By Anonymous
on Tuesday, October 09, 2001 - 12:29 pm:
My question deals with
terminating a contract in the event work is not successfully
accomplished within the period provided by the contract and when
the contract includes items that are not readily available on
the open market.
In this case, we have a vegetative planting requirement. The
requirement calls for a specific species of plant to be grown
under stringent conditions by a licensed grower, and be ready
for planting by a specific date after award. Plants are
basically considered ready for planting when they are a specific
size, have a minimum number of stems, and be viable and actively
growing.
Here's the problem, if the contractor doesn't have the plants
ready for planting or all the plants aren't in the ground by the
end of the planting date, then the contract must be terminated.
The objectives of my program people will not be met if all the
plants aren't planted.
Therefore, what can a C.O. do to ensure that the contractor
meets the critical time requirements of the contract? Also, what
action can the Government take if the contractor doesn't have
the plants planted by the end of the planting time?
By
Anonymous
on Tuesday, October 09, 2001 - 12:32 pm:
What is the contract type:
Firm-fixed price?
By
Anonymous
on Tuesday, October 09, 2001 - 02:14 pm:
Yes, a firm-fixed price contract.
By
Peggy Richter
on Wednesday, October 10, 2001 - 11:19 am:
Given the current emphasis on
using performance based contracting, your first line of defense
is probably getting & requiring good past performance data --
what is the contractors track record on doing these kinds of
jobs with these kinds of plants? A contractor with a 99% track
record of success in these kinds of jobs is going to be a much
better risk than one with say, a 50% success rate. You can
certainly ask for regular progress reports, which might give you
a clue about problems before the "planting date" but salvaging
the planting in a given season if something goes wrong is going
to be hard no matter what kind of contract you have.
The old method (non performance based) would be to set up the
contract with specific inspection periods or checkpoints to
verify where the contractor is: X number of plants planted, X
number Y" high on such and such a date, X number Y+1" high by
date A+whatever, and so forth. This would at least give you the
chance to detect if the contractor isn't doing the job well in
advance of the final planting date. It is still not going to do
much to salvage things if it goes wrong, but it will keep you
informed.
By
joel hoffman on Wednesday, October 10, 2001 - 11:44 am:
Anon, you said: "Here's the
problem, if the contractor doesn't have the plants ready for
planting or all the plants aren't in the ground by the end of
the planting date, then the contract must be terminated. "
My question is, what do you intend to do at the time you need
the plants, they aren't all in the ground and after you
terminate the contract? Cancel the requirement? Will it be too
late to find someone else?
OR - would you like to be able to write something into the
contract, that if the contractor fails to provide the plants in
time to meet the requirement, that the Government may delete the
requirement, take a credit, find another source and backcharge
the Contractor for any extra costs for the other source?
I think the latter is possible, in a bilateral contract.
I would also develop intermediate performance milestones, so
both parties will be able to tell whether the grower is going to
provide satisfactory plants
happy sails! joel hoffman
By
Anonymous
on Wednesday, October 10, 2001 - 11:48 am:
It seems to me that if this
project is critical good government inspection during the post
award "growing" phase is your best bet. Then if things appear to
be going south there may be time to remedy.As you know you do
not have to wait for failure to terminate....not making progress
and endangering the contract performance allows you to move.
By
joel hoffman on Wednesday, October 10, 2001 - 12:30 pm:
Anon1, is this the entire scope
of work or is it a part of a larger requirement? If this is the
entire scope of work, I agree with Anon 11:48 PM, including
adding a provision specifically stating that if things are going
south, the contract may be immediately terminated for default,
the Government can take immediate action to reprocure through
other means. Be aware, if this is a performance bonded project,
termination for default, in itself, won't necessarily allow you
the freedom to move out immediately to reprocure. The bonding
company has the right to take over the job and they always take
some time to act. Therefore, I would write in special procedures
in case termination for failure to meet schedule. happy sails!
joel
By
Anonymous
on Wednesday, October 10, 2001 - 03:39 pm:
It's part of a fixed price
contract for construction of earthen terraces. The terraces are
built and then vegetated within 15 days after completion of each
terrace. During the plant growing period we have added various
types of checks to ensure ourselves that the plants are being
grown in accordance with our specifications. We have specific
requirements to be met by the contractor during pre-growing
phase, growing phase, and post-growing phase.
