.
Eric
By
Anonymous
on Wednesday, May 02, 2001 - 09:22 am:
Anon4,
No, $0.00 is not standard, I agree. But that was just a
company's unorthodox (though not entirely unheard of) bidding
strategy, and I, too, agree with the court decision. Anyway,
that's not what Ex Fed has been complaining about.
What bother's Ex Fed, and what I'm talking about, is the
inclusion of a CLIN for program manager, which ex fed considers
"odd to bizarre." Here's his first reaction to it:
"Let me get this straight. There will be a menu of options
forming a program of different composition and flavor for
various ordering agencies. Some will order the program with and
some without a program manager. Interesting.
I would think the management function was a necessity to some
degree regardless of whether the full or partial menu was
ordered. "I'll have the Caesar salad, surf and turf, baked
potato, asparagus without management please." The logic
still escapes me.
On a FFP it would seem to me the sensible thing is to include
"management" among the non-directs with every order
paying a share according to consumption. Even varied CLIN
difficulty levels could be covered by varied rates on the
deliverable CLINS. That avoids violation of the KISS principle
-- one FFP objective I believe."
It looks to me that his complaint about unmanaged work is based
entirely on the fact that the contract includes a separate CLIN
and rates for a program manager. That doesn't make sense to him.
He wants management to be included as an overhead cost in every
other hourly labor rate. But that is not how task order
contracts are usually priced because it is not sufficiently
flexible to encompass a wide range of tasks, so I don't see it
as a valid reason to take the contracting officer to task for
violating "principles" and to call the contract
"odd to bizarre."
Go to http://www.fss.gsa.gov,
look at the Schedules E-Library for FSC Group 70, and check out
the SIN for services. Look at the contractors' prices. They
include hourly rates for program managers. Look at any number of
task order contracts for services and you'll see that they
include hourly rates for program managers. It's done that way so
the parties can tailor each task order to suit their needs. I
don't know why anyone would consider that practice to be odd
unless they were not familiar with it. But with thirty years of
experience as in contracting, I can tell you that there is
nothing odd about it.
Again, I apologize to Ex Fed for sounding so frustrated with
him, but I've been reading him trashing the CO for several days
now and I still don't understand why he considers what the CO
did to be odd or bizarre.
By
Anonymous
on Wednesday, May 02, 2001 - 09:37 am:
Eric:
My issue with Ex Fed is not about the $0.00 bid and that doesn't
seem to be what he is complaining about. His complaint appears
to me to be based on the mere fact that the contract included a
separate CLIN for a program manager, which IS standard practice.
The Army had a very specific reason for including a separate
CLIN for a program manager -- to give ordering agencies
flexibility to price task orders encompassing a wide range of
complexity and difficulty. As the GAO said in its first
paragraph, the contract was designed to meet
"worldwide" requirements of government agencies for IT
services. Including management as an overhead rate would have
been a one-size-fits-all solution that would have been
inappropriate in this case.
If there's one thing that government technical people worry
about it's program management. It's an obsession with them. They
want to see it in the contractor's proposal; they want to know
how much of it they're going to get; they want to know who
they're going to get; and they want to know how dedicated he or
she is going to be. You may not agree with their concern, but
there it is. Including management as an overhead item in the
hourly rates for other labor categories doesn't provide enough
visibility into a contractor's plans for a specific task order
and won't cut it.
By
ex-fed
on Wednesday, May 02, 2001 - 09:59 am:
Anonymous,
The description of this contract being "just about as
common as dirt these days" does not impress me. It
discourages me if you are speaking of the exact slice and dice
used in the PM instance. I don't have too much problem with what
you described in your first response and you seem to think it
describes the contract at hand. Therefore, you and perhaps
others may have missed what is bothering me.
From the decision: "(3) Pricing for any CLIN/SLIN must
stand alone, and not be dependent upon the authorization of any
other CLIN/SLIN, Id. at 46" and "Among other issues,
FDC argued that GTSI's pricing approach for the project
manager CLINs" [my emphasis]. Not project manager
rates. Not a line item within a CLIN. Not even a linked and
dependent CLIN, but project manager CLINs that must
not be dependent on any other CLIN. To me this reads
"project manager CLINs" that "must stand alone,
and not be dependent upon the authorization of any other CLIN/SLIN."
