By
randy on Thursday, April 26, 2001 - 02:21 pm:
Is it permissible to show the
weight factors in an RFP. This particular RFP, we wanted to show
the weight. Under the Evaluation Criteria we would put the
weight beside each criteria. Example:
1. Cost (25).
For specific reasons we wanted to insert it in the RFP.
By
Anonymous
on Thursday, April 26, 2001 - 02:40 pm:
randy:
FAR does not prohibit the disclosure of specific factor weights.
Some agency FAR supplements might prohibit such disclosures.
By
anon4 on Friday, April 27, 2001 - 07:43 am:
Randy,
I was wondering, why do you want to assign a weight to COST?
By
joel hoffman on Friday, April 27, 2001 - 08:47 am:
Randy, years ago, the Army FAR
Supplement prohibited disclosing points or weights. That was
rescinded in the early 90's. However, many people still thought
it was prohibited. I don't know of any other agency prohibiting
disclosure. Please note that AFARS has prohibited scoring of
price for as long as I've been involved in RFP's. In order to
assign a "weight" to price, I believe it is necessary to score
price.
I don't know if you work for an Army organization.
Regardless, I do not advocate scoring the price factor.
By the way, about 4 weeks ago, SARDA put out new policy
prohibiting weighting or scoring of factors, period. All
weighting or expression of extent of relative importance of
evaluation factors must now be done with narrative descriptions
(for Army RFP's). Happy Sails! Joel
By
Monty on Monday,
April 30, 2001 - 10:58 pm:
I was looking at a Navy proposal
evaluation recently that did not assign weights to the
evaluation factors. But the way the evaluation scheme worked,
the overall rating for each offerer's proposal was equal to the
rating for the lowest-rated sub-factor in the proposal. After
all the evaluations were completed, all of the proposals were
rated "Unacceptable."
The source selection document--which had to explain which of the
"Unacceptable" proposals was the least-unacceptable--was a kind
of interesting piece of logic.
By
Anonymous
on Tuesday, May 01, 2001 - 08:55 am:
Did'nt DoD,or a component
thereof,just recently issue dicta prohibiting this practice? I
thought I may have read something somewhere.
By
Anon X on Tuesday, May 01, 2001 - 09:19 am:
It is entirely possible for the
least important factor to render to entire proposal
"unacceptable," depending on what unacceptable means.
Say that an RFP describes four factors: offer acceptability,
experience, past performance, and price and says that price is
significantly more important than the nonprice factors and that
offer acceptability is the least important of the nonprice
factors. The RFP also says that an offer is acceptable when the
offeror agrees to the terms of the RFP without exception and
that the Government will evaluate offer acceptability on a pass
or fail basis.
If an offeror takes exception to any material term of the RFP,
then based on GAO case law its offer is "unacceptable" and
ineligible for contract award, even though the RFP said that
offer acceptability was the least important factor.
If all of the offers received are unacceptable and the agency
decides to conduct discussions in order to produce an acceptable
offer at a fair and reasonable price, then when establishing the
competitive range the CO should determine which offers are most
susceptible of being made acceptable, which is another way of
saying which is least unacceptable.
By
joel hoffman on Tuesday, May 01, 2001 - 03:47 pm:
Dear 8:55 anonymous: As stated in
my 27 April post, the Army has prohibited numerical scoring or
weighting of factors. Happy Sails! Joel
By
joel hoffman on Tuesday, May 01, 2001 - 03:53 pm:
To clarify, the Army prohibited
numerical weighting of factors. Relative importance must be
expressed in adjectival terms. Factors must be rated, using an
adjectival or color (based on adjectival description) rating
scheme. It sounds like the example you were referring to used
adjectival weighting and rating schemes. Happy Sails! Joel
By
Eric Ottinger on
Tuesday, May 01, 2001 - 07:00 pm:
Monty and Anon X,
That's interesting.
I am not sure that you can say that anything is "not acceptable"
in a negotiated procurement when it is at least possible that
the deficiency can be fixed after discussions. If you are saying
that a single "red," even under a small evaluation factor, is
enough to justify not selecting an offer, I agree. This is true,
even if the offeror scores numerous points under the remaining
factors. This is a fundamental problem with numerical evaluation
schemes.
Was the Navy saying that the system should be rated based on
it's greatest vulnerability? That would make sense for a system
to be used in combat or some other kind of very hostile
environment.
Eric
By
Anon X on Tuesday, May 01, 2001 - 08:26 pm:
A determination of acceptability
doesn't depend on any numerical scoring technique, or adjectival
or color-coded for that matter. The GAO says that if an offer
fails to conform to a material requirement of an RFP it cannot
be accepted. So it's "unacceptable," whether the deficiency is
correctable or not. If the RFP said that the agency intends to
award without discussions, and if the agency decides to stick to
that course of action, then that's the end of the trail for that
offeror.
If the agency decides to conduct discussions, then the CO has to
decide whether or not the proposal should be included in the
competitive range. That's a judgment call that depends on the
offeror's ranking based on all of the evaluation factors.
I don't know what the Navy's RFP said.
By
Eric B. Ottinger
on Wednesday, May 02, 2001 - 12:00 pm:
Anon X,
DAU -- CON 210; Government Contract Law Course Text; (1999
Edition)
7-12. "The Government’s determination of which proposals are
within the competitive range is to be based on the "cost or
price and the other factors included in the solicitation." 10
U.S.C.2305(b) With the passage of Clinger-Cohen Act, the
Contracting Officer can "limit the number of proposals in the
competitive range to the greatest number that will permit an
efficient competition among the most highly rated proposals"
(FAR 15.306(c)(2)). The new attitude is "when in doubt, leave
out." The competitive range determination can also be amended
and narrowed during discussions after the Government has
notified each offeror of their significant weaknesses and
deficiencies. Excluded offerors do not have to be given the
opportunity to revise their proposals. In general, an agency
determination will not be overturned in the absence of a showing
that the agency has abused its discretion. It should be noted in
this regard that the determination of the competitive range is
not analogous to the determination whether an offer made by
sealed bid is responsive. UNLIKE A NONRESPONSIVE BID, A
NONRESPONSIVE PROPOSAL IS NOT NECESSARILY EXCLUDED FROM
CONSIDERATION; IF IT IS WITHIN THE COMPETITIVE RANGE ON THE
BASIS OF THE GIVEN EVALUATION CRITERIA, THE CONTRACTING OFFICER
MAY ALLOW IT TO BE CLARIFIED OR SUPPLEMENTED TO CONFORM TO THE
SPECIFICATIONS."
Eric
By
Anon X on Wednesday, May 02, 2001 - 12:15 pm:
Why are you quoting that?
The GAO doesn't say that you can't keep an unacceptable proposal
in the competitive range. The GAO says you cannot accept an
unacceptable proposal. If you want to conduct discussions and if
you keep the unacceptable proposal in the competitive range then
you can ask the offeror to fix the proposal and accept it if the
offeror does.
That does not change anything that I've said. If an agency
decides to award without discussions and if the proposal is
unacceptable on the basis of the least important evaluation
factor the proposal is just as dead as if the factor were the
most important factor. If the agency decides to conduct
discussions but decides that the proposal is not within the
competitive range then it is dead then, too.
By
Eric Ottinger on
Wednesday, May 02, 2001 - 01:07 pm:
Anon X,
Definitive responsibility criteria may also be evaluation
factors. That is: The same factor may be used as both a go/no go
factor and as an evaluation factor.
The reverse is not true. Evaluation factors are not definitive
responsibility criteria.
I am not aware of any document called a “Determination of
Acceptability.”
If an offeror has a Red (Unacceptable) for a small evaluation
factor, I believe I can choose to not select that offeror, even
the offeror has more points than any other offeror using a
numerical rating scheme. However, if I do choose to select that
offeror, I am not aware of any policy that would prevent me from
selecting that offeror. It may be that the government has other
ways to obtain the necessary capability, even if the offeror
cannot.
