By Anonymous
on Wednesday, July 11, 2001 - 09:37 am:
Why is the contract type
prohibited?
By
PWG on Wednesday, July 11, 2001 - 09:50 am:
Because that type of contract
would encourage wasteful spending rather than fiscal
responsibility. The higher the cost a company incurs, the more
profit they would make. The Government wants to encourage cost
savings not cost escalation.
By
Eric Ottinger on
Wednesday, July 11, 2001 - 09:55 am:
Anon,
U.S. Supreme Court,
MUSCHANY ET AL. v. UNITED STATES; ANDREWS ET AL. v. SAME., (Feb.
05, 1945)
"The purpose of Congress was to protect the Government against
the sort of exploitation so easily accomplished under
cost-plus-a-percentage-of-cost contracts under which the
Government contracts and is bound to pay costs, undetermined at
the time the contract is made and to be incurred in the future,
plus a commission based on a percentage of these future costs.
The evil of such contracts is that the profit of the other party
to the contract increases in proportion to that other party’s
costs expended in the performance. The danger guarded against by
the Congressional prohibition was the incentive to a government
contractor who already had a binding contract with the
Government for payment of undetermined future costs to pay
liberally for reimbursable items because higher costs means a
higher fee to him, his profit being determined by a percentage
of cost. Congress certainly did not intend to prevent a party
who was merely submitting a bid to the Government from computing
the amount of his bid by taking into consideration his costs and
then adding a certain percentage of the cost as his profit, the
resulting sum bid being fixed in amount and not subject to
change. Congress, by changing the original prohibition in the
act from one outlawing any “cost-plus” system of contracting so
as to expressly authorize use of a “cost-plus-a-fixed-fee” form
of contract, indicated it did not care how the contractor
computed his fee or profit so long as the fee or profit was
finally and conclusively fixed in amount at the time when the
Government became bound to pay it by its acceptance of the bid.
By eliminating the risk of loss and permitting the guarantee of
a satisfactory but fixed fee, Congress sought prompt performance
and lower over-all expenditures for contracts in a rising labor
and commodity market than would be offered by contractors who
were compelled themselves to assume the risk of these
unpredictable costs."
By
Roger Miller on Wednesday, July 11, 2001 - 10:45 am:
So in layman terms - If a
contractor purchase material for 50.00 the Government would give
him a percentage of the 50.00. It base the contractor's fee on
the amount of funds it expends. So, rather than paying 10.00 for
the material he would pay 50.00 to increase his profit. Is this
the right understanding. Eric and Bob you guys are really great,
but remember I am stll learning, and you have been very helpful.
By
Eric Ottinger on
Wednesday, July 11, 2001 - 11:07 am:
Roger,
I would say that you have done a good job of summarizing what
the Supreme Court had to say.
This goes back to the period after WWI when defense contractors
had a bad reputation. ("Merchants of Death," "war profiteer,"
etc.) It is interesting that Congress initially intended to
prohibit all cost type contracts.
Evidently some wise heads advised Congress that it would be very
hard to fight a war in the future if all contracts were strictly
fixed price.
To understand CPPC you must read Cibinic and Nash. It is
important to understand that it is the CPPC "system" which is
illegal, and any contract which works like a CPPC, very likely
is a CPPC.
On the other hand, because auditors consider it a coup to allege
outright illegality, auditors (and other amateurs) often find
CPPC in situations which are entirely legal.
As long as the fee is subject to negotiation there is no CPPC.
As long as the fee may be more of less, depending on the
contractor's ability to control costs, there is no CPPC.
Eric
By
bob antonio on Wednesday, July 11, 2001 - 11:38 am:
Roger:
The key Court and Comptroller General decisions provide a three
or four-step process for the identification of an illegal
cost-plus-a-percentage-of-cost system of contracing. If anything
meets the steps outlined, then it is illegal.
I do not have access to information I am looking for but the
illegal contract is not always obvious.
By
Eric Ottinger on
Wednesday, July 11, 2001 - 01:18 pm:
Roger and Bob,
Correction: “more of less” should have been “more or less.”
The four tests are in the Deskbook.
Title: Contract Pricing Reference Guide; Volume 3; Cost
Analysis; 13 June 2000
Cost-Plus-Percentage-Cost ( CPPC ).
“Beware! The CPPC contract is illegal in Government contracting.
A CPPC contract can occur in any situation where the contractor
is allowed to increase fee by increasing cost, thereby creating
a negative cost control incentive. If the answers to the
following four questions are yes, you have a CPPC contract.
• Will fee be paid based on a predetermined percentage fee rate
instead of an identified dollar value?
