By Linda
Koone on Thursday, June 21, 2001 - 03:29 pm:
I can't seem to find a definitive
answer for the following questions, so any help you can provide
is appreciated.
Does the contractor responsibility determination that I make
prior to awarding a requirements contract carry over to the
individual orders issued, or must a separate responsibility
determination be made prior to issuing each order?
How about for an IDIQ contract or a contract with options? Does
the initial determination cover all orders/options or must a
separate determination be made prior to issuance of an
order/option?
By
Eric Ottinger
on Thursday, June 21, 2001 - 05:01 pm:
Linda,
As I am sure you are aware, the signature on the contract is now
the determination of responsibility.
FAR 9.105-2 Determinations and documentation.
(a) Determinations. (1) "The contracting officer’s signing of a
contract constitutes a determination that the prospective
contractor is responsible with respect to that contract. When an
offer on which an award would otherwise be made is rejected
because the prospective contractor is found to be nonresponsible,
the contracting officer shall make, sign, and place in the
contract file a determination of nonresponsibility, which shall
state the
basis for the determination."
On the other hand, there is always the possibility of a
determination of nonresponsibility.
I assume that a determination of nonresponsibility for an order
under a contract would be the same thing as a termination.
All and all, I don't think we would do a determination of
nonresponsibility for an order under a contract unless we were
ready to terminate. If we choose to terminate, there is no need
for the determination of nonresponsibility.
Eric
By
Linda Koone on Thursday, June 21, 2001 - 08:06 pm:
Eric:
I am aware that the signature signifies a determination of
responsibility pursuant to FAR 9.105, however, under FAR Subpart
4.8 (don't have the exact cite handy), the contractor
responsibility determination is listed as an item that should be
in the contract file. We've gone round and round with this, but
higher level authority has more or less mandated that we
document contractor responsibility or non responsibility.
I also agree that you would terminate a requirements contract if
the contractor's performance was subpar.
But considering our requirement to document contractor
responsibility, right or wrong, do you think it's necessary to
document it for each order or is the original determination
sufficient for the entire period of performance?
By
Vern Edwards on
Friday, June 22, 2001 - 05:50 am:
Linda:
The FAR does not explicitly require a determination of
responsibility prior to the issuance of an order or the exercise
of an option. However, I would say that both orders under an
IDIQ contract and exercises of options constitute purchases or
awards. FAR 9.103 says, "No purchase or award shall be
made unless the contracting officer makes an affirmative
determination of responsibility." Italics added. The award of an
IDIQ contract does not purchase anything; it's the issuance of
an order that makes the purchase (see the Ordering clause at FAR
52.216-18 and the Indefinite Quantity clause at FAR 52.216-22);
the exercise of an option is the purchase of something that
would not have been purchased if the option had not been
exercised.
You can also approach it this way: Suppose that you are about to
issue an order under a task order contract or exercise an option
under any contract and that you learn or suspect that the
contractor is about to declare bankruptcy -- would you still
issue the order or exercise the option? What if you learned that
the contractor would not be able to comply with the order or
with the contract after the exercise of the option? What if the
contractor's record of performance had not been satisfactory?
What if it did not have a satisfactory record of integrity or
ethics?
In my opinion a contracting officer should make an affirmative
determination of responsibility before issuing an order or
exercising an option. However, I do not think that means the CO
must obtain another preaward survey or make any other extensive
investigation; that's a different issue and depends on how much
time has passed since the original determination of
responsibility and on what information has come to the CO's
attention since then.
Having said all of this, I acknowledge that since the regulation
does not expressly state such a requirement either in FAR 16.505
or 17.207 one could argue that such a determination is not
necessary.
By
bob antonio on
Friday, June 22, 2001 - 08:18 am:
Linda:
You asked a complicated question. I thought about it a bit last
night and during my subway ride this morning. Here are my
thoughts. I am adding FAR sections only to make my point. I am
sure you have committed the FAR to memory.
On a requirements contract (FAR Part 16), the FAR states "For
the information of offerors and contractors, the contracting
officer shall state a realistic estimated total quantity in the
solicitation and resulting contract." "The contracting officer .
. . should base the estimate on the most current information
available." With this in mind, I consider the initial
responsibility determination, at the signing of the contract, to
cover all possible quantities within the scope of the contract.
That would negate the need for a complete responsibility
determination on orders under a requirements contract. However,
things change. In my view, you cannot issue an order with a firm
that cannot complete the order. So, you would have to at least
consider some aspects of a responsibility determination. I think
having a checklist with all the standards in the file would be a
useful idea. However, I have one caveat. I would be careful to
make sure that any actions cannot be construed to be a
constructive suspension or debarment. For example, FAR Part 9
says "Ordering activities may continue to place orders against
existing contracts, including indefinite delivery contracts, in
the absence of a termination" with debarred or suspended
contractors. This issue will take some additional time and
thought.
On an indefinite quantity contract, things are a bit different.
Again, FAR Part 16 says "(1) The contract must require the
Government to order . . . at least a stated minimum quantity of
supplies or services." "The contracting officer should establish
a reasonable maximum quantity based on market research, trends
on recent contracts for similar supplies or services, survey of
potential users, or any other rational basis." So the original
responsibility determination may cover the estimated quantity.
Even on a multiple award, indefinite quantity contract, I think
this would be so. However, under an indefinite quantity
contract, the FAR explains "(iii) The contracting officer should
consider the following when developing the procedures (for
placing orders): (A)(1) Past performance on earlier orders under
the contract, including quality, timeliness and cost control.
(2) Potential impact on other orders placed with the
contractor." You are required to do some parts of a
responsibility determination here. Again, I would suggest a
checklist with the same caveats about a constructive suspension
or debarment.
I consider the exercise of an option to be similar to the items
above. There is one case where you must do a new responsibility
determination on an order or option exercise. If there is an
action beyond the scope, it is a new procurement. If the option
is exercised improperly, it is a new procurement.
I am sure I have not thought everything out. This is a
complicated issue. In short, I think a partial responsibility
"update" should be made. However, it should not constructively
suspend or debar a contractor.