Eric
By
Anon X on Wednesday, May 02, 2001 - 01:32 pm:
Eric:
Are you saying that you believe that evaluation factors other
than definitive responsibility criteria cannot be evaluated on a
pass or fail (go/no go) basis? If that's what you're saying,
please cite a regulation or GAO decision to that effect.
By
Eric Ottinger on
Wednesday, May 02, 2001 - 02:04 pm:
Anon X,
If the factor is evaluated on a pass/fail basis, it is a
definitive responsibility criteria.
That is pretty much the definition of a "definitive evaluation
criteria."
Before I start thrashing GAO decisions, etc., please identify a
source for this "Determination of Acceptability," for the
benefit of our readers.
Eric
By
Anon X on Wednesday, May 02, 2001 - 03:11 pm:
Evaluating something on a pass or
fail basis doesn't make it a definitive responsibility
criterion. Only responsibility-type factors, as described in FAR
9.104 and that go to the question of an offeror's capability to
perform, can be definitive responsibility criteria. See 4 CFR
21.5(c). See also Compro Computer Services, Inc., B-278651, Feb.
23, 1998, in which the GAO said:
"Definitive responsibility criteria are specific and objective
standards, qualitative or quantitative, established by a
contracting agency in a solicitation to measure an offeror's
ability to perform a contract."
An example of a definitive responsibility criterion would be a
requirement that an offeror have no less than five years of
experience doing work of a certain type.
FAR 15.101 permits the evaluation of other than
responsibility-type factors on a pass or fail basis by stating
that agencies may use a combination of LPTA and tradeoff
processes. Also, nothing in FAR or in case law prohibits the
evaluation of nonprice factors other than responsibility-type
factors on a pass or fail basis.
With regard to the determination of acceptability, the CO must
determine whether or not proposals conform to the material terms
and conditions of the solicitation, i.e., whether or not they
are acceptable. That is because the GAO has said:
"In a negotiated procurement, all offerors must be provided a
common basis for preparation and submission of proposals. CNA
Indus. Eng'g, Inc., B-271034, June 7, 1996, 96-1 CPD ¶ 279 at 4.
Any proposal that does not conform to material terms and
conditions of the RFP should be considered unacceptable and may
not form the basis for an award." SWR, Inc., B-284075, Feb. 16,
2000.
If an RFP says that a proposed black box must weigh no more than
15 pounds, pass or fail, that is not a definitive responsibility
criterion because it does not go to the question of whether or
not an offeror is capable of performing, but to the question of
what the Government will accept. If an offeror proposes a black
box that weights 16 pounds its proposal is unacceptable and the
offeror is not eligible for award, even if box weight was the
least important evaluation factor, and no matter whether you
score it as "unacceptable," 0 points, or Red.
Some RFPs expressly state that the agency will make a
determination of acceptability. In Matrix General, B-282192,
June 10, 1999, a Dept. of Interior case, the GAO described an
RFP that expressly stated that the agency would make a
determination of acceptability:
"The RFP stated that award would be made to the offeror whose
offer represents the best value to the government on the basis
of (1) the merits of the offer and (2) the offeror's capability.
RFP § M.1. The RFP stated that the agency would determine the
acceptability of each offer on a pass/fail basis and that an
offer is acceptable when it manifests the offeror's assent,
without exception, to the terms and conditions of the RFP. RFP §
M.2.a."
The GAO described another such RFP in Systems Integration and
Research, Inc.; Presearch, Inc., February 16, 1999, a Navy case:
"Offerors were instructed to submit proposals in four separate
volumes: offer (volume I); written capability information
(volume II); supporting cost data (volume III); and oral
presentation (volume IV). Id. § L-3. Section M of the RFP stated
that the agency would first determine the acceptability of each
offer on a pass/fail basis."
But whether the RFP expressly says so or not the CO must
determine that a proposal is acceptable before selecting it for
award. Failure to do so can result in a sustained protest. There
have been three such sustained protests already this year.
I hope this makes my position clear to you and that you'll
agree. But if it doesn't or you don't, then we can disagree and
you can debate it with somebody else.
By
Eric Ottinger on
Thursday, May 03, 2001 - 06:40 pm:
Anon,
The reader can sense my frustration when I start resorting to
large reference books. Take a look at "The Government Contracts
Reference Book," Second Edition, Nash, Schooner and O'Brien.
"RESPONSIVENESS An objective, nondiscretionary determination by
the contracting officer … that a bid conforms in all material
respects to the IFB in order to be considered for award. … The
concept of responsiveness does not apply to procurements by
negotiation. …"
In the cases that you cite, the Comp. Gen. sustained the protest
because the agency relaxed a requirement in the solicitation.
CNA Industrial Engineering, Inc., No. B-271034., June 7, 1996
"It is a fundamental rule of competitive procurement that all
offerors be provided a common basis for submission of proposals.
Container Prods. Corp., B-255883, Apr. 13, 1994, 94-1 CPD 255.
When an agency relaxes its requirements, either before or after
receipt of proposals, it must issue a written amendment to
notify all offerors of the changed requirements. Id. We will
sustain a protest where an agency, without issuing a written
amendment, relaxes an RFP specification to the protester's
possible prejudice (e.g., where the protester would have altered
its proposal to its competitive advantage had it been given the
opportunity to respond to the altered requirements)."
This is not the same thing as determining that the contract per
se was not valid (due to some defect in the "acceptance"
process). "If, after evaluating the revised proposals, … the
evaluation results in a decision in favor of GI, the award to GI
may stand." Otherwise the contract should be terminated, which
clearly implies that there is a valid contract to be terminated.
The requirement relaxed in CNA was in Appendix K and restated in
the preproposal conference Q's and A's. Appendix K is a long way
from Section M.
There are numerous formal determinations required by the FAR and
DFARS. However, there is nothing termed a "Determination of
Acceptability." The reader can go to the AF FARSITE and plug
"Determination of Acceptability" into the search, as I did, to
verify this.
Also, I put "Determination of Acceptability" into the CCH search
and got 19 hits. It is clear that most of these refer to a
determination of technical acceptability. All of these hits are
cases; the phrase is never used in a policy document.
In Matrix General, Inc., B-282192, "The RFP stated that the
agency would determine the acceptability of each offer on a
pass/fail basis and that an offer is acceptable when it
manifests the offeror's assent, without exception, to the terms
and conditions of the RFP." This clearly a different issue and
nothing to do with technical acceptability.
You are correct regarding LPTA. I should have included Low Price
Technically Acceptable under the heading of go/no go factors
Definitive responsibility factors are "specific and objective
standards, qualitative or quantitative, established by a
contracting agency in a solicitation to measure an offeror's
ability to perform a contract." (AT&T Corporation, Comptroller
General Decision , No. B-260447.4, March 4, 1996) I am having a
very hard time conceptualizing a go/no go evaluation factor that
doesn't fit that description. Perhaps more imaginative minds
could enlighten me.
As a practical matter the PCO must do a careful review of the
proposal to be sure that it is responsive. We use a checklist
and do this immediately after the proposals are opened. I looked
for a section in the FAR which states that this must be done. I
couldn't find it. Maybe I didn't look hard enough. Maybe this is
taken for granted. In any case, if you wish to say that there
should be something in writing to establish that the proposal
has been reviewed and that the proposal is fully responsive, I
would not disagree with that.
By the way--
FAR 15.101 does not explicitly permit "the evaluation of other
than responsibility-type factors on a pass or fail basis by
stating that agencies may use a combination of LPTA and tradeoff
processes."
FAR 15.101 states "An agency can obtain best value in negotiated
acquisitions by using any one or a combination of source
selection approaches." The idea that this should be interpreted
to mean that LPTA and Tradeoff processes can be combined is the
opinion of Cibinic and Nash.