Please explain to me how "project manager CLINs" that
"must stand alone, and not be dependent upon the
authorization of any other CLIN/SLIN" tie directly to
these supposedly well defined tasks they are dependent
upon? This is like a shipping CLIN that "must stand alone,
and not be dependent upon" what or even if something is
shipped. In fact, this wording appears to allow a nonsensical
"unmanaged" project or project management
without project! It is the logical structuring of CLINs here
that bothers me.
I agree with you that the PM's work varys depending on the
nature of the work managed. I also generally agree that
"tasks may need more project management than others and
including a line item for project managers on an hourly, daily
and weekly basis lets the parties determine and price the
management requirements for each task on an ad hoc basis."
I'd strike the "ad hoc." We would hope each CLIN's
tasking is predetermined and well defined for a fixed price
contract. I would get even more agitated to find highly varied
or undefined tasking is involved here. With task definition well
within a commercial analogue, FFP I would think the contractor
could define PM with acceptable risks. If they can't it is their
risk anyway.
I would have no problem if each tasking CLIN had an
integrated PM price/description line defining the intensity and
expertise of PM appropriate for the CLIN's tasking. That
is a pricing arrangement subject to evaluation for exactly those
terms needed: intensity and level appropriate for drop shipping
hardware, software or other COTS items and that appropriate for
on-site network support. That is not what is being described in
the decision and it must have involved some look at the SOW so I
doubt it is off on some wild tangent even if we cannot be
absolutely certain.
Project management inclusion within the CLIN is something
like what I suggested way up in the thread with a step further.
This appears to be for essentially commercial services so I
questioned whether it is really necessary to get into the level
of detail of carving out the PM when there is some real
justification to consider it a sort of overhead to the actual
tasking. My example of airline tickets involves a much more
complex backdrop of labor. Sensible market research and shopping
is done continually with their rolled up bottom line.
The question of the contractor's judgment in allocating
management to tasking may be interesting, but here may well be
complicating simplicity. There is adequate fodder for good
market research and a sound sense of the parameters. I have no
real problem if the government has a solid reason to complicate
its shopping this way. I suspect it does not and is just being
nosey and operating on its "audit" instinct.
I really do hope nobody would really try to take advantage of
"project manager CLINs" that "must stand alone,
and not be dependent upon the authorization of any other CLIN/SLIN"
and actually order "unmanaged." It has been hinted at
by others in the thread and from the black letter decision is
apparently possible. In my experience, to paraphrase and old
Army dictum, what can happen will happen. This is particularly
applicable when the scope of misunderstanding covers
"Ordering from the contract(s) was to be permitted by any
federal agency, including foreign military sales customers"
-- in other words nearly the world.
You are right, the $0.00 bit doesn't bother me much at all in
comparison. At a fine technical level NSP and $0.00 are not the
same, yet I'd guess quite a few might consider that another way
of saying the price is not broken out separately. In this case
I'd consider it merely a poor choice of wording.
By
Anonymous
on Wednesday, May 02, 2001 - 10:48 am:
Ex Fed,
Two questions:
Do you believe that the contract CLINs are for types of
services, like a "job order" contract, with one CLIN
for program manager?
Would you think differently if you knew that the CLINs for
services were labor category CLINs and not task CLINs?
By
ex-fed
on Wednesday, May 02, 2001 - 12:59 pm:
Anonymous,
To your Q1:
In part. Of the tasks listed in the decision
commercial-off-the-shelf servers, workstations, operating
systems, compilers, software applications, peripherals, leasing,
documentation, consumables and system upgrades probably fit a
"job order" model. They could be drop shipments, but
they could include some level of service. Numbers within the
packages would of course vary.
Local and wide area networking, engineering and support
services, managed environment support, maintenance and training
are likely not. This is one of the areas the decision does not
make clear, but I would expect not. These services should be a
clearly defined package in terms of tasking, but the labor
levels (the numbers again) would depend on task volume.
That is I presume why the requirement of "(4)" listed
within the description section L of the RFP is stated as it is.
Your Q2:
No. The service tasking must be well and clearly defined to meet
FFP requirements. The labor types must fit the task to make
sense. Some arrangement for variance on mix and certainly
numbers could be made for scale. The management of the tasking
complexity and labor skill level should then be reasonable clear
from the tightly defined portion. The intensity, or volume, of
management must then be tailored to the scale of labor required.
There is coupling of manager type and task type.
Management for "engineering and support services, managed
environment support" may quite different than for
"training." I rather doubt a poor selection under
"stand alone, and not be dependent upon the authorization
of any other CLIN/SLIN" of an engineering manager for
training or the reverse would benefit anyone.