By
Eric Ottinger on
Friday, June 22, 2001 - 11:29 am:
Linda,
I am not a lawyer, but it seems to me that if you do a
determination of nonresponsibility and you do not award the
order, you have breached the contract. Of all the possible ways
to breach the contract, this would about as shoddy and
inappropriate as anything that I could imagine.
If the contractor really can’t perform, you should do a
termination. A determination of nonresponsibility as a de facto
termination would be a really bad idea.
If your higher headquarters wants a stand-alone affirmative
determination of responsibility in spite of the plain language
in FAR 9.105-2 you should give them whatever redundant,
pointless piece of paper their hearts desire as long as you
don’t do something patently improper or illegal. Modern word
processing equipment makes it easy to crank out meaningless
boilerplate. I recommend it highly.
For whatever it is worth, indefinite quantity contracts started
out as vehicles to order routine commercial type items. The
authority to issue orders is often delegated. I can’t imagine an
ordering officer in a motor pool, buying tires or batteries,
writing a determination of responsibility to go with each order.
In short, since we are talking about something which isn’t
really required, doesn’t do any good, and might do some harm, I
can only say to give higher headquaters whatever it takes to
make them happy.
To whomever it may concern,
Here we have at least three really smart people pursuing a
really arcane convoluted piece of logic, because higher
headquarters thinks the checklist in FAR 4.8 takes precedence
over the plain language in FAR 9.105-2.
If you wish to understand why acquisition reform is hard, this
is a great example.
Eric
By
Kennedy How on
Friday, June 22, 2001 - 12:08 pm:
We've generally considered any
award of a delivery order/whatever as a separate contractual
action in it's own right. So, if you take that at face value,
you probably be safe in making a responsibility determination.
What I remember doing is checking to see if the contractor is
performing satisfactorily, checking the Debarred list to make
sure they aren't on it, and maybe checking with DCMC just in
case. This last one isn't done always, unless we suspect
something. As stated earlier, if something bad comes up, we
would have to work up some documentation as to why we don't make
an award. If things are clean, we go ahead and award, thus using
the definition that the KO signature on the award signifies that
the contractor is responsible.
Kennedy
By
CMercy on Friday, June 22, 2001 - 01:43 pm:
To all
would you consider a responsibility determination on a FSS
holder before placing an order?
By
Eric Ottinger on
Friday, June 22, 2001 - 01:54 pm:
CMercy,
I would say "no." But that is because GSA is the Contracting
Officer.
I don't believe the rest of us have that authority.
If your point is that ordering officers are often not
contracting officers or not "the" contracting officer, I agree.
Eric
By
Anonymous
on Friday, June 22, 2001 - 02:23 pm:
The scope of subpart 9.2 says it
covers prospective contractors, that is contractors that do not
yet have a contract. The responsibility determination is made at
the time of award and covers the entire scope of the contract
(this includes orders that are placed under an IDIQ contract).
By
bob antonio on Monday, June 25, 2001 - 05:38 am:
Linda:
I have a few moments so I will be brief. I don't like the idea
of documenting an "intra-contract" determination of
responsibility. If one needs to document such a thing on a
contract that they award and issue orders against, then I wonder
about the quality of their contract administration. If the
agency has an ongoing order with the contractor, they should be
aware of any changes with the contractor.
The constructive suspension stuff is real. It happened with GSA
and Art-Metal.
By
Eric Ottinger on
Monday, June 25, 2001 - 11:31 am:
Linda and All,
I would read FAR 9.103(b) in light of FAR 9.103(a):
(a) Purchases shall be made from, and contracts shall be awarded
to, responsible prospective contractors only.
(b) No purchase or [contract] award shall be made unless the
contracting officer makes an affirmative determination of
responsibility.
If FAR 17.2 requires a determination of responsibility to
exercise an option, I would expect that the FAR would say so.
More to the point, there is an explicit list of issues that must
be considered. Responsibility issues are not included.
Regarding Kennedy’s comments, the FAR allows orders under an
existing contract to a debarred contractor. The DFARS forbids
orders to a debarred contractor after the ID/IQ minimum has been
satisfied.
FAR 9.405-1 (b) “Ordering activities may continue to place
orders against existing contracts, including indefinite delivery
contracts, in the absence of a termination.”
DFARS 209.405-1 Continuation of current contracts.
“(b) Unless the agency head makes a written determination that a
compelling reason exists to do so, ordering activities shall
not--
(i) Place orders exceeding the guaranteed minimum under
indefinite quantity contracts: or
(ii) When the agency is an optional user, place orders against
Federal Supply Schedule contracts.
(c) This includes exercise of options.”
I would infer that there is no requirement to make a
responsibility determination for orders at the FAR level. In DoD
it would be highly prudent to check the debarred list.
I initially found Anon convincing because I agree with him.
However, it is 9.1, not 9.2, and Anon is reading quite a bit in.
In any case, we all agree that it would be imprudent to issue an
order when we know that the contractor can no longer perform.
The question is, what should be done at that point.
I checked my CCH to see what I could find about “constructive
suspension.” This appears to be strictly a construction
contracting term.
The Art Metal case is too old to be included on my CCH disk.
From what I can see, it appears that “de facto debarment” would
be a better term.
For those who don’t have long memories, Art Metal was for many
years the most successful low-bid supplier of ugly, gray GSA
office furniture. Art Metal, with the help of a Washington Post
expose, made significant contributions to the concepts of best
value and past performance.
Eric
By
bob antonio on Monday, June 25, 2001 - 11:51 am:
Eric:
The Art-Metal case is below. I was there.
http://www.wifcon.com/analmetal.htm
The Art-Metal case is a little different because it involved a
few more non-actions. However, it results in about the same end.
You just have to use a little imagination and see where things
could lead.
By
Eric Ottinger on
Monday, June 25, 2001 - 12:36 pm:
Bob,
Thanks. Everyone should be aware of Art Metal.
After giving the matter some more thought, i would say that the
risk of litigation would depend quite a bit on the
circumstances.
Using an "intra-contract" determination as a de factor
termination when a termination would be more appropriate strikes
me as a very dubious procedure.
On the other hand there may be situtations where the contractor
may prefer that we not issue orders for some period of time.