I don't really agree or disagree. However, I question whether a
"go/no go" factor, for which a "no go" immediately eliminates
the offeror from consideration fits anywhere in an order of
importance. "Trade off" evaluation factors must fit somewhere in
a stated order of importance. Accordingly, I question whether
"trade off" factors mix with "go/no go" factors.
Eric
By
Ron Vogt on
Thursday, May 03, 2001 - 07:44 pm:
Eric, I think you are using
"definitive responsibility factors" and "go/no go evaluation
factors" interchangeably. They are not always the same.
"Responsibility" encompasses business factors, such as financial
resources, production line capability to handle the contract,
satisfactory record of integrity, necessary accounting and
operational controls, etc. "Responsiveness" means conforming to
the requirements of the IFB, and usually refers to the technical
requirements, i.e., are you offering the exact item asked for?
In other words, ability to perform, and providing the requested
item, are not the same thing.
Although I have never examined the issue, My guess is that go/no
go evaluation factors can be both responsibility and
responsiveness factors. Furthermore, it is easy to come up with
a go/no go factor that tests responsiveness, not responsibility.
For example, an item must weigh under x pounds. This can be
measured on a go/no go basis, and is certainly a responsiveness
factor, not responsibility.
By
Anonymous
on Thursday, May 03, 2001 - 08:00 pm:
Eric,
If an RFP specifies that the proposed weight of an item must be
10 pounds or less, and if an offeror takes exception to that
requirement and proposes an item that weights 12 pounds, would
you say that the consequence is that the offeror is "nonresponsible"?
Do you believe that the CO could award the contract to that
offeror without first amending the RFP and allowing the other
offerors to revise their proposals?
And if the CO can't award the contract to the offeror because
the proposal does not conform to a material requirement of the
RFP and the GAO would nail him if he did, then isn't it true
that the CO cannot "accept" the offer and that it is, therefore,
"unacceptable"?
Does the type of scoring system that the agency is
using--adjectival, numerical, color coding--make any difference
in that regard?
I'm going TDY now and won't have internet access for a month (OOTW),
so I guess I have to drop out now.
Have fun everybody.
By
joel hoffman on Friday, May 04, 2001 - 01:00 pm:
As stated above, the term
"non-responsive", as defined with respect to an IFB, is not
applicable per se to negotiated procurement, for various
reasons.
I prefer to use the term "non-conforming". Yes, go/no-go factors
and criteria are applicable to much more than responsibility
type factors (those related to the ability to perform or
"performance capability").
We also use go/no-go criteria to evaluate factors which are
necessary to determine whether the offeror understands the scope
of work and will comply with various technical criteria.
Go/no-go is appropriate when there is little or no expected
difference in either the industry capability or the technical
approach to a specified need.
We include a statement in the "basis of award" criteria that
award will be made to a conforming offer from a responsible
offeror. We also define what constitutes conformance in the RFP.
Happy Sails! Joel
By
Eric Ottinger on
Monday, May 07, 2001 - 08:34 pm:
Joel,
Thanks.
Just a few points for discussion.
· I believe that a red under any factor, even a small evaluation
factor may be a de facto "no go/don't select" even if the
offeror has the highest rating on all of the other factors.
· pass/fail factors may be "definitive responsibility [or
performance] factors" but it may make sense to rate some
evaluation factors on a pass/fail basis where it is not worth
the effort to do blue/green/yellow/red. A fail would not put the
offer out of the competition but it would raise a warning flag.
Is this what you had in mind?
· Responsibility and qualification issues are all addressed
under Section 9 in the FAR. This grouping may be more convention
than logic.
Anon,
It is a common observation that every source selection has a
flaw in it somewhere. If nobody protests, nobody notices. We
sign the contract and the contract is a valid contract. If there
is a protest, the protester will dig to find every flaw and
embarrass us as much as possible. The protest may be sustained
or the protest may not be sustained.
There are a few things that you can do that will make your
contract void from the get-go. CPPC is most conspicuous. Most of
the bad things that you might do in a source selection don't
have the effect of immediately making the contract void. Even if
the protest is sustained and another offeror is selected, you
still have a contract, which must be terminated for the
convenience of the government.
Ron,
(Back to the big thick books--) "Formation of Government
Contracts," Third Edition, Cibinic and Nash, page 422.
"Contracting officers are permitted to define the responsibility
criteria more specifically by including special standards of
responsibility, sometimes called "definitive performance
criteria, " in the solicitation. FAR 9.104-2(a) states.
'When it is necessary for a particular acquisition or class of
acquisitions, the contracting officer shall develop, with the
assistance of appropriate specialists, special standards of
responsibility. Special standards may be particularly desirable
when experience has demonstrated that unusual expertise or
specialized facilities are needed for adequate contract
performance. The special standards shall be set forth in the
solicitation (and so identified) and shall apply to all offerors.'"
Regarding the 12 lb box and the 15 lb box. In a sense, every
specification is a go/ no go selection factor if you want to
look at it that way. But we usually don't.
Ability to perform is certainly a responsibility issue. If the
offeror proposes something conspicuously different from what I
have specified, I would question whether the offeror is capable
of performing to my specification.
Anon and Ron,
I appreciate your prompt and thoughtful responses. This forum is
sometimes a bit tactless and abrupt. I hope we don't discourage
you, and I look forward to your future postings.
Eric
By
Ron Vogt on
Tuesday, May 08, 2001 - 06:40 pm:
Eric,
At the risk of beating this to death (yet I will because many
look to this forum for guidance), I still believe that you are
confusing the concepts of responsiveness and responsibility.
Your quote from N&C is correct, but from it you seem to
extrapolate a conclusion that any go/no go criteria must be
definitive responsibility factors. Recall your earlier post: "If
the factor is evaluated on a pass/fail basis, it is a definitive
responsibility criteria." No it is not.
In your next post you state: "I am having a very hard time
conceptualizing a go/no go evaluation factor that doesn't fit
that description [of a definitive responsibility factor]."
Again, no.
There is a whole universe of go/no go technical specifications
that are responsiveness criteria, not responsibility.
If the IFB calls for a 10-lb. max widget, and you offer a 12-lb.
widget, you are non-responsive, even though you may be the most
responsible contractor in the world and are perfectly able to
provide 12-lb. widgets. The weight is most definitely a go/no
criterion, but it does not measure responsibility.
On the other hand, you may offer a 10-lb. widget, but because
the IFB requires a certain level of experience, you lose. This
is a definitive responsibility criterion.
True, Part 9 does address both responsibility and
qualifications, but that does not mean they are related
concepts. Part 9 addresses suspension and debarment too.
A responsibility criterion becomes definitive when the failure
to have it eliminates you from the competition. So does a
responsiveness factor. "Go/no go" can make either responsiveness
or responsibility definitive.
I'm not trying to be strident, and admittedly, there can be a
grey area where a contractor would need special facilities to
successfully produce an item, i.e. the contractor would be
non-responsible for not having the facilities, and
non-responsive because it could not meet the specs without the
special facilities. Nevertheless, responsibility and
responsiveness remain distinct conceptual issues.
By
joel hoffman on Tuesday, May 08, 2001 - 08:31 pm:
Ron, I agree with you, in
concept, except that I use the term "conforming" rather than
"responsive", when referring to an offer which must conform to
the minimum RFP requirements.
Eric, what I'm saying is, we don't award a contract to a
non-conforming offeror. We will conduct discussions, to include
non-conforming criteria, if there are no conforming offers or if
there is/are conforming offer(s) but it is in the best interest
of the Government to work with a non-corming offeror, to allow
it to fix its proposal.