Now, one of the areas I cannot know is whether there were
conditions not mentioned in the decision that mitigated that
apparent unlimited free choice on project management. I'd hope
so. Without the SOW and particularly ordering instructions to
agencies we cannot know precisely. I'm of little faith here
though.
I'd also hope those ordering would simply have more sense than
to order the equivalent of apple pie with soy sauce. My
experience tells me someone out there among all agencies and
military assistance countries would try.
I believe the Army here had a logical flaw that led to immediate
problems on the responses. The fact everyone came back with
"NSP" or that "$0.00" that was probably an
attempt at doing so indicates to me the contractors also
scratched their heads. The Army should have remembered its
dictum: "An order that can be misunderstood will be
misunderstood" and avoided both this case and the potential
weird customer who wanted that apple pie soaked in soy sauce
equivalent in CLIN matches.
By
Anonymous
on Wednesday, May 02, 2001 - 01:38 pm:
Ex Fed:
It is clear to me that you simply don't understand the kind of
contract that the Army awarded. All I can say to you is that
what the Army did was quite orthodox, made perfect sense, and
didn't violate any principles.
I'm signing off. Take care of yourself and best wishes.
By
ex-fed
on Wednesday, May 02, 2001 - 02:18 pm:
Anonymous,
I understand only what is in the decision, that it was a
FFP-IDIQ and it ran into trouble. I'd be happy to have the
secret of the mix and match logic made clear.
No, I don't understand why that degree of "freedom"
was allowed and think it nonsense. You haven't taken me up on
clarifying why it might make sense despite my provision of the
explicit example from the decision. I will also waste no more
finger tapping in response to unsubstantiated "this is the
way it is done." I've seen entirely too much of "the
way it is done" that is wasteful, illogical,
counterproductive and any number of other such descriptions.
By
anon4
on Thursday, May 03, 2001 - 07:50 am:
Dear Ex-Fed,
Believe it or not I understand the significance of what you are
saying with the post of 9:59 am of May 2 concerning the
dependence of that CLIN/SLIN in relationship to other CLINs.
Anon4
By
ex-fed
on Thursday, May 03, 2001 - 12:17 pm:
anon4,
I think most will "get it" if they really think about
the impact of severing real dependencies.
Going back to my technology development days one strives to
minimize dependencies in technology, schedule and the contract.
In IT development a good rule is to minimize and simplify
interfaces to the greatest reasonable degree, another
form of that rule. So many problems in all these areas, in fact
any job, are caused by unrealistic or unnecessary dependencies.
A thorough scrub at the planning and paper stage bears real
reward during implementation. In many cases that is the
difference between success or failure.
Conversely, severing an actual dependency can and quite often
will give "weird and bizarre" results. As far as I can
see from the information in the decision the Army apparently
severed a real dependency between management and what is
managed.
Skilled IT people could, with care, cure the situation for an
actual delivery. Both my experience and research on the subject
tell me that such skill is not really all that common. With the
customer scope of this thing I think effort is needed to
mitigate risk of the unskilled creating nasty accidents.
As one example, I'd feel a bit better to find that even a half
step toward linking was made:
CLIN XXX1: Training (units)
CLIN XXX2: Training Project Management (units). CLIN XXX2 may
only be ordered with CLIN XXX1.
That might not solve the "unmanaged" issue, but it
would prevent the "apple pie with soy sauce" issue of
training managed by a network maintenance manager without a clue
of training issues or a sole order of management with nothing to
manage. As long as "must stand alone, and not be
dependent upon the authorization of any other CLIN/SLIN"
governs (we can only hope mitigation is elsewhere in the
contract) there is a problem.
Unfortunately we have these contracts churned out somewhat
routinely by people who really don't have the experience in IT
(or other) systems work or are too rushed to do the needed
analysis. Too many remind me of an old Far Side cartoon where a
sheriff looks out upon a pile of men, horses, tack and tells his
deputy something like "Smith, a posse requires
organization." "Let's throw together a wide scope IDIQ"
seems to be in vogue. Oversight is overdue.
By the way, Anonymous, avoiding the requested explanation or
pointing me to something I've missed by "you simply don't
understand the kind of contract" is first a cheap way out
and second an interesting assumption. I'd still like to have
benefit of your secret knowledge explaining how "project
manager CLINs" that "must stand alone, and not be
dependent upon the authorization of any other CLIN/SLIN"
tie directly to these supposedly well defined tasks they are
dependent upon?