Even if we have satisfied our minimum requirement, a contract is
still a two way relationship. We should communicate and be
honest with the contractor.
Looking at it from the contractor's point of view, I can see
where the government should set strict standards of
responsibility before making an award. However, there shouldn't
be double jeopardy.
The only relevant case that I could find was Trilon:
Trilon Educational Corporation v. The United States.
In the United States Court of Claims. No. 241-76. Decided , June
14, 1978, 578 F2d 1356
Bidder Responsibility--Erroneous Affirmative
Determination--Government Challenge.
"--The government was bound by a contracting officer’s allegedly
erroneous determination that a contractor was responsible
because the same considerations and reasoning that prevent an
unsuccessful bidder from challenging an affirmative
responsibility determination apply to challenges by the
government. The government awarded a contract for small arms
gunfire flash-noise simulators and then discovered that the
president of the contractor’s parent company had been convicted
of defrauding the government. After this discovery the contract
was terminated. The contractor argued that the termination was
for the convenience of the government and claimed costs. The
government argued that it was not liable for costs as the
finding of responsibility was erroneous and the contract was
void. Absent allegations that there was fraud or bad faith in
making an affirmative responsibility determination, such
decisions will not be overturned because they are based, in
large part, on subjective judgments that are not readily
susceptible to review. The same reasons for not revewing the
decision applied when the government was the one questioning it,
and therefore, the government was bound even if its initial
judgment was incorrect."
Eric
By
Linda Koone
on Monday, June 25, 2001 - 03:53 pm:
My thanks to all of you for your
time and considered opinions and offerings.
Eric: In the Trilon case, what was the basis for the
Government's claim that there was an 'erroneous responsibility
determination'? Was it based on a lack of consideration of the
element of contractor responsibility, or a difference of
opinion?
Bob: I understand your position, but think that there are
instances where the most proactive contract administration can't
prevent changed circumstances under a long term contract, which
many IDCs and option contracts are, such as the death of the
owner of a small business.
By
Eric Ottinger on
Monday, June 25, 2001 - 04:10 pm:
Linda,
It turned out that the CEO was an Ill Wind sleaze.
Like the Art Metal story that Bob provided, the government had
second thoughts about the award after reading the Washington
Post.
It isn't entirely on point for the question which you asked,
because the contractor had already started work on the orders.
However, I am sure that it would be cited if this issue were
ever litigated.
Eric
By
Vern Edwards
on Tuesday, June 26, 2001 - 06:20 am:
Linda:
Getting back to your original question:
While I think that a CO should make a determination of
responsibility before issuing an order or exercising an option,
I think that a separate written memo in support of an
affirmative determination of responsibility is unnecessary.
However, there may be some merit to such a requirement as a
device for forcing COs to think consciously about an offeror's
responsibility. That may be especially true in an organization
that deals with a large number of small manufacturers and when
delays in product delivery could adversely affect operational
effectiveness.
I don't understand the talk in this thread about breach of
contract. If a CO finds that an IDIQ contractor has become
nonresponsible since the initial award, and if the minimum
requirement has not been ordered, then the proper response could
be to either: (1) terminate the contract for convenience or
default, depending on the circumstances, or (2) talk about the
problem with the contractor and give it time to fix the present
shortcomings in its capability or qualifications, assuming that
they are fixable within the time remaining in the ordering
period. If the contract involves multiple awards and a fair
opportunity to be considered, then a determination of
nonresponsibility would fulfill that requirement -- a CO should
always consider a contractor's present responsibility when
giving it a fair opportunity. If the contract action is the
exercise of an option, no further action is required by the CO
following a determination of nonresponsibility, since
contractors are not entitled to the exercise of an option.
By
bob antonio on
Tuesday, June 26, 2001 - 07:52 am:
Linda:
I see nothing wrong with a mental check for contracting officers
before placing orders. As I mentioned in my first note, a
checklist may be useful. My concern is with documenting some
action that is not required. If the contracting officer's
analysis reveals reasons for not executing an order, the
appropriate action on the appropriate contract may be taken as
Vern suggested.
As we all know, contract files are required to include certain
basic items by law or regulation. Then there are agency add-ons.
They should be kept to the minimum necessary to document the
history of a procurement.
Many years ago, I was reviewing a source selection when I came
across a document with the following: "(Program title) source
selection or (Program title) Watergate." After spending three
months reviewing the source selection, I was confident that it
represented the best efforts of over 200 federal employees and
their consultants to identify the best contractor for the
specific mission. I took the file with the document to the
source selection team and asked if the document was needed in
the file. That was the last anyone saw of the document.
The Art-Metal case was an oddity. I don't think there is
anything else like it. However, it usually appears somewhere in
federal contracting texts and it is on record in the federal
court system. It is an excellent example of what a skilled
attorney can do. Art-Metal's attornies were well-practiced.
By
Kennedy How on
Tuesday, June 26, 2001 - 12:08 pm:
If I remember correctly, we used
to have a boilerplate form which the Contracting Officer signed
when he was exercising an option. There were some words to the
effect that there was a check done to make sure the contractor
was still eligible for the award (as in, he wasn't debarred in
the interim). I also believe that there was a blurb regarding
the fact that the contractor was currently performing
satisfactorily.
As far as Delivery Order awards are concerned, I'm with Vern in
that we don't really need a full blown Responsibility
determination every time we award one, but you can be if the
contractor went into the tank or screwed up royally in the
interim, we'd be documenting that fact for further consideration
as to what steps to take next. In other words, status quo, no
formal documentation. If negative/adverse info, formally
document!
Kennedy
By
CMERCY on Tuesday, June 26, 2001 - 03:21 pm:
I agree with Bob but further,if a
nonresponsibility determination was written to support a T4D,
and the contractor was a small business,aren't you opening a
door that is best left closed? If a termination for default is
called for ,of what value is a responsibility determination at
that point? I simply cannot accept that a determination is an
alternative to termination. And it is because of that that in my
opinion a RD before any contract action would be indicative of
poor contract admin...not vigilant admin.