I would also like to point out that if we eliminate a small
business offeror for an unacceptable or no-go rating on what is
considered to be a "responsibility" type factor, case law says
we have to get the SBA involved in the determination. Happy
Sails! Joel
By
Eric Ottinger on
Thursday, May 10, 2001 - 06:34 pm:
Ron,
You have driven me to spend even more time with big books and
large databases. Keep in mind that I do not pretend to be an
expert, and my motivation is mainly to keep things simple, as
much as possible by discouraging unnecessary and unsupported
elaborations on the actual rules in the regulations and case
law.
In our career field we have a lot of people who like to propound
rules based on a little knowledge, a little speculation and a
lot of their personal (egotistical and irrefutable) logic. And,
we have a few people who are willing to do some digging and to
keep their personal opinions separate from actual policy. I
would like to see the ratio change a bit.
(By the way, strident doesn't particularly bother me,
particularly in a "chat" room.)
By way of Cibinic and Nash I found this very illuminating Comp.
Gen. case.
Data General Corporation, No. B-252239, (June 14, 1993)
"A definitive responsibility criterion is defined as a specific
and objective standard, i.e., qualitative and quantitative, that
is established by a procuring agency in a solicitation to
measure a bidder's ability to perform a contract. W. H. Smith
Hardware Co., B-228576, Feb. 4, 1988, 88-1 CPD 110. Such
criteria do not include a bidder's performance obligations under
the contract, as set forth in the specifications. Id. The
portion of the IFB relied upon by Data General relates to
requirements applicable to personnel "performing under the
contract." The experience provision is, therefore, a performance
requirement and does not establish an experience standard with
which the bidder, as a condition of award, must demonstrate
compliance. See Power Testing, Inc., B-197190, July 28, 1980,
80-2 CPD 72. The ability to satisfy performance requirements is
a subject for the contracting officer's general responsibility
determination, which we will not review absent a showing of
fraud or bad faith--circumstances which are not present here.
King-Fisher Co., B-236687.2, Feb. 12, 1990, 90-1 CPD 177."
Go/no-go factors based on specifications are not "definitive
responsibility factors."
However, "The ability to satisfy performance requirements is a
subject for the contracting officer's general responsibility
determination,…"
In short, the alleged failure to satisfy a particular
specification in the SOW is not a "definitive responsibility
criterion," but it is nevertheless a responsibility issue to be
considered in the "contracting officer's general responsibility
determination."
I guess you can slice this fine by saying "the ability" is a
responsibility issue and "the promise" (expressed in writing in
the proposal) is a responsiveness issue.
As far as I can tell, every single clause and specification in
the RFP is equally a responsiveness selection factor, if you
want to look at it that way.
I put "go" and "no go" into the CCH search. Most hits were
clearly traditional responsibility factors. The second most
common category of hits were clearly LPTA. After that, there
were a few cases that fit in the pre-qualification category.
Evidently, the typical situation where you would select a few
specifications for particular attention would be a situation
where you wanted to do some kind of pre-qualification test.
At first glance, Corion Corporation ( No. B-265602; B-265602.2,
December 15, 1995) appears to be a good example of
specifications used as go/no-go selection factors. After a more
careful reading it becomes apparent that (1) all of the
specifications in the SOW will be evaluated to the "degree" that
the binocular samples met SOW requirements and four key
specifications would be evaluated on a "go/no-go" basis.
However, "Where the offeror's bid samples submitted do not meet
a specified requirement, the degree of risk associated with any
proposed modifications which are needed to enable it to meet the
requirements in time for delivery of test and production
hardware will be evaluated." Ultimately, the evaluation is not
"go/no-go," it is "degree of risk."
Earlier, in this forum we discussed the feasibility of
downselecting using a single factor such as cost or technical to
get down to a manageable number of offers. As much as this would
make sense, it appears that it would be illegal because current
law requires that all of the factors which the FAR requires must
be evaluated before an offeror is eliminated.
(Strictly personal opinion: ) In this light, a prequalification
test of sample products would probably be OK. However, an
evaluation factor which had the effect of eliminating an offer
without consideration of the other factors, would probably be
improper.
I've already admitted that I neglected LPTA when I argued that
"definitive" go/no go factors are synonymous with "definitive
responsibility factors." Also, I agree that you can regard any
firm specification as a go/no-go selection factor, if you wish
to do so.
However, regarding the offeror who proposes a twelve pound
widget when we have specified a ten pound widget, you should
keep in mind that we have specified that it must be painted
black, it must get fifty miles to the gallon, it must be able to
withstand 10 g's in a turn, it must fit in a specified shipping
container, etc. etc.
If someone can show me a real world example of a definitive
go/no go factor from an authoritative source, which is clearly
not a "definitive responsibility criterion" (AKA "definitive
performance criterion") and not merely a specification, I will
be happy to modify my opinion. Otherwise, I will continue to
resist the additional complication.
Eric
By
Ron Vogt on
Thursday, May 10, 2001 - 07:40 pm:
Eric,
I and several others have questioned your lumping of all "go/no
go" or "pass/fail" evaluation factors into the category of
definitive responsibility factors. Our point is simply that many
of these factors are responsiveness factors, not responsibility,
a point which you have yet to disprove. You haven't made your
case any stronger by claiming that our position is based on a
little knowledge and personal, egotistical logic. On fact, I
find it insulting.
Worse, it is difficult to determine exactly what your position
is. In an earlier post you stated: "If the factor is evaluated
on a pass/fail basis, it is a definitive responsibility
criteria." In your last post you state: "Go/no-go factors based
on specifications are not "definitive responsibility factors."
I'll take my egotistical logic over that any day.
'Nuff said.
By
Eric Ottinger on
Thursday, May 10, 2001 - 10:02 pm:
Ron,
I put in the comment to the effect that I don’t mind “strident”
to let you know that I didn’t have you in mind. If I didn’t make
myself clear, I apologize. You should note that you are not the
only “strident” voice in this thread.
I oversimplified in an earlier post, and you are quite right I
have had to admit my error and modify my position.
That, "Go/no-go factors based on specifications are not
"definitive responsibility factors" is the opinion of the Comp.
Gen. As Casey Stengel said, “You can look it up.” Whether it
supports my previous position or not, it’s authoritative and I
don’t mind passing it along.
Further, the Comp. Gen. made it clear that the alleged
noncompliance with a specification was clearly an issue for a
“contracting officer’s general responsibility determination” not
to be reviewed “absent a showing of fraud or bad faith.”
It is sufficient for my purpose that the Comp. Gen. views
noncompliance with a specification as a responsibility issue.
As for this “universe of go/no go technical specifications that
are responsiveness criteria, not responsibility” you’ve put your
finger on my problem. I can manage a few selection factors, I
can’t manage a universe.
If I may quote your earlier post (not to embarrass you but to
highlight the point where we disagree) –
“"Responsibility" encompasses business factors, such as
financial resources, production line capability to handle the
contract, satisfactory record of integrity, necessary accounting
and operational controls, etc. "Responsiveness" means conforming
to the requirements of the IFB, and usually refers to the
technical requirements, i.e., are you offering the exact item
asked for?
In other words, ability to perform, and providing the requested
item, are not the same thing.”
In the Data General case, the Comp. Gen. clearly views “the
ability” to provide “the requested item” (i.e. meet the
specification) as a responsibility issue.
If you want to say “ability to perform, and [promise to provide]
the requested item, are not the same thing,” we don’t really
have a disagreement.
Eric
By
Eric Ottinger on
Friday, May 11, 2001 - 10:03 am:
Ron,
For whatever it is worth—
The first draft started out as follows.
“The charm of this disagreement is that it has very little
practical significance and we can’t do anyone any real harm with
our opinions.
You don’t want your definition of the term “responsibility”
stretched to encompass issues that don’t fit. I respect that.