By
Anonymous
on Thursday, May 03, 2001 - 01:56 pm:
Ex-Fed:
There's no secret to it. The CLINs aren't for tasks, they're for
labor hours:
CLIN 0001 Labor
0001AA Program Manager
0001AB Systems Engineer
0001AC Senior Programmer
0001AD Journeyman Programmer
0001AE Network Analyst
and so forth. The labor categories reflect the kinds of skills
needed to perform the kinds of work described in the SOW.
When an agency has a task it sends the contractor a draft SOW
and asks which labor categories are needed to do the job,
including program manager. The contractor then proposes the
labor mix and the appropriate level of management. The parties
then negotiate to agreement on labor mix before the CO issues
the task order.
This arrangement is extremely common and has been common since
the late 50s when its use began in DOD weapons work. Its great
virtue is flexibility. By setting up the CLINs as labor
categories you can use the contract for a an almost infinitely
wide range of tasks. In order to provide that kind of
flexibility with task CLINs you would have to have a CLIN list a
mile long.
The CLINs in this arrangement are required to be independent of
one another because in order to provide tasking flexibility you
need to be able to buy from them on an ad hoc basis. For
example, I might want to buy 20 hours of program manager time to
help me plan a task without having to buy the labor needed to
actually hire the contractor to do the work.
Now go to http://www.fss.gsa.gov
and then click on the schedules library. Go to Group 70, Special
Item No. (SIN) 132 51 and get the list of contractors. Click on
the very first contractor on the list and then click on the link
to its prices for on site and off site work. You will find
prices for Sr. Program Manager @ $79.19/hr, Sr. Business Analyst
@ $88.10/hr, and so on. Check out other contractors as well.
Go to Fed Bus Ops and search for RFPs for IDIQ task order
contracts for technical services and look at how they're priced.
Pricing management as an overhead cost included in each hour of
labor would apply the same level of management to every such
hour of labor, regardless of the nature of the task. That's a
one-size-fits-all solution that's inappropriate given the
objectives of such a contract.
Everybody in this business must be stupid except you.
By
ex-fed
on Thursday, May 03, 2001 - 02:49 pm:
Anonymous,
Thanks for the backhanded compliment about me being so smart,
but it is another unfounded assumption on your part.
I'm well aware of the structure you use as an attempted answer,
have dealt with it and generally approve of the arrangement when
reasonably structured. It isn't uncommon and it works.
One little problem. Your example of CLIN 0001 isn't what is
described in the decision. It is roughly what I've already said
I have no real problem with such structure as it links
management appropriately with labor.
The decision is clear on independent project management CLINs,
not sub-CLINs, apparently covering a very varied grab bag of
deliverables, both things and services. The fact the decision
uses the plural in project management options does give some
hope there is recognition of varied management requirements. So
far it is only a dim hope.
Your CLIN 0001 involves similar labor types. Your CLIN 0001
could possibly fit the engineering support of the contract at
hand and I would not have much problem with the arrangement. It
could even be reasonably expanded to fit a number of the
technical service categories. If you have information that the
contract being discussed uses such structure much of my concern
vanishes. What you describe is not unreasonable, but it does not
address the specifics of the contract being described in the
decision.
What is described are "CLINs [plural] that required hourly,
daily, weekly, monthly, and yearly rates for a program
manager" and not your management sub-CLINs within
appropriate labor/task groups. Then it states "Pricing for
any CLIN/SLIN must stand alone, and not be dependent upon the
authorization of any other CLIN/SLIN" to apparently
completely sever the reasonable linking of management with like
labor/tasking.
It is possible this is all about semantics, but until new
evidence is presented I can only deal with what the decision
states. I presume they are competent to state the situation
clearly and precisely. No snide comment, but I suggest you read
again closely, think a bit on the specific rather than general
and then if you come back have something that addresses the
explicit issue, not some general example. I'm really not
interested in discussing the tangential with you further.
By
Anonymous
on Thursday, May 03, 2001 - 04:17 pm:
Ex-Fed:
I have read the decision and you are seeing things in it that I
don't. I don't think we can sort it out between us, since we've
both read the same words and come to different conclusions.
Since you "generally approve" of the pricing
arrangement that I've described, I don't have anything more to
discuss with you, because I presume that means you do not think
that arrangement to be "odd to bizarre."