By
Eric Ottinger on
Tuesday, June 26, 2001 - 03:39 pm:
CMERCY,
I agree. Endorsing something like an affirmative determination
of responsibility for orders without thinking through the
consequences of a negative determination is illogical.
Certainly, we should assure that the customer is actually going
to obtain the product on schedule. However much that might be
like a determination of responsibility, it is not the same
thing. The Trilon case should make it clear that the
determination of responsibility is a one-time action not an
ongoing process.
Eric
By
Vern Edwards
on Tuesday, June 26, 2001 - 03:50 pm:
CMercy:
I don't think that anyone in this thread has said or suggested
that a determination of nonresponsibility is an alternative to
contract termination. A determination of nonresponsibility might
be a reason for termination, but it is not a way to end an
existing contract.
Please explain how making a determination of responsibility
after award but prior to any subsequent contract action -- such
as issuance of an order or exercise of an option -- would be
indicative of poor contract administration. The contractor might
be nonresponsible for reasons that have nothing to do with the
contract in question.
By
Eric Ottinger on
Tuesday, June 26, 2001 - 04:13 pm:
Vern,
I (and I think CMERCY) would say that an affirmative
determination of responsibility implies a determination of
nonresponsibility.
An affirmative determination of responsibility without any
possibility of determination of nonresponsibility is like a one
sided pancake.
Would you do only affirmative determinations of responsibility
at the outset of a contract without ever doing a determination
of nonresponsibility?
If you think the contractor may be nonresponsible (after award)
for reasons that have nothing to do with the contract in
question, you really should read Trilon.
Eric
By
Eric Ottinger on
Tuesday, June 26, 2001 - 05:09 pm:
In the United States Court of
Claims. No. 241-76. Decided , June 14, 1978,
Trilon Educational Corporation v. The United States., (June 14,
1978)
"Absent allegations of fraud or bad faith, then, affirmative
determinations of responsibility generally will not be
overturned, and ordinarily
protests in this regard will not even be entertained. See
Central Metal Products, Inc., 54 Comp. Gen. 66 (1974). Although
this reasoning
usually appears in the context of challenges by unsuccessful
bidders, this court has implied that it also is applicable to
the recipient of a
government contract who later realizes that the favorable
responsibility determination as to him was erroneous.
Transcountry Packing Co. v.
United States [24 CCF¶82,055], 215 Ct. Cl.--,--, 568 F. 2d 1333,
1338 (1978). Similarly, then, the government should also be
bound by its own
assessment even if it should later conclude that the initial
judgment was incorrect."
By
Vern Edwards
on Tuesday, June 26, 2001 - 06:19 pm:
Eric:
Trilon is not applicable to the matter under discussion.
In Trilon the government awarded a contract and then
learned of facts that it did not know about when it made the
initial affirmative determination of responsibility. The facts
were available, but the government did not discover them. Upon
discovering the facts the government declared the contract
"cancelled," i.e., void, and refused to terminate the contract
for convenience. This meant that Trilon was not entitled to
reimbursement of costs that it had incurred in preparing to
perform. Trilon went to court to obtain a convenience
termination, seeking recovery of those costs.
The Trilon court effectively held that the contracting
officer was negligent in making his original determination of
responsibility and that the contractor was not to blame for
this. The court held that the facts of the case did not justify
a declaration that the contract was void and converted the
"cancellation" to a termination for convenience. The court did
not hold that a termination for convenience was improper; it did
not order the government to continue in the contract; it held
that a "cancellation" was improper under the circumstances and
ordered it converted to a termination for convenience.
In the matter that we have been discussing the issue is whether
contracting officers should make a new determination of
responsibility prior to placing an order under an IDIQ contract
or exercising an option. I have not been discussing a situation
in which the contracting officer has learned new facts that were
in existence at the time of the original determination and that
have led him to change his mind. I have been talking about cases
in which new facts have come into existence since the original
award and that have affected the contracting officer's thinking
about future contract actions.
So Trilon is inapplicable to the circumstances that I
have been discussing. But even if it were applicable, it simply
says that termination, not cancellation, may be the more
appropriate course of action upon discovering that a contractor
has become nonresponsible since the original contract award. It
does not say that there is no way for the government to get out
of the contract.
Trilon is short and easy to read and to understand, and
anyone who has been following this thread should look it up and
read it. You will see that my reading is the correct one and
that the case does not apply to my response to Linda's question.
Trilon Educational Corp. v. United States, 217 Ct.Cl. 266
(1978).
By
Eric Ottinger on
Tuesday, June 26, 2001 - 09:42 pm:
Vern (03:50): “Please explain how
making a determination of responsibility after award but prior
to any subsequent contract action …. The contractor might be
nonresponsible for reasons that have nothing to do with the
contract in question.”
Court of Claims: “… the government should also be bound by its
own assessment even if it should later conclude that the initial
judgment was incorrect."
The Court has made a plain English statement to the effect that
the government may only make one responsibility determination
per contract. After that, the government is “bound.”
You seem to contemplate that the contractor might be
“nonresponsible” under an existing contract for some reason
having “nothing to do with the contract in question.”
I have no idea how you can reach that conclusion, if there is
only one responsibility determination per contract and the
government is subsequently bound by that determination.
Eric
By
bob antonio on Wednesday, June 27, 2001 - 05:25 am:
Vern:
Linda also mentioned a requirements contract.
By
Vern Edwards
on Wednesday, June 27, 2001 - 07:01 am:
Eric/Bob:
Eric: When I say "nothing to do with the contract," I mean
nothing to do with anything the contractor has done under the
contract in question. One example of a way in which the
contractor might be nonresponsible for reasons having nothing to
do with anything the contractor did under the contract would be
financial incapacity that makes the contractor incapable of
further performance. Another might be fraudulent conduct under
other government contracts that affects its record of integrity.
Yet another might be fragrant violations of the terms of other
government contracts, e.g., intentional failure to make a good
faith effort to meet the small business subcontracting goals in
its subcontracting plan. Another might be seizure of its assets
by the IRS that makes it incapable of performing. Any of these
and numerous other circumstances that are not directly related
to what the contractor has done under the contract in question
may justify a determination of nonresponsibility prior to the
issuance of an order or the exercise of an option.