• Will the predetermined percentage fee rate be applied to
actual future performance costs?
• Is the contractor’s fee entitlement uncertain at the time of
contract pricing?
• Will the contractor’s fee entitlement increase as performance
costs increase?”
A “situation where the contractor is allowed to increase fee by
increasing cost” describes almost every situation in government
contracting, excepting a cost contract with no fee or a cost
contract in an overrun condition.
(Actually, the temptation to increase cost, with or without an
increase in fee, is also corrupting. Defense contractors will be
motivated to increase costs just for the purpose of keeping
their employees working and paid. Small firms can get along with
zero or a very small profit if the principals are being paid
well with direct and indirect cost dollars.)
The four tests were established by the Comp. Gen. It is
important to understand that any contract which conforms exactly
to the four tests is an illegal CPPC. It doesn’t follow that
every illegal CPPC will conform exactly to the four tests. (See
Cibinic and Nash.)
Eric
By
bob antonio on Wednesday, July 11, 2001 - 02:31 pm:
Eric:
I do not have my materials with me but I believe the Deskbook is
incorrect in its terminology. I think the word "fee" may be
absent from the decisions because it covers more than fee.
However, I am speaking off of the top of my head. If I get a
chance tonight, I will check.
By
Eric Ottinger on
Wednesday, July 11, 2001 - 02:54 pm:
Bob,
I think the key is the following in Muschany:
“[Congress] did not care how the contractor computed his fee or
profit so long as the fee or profit was finally and conclusively
fixed in amount at the time when the Government became bound to
pay it by its acceptance of the bid. By eliminating the risk of
loss and permitting the guarantee of a satisfactory but fixed
fee, Congress sought prompt performance and lower over-all
expenditures for contracts …”
Although the Supreme Courts talks about “fee or profit,” in the
context of our normal Part 16 contract types, it is only fee
that should remain fixed.
I don’t like the Pricing Guide language because it is the kind
of loose, inexact logic that allows auditors to casually accuse
buying offices of an illegality.
Eric
By
bob antonio on Wednesday, July 11, 2001 - 06:22 pm:
I did a good deal of research on
this years ago and the oversight that appears to be made by the
pricing manual authors is that the illegal contract is linited
to fee. It also includes, if I remember correctly, overhead and
general and administrative costs. Actually, any percentage
attached to a cost or costs may end up as a problem. I cannot
remember the bizarre conditions for this to happen. However, I
am quite sure there is at least one case on this.
I would have to do a good deal of research on what I did years
ago but there are numerous areas for a serious scholar to do
research and write an article on the subject.
Is it worth someone's time to worry about this illegal system of
contracting? Probably not. I have never seen one. It is a near
hopeless search looking for them. I have seen a claim that an
agency was systematically doing this around 1980. However, I do
not know where the documents are for that either.
By
Vern Edwards on
Thursday, July 12, 2001 - 06:31 am:
The CPPC prohibition is not
limited to fee. See 35 Comp. Gen. 434 (1956):
"The fixed percentage rates specified in the subject contracts
were intended to represent payment for reimbursable indirect
costs and were not intended to enhance the net return to the
contractor. Nevertheless, inasmuch as the amount paid as
reimbursement for overhead will diminish or increase in
proportion to the direct costs incurred rather than the overhead
incurred by the contractor, we are of the opinion that the
contracts violate the express prohibition against the
cost-plus-a-percentage-of-cost system of contracting and,
therefore, are illegal."
The GAO has cited that decision as recently as 1993. See the
Comptroller's letter to Mr. James K. White, Assistant General
Counsel for Finance and Litigation, Office of the General
Counsel, Department of Commerce, dated September 21, 1993,
B-252378.
By
bob antonio on
Thursday, July 12, 2001 - 07:29 am:
Vern:
Thanks. I have a list of cases somewhere at home. That is very
much like the one I was hoping to find.
By
Eric Ottinger on
Thursday, July 12, 2001 - 09:43 pm:
Bob and Vern,
I see your point.
The rate may be any percentage factor applied to actual costs,
not just fee.
However, I don’t think you will see a CPPC issue unless the
factor includes some element of additional profit for the
contractor.
See Cibinic and Nash, “Formation of Government Contracts” Third
Edition, pages 1067 and 1068.
“Neither the board nor the court found that payment of material
handling costs as a percentage of material costs was proscribed
as long as the material handling costs were excluded from the
contractor’s overhead [to assure that there would not be any
double counting].”
“The problem created by contracts where one type of costs is
paid on a percentage basis is that such compensation may be
greater than the actual costs incurred by the contractor, with
the result that part of this compensation will be additional
profit.”