My main worry during the growing period is if, for some reason,
the contractor doesn't have the plants ready for the planting
portion of the contract. There is not enough window of
opportunity to begin growing additional plants.
My second concern is if the contractor doesn't meet the planting
deadline. No further time can be provided. The contract stops at
that point.
Reprocurement is not an issue. My technical people say they
can't wait until the next growing or planting period to complete
the work. If either of my concerns comes to pass, the only
course of action I see I have is to terminate the contract for
default, but not reprocure. I feel my options are very limited.
In that case, the Government doesn't get it's requirement and
the contractor doesn't have any excess costs charged to it.
I can see that one of the best defenses available to me is the
wise use of past performance in awarding a contract. Other than
that, I can only hope we have enough inspection and other
controls to ensure we get the plants grown and placed in the
ground within the time provided.
By
joel hoffman on Wednesday, October 10, 2001 - 06:08 pm:
Anon,
(If the contract isn't awarded yet) I strongly suggest that you
take my suggestion and write in the safety valve option to
delete and take a credit for failure to perform - as measured at
various points, including during the nursery phase. As an
option, temporary cover could be provided by other type
plantings - you could also make that a requirement, if the
permanent plantings fail or somehow aren't available.
Of course, you can also issue interim unsatisfactory performance
ratings under the FAR Part 36 Contractor performance rating
system. Although that won't prevent failure, it will serve as an
incentive and should affect chances for future work, if the
plantings are a critical feature of the work. happy sails! Joel
By
joel hoffman on Wednesday, October 10, 2001 - 06:18 pm:
Anon, I forgot to mention that,
if the plantings are not the primary portion of the contract
(perhaps they are ancillary to the primary work? and primary
cost? - the terraces?), and are mainly for "looks", it may not
be justifiable to TFD the entire contract for only failure to
meet the planting schedule. There are many cases in which TFD
for failure to fulfill minor terms of the contract were
successfully challenged, resulting in conversion to TFC. You
have a stronger legal position by taking a credit deletion and
separately procuring the planting.
You can also write a provision into the contract which allows
the Government to do this if the Contractopr can't perform
critical planting on schedule. happy sails! joel
By
Anonymous
on Thursday, October 11, 2001 - 09:38 am:
The plants aren't for looks, but
for holding the terraces together. The terraces are constructed
using the soupy muck that rests under 2-3 feet of marsh water.
That's the reason for requiring the plants to be planted within
15 days of completion of each terrace.
Our technical folks are working closely with state personnel to
re-introduce "native" species of plants into the environment.
It's a cost-shared federal project and my agency is the federal
sponsor.
The temporary cover idea should work. Especially coupled with
specific deletion language should something go awry during the
growing phase. Thanks a bunch to all who responded, especially
Joel.
By
Anonymous
on Tuesday, October 16, 2001 - 11:29 am:
If there's no possibility of
reprocurement and a safety option to delete for non-performance
is included, are there any damages the Government can collect
due to the T4D?
By
Dave Barnett on Tuesday, October 16, 2001 - 01:15 pm:
I've never used them, and have
been warned away from using them, but could liquidated damages
provide an answer?
By
Newtothis on Tuesday, October 16, 2001 - 02:52 pm:
Joel, I do not understand what is
meant by write in the safety valve option to delete and take a
credit for failure to perform. Please clarify what is meant by
take a credit for failure to perform.
By
Vern Edwards on
Tuesday, October 16, 2001 - 03:41 pm:
Anonymous:
You asked two questions: First, "What can a CO do to ensure that
the contractor meets the critical time requirements of the
contract?" Second, "What action can the Government take if the
contractor doesn't have the plants planted by the end of the
planting time?"