I usually object when I think that one of our participants has
confused his/her personal opinion or preferences with actual
authoritative policy. It may seem paradoxical, but it is the
most belligerently (self-confessed) logical and dogmatic
participants who come up with the most diverse and contradictory
opinions.”
After doing more research, I decided that I shouldn’t be so
wishy-washy and edited some of this out.
I understood that you might think that my comment regarding
people who rely too much on logic (and too little on research)
was directed at you. To assure you that you were not my target,
I put in an additional comment to the effect that “strident” was
OK with me.
Again, if I didn’t make myself clear, I apologize.
Eric
By
Kennedy How on
Friday, May 11, 2001 - 12:17 pm:
Reading Eric's comment about the
ability to provide the required item, yes or no, by itself, I
can see what he's saying about responsibility. If the offeror
isn't providing what you want, can we make the jump to "does he
have the ability to make what we want"? My answer is "it depends
on the circumstances".
Here's an example from my own experience. There was a
requirement for a towing winch. Our requirement was for it to
have a capacity of xTons, 105' of cable, and fit into a 2'x3'
space. (There were other interface requirements, hose hookups,
control leads, etc., but those were minor detail for this
example). We sent RFPs to a number of winch manufacturers.
Any winch manufacturer could have made us one as a "one-off"
production run, but we were more interested in off-the-shelf
stuff. If a winch manufacturer came in and said, yeah we have a
winch that can meet 2 of the 3 main criteria, would you consider
them to be Not Responsible?
Given Eric's statement in this regard, yeah, I suppose you
could, but I don't think that a PCO would go that route. There's
too many potentially adverse things that could happen to go this
route. The fact that you offered up a non-conforming part even
though you COULD make a conforming part (albeit on that would be
"Custom Made"), I think, makes the responsibility issue not
appropriate.
Kennedy
By
Old Timer on Sunday, May 13, 2001 - 06:17 am:
There is no charm to this
disagreement and misunderstanding about these matters can lead
to sustained protests. There are real differences among being
nonresponsible, nonresponsive, and unacceptable.
"Responsibility" is a matter of a firm's ability (capability,
capacity) to perform and/or its legal eligibility for the award,
not of its willingness to assent to the terms of the
solicitation or of the conformity of its bid or proposal with
the terms of the solicitation. Responsibility must be determined
based on the anticipated date of award, not the time of proposal
submission. A bidder or offeror who is nonresponsible at the
time of submission may be permitted to become responsible before
award.
"Responsiveness" and "acceptability" are matters of a proposal's
compliance with the terms of an IFB or an RFP and must be
determined as of the time of proposal submission.
If a sealed bid is "nonresponsive" then the CO cannot allow the
bidder to revise it, but must reject it and give it no further
consideration. The CO may not amend the IFB after opening in
order to make the bid acceptable and his or her freedom to
cancel and reissue the IFB is rather strictly limited.
If a proposal is "unacceptable," in the sense with which the GAO
uses that term, then it cannot be accepted (cannot be the basis
for an award), but its offeror need not be eliminated from
further consideration; the CO may include the offeror in the
competitive range at his or her discretion and conduct
discussions in order to allow or persuade the offeror to revise
its proposal to make it acceptable; alternatively, the CO can
amend the RFP after receipt of proposals in order to make the
proposal acceptable as submitted as long as he or she gives the
other offerors the chance to revise their proposals, as well.
These rules as I have described them are based on the FAR and
the decisions of the GAO. They are not new and can be traced
back to ASPR days.
Careless use of acquisition terminology suggests ignorance of
the rules and is a great source of confusion and trouble.
By
Eric Ottinger on
Sunday, May 13, 2001 - 01:42 pm:
Old Timer,
Quoting one of my favorite former supervisors-- “Everything you
have said is correct, but…”
The topic on the table was go/no-go selection factors.
Based on experience more than logic, I was of the opinion that
the terms, “definitive responsibility criteria,” “definitive
performance criteria,” “qualification criteria,” “go/no-go,” and
“pass/fail” were all synonymous.
Ron objected because he felt that I was stretching the
definition of “responsibility” beyond the specific issues which
he understood to be responsibility issues.
This seemed like a reasonable argument to me. However, I didn't
agree; in part, because responsibility covers a grab bag of
loosely related issues.
However, I couldn’t see a responsiveness selection factor. My
objection was more pragmatic than strictly logical.
Responsiveness issues are numerous. Selection factors should be
focused, not numerous.
I did a word search in CCH using “no go” w/20 “specification”.
(I expect somebody to complain loudly that I have changed my
mind again. Doesn’t bother me. This is what happens when you
keep an open mind and do some research.)
** “Conforming to specification requirements” may well be a
responsibility issue as long as the phrase is preceded by “will
be able to perform.”
Rockwell International Corporation, (Feb. 15, 1991)
“Protest challenging agency’s determination that awardee will be
able to perform the contract by supplying items conforming to
the specification requirements involves an affirmative
determination of the awardee’s responsibility which the General
Accounting Office will not review absent a showing of possible
fraud or bad faith or misapplication of definitive
responsibility criteria.”
Berema, Inc., (June 22, 1990)
“Furthermore, to the extent that Berema is challenging Skidril’s
ability to furnish a product meeting the specification’s
requirements, this is a matter concerning Berema’s
responsibility. Our Office will not consider a protest of an
agency’s affirmative determination of responsibility absent a
showing of fraud or bad faith on the part of procurement
officials or an allegation that definitive responsibility
criteria were not applied. 4 C.F.R. §21.3(m)(5).”
Comptroller General’s Decision Nos. B-197236, B-197236.2,
B-197236.3., (July 28, 1980)
(CCH Digest of Decision)
“Companion protests against an awardee of a vehicle rental
requirements contract were dismissed because they involved
matters of responsibility which GAO would not review. The
specifications required that each contractor competing for the
award was to provide 24-hour, 7-day a week service. The
protesters argued that the awardee did not offer
around-the-clock coverage because he closed his office during
early morning hours and provided service only on an “on-call”
basis.
Carter Chevrolet Agency, Inc., (May 01, 1996)
“In this case, there is no dispute by any of the parties that
the manufacturer’s letter of commitment clause at issue in this
protest constitutes a definitive responsibility criterion since
it establishes a specific and objective standard to measure the
offeror’s ability to perform. See Software City, B-217542, Apr.
26, 1985, 85-1 CPD 475 (specification requiring each offeror of
software to obtain a manufacturer’s letter of commitment for
each product offered guaranteeing the supply of the product to
the offeror for the term of the contract is a definitive
responsibility criterion).”
** A contracting officer can raise a specification to the level
of a definitive responsibility criterion. However, it doesn’t
appear that this is done very frequently.
Comptroller General’s Decision Nos. B-197236, B-197236.2,
B-197236.3., (July 28, 1980)
(CCH Digest of Decision)
“ In determining whether an awardee met definitive
responsibility criterion in an IFB, a contracting officer acted
reasonably in giving more weight to test results from tests
conducted by her agency than to test results of a competing
bidder. THE IFB REQUIRED THAT A BIDDER DEMONSTRATE THAT HIS CAR
RENTAL DISPATCH POINT WAS WITHIN 15 MINUTES TRAVEL FROM VARIOUS
TRANSPORTATION TERMINALS. The protester contended that the
proposed awardee failed to meet this requirement based on tests
he conducted which allegedly showed that the distance to the
awardee’s dispatch point exceeded 15 minutes by at least 4, and
as much as 11, minutes. However, tests conducted by the
procuring agency showed that the distance was 12.5 minutes from
one terminal and 8 minutes from another. Under the
circumstances, it was not unreasonable for the contracting
officer to rely on the agency test results rather than the
protester’s self-serving tests.”
[A requirement that an offeror must have a facility within a
specified number of miles or within 30 minutes of travel time,
is fairly frequent in my experience.]