If the contract is priced the way that you describe, then I
would want to know more about the reasoning of the people who
designed it before joining you in trashing my colleagues.
By
Anonymous
on Thursday, May 03, 2001 - 06:10 pm:
Ex Fed:
I have looked at the RFP schedule. You can look at it, too. I
found it by searching the CBD archives for RFP No.
DAAB07-00-R-H254, which is the number given in the GAO decision.
I found the synopsis with a web link to the solicitation. The
link takes you to an Army business page. Search in the CECOM
solicition archive until you find it. You can find the complete
documentary history of the solicitation. I downloaded the entire
RFP in a zipped file, then unzipped it and printed out Section
B, which is a 24 page long Excel spreadsheet.
There are 52 CLINs and hundreds of SUBCLINs. CLINs 0001 through
0035 are for hardware. There are no CLINs 0036-0039. CLINs 0040
and 00041 are for "SERVICES" and consist of SUBCLINs
0040AA through 0040WQ and 0041AA through 0041GQ. The remaining
CLINs are for training, priced on a per student basis, travel
and ODC.
Within CLIN 0040, SUBCLINs 0040AA though 0040AD are described as
"system configuration and integration," "physical
site analysis," "installation and relocation service,'
and "high availability configuration." An accompanying
note in the RFP says: "CLINs 0040AA thru 0040AD will be
used as a rollup of labor categories and hours needed to perform
these functions. Individual Kos will negotiate this [sic] items.
These CLINs will NOT BE EVALUATED in the Price Model."
All of the remaining SUBCLINs are labor categories,
beginning with 0040BA through 0040BQ for "program
manager," and continuing with SUBCLINs for "network
engineer," security engineer,"
"database/application programmer," "managed
system engineer," "system engineer,"
"database engineer," "database/application
programmer," "system administrator,"
"network administrator," etc.
Gee. You must have read that GAO decision wrong. Check it out.
By
ex-fed
on Friday, May 04, 2001 - 10:49 am:
As for your last little closing comment, no, I did not
misread the decision. The words are there for all to read at the
initial link of this discussion. With the thought of "could
I have" I checked again. I won't consume WIFCON space with
a long quote, but they are in "Background," numbered
items 1-4 and the next paragraph.
I'm sorry you seem to be taking this personally. I'd expect
we've both seen some pretty odd and trouble prone contract
structure. It happens. It gets to GAO and the courts and it
sometimes really goes public. It is not "trashing"
people to point out problems in these things. It can be lessons
learned. Illogical or poorly considered CLIN structure has
caused difficulty in many contracts including one I had to deal
with from the consumer end that would be amusing if it hadn't
been so pitiful and expensive.
I've said all along that we had knowledge on this limited to the
CG decision. I'm still not sure you ever took time to think upon
the apparent issue of severance that I raised based on
the decision's wording. Now you are countering with data. Good
work. My confidence level rises though I have not been able to
get to the data yet. Your CLIN examples seemed sound enough and
I'm reassured that you seem to think the difficulty is not in
the contract.
I've tried to recreate your path to the document and get
passwords and other blocks. Using a direct attempt through
http://www.monmouth.army.mil/cecom/ac/ac.html and searching on
"DAAB07-00-R-H254" I get a meaningless "329
documents found" with a long identical list. I'd be
interested in looking at the actual structure, but lack of .mil
or .gov access may restrain me. If you have a direct link I'd
like to try it.
In any case, I'll presume you have studied the thing. I'm not
quite sure what to make of "All of the remaining SUBCLINs
are labor categories, beginning with 0040BA through 0040BQ for
"program manager," and continuing with SUBCLINs for
"network engineer," security engineer,"
"database/application programmer," "managed
system engineer," "system engineer,"
"database engineer," "database/application
programmer," "system administrator,"
"network administrator," etc."
Assuming these are all options for the contractor to
propose against a given SOW and there are adequate protections
against some of that galaxy of potential ordering entities
playing foolish games with the proposed structure my confidence
level goes up notches. If not, are 0040BA through 0040BQ for
program manager tied somehow to the labor they manage? What are
the safeguards?
By
Anonymous
on Friday, May 04, 2001 - 11:52 am:
Ex-Fed:
I'm sorry about getting angry with you, but I want to tell you
why I did.
You have been extremely critical of a CO on the basis of the
limited information in the GAO decision and unfounded
conclusions drawn from that information. The procurement is
question was very complex and difficult and the CO who
did it--Marcia Easton of CECOM, assisted by Michael Doelling--did
an excellent job under the circumstances, even showing that they
were smarter than the HQ AMC lawyers.