Eric: The Trilon court did not make any "plain English"
or other statement to the effect that the government is limited
to one responsibility determination per contract. It didn't come
even close to that. If it did, please quote it the plain English
statement you are talking about. (The quote in your June 26,
5:09pm message is not a plain English statement to that effect
and, in any event, was quoted out of context.) What the court
said was that since the government had been careless in making
its original determination of responsibility, and since the
contractor had not contributed to that mistake in any way, the
government could not "cancel" the contract but had to terminate
it for convenience, instead.
Bob: The fact that the contract is a requirements contract makes
no difference. I believe that if something has happened
subsequent to the initial award, but prior to the placement of a
new order, that renders the contractor nonresponsible, then the
contracting officer can use a determination of nonresponsibility
to justify a good faith termination for convenience.
Eric/Bob: In the spirit of theorizing: I think that a good
lawyer could make a pretty good argument that under a government
indefinite-delivery contract (definite-quantity,
indefinite-quantity, and requirements) the contractor has an
implied obligation to conduct its business in a manner that
maintains its responsibility, as defined in FAR 2.101 and 9.104,
throughout the ordering period of the contract, and that failure
to do so entitles the government to refuse to issue further
orders under the contract.
Maybe such contracts should include a Section H clause to that
effect.
By
Anonymous
on Wednesday, June 27, 2001 - 10:43 am:
Vern,
I'm not sure I agree with your June 22, 5:50 AM analysis of FAR
9.103 regarding the "purchase or award" language. The analysis
appears to ignore the FAR 9.102 "Applicability" language which
states the Responsibility regulations apply to "all proposed
contracts." I would argue that orders under ID contracts and
mods exercising options aren't "contracts" as defined in FAR
Part 2.
The practical effect of this may be that a 3rd party couldn't
challenge an order or option mod as violating the FAR when the
Government fails to support the order or option exercise with a
responsibility determination, even if the contractor was
"non-responsible" at the time of the order or mod.
That being said, I believe proper contract administration
necessitates a responsibility-type analysis before issuing an
order or exercising an option. This is just common sense. In all
but the rarest circumstances, the Government shouldn't make a
"purchase" with a Kr that would fail a FAR 9.104 analysis at the
time of such "purchase."
By
Vern Edwards
on Wednesday, June 27, 2001 - 11:12 am:
Anonymous:
I'd argue that an order under an IDIQ contract is a
"contract" as defined by FAR 2.101. It's mutually binding, it
commits the government to an expenditure of appropriated funds,
and it's in writing. I also think a task order is clearly a
"purchase."
However, as I said in one of my earlier messages, I'm not hard
over about any of this. FAR does not explicitly require a
responsibility determination before the issuance of an order or
the exercise of an option, so if I was working in a contracting
office I wouldn't make an issue about making formal
responsibility determinations.
I'm in complete agreement with your common sense analysis.
Vern
By
Anonymous
on Wednesday, June 27, 2001 - 12:34 pm:
And I would argue a delivery
order is not a contract within the meaning at FAR 2 as it is not
mutually binding on its own terms,and since it has no terms it
does not constitute a writing in the legal sense.If each order
were so constructeed then what does one call the instrument
against which it is issued? Also Part 9 repeats several times
the term "prospective contractor". The term means a contractor
who,as yet has no contract. Once he does he is no longer
"prospective" and therefore nothing in Part 9 is or can come
back to life.
By
Eric Ottinger on
Wednesday, June 27, 2001 - 12:53 pm:
Anon,
Before you invest too much in this argument, there is a recent
case which states that delivery orders are contracts.
Eric
By
Vern Edwards
on Wednesday, June 27, 2001 - 01:39 pm:
Anonymous:
FAR 2.101 defines "contract" as follows:
"'Contract' means a mutually binding legal relationship
obligating the seller to furnish the supplies or services
(including construction) and the buyer to pay for them. It
includes all types of commitments that obligate the Government
to an expenditure of appropriated funds and that, except as
otherwise authorized, are in writing. In addition to bilateral
instruments, contracts include (but are not limited to) awards
and notices of awards; job orders or task letters issued under
basic ordering agreements; letter contracts; orders, such as
purchase orders, under which the contract becomes effective by
written acceptance or performance; and bilateral contract
modifications. Contracts do not include grants and cooperative
agreements covered by 31 U.S.C. 6301, et seq."
Task and delivery orders issued against IDIQ contracts satisfy
every requirement of that definition. Besides--if "job orders,"
"task letters" issued under BOAs are contracts, then it seems
clear to me that task and delivery orders issued under
indefinite-delivery contracts are contracts.
By
Anonymous
on Wednesday, June 27, 2001 - 02:28 pm:
At the risk of being unctuouness
how is a delivery order against an IDIQ mutually binding? Where
is the offer and acceptance? In the context of Lindas original
inquiry I believe the delivery order is more properly defined as
a "contract action" as opposed to a "contract". It is also
interesting to note that job orders and task letters are not
considered,within the definitation,bi-lateral..therefore would
not be considered mutually binding until some other evernt.
By
Vern Edwards
on Wednesday, June 27, 2001 - 03:04 pm:
Anonymous:
A delivery order requires a contractor to delivery supplies and
requires the Government must to pay for them upon acceptance and
invoice submission. The basic IDIQ contract doesn't obligate the
Government to pay anything, since nothing is purchased
until an order is issued.
Since a delivery order requires both parties to do something, it
is mutually binding.
By
Eric Ottinger on
Wednesday, June 27, 2001 - 03:37 pm:
Anon,
Trust me Anon. There is no risk of you being unctuouness.
We had a long thread on this topic a year or two ago, so the
answer is not self-evident.
However, Vern is right. When the relevant case surfaces, I will
provide it.
Eric
By
Eric Ottinger on
Wednesday, June 27, 2001 - 07:47 pm:
I drafted a reply to Vern. Then I
found a case which makes further discussion unnecessary.
Note that Cibinic and Nash cite an old case, (which I find
convincing) which equates orders under indefinite quantity
contracts with options.
E. Huttenbauer & Son, Inc.
Comptroller General Decision , , No. B-258018.3, March 20, 1995
Alan M. Grayson, Esq., for the protester.