Holiday Inn Lakeside City Center, (June 17, 1992)
“The IFB, issued on February 18, 1992, contemplated the award of
a firm, fixed-price contract for a base year and 4 option years.
The solicitation provided that award would be made to the low,
responsive, responsible bidder and contained the following
definitive responsibility criteria which bidders had to meet as
a condition of award: (1) that the bidder’s facility be located
within 5 miles of the MEPS, (2) THAT THE BIDDER’S FACILITY PASS
AN INSPECTION BY THE MEPS FOR COMPLIANCE WITH THE
SPECIFICATIONS, (3) that the bidder’s facility have six or less
reported crimes within a 12-month period, and (4) that the
bidder’s food/meal establishment have passed its last two
sanitation inspections by a public health department.”
Unison Transformer Services, Inc., (Nov. 10, 1988)
“The gist of Unison’s protest is that Sun did not and could not
provide sufficient documentation to establish that it satisfied
the definitive responsibility criterion of having successfully
reclassified a high concentration PCB transformer to non-PCB
status for a minimum of 1 year without polishing.
Definitive responsibility criteria are standards established by
a contracting agency in a particular procurement to measure an
offeror’s ability to perform the contract. Repco, Inc.,
B-225496.3, Sept. 18, 1987, 87-2 CPD 272. Such criteria in
effect represent the agency’s judgment that an offeror’s ability
to perform in accordance with the specifications for the
procurement must be measured not only against the traditional
and subjectively rated factors, such as adequate facilities and
financial resources, but also against more specific
requirements, compliance with which at least in part can be
determined objectively.”
** On second thought, I am going to take some exception with
Cibinic and Nash.
“Definitive responsibility criteria must also be distinguished
from specification requirements.” (“Formation of Government
Contracts” Third Edition, page 425)
Since the agency’s evaluation of definitive responsibility
criteria can be challenged in a protest, the protester will, not
infrequently, characterize some firm specification as a
definitive responsibility criterion and allege that the
successful offeror failed to satisfy this “definitive
responsibility criterion.”
The Comp. Gen. will typically respond with something like the
following:
PTR-Precision Technologies, Inc., (Aug. 01, 1991)
"We also do not view the RFP requirement as a definitive
responsibility criterion. … The requirement here for a current,
proven commercial design is simply one of many design and
performance requirements found in the specifications, all of
which the contractor must meet, and THE CONTRACTOR’S ABILITY TO
DO SO IS ENCOMPASSED BY THE CONTRACTING OFFICER’S GENERAL
DETERMINATION OF RESPONSIBILITY. Neither the commercial design
provision nor any of the other specification requirements
establishes a separate, objectively determinable definitive
criterion of responsibility. See Clausing Mach. Tools, B-216113,
May 13, 1985, 85-1 CPD 533. ACCORDINGLY, THERE IS NO BASIS FOR
OUR REVIEW."
Blue Tee Corporation, (Mar. 18, 1992)
“The requirement here for a commercial item is simply one of
many design and performance requirements found in the
specifications, all of which the contractor must meet, and the
contractor’s ability to do so is encompassed by the contracting
officer’s general determination of responsibility.”
(Personal Opinion: The reason that contracting officers rarely
raise individual specifications to the level of definitive
responsibility criteria, is not that it is irrational or
improper. In most procurements it simply doesn’t make sense to
single out one or a few, out of numerous specifications, for
special treatment.)
If however, an RFP identifies a specific specification as a
“definitive performance specification,” I don’t think the Comp.
Gen would object. For instance, in the Holiday Inn case, the
agency did an inspection to “verify compliance with the
specifications.”
It is not objectionable for a contracting officer to single out
a specification for special treatment as a “definitive
responsibility criterion.” (e.g. Hotel rooms must be clean.).
However, the Comp. Gen will not allow a protester to select one
out of numerous specifications and characterize it as a
“definitive responsibility criterion.”
By the way, I would not fault anyone for not getting this
exactly right. Without a large database of Comp. Gen. cases and
a word search capability, I don’t see how the typical 1102 (or
lawyer) would have had either the opportunity or the occasion to
dig into this.
Eric
By
Old Timer on Monday, May 14, 2001 - 05:06 am:
Mr. Ottinger,
I must say that your long series of quotations and interjections
shed no light either on the issues or the current state of your
opinion, at least not from my perspective. But rather than
inspire another long missive from you, I am content to let my
last message stand and leave the field. I am, indeed, old, and I
don't want to breathe my last breath while reading this sort of
thing. I'm in London and I'd rather die in the British Museum
arguing with some Greek about the Elgin Marbles.
Anyway, Anon X explained things well enough on May 2 at 3:11pm.
By
Eric Ottinger on
Monday, May 14, 2001 - 06:27 pm:
Old Timer,
Enjoy the marbles.
If you are endorsing Anon X’s opinion as well as his attitude,
you are welcome to find, in some authoritative text that we all
can reference, one these “Determinations of Acceptability” that
he considers essential, and post it here.
If you believe there are go/no-go, definitive responsiveness
selection factors endorsed by the Comp. Gen. or some other
appropriate authority, you are welcome to find an example and
post it here.
That should be simple enough.
(In every instance that I found, the Comp. Gen. regarded
specifications used as selection factors to be either go/no-go
definitive responsibility criteria or “simply one of many design
and performance requirements found in the specifications, all of
which the contractor must meet, and the contractor’s ability to
do so is encompassed by the contracting officer’s general
determination of responsibility.")
(Note my earlier comment to Ron: "Regarding the 12 lb box and
the 15 lb box. In a sense, every specification is a go/ no go
selection factor if you want to look at it that way. But we
usually don't.")
As for my opinion-- It really doesn’t matter. I expect the
reader to go back to the appropriate authorities and think
things through for him (her) self.
If one of our participants presents an argument in the form,
“You can’t take that path because you might step in the unicorn
poop,” it might be intuitively obvious to me that an argument
premised on the existence of unicorns is probably not something
that I need to worry about. But it is relatively easy to
demonstrate that something exists and rather difficult to
demonstrate, beyond a doubt, that something does not exist.
I realize that if one of our participants really believes in the
hazards of unicorn poop, it will be very difficult to convince
him otherwise.
All that I can ask in that situation is that our participant
produce a real unicorn rather than a hypothetical unicorn for
the benefit our readers.
Eric
By
Anonymous
on Tuesday, May 15, 2001 - 02:19 am:
For a perfect example of one of
Anon X's go/no technical evaluation factors, see Systems
Management, Inc.; Qualimetrics, Inc., B-287032.3, April 16,
2001, a sustained protest.
The RFP required, among other things, that an offeror's proposed
system be certified by FAA as of the date of proposal
submission. The USAF awarded the contract to an offeror whose
system was not so certified. The GAO held that by accepting the
uncertified system USAF had relaxed the requirement for one
offeror but not for the others. GAO sustained the protest and
recommended a new competition and reimbursement of protest
costs.
This is a clear example of a go/no go technical factor--a system
was either certified or it wasn't. Since the selected offeror's
system was not certified, its proposal was unacceptable (USAF
could not legally accept it without first changing its
requirement). The requirement had nothing to do with
responsibility. If the CO had recognized the requirement for
what it was--a go/no go subfactor--and made a "determination of
acceptability," he or she would not have lost this costly
protest.
This is all so clear and Anon X and Old Timer have made it so
well that I can't understand why Eric is continuing to argue
about it. Face-saving?
By
George on Tuesday, May 15, 2001 - 11:40 am:
Eric:
You don't need an "authoritative text" or the "endorsement" of
the Comp. Gen. An agency can use any evaluation factor that it
wants in any way that it wants as long as it isn't prohibited by
statute, FAR, or case law. Do you know of any statute, FAR, or
case that prohibits the use of such factors?
And the term "responsiveness" does not apply in negotiated
acquisitions. The correct term is "acceptability."