Alisa Corporation AGBCA No. 84-193-1, June 9, 1994, is a recent
case where a contract was determined to be void ab initio.
If CPPC is a very rare occurrence, it is probably because this
is an issue where everybody is highly sensitized. I would not
say that it is unimportant.
Even if actual CPPC contracts are rare, I have seen the issue
raised frequently enough by audit types, reviewers and other
kibitzers. It is worthwhile to get Cibinic and Nash out and read
carefully, for self-protection, if nothing else.
Personal Opinion: We put a little too much weight on the four
criteria. More attention should be paid to Muschany.
In this era of creative contracting some clever fellow is going
to contrive a contract with a sliding fee, in which the fee
increases as the cost increases, in which however, fee isn’t an
exact percentage of the cost. At that point, the Comp. Gen. or
somebody is going to dig up Program Resources, Inc., ASBCA No.
21656, November 8, 1977.
“It is inherent in cost-plus-fixed-fee contracts that before the
fixed fee may be increased or decreased there must be some
change in the scope or nature of the work to be performed by the
contractor. A contract in which the fee increases or decreases
in proportion to the reimbursable cost of the work is a
‘cost-plus-percentage of cost’ contract and is prohibited by
law.”
Going back to the pricing guide, I don’t believe that every
“situation” “where the contractor is allowed to increase fee by
increasing cost” is going to be CPPC. (If that were true, we
would never include additional fee in an equitable adjustment.)
I do believe that every “contract” which provides that fee will
increase, in whatever proportion, merely because the cost
increases, is very likely not legal.
“[Congress] did not care how the contractor computed his fee or
profit so long as the fee or profit was finally and conclusively
fixed in amount at the time when the Government became bound to
pay it by its acceptance of the bid.” (Muschany)
I would like to nominate Tero Tek International, Inc. for “Most
likely to get everyone confused and be reversed on appeal.”
Tero Tek International, Inc., (Feb. 10, 1988) No. B-228548.,
February 10, 1988
“We find that the travel reimbursement portion of the contract
does not constitute a CPPC contract. … Here, condition number 3,
that the contractor’s entitlement is uncertain at the time of
contracting, is not met. The contract limits the cost of travel
to rates established in various Federal Travel Regulations.
Further, the contract also provides that all travel requests by
the contractor are subject to prior governmental approval. Thus,
we cannot conclude this is a CPPC contract since the
contractor’s entitlement is not uncertain at the time of
contracting.”
The contractor’s projected travel costs are certain (or “not
uncertain”) merely because the government specifies the rates in
the JTR and the government approves the contractor’s travel.
Huh.
Eric
By
Vern Edwards on
Thursday, July 12, 2001 - 11:29 pm:
Eric:
It is precisely the four criteria to which we should pay
attention. You can't put too much weight on them. The criteria
were established by the GAO, it's the GAO that is most likely to
rule on any CPPC issue, and the GAO has adhered to the four
criteria for at least 46 years. Here is how they articulated
those criteria in 1975:
"WE HAVE RENDERED DECISIONS INVOLVING THE ISSUE OF WHETHER
CERTAIN TYPES OF CONTRACTUAL ARRANGEMENTS CONSTITUTED PROHIBITED
COST-PLUS-A-PERCENTAGE-OF-COSTS ARRANGEMENTS. CF. 35 COMP.GEN.
434 (1956); 38 ID. 38 (1958); AND 46 ID. 612 (1967). THE
GUIDELINES APPLICABLE TO THIS CONSIDERATION ARE: (1) PAYMENT IS
ON A PREDETERMINED PERCENTAGE RATE; (2) THE PREDETERMINED
PERCENTAGE RATE IS APPLIED TO ACTUAL PERFORMANCE COSTS; (3)
CONTRACTOR'S ENTITLEMENT IS UNCERTAIN AT THE TIME OF
CONTRACTING; AND (4) CONTRACTOR'S ENTITLEMENT INCREASES
COMMENSURATELY WITH INCREASED PERFORMANCE COSTS."
35 Comp.Gen. 434 (1956). (Forgive the capital letters; that's
the way the decision was printed.)
Here is the way the GAO articulated the four criteria 37 years
later:
"Our Office uses the following criteria to determine whether a
method of payment represents a prohibited
cost-plus-a-percentage-of-cost arrangement:
(1) Payment is at a pre-determined rate,
(2) the pre-determined rate is applied to actual performance
costs,
(3) the contractor's entitlement is uncertain at the time of
contracting, and
(4) the contractor's entitlement increases commensurately with
increased performance costs."
B-252378 (1993).
Stick with the four criteria and you won't have any trouble. |