[Text of Official Digest]
“A decision not to exercise an option based on
responsibility-type concerns does not require referral to the
Small Business Administration where the contractor is a small
business since such decision does not involve a responsibility
determination; the concept of responsibility is applicable only
in the contract formation process and not in the administration
of contracts already awarded.
[See 5275 ]
[Text of Decision]
E. Huttenbauer & Son, Inc., a small business, requests
reconsideration of our decision, E.Huttenbauer & Son, Inc.,
B-258018.2, Feb. 21, 1995, in which we dismissed E.
Huttenbauer’s protest that the Defense Logistics Agency was
required to refer the question of Huttenbauer’s responsibility
in connection with the agency’s decision not to exercise an
option in Huttenbauer’s contract to the Small Business
Administration (SBA). We held that contract options are
exercised solely at the discretion of the contracting officer
and that there is no requirement for a referral to the SBA prior
to a decision not to exercise a contract option.
In its reconsideration request, Huttenbauer argues that we
ignored the Small Business Act in rendering this decision.
Huttenbauer states that under the act only the SBA, not the
contracting agency, can determine that a small business is not
responsible, asserts that the decision not to exercise the
option was based on a nonresponsibility determination, and
concludes that therefore a referral to the SBA was required
before the agency could properly decide not to exercise the
option.
We did not ignore the requirements of the Small Business Act in
rendering our decision. We explicitly noted that the SBA has the
conclusive authority to determine the responsibility of a small
business for the purpose of receiving and performing a
government contract. We further stated, however, that the SBA
referral requirement is not applicable to post-award situations.
We reached this conclusion because the concept of
“responsibility” has no applicability with respect to a contract
once that contract has been awarded. Responsibility is a
contract formation term that refers to the ability and
willingness of a prospective contractor to perform the contract
for which it has submitted an offer; by law, a contracting
officer must determine that an offeror is responsible before
awarding it a contract. See 10 U.S.C. §2305(b)(3), (4) (Supp. V
1993); Federal Acquisition Regulation (FAR) §9.000 et. seq. Once
that offeror is determined to be responsible and is awarded a
contract, the role of “responsibility” with respect to that
contract is over.
The new relationship between the government and the awardee/contractor
is not governed by contract formation rules; instead, it is
governed by principles of contract administration, any
applicable FAR provisions, and the provisions of the contract
itself. That means that if the contractor should perform poorly
or not comply with specification requirements, the contracting
officer does not then make a new responsibility determination
and find the contractor to be nonresponsible; instead, the
contracting officer proceeds under contract provisions
permitting him to take certain actions up to and including
termination of the contract for default or for the convenience
of the government.
Similarly, if a contract contains option provisions, the
contracting officer is not required to make a new responsibility
determination before deciding whether to exercise an option; he
simply proceeds pursuant to those option provisions and to the
applicable provisions in FAR §17.207. Those provisions establish
no prerequisites for a decision not to exercise an option; thus,
that decision is solely within the discretion of the contracting
agency. In other words, in administrating the contract the
contracting agency is free to decide, whether on the basis of
concerns about performance or for any other reason, that it does
not wish to extend or expand the contract through the exercise
of an option.
In short, a decision not to exercise an option, even if based on
responsibility-type concerns 1 about acceptable contract
performance, does not involve a determination that the
contractor is not responsible--it is simply one of several
decisions--such as whether to issue a cure notice, see FAR
§49.402-3, whether to impose liquidated damages, see FAR
§49.402-7, and whether to terminate the contract, see FAR part
49, that a contracting agency having such concerns might make in
administering its contracts.
Since a responsibility determination is not being made, there is
no requirement that such a matter be referred to the SBA
pursuant to its authority under 15 U.S.C. §637(b)(7)(A) (1988)
to certify the responsibility of a small business to receive and
perform a contract.
The decision is affirmed.
Robert H. Hunter Senior Associate General Counsel
1It is not uncommon for responsibility-type concerns to be taken
into account in situations that do not involve responsibility
determinations and therefore do not require SBA referral. See,
e.g., Tri-Services, Inc., B-256196.4, Sept. 30, 1994, 94-2 CPD
121.”
If I may quote the excellent words of my good friend Old Timer.
“Careless use of acquisition terminology suggests ignorance of
the rules and is a great source of confusion and trouble.”
I think the following comments are still apropos, from am
acquisition reform point of view, if nothing else--
Vern,
(I am glad you are no longer hard over, but …) In my dictionary
“bound” is defined as, “Under legal or moral obligation or
contract.” That sounds like “for better or for worse” to me. You
can’t just say, “I didn’t think you were ugly when we started
this relationship, but now I think you are ugly.”
To me, “bound” is plain English, meaning, “You only get to make
this decision once.”
You are going way out of your way to make my acquisition reform
argument. Your doctrine is redundant, unnecessary, one sided,
and unsupported by anything other than your own suppositions.
Nobody is arguing that we don’t have appropriate policy and
procedures for doing terminations or negotiating deductive
changes. We know how and when to do these things. If a
termination is appropriate, there is no need for a
nonresponsibility determination to support the termination.
In a way we are making progress. Last year I had to argue that
orders are each separate contracts. Now, it seems most of us are
agreed on that point.
I can see Linda’s logic for doing a separate determination of
responsibility for an individual order (assuming the government
is not contractually bound to award the order). But, I don’t see
how you can do a nonresponsibility determination for an order,
without repudiating the affirmative responsibility
determination, which the government has made for the overall
contract, and making that responsibility determination an
ongoing process rather than a one-time determination.
At the FAR level, it is not even contemplated that the
Government will withhold orders from a debarred contractor
(albeit the DFARS goes the other way, with the possibility of a
high level waiver). That should have been enough to bring this
argument to closure, but this forum is off making policy in
places that the FAR clearly doesn’t want to go.
If one of our participants started talking about a contract,
which is not really a contract, but it is something like a
contract, or a termination which is not really a termination, I
don’t think most of us would consider that good practice.
Significant terms, which have exact meanings, should not be used
imprecisely.