By
Loki on Tuesday, May 15, 2001 - 02:51 pm:
In the case of the Narrow reading
of Responsibility vs. the Expansive reading of Responsbility.
Please consider --
Competitive Negotiation, The Source Selection Process, 2nd Ed.,
Nash, Jr., Cibinic, Jr., O'Brien.
Softcover - Page 230
In the discussion of Lowest-Price, Technically Acceptable
Process ---
"A key element of this technique is that the non-cost evaluation
factors are all of equal importance. The failure of a proposal
to meet any of the factors will preclude award to the offeror
submitting the proposal. However, the offeror may be given an
opportunity to cure the noncompliance through oral or written
discussions if award on initial proposals will not be made and
the proposal would otherwise be in the competitive range.
The term 'technically acceptable proposals' as used in the FAR
refers to all non-cost factors. It includes factors dealing with
the capability of the offerors, as well as the technical details
of the performance that is offered in the proposal. Although FAR
15.102-2(b)(1) refers only to determinations of unacceptable
past performance as requiring reference to the Small Business
Administration (SBA), the same rule would apply to other lack of
acceptability based on any other capability factor. See, e.g.,
Vantex Serv. Corp., Comp. Gen. Dec. B-266199, 96-1 CPD _29,
holding that when traditional responsibility factors such as
'experience' are evaluated on a go/no-go basis, the matter must
be referred to the SBA if a proposal is determined unacceptable
because of such factors. See also Dynamic Aviation -
Helicopters, Comp. Gen. Dec. B-274122, 96-2 CPD _166; and
Environsol, Inc., Comp. Gen. Dec. B-254223, 93-2 CPD _295."
+++
So it seems to me that we need to take into account if we are,
or are not, talking about TRADITIONAL RESPONSIBILITY FACTORS.
What is the acid test? Here's where we come up with a difference
of opinion, much like our Supreme Court. The clear-cut
responsibilty factors are enumerated in the FAR, but the
question is how broad is the definition (does the specific
language of the FAR create clear limitations on responsibility
that would support the narrow view, or does it support the
expansive view?)
Eric seems to be arguing that the FAR definition of
responsibility accounts for just about every technical
performance criteria under the sun (you may, of course, speak
for yourself). Others want a narrower field of inclusion.
I would err on the side of finding most things to be
responsibility criteria, as the definition of responsibility IS
broad. I don't find a restrictive or hypertechnical limitation
of responsibility supported in plain language of the FAR
definition of responsibility itself.
+++
Here's the FAR just for kicks --
9.104 Standards.
9.104-1 General standards.
To be determined responsible, a prospective contractor must--
(a) Have adequate financial resources to perform the contract,
or the ability to obtain them (see 9.104-3(a));
(b) Be able to comply with the required or proposed delivery or
performance schedule, taking into consideration all existing
commercial and governmental business commitments;
(c) Have a satisfactory performance record (see 9.104-3(b) and
Subpart 42.15). A prospective contractor shall not be determined
responsible or nonresponsible solely on the basis of a lack of
relevant performance history, except as provided in 9.104-2;
(d) Have a satisfactory record of integrity and business ethics
including satisfactory compliance with the law including tax
laws, labor and employment laws, environmental laws, antitrust
laws, and consumer protection laws. [This language stayed
indefinitely. Please use paragraph (e) below.]
(e) Have a satisfactory record of integrity and business ethics;
(f) Have the necessary organization, experience, accounting and
operational controls, and technical skills, or the ability to
obtain them (including, as appropriate, such elements as
production control procedures, property control systems, quality
assurance measures, and safety programs applicable to materials
to be produced or services to be performed by the prospective
contractor and subcontractors). (See 9.104-3(a).)
(g) Have the necessary production, construction, and technical
equipment and facilities, or the ability to obtain them (see
9.104-3(a)); and
(h) Be otherwise qualified and eligible to receive an award
under applicable laws and regulations.
9.104-2 Special standards.
(a) When it is necessary for a particular acquisition or class
of acquisitions, the contracting officer shall develop, with the
assistance of appropriate specialists, special standards of
responsibility. Special standards may be particularly desirable
when experience has demonstrated that unusual expertise or
specialized facilities are needed for adequate contract
performance. The special standards shall be set forth in the
solicitation (and so identified) and shall apply to all offerors.
I suggest those who would like to find a narrower scope of what
is a responsibility criterion to approach it from two
perspectives:
1) Find a way to place the factor out of the responsibility
definition in the FAR based upon the FAR definition itself.
2) Find a precedent on point.
By
Ron Vogt on
Tuesday, May 15, 2001 - 06:22 pm:
To Anonymous,
I feel slighted. I must not have made my points as well as Anon
X and Old Timer!
Actually, I gave up. I just couldn't shake Eric from his belief
that virtually all evaluation factors are responsibility
criteria. This is unfortunate, because as Old Timer pointed out,
there are very real differences between responsiveness and
responsibility, and the consequences of not understanding this
could be great.
Perhaps Eric's confusion arises from the GAO's frequent use of
the phrase "ability to meet" performance requirements and
specifications, and calling it part of the CO's responsibility
determination. True, the ability to turn out the product
falls under the category of responsibility (along with financial
resources, production capacity, integrity, etc.), but actually
proposing a product that meets the specifications is a matter of
responsiveness.
Eric's cases may appear to support his position, but I suspect
that a complete reading would find that the GAO uses the terms
properly.
This debate really has to end. It's driving me closer to Old
Timer's age.
By
Eric Ottinger on
Tuesday, May 15, 2001 - 08:11 pm:
George,
Looking for something that probably doesn’t exist gets real
tedious. I don’t believe that there is a concept of
“acceptability” for negotiated procurements, which is synonymous
with “responsiveness” for IFBs. If, however, you can refer us to
a page in Cibinic and Nash or some other appropriate authority,
I will be happy to change my opinion.
I think by “acceptability” you mean “technical acceptability.”
And I think you would agree that “technical acceptability” is
not exactly synonymous with “responsiveness” because
“responsiveness” includes several issues in addition to
“technical acceptability.”
Loki,
Aren’t you the trickster who keeps changing names?
In any case thanks for the moral support.
A week ago I really had no opinion, one way or the other on
these issues. The idea of a definitive selection factor, which
was not a “definitive responsibility criterion,” was new to me.
After reviewing Cibinic and Nash, the Deskbook, and CCH, it
appeared that this significant concept had escaped the attention
of these authorities. (On the other hand, maybe I wasn’t reading
closely enough.)
The idea that responsibility can be stretched to encompass all
of the firm specifications in the RFP is not mine but the
opinion of the Comp. Gen.
See: Blue Tee Corporation, (Mar. 18, 1992)
“The requirement here for a commercial item is simply one of
many design and performance requirements found in the
specifications, all of which the contractor must meet, and the
contractor’s ability to do so is encompassed by the contracting
officer’s general determination of responsibility.”
I think we sometimes use the terms “technically acceptable” or
“acceptability” outside the context of LPTA. I don’t think this
does any harm as a kind of casual usage. However, I question
whether there is a precise meaning outside the context of LPTA.
(I am only raising this for discussion. Any expert, well
supported, opinion establishing the contrary will be welcomed.)
(In the case cited by Anon, the Comp. Gen. quotes the
protester’s allegation that the successful proposal was not
“technically acceptable.” The Comp. Gen. clearly agrees because
the protest is sustained. However, the Comp. Gen. does not
sustain the protest because the offer is not “technically
acceptable.” Rather the Comp. Gen. finds that the agency has
relaxed the “mandatory requirement” with the result that the
playing field is not level and other offerors would have
submitted better proposals if they had been allowed to propose
to the same relaxed requirement.)
In any case, the FAR does not use the phrase “technically
acceptable” in any context other than LPTA.