I believed you were drawing unfounded conclusions about the RFP
based on the GAO decision before I ever saw the RFP, because
based on extensive research I know that most agencies price such
contracts on the basis of labor categories, not tasks, and I
know why they do it.
You started to get to me with your comment to Rob Bristow on
April 27 at 1145, in which you wondered how he could praise the
CO for "mistaking the principle" and
"meddling." The CO made no such mistake and was not
meddling. His praise was well-merited.
You then followed with your "unmanaged" line of
discussion, in which you failed to consider the possibility that
"program manager" simply described a person with
certain knowledge and skill, someone who might be hired to plan
a project instead of to manage one and in which you showed that
didn't understand the operation of the most common type of task
order contract. You ignored a different Anonymous's and Anon
Zed's attempts to explain to you what the contract was really
about. You described the CO's work as "odd to
bizarre." That comment really pissed me off.
I understand what you've said about the separation of management
from work. The point is that your analysis does not apply to the
facts at hand concerning the RFP. Had you made a more general
point without applying your analysis to the RFP in question I
would not have considered it controversial.
I would not have joined this discussion, much less become angry
with you, had you simply discussed the pros and cons of
different pricing strategies without being so damning of the CO.
I don't think COs are perfect; in fact, I believe that there are
many incompetent COs. However, when you are talking about
specific work done by real human beings, I suggest that you
either do your homework before criticising them or that you be
more circumspect in your criticism.
It was not my responsibility, or anyone else's, to "counter
with data." It's your responsibility to get data before you
open fire on people.
To find the RFP go to http://www.abop.monmouth.army.mil and then
search the CECOM award archive for the RFP number.
By
Anonymous
on Friday, May 04, 2001 - 01:48 pm:
The correct web address is http://abop.monmouth.army.mil.
You have to drop the "www".
By
ex-fed
on Wednesday, May 09, 2001 - 03:01 pm:
Anonymous,
The address you've given is the one that gave me the
"search results for "DAAB07-00-R-H254: 329 documents
found" that result in a password requirement and
"Error 401- You are not authorized to perform this
operation" upon clicking. I've tried other approaches and
none worked. As an "ex-fed" I apparently do not have
access to this web document.
I can somewhat understand your irritation and I'll accept that I
was perhaps too harsh on the contracting officer. Protests
happen, sustained protest happen much more rarely. When they do
there is often a problem that could have been avoided. On the
other hand I do not presume CG decisions contain random,
material errors. I do not think the conclusion I drew from
information in the decision was "unfounded," but that
is opinion.
You have stated your views and I understand how you got to them.
I cannot look at the data and am also losing interest in going
round this matter. I'll take your word about the general
reasonableness and high quality of the contract with a
reservation. My issue involves project (program) management in
terms of that managing the delivering contract. You seem
to be speaking of project management as a i{deliverable labor
category}. I am familiar with deliverable labor to assist the
government in its project management and this type contract.
The decision did not define which "project management"
was involved. I did conclude it was management of the delivering
contract for a reason. The contractors quoted "NSP" or
the odd "$0.00" for management. That is consistent
with internal management for the delivering contract. It
is inconsistent for deliverable project management to assist the
government in its own project management tasks. That makes no
more sense than "NSP" for a programmer, network
analyst or any other labor category. Perhaps the only way I'd
expect to see this would be within a task price where the
solicitation for a FFP on the task listed required labor
and for some reason provided a line for labor category price.
Then my comments about unnecessary inquiry into the FFP become
effective.
If the descriptions of the project management here fall
exclusively under deliverable service hours to the government
then my severance issue is null. If they are for management of
the delivering contract I stand by my criticism of severing
essential linkage.
In any case our positions are clear and there is no reason to
beat this thing any more.
By
Eric
Ottinger on Thursday, May 10, 2001 - 06:48 pm:
Ex-fed,
Try this.
http://abop.monmouth.army.mil/busopor27.nsf/Solicitation+By+Number?
OpenView&Startkey=DAAB07-00-R-H254&expandview
I works from my home computer. I don't think "mil" is
the issue.
Anon,
From the little that I saw in the case, I would say Ms. Easton
did an excellent job.
All,
I think we are getting into "blind man and the
elephant" problems because we are reading this though the
lens of our personal experience.
Eric
|