Linda asked whether she should be doing a determination of
responsibility, not whether she should be doing something like a
determination of responsibility.
Eric
By
Anon2U on Wednesday, June 27, 2001 - 10:40 pm:
Once again I must say that
contracting is far too complicated for even KO's with 10 years
or more experience let alone the rest of us who are just coming
on board. The Office of Federal Procurement Policy, the FAR
council, or some other policy making agency should beat these
gray areas to death and issue a single federal policy that all
can understand. Not likely to happen due to politics however.
I discussed FAR policy with someone who works with the FAR
council and they said that every time they issue a proposed rule
for public comment, the lobbyists file hundreds of briefs with
opposing positions. So after months of writing and rewriting to
account for differing political pressures, the guidance that
results is no longer understandable. We leave it to the GAO and
legal systems to interpret it.
You go to contracting classes at DAU, MCI, ESI/George Washington
and they all put a different spin on the same topic. Their
instructors debate topics just like everyone does on this
bulletin board, which leaves you not knowing which is the right
way. You are always damned if you do or damned if you don't.
I'll grant you that a portion of the career field has to be art,
but most should science. Follow the procedure and you will be
right 99.9% of the time. But here we are with years of
experience still debating what is an offer and what is not.
So, we beginners do the best job we can. If someone proves I'm
wrong, I try to fix it. If I lose a protest, I may know how to
do it right next time (provided a different lawyer don't
interpret the same law differently). However, I don't think the
taxpayers should have to pay for my getting experience by trial
and error. And just think, half of the current experience is
supposed to retire in the next 5 years. No wonder everyone is
bailing out of contracting and my agency is complaining they
can't hire enough contract specialists.
By
Vern Edwards
on Wednesday, June 27, 2001 - 10:53 pm:
Eric:
Good catch with GAO's Huttenbauer decision. I surrender on that
basis. However, the rest of your comments are nonsense.
Vern
By
Linda Koone
on Thursday, June 28, 2001 - 04:17 pm:
Thanks for the assistance!
By
John Ford on Thursday, June 28, 2001 - 08:46 pm:
Eric, not wanting to pile on, but
your assertions that individual orders under IDIQ contracts are
contracts is unsupported by the regulations and case law that I
have been able to find. I know we had this discussion several
months ago, but your position means that we have a contract, or
several contracts, within a contract. You mention that you found
a recent case that supports your position, but you did not
identify the case. Please do so, as I explained in our previous
discussion, I have found case law to the contrary.
By
joel hoffman on Thursday, June 28, 2001 - 09:34 pm:
John, I feel that too many people
take the FAR definition of a "contract" too literally. I think
the definition was generalized so that it wouldn't have to be
defined umpteen thousand times throughout the FAR. Note that
in-scope modifications are lumped into the definition. Does that
mean that every mod is a new contract? Heck no! happy sails!
joel
By
Vern Edwards
on Thursday, June 28, 2001 - 10:56 pm:
John and Joel:
I'm with Eric on this one. See the GAO's decision in Sea-Land
Service, Inc., B-278404, Feb. 9, 1998:
"An IDIQ contract for services contemplates the issuance of
orders for the performance of tasks during the period of the
contract. See 10 U.S.C. § 2304d(1) (1994). Such orders are
contracts within the overall IDIQ contract, see FAR § 2.101
(definition of contract), and are subject to the terms and
conditions of that contract."
By
joel hoffman on Friday, June 29, 2001 - 10:19 am:
Vern, the Decision you cited
merely confirmed that there was a contract when cargo was booked
for shipment, even though the shipping order is prepared after
the booking and/or sailing date. The booking is the contract
order. All it really said was that an order is a contract
instrument to obtain the service.
I didn't read it as though each order is a separate contract,
any more than a bilateral modification is. Happy Sails! joel
By
Vern Edwards
on Friday, June 29, 2001 - 11:03 am:
Joel:
I'm sorry to disagree with you, but the GAO said what it said in
very clear terms. The paragraph that I quoted was introductory
and general and was not restricted to the specific facts of the
case.
I don't understand on what basis you and John dispute that
delivery and task orders are contracts. FAR 2.101 says that the
term contract "includes all types of commitments that
obligate the Government to an expenditure of appropriated funds
and that, except as otherwise authorized, are in writing."
Underlining added. That language describes delivery and task
orders perfectly. The GAO says that task orders "are contracts
within the overall IDIQ contract."
Where are you guys coming from on this?
By
Eric Ottinger on
Friday, June 29, 2001 - 11:10 am:
All,
Take a look at Ness Manufacturing, Inc. ASBCA No. 50747, January
17, 2001
http://www.law.gwu.edu/asbca/decision/pdf2001/50747.pdf
This is a case where the parties get into a lot of confusion
because it isn’t clear which contract is the contract. However,
the ASBCA doesn’t seem to be confused.
“The disputed language applies where a purchase order is
converted to a bilateral contract …”
“…recognizing that issuance of a purchase order ‘constituted an
offer to enter into a unilateral contract’”
Note that the ASBCA uses the terms “delivery order” and
“purchase order” synonymously in this case.
I think “orders” are viewed as nice, easy to do, and easy to
manage little creatures. When we collectively realize that we
are proliferating little contracts, and each must be separately
negotiated, separately funded, separately administered and
separately closed out, there will be some second thoughts.
One thing that you learn doing contract administration-- On the
average a small contract is less hassle than a large contract.
However, the hassle per dollar is much greater for small
contracts.
Although I agree with John that the idea of a contract inside of
a contract makes my head hurt, this doesn’t seem to be an issue
with the legal community.
Eric
By
joel hoffman on Friday, June 29, 2001 - 11:51 am:
Vern, I apologize for appearing
to disagree with you. I have no disagreement whatsoever with
anything you said. I wasn't closely following this thread. I
reread what discussions you were responding to and agree with
you. I thought someone was resurrecting another argument.
To me, a contract within a contract means that,although each
ordering action or obligation is separate, they are under the
umbrella agreement (contract) within existing scope limitations,
terms and conditions, etc., unless modified in the bilateral
agreement. A task order must fall within the scope of the
contract, unless an out-of-scope supplemental agreement is
otherwise authorized. Happy Sails! Joel
By
Anonymous
on Friday, June 29, 2001 - 12:11 pm:
BC "It depends on what the
definition of is is." I,along with others,conclude that since a
DO/TO has no meaning unless issued within the terms of a
"contract" they are simply not contracts of or by themselves.