Anon,
Yes, I thought the case was relevant to our discussion.
Taking one “mandatory requirement” out of numerous “mandatory
requirements” and characterizing it as a go/no-go selection
factor is, I guess, a perfectly logical thing to do after the
fact, when you know the outcome of the protest.
I don’t agree. To my logical mind, if you are going to take one
firm requirement and make it a selection factor, you have to
treat all such specifications as selection factors. Our less
experienced readers should be looking for selection factors in
Section M (or maybe Section L) but not in the Statement of Work
or other attached specifications.
However, in this case, the Comp. Gen. never uses the terms,
“go/no-go,” “factor,” or “criteria” with reference to the
certification requirement. Nor is there any indication that the
agency used any kind of go/no-go evaluation scheme. The
evaluation was strictly colors and risk.
Ron,
I admire your self confidence. However. The concept of
responsiveness doesn’t apply to negotiated procurements. That is
plain English. And I can back it up with the authority of
professor Nash.
When we do a source selection, we use a checklist to make sure
that each proposal conforms to the solicitation. There are
numerous boxes to check and we don’t award unless there is a
check in each box. I don’t doubt that any one of those checks
may be regarded as a selection factor. It defies common sense to
suggest that every box to be checked is to be regarded as a
selection factor.
If I may quote you, “Eric's cases may appear to support his
position, but I suspect that a complete reading would find that
the GAO uses the terms properly.”
It appears that I am doing the reading, complete or otherwise,
and you are merely debating. I would advise our readers to go
read the cases and make up their own minds.
Eric
By
Eric Ottinger on
Tuesday, May 15, 2001 - 09:20 pm:
Ron,
As anyone who reads Comp. Gen. cases regularly must be aware,
the Comp. Gen. uses a number of verbatim formulas to express
well established principles. Your suggestion that the Comp.
Gen.’s language is not clear on its face or somehow out of
context should be evaluated with this in mind. When they say
exactly the same thing over and over, they mean it.
Eric
By
Anonymous
on Wednesday, May 16, 2001 - 02:20 am:
Ron:
Didn't mean to slight you. You did well, too.
You can't shake Eric from one of his "personal" opinions. Think
of it this way--we're really writing to protect the innocent
from Eric who might believe him if we didn't speak up.
What I find funny is his citing Prof Nash, who he used to be
skeptical of when Vern Edwards cited him.
By
Anonymous
on Wednesday, May 16, 2001 - 02:36 am:
Loki:
Here's the GAO:
"Information relating to offerors' ability to perform contract
is a matter of responsibility and not related to the technical
acceptability of proposals and, even though solicitation
required
submission of information with proposals, requirements that
relate to responsibility may be satisfied at any time prior to
award."
3DAV Development, Inc.; San Sebastian Shopping Center, S.E.,
B-274933.2; B-274933.5; B-274933.6, January 16, 1997.
By
formerfed on Wednesday, May 16, 2001 - 10:02 am:
This debate is entertaining. The
fall out is lots of people probably are confused. The bottom
line is, whether you agree with Eric or not, I hope no one gets
into a situation where this is relevant. The best bet is read
Anon X's comments above and stick with that philosophy. You
won't go wrong.
By
Linda Koone
on Wednesday, May 16, 2001 - 10:08 am:
Eric:
You seem to be hung up on the fact that recognized authority
does not define the concept of acceptability of an offer. In
light of the fact that the FAR does not define 'acceptable' or
'unacceptable', don't you find it amazing how many protests are
based on the acceptability of the awarded offer?
Have you read the Beckman Coulter, B-281030; B-281030.2,
December 21, 1998 decision? It involved several issues, one
being the inclusion of terms that were in violation of the
termination clause in the solicitation.
How do you view an offer that contains terms that violate
statutory requirements in your solicitation?
I consider the offer to be unacceptable, and unless I hold
discussions, ineligible for further consideration or award. Yet,
I can't find specific guidance in the FAR that tells me to do
this.
Linda
By
Vern Edwards
on Wednesday, May 16, 2001 - 01:19 pm:
Linda:
Actually, a recognized authority has defined the concept of
acceptability of an offer -- the GAO. In the very decision that
you cited the GAO said:
"In negotiated procurements, any proposal that fails to conform
to material terms and conditions of the solicitation should be
considered unacceptable and may not form the basis for an award.
Barents Group, L.L.C., B-276082, B-276082.2, May 9, 1997, 97-1
CPD para. 164 at 10; Martin Marietta Corp., B-233742.4, Jan. 31,
1990, 90-1 CPD para. 132 at 7."
I call this the "acceptability rule" for negotiated
procurements. A proposal that conforms to the material terms and
conditions of the solicitation is acceptable and one that does
not is not. Note the terminology -- a proposal that fails to
conform is to be considered "unacceptable," not nonresponsive.
Note, too, that the GAO has held this position for many years.
What confuses some people about this rule is the fact that some
agencies unwisely use the term "acceptable" as an adjectival
score to describe a degree of value -- as in excellent, very
good, acceptable, marginal and unacceptable -- without regard to
the legal definition established by the GAO. When the term is
used in this way it may happen that a legally unacceptable
proposal is scored as acceptable. You will note that in Systems
Management, Inc.; Qualimetrics, Inc., B-287032.3, April 16,
2001, cited above by Anonymous, the offeror received a score of
"blue," for the factor "technical compliance," signifying
"exceptional," even though the GAO held it to be unacceptable on
that evaluation factor because it did not comply with a
solicitation requirement. It's possible that the contracting
officer in that case either was unaware of the solicitation
requirement or unaware of the acceptability rule. Maybe both.
The GAO has also approved of a pass/fail evaluation factor other
than a responsibility-type factor. Here's the GAO describing an
agency's RFP in Matrix General, Inc., B-282192, June 10, 1999:
"The RFP stated that award would be made to the offeror whose
offer represents the best value to the government on the basis
of (1) the merits of the offer and (2) the offeror's capability.
RFP sect. M.1. The RFP stated that the agency would determine
the acceptability of each offer on a pass/fail basis and that an
offer is acceptable when it manifests the offeror's assent,
without exception, to the terms and conditions of the RFP. RFP
sect. M.2.a. Under capability of the offeror, the RFP provided
that the government would assess the capability of each offeror
on the basis of (1) its organizational experience, (2) its
organizational past performance, (3) qualifications and
experience of key personnel, and (4) its demonstrated ability to
comply with instructions. RFP sect. M.3. The RFP also stated
that the agency would not assess capability on a pass/fail
basis, but would use its assessments of capability as a basis
for comparing offerors to determine best value. Id. The RFP
provided that an offeror's capability assessment was
significantly more important than its price. RFP sect. M.4.1.
The RFP further stated that in order to select the winning
offeror, the government would rank the offers from best to worst
by making a series of paired comparisons among them, trading off
the marginal differences in capability and price between the
members of each pair. RFP sect. M.5."
In denying the protest the GAO said:
"Contrary to Matrix's assumption, the RFP did not provide for
award on the basis of the low, technically acceptable offer;
rather, as explained above, the RFP specifically stated that
award would be made to the offeror whose offer represents the
best value to the government on the basis of (1) the merits of
the offer and (2) the offeror's capability. While the RFP
provided for an assessment of acceptability on a pass/fail
basis, it provided for an assessment of capability as a basis
for comparing offerors to determine best value."
So we see an offer acceptability factor evaluated on a pass/fail
basis while responsibility-type factors were evaluated on a
tradeoff analysis basis. Note, too, that the responsibility-type
factors are most important, but that failure to conform to the
terms of the solicitation would have rendered the offeror's
proposal unacceptable and ineligible for award. This proves the
validity of Anon X's assertions, also Ron's and Old Timer's.
By
formerfed on Wednesday, May 16, 2001 - 01:30 pm:
Vern,
It's good to have you back |