They are merely events that take place within the four corners
of "the" contract. It may be handy to think of them as such but
that alone does not bring them within the definition of the FAR.
The fact that casual use of the term in the referenced decisions
should not be construed as the definition. The statement about
contract mods not being contracts is on point . Another way of
looking at it is the definite delivery contract. Fully obligated
at award it still requires an order for events to occur. Does
that meet the "contract" test? In all I think there are some of
us who simply do not subscibe to the notion that you need a
contract to carry out a contract.
By
Eric Ottinger on
Friday, June 29, 2001 - 12:46 pm:
Anon,
It is important to distinguish Technical Instruction Letters,
Task Assignments, etc. which are technical direction under a
contract, from Task Orders and Delivery Orders which are, in
fact, contracts.
One key is the fact that the FAR (and the statute) specify that
each order will have a distinct Part 16 contract type. The
language in the FAR is about as muddy as you can get, but I have
construed this language in the only way that you possibly can.
Part 16 is contract types.
FAR 16.501-2 (c) “Indefinite-delivery contracts may provide for
any appropriate cost or pricing arrangement under Part 16. Cost
or pricing arrangements that provide for an estimated quantity
of supplies or services (e.g., estimated number of labor hours)
must comply with the appropriate procedures of this subpart.”
Also, it is typical for the indefinite quantity umbrella
contract to specify that the orders may be more than one
contract type (e.g. FFP and CPFF). It really isn’t possible for
an order to have a contract type unless the order is itself a
contract.
In any case, you are pursuing an argument long after you have
lost the argument. You should find a better interpretation for
the case law cited, or find better case law.
You should be at least a full professor before you should be
allowed to let your preconceptions and irrefutable logic take
precedence over the opinions of a court in this forum.
Eric
By
Anonymous
on Friday, June 29, 2001 - 02:30 pm:
Neither case was a court
decision...legal forum but not a court.
By
Anonymous
on Friday, June 29, 2001 - 03:04 pm:
I admit the FAR Part 2 definition
is poorly written, and a literal interpretation of the language
would lead those unfamilar with contract law to conclude a
unilateral order under an ID contract is a new contract,
separate from the ID contract. Although I doubt it, perhaps the
drafters of this definition even intended such to be the case
under the FAR.
However, it doesn't take a professor in contract law to
recognize unilateral ID orders are not separate contracts. As
established through more than 1000 years of contract law, an
essential element of any contract is "mutual assent." (most
commonly, this element is satisfied through offer and
acceptance).
There is no separate "mutual assent" in a unilateral task or
delivery order. The contractor has already assented to perform
the order in the base ID contract.
As stated above, I don't believe the drafters of the FAR 2
definition ever intended ID orders to be separate contracts.
Note that all examples of "contracts" in the FAR 2 definition
meet the common law requirement for "mutual assent." Even BOA
orders, which are cited in the definition, require the
contractor's assent as the contractor doesn't assent to anything
upon formation of the non-contract BOA.
By
Eric Ottinger on
Friday, June 29, 2001 - 03:23 pm:
Anon,
You are correct of course.
However, anyplace where I address the judge as "Judge" would
seem to be a "court" to me.
If I understand correctly-- (Keep in mind, I am not a lawyer.)--
these fora are outranked in the judicial pecking order by actual
courts, but no one would say that they don't know a contract
when they see one.
Eric
By
Ron Vogt on
Friday, June 29, 2001 - 07:08 pm:
I have no problem with the
concept of a contract within a contract. We frequently do
alliances, overriding agreements, or general terms agreements,
under which orders are placed by issuing purchase orders or
separate contracts. Both the top-level contract and the purchase
order are separate contracts. Usually, the top contract states
that any purchase order incorporates and is subject to the Ts
and Cs set forth in the contract. That makes the order a
complete contract.
Despite the interrelationship, the top contract and the orders
placed under it are separate contracts. A breach of one is not
necessarily a breach of the other. From a seller's perspective,
you want the overall contract to survive even if there is a
breach of an individual purchase order. Depending on how your
write each contract, a breach of the top contract might
terminate all orders placed under it, or it might call for
completion of any pending orders.
The point is still the same - they are separate contracts with
separate obligations and separate remedies. How much they affect
each other depends on how you write them.
By
Vern Edwards on
Saturday, June 30, 2001 - 10:58 am:
All:
One mistake that some of you -- like Anonymous of June 29 at
03:04 p.m. -- are making is in thinking that the definition of
contract in FAR 2.101 defines the legal concept of
contract. It doesn't.
Read the beginning of FAR 2.101. The definition of contract
in FAR 2.101 merely defines the term "as used throughout this
regulation." Among other things, the definition serves to
distinguish contracts to which the FAR applies from grants and
cooperative agreements and from contracts awarded by
nonappropriated fund instrumentalities.
As a definition of the legal concept of contract the definition
in FAR 2.101 is entirely inadequate. All you have to do to see
that is to compare it to the one in Black's Law Dictionary.
Note that the definition in FAR 2.101 excludes contracts awarded
by nonappropriated fund instrumentalities, even though they are
contracts under the law. Also, while most grants are contracts
under the law (see Cibinic and Nash, Formation of Government
Contracts, 3d ed. (1998), p. 15.), they are not contracts
under the FAR.
Talk about judicial pecking orders is beside the point. I quoted
the GAO because John Ford asked for such a reference and to show
that someone besides Eric and I think that delivery and task
orders fall within the definition in FAR 2.101. The quote from
the GAO is dicta; it is not a holding in that case. Note
that it cites FAR 2.101 as authority, not a court decision or a
contact law textbook.
I agree that the definition in FAR 2.101 is badly written, but
it is not entirely obscure. The second sentence in the
definition is clear enough and it clearly includes delivery
orders and task orders. The Comptroller General agrees, which
should be worth something.
What I don't understand is why this troubles some of you.
|