I'll answer your second question first, because it's the
easiest. Given the conditions that you described on Oct 10 at
3:39pm, the only thing you can do is terminate the contract for
default. What else is there to do? You said that no further time
could be provided and that your tech people told you that they
couldn't wait until the next planting season. If the contractor
fails, you're done for. So if you let the problem develop to the
point that you have no alternative if the contractor breaches
the contract, then you T for D and go for damages. Given what
you have said, there is no question in my mind that the breach
would be material and would warrant a termination for default.
Your first question is the more important of the two and the
more difficult to answer. The solution does not lie in writing a
contract clause. The solution lies in selecting a contractor who
has a good specific plan for making sure that the plants
are ready and will be planted in time. That is not a matter of
past performance (although past performance will be something to
consider), but of the arrangements that the contractor can make
to minimize the chance that the plants won't be ready or won't
be put into the ground on schedule. You can find out about the
competing offerors' plans in this regard by conducting oral
presentations and asking them about those plans. You should also
ask about their contingency plans. (What if the truck
transporting the plants catches fire and all of the plants are
destroyed? What's the fallback position?) If the plants and/or
the planting will be subcontracted work, you might want to ask
the offerors about what arrangements they will make for
alternate subcontractors in case their first subcontractor goes
belly up.
The next thing that you can do is to make your own advance
contingency arrangements in case the contractor doesn't come
through. This may entail locating an alternate source for the
plants and the planting operation and discussing with them the
possibility of their being willing and able to step in on a sole
source basis (using the urgency exception) if the original
contractor fails. You might want to develop and obtain approval
for an acquisition plan for an emergency procurement in that
event, that way you won't lose time while you wrangle with
contracting and legal staffs at the last minute if you have to
go into action.
The next thing that you can do is perform intensive contract
administration with regard to the planting and the plants to
makes sure you know at all times where the contractor stands
with regard to that part of the work. You should be ready to
step in to offer your assistance or take over at any time if it
appears that the performance of that part of the work is
threatened.
Even if you're already on contract, it's not too late to do some
of these things. The key is for you to be proactive, and not to
passively sit by while things happen around you.
By
Vern Edwards on
Tuesday, October 16, 2001 - 03:44 pm:
Anonymous:
P.S. Yes, you can get compensatory damages if the contractor
defaults. If actual damages would be difficult to measure, then
you should consider putting a liquidated damages clause in the
contract.
Expect the worst and plan for it!
By
joel hoffman on Wednesday, October 17, 2001 - 12:00 pm:
Dear "Newtothis on Tuesday,
October 16, 2001 - 02:52 pm:"
What I meant was, in a situation where it doesn't make sense to
terminate an entire contract or even a partial termination for
failure to perform a small portion of the primary contract, you
could write a provision in the specifications or statement of
work which allows the Government an opportunity to delete the
landscaping for lack of performance - it is a type of
performance based contract provision. The contract is a
bilateral agreement. If the offerors/bidders agree to the
provision, they will submit a proposal or bid.
After award, if the Contractor performs, it gets paid. If it
doesn't, it doesn't get paid and the specs should state that the
Government reserves the right to procure the final landscaping,
separately.
The definition of performance specifying includes an inherent
requirement that satisfactory performance be verifiable. This is
"quality assurance." You can certainly establish reasonable
performance milestones, including early and intermediate
checkpoints in the performance specification to verify that the
plants are growing.
A safety valve could be a provision for temporary erosion
planting, in the event that there is a failure to perform by the
deadline. In that event, you can go, try again to grow the
plants in time for the next planting opportunity.
These are just some thoughts about an outline for one approach.
I don't agree that the only option available is to terminate the
contract for default. Performance based payments/ performance
specifying are legal alternatives to termination and a heck of a
lot cheaper, faster, and easier. Nobody wins in a TFD and it is
a real big pain in the butt to have to do one. happy sails! joel
By
Anonymous
on Thursday, October 18, 2001 - 09:45 am:
I appreciate all the input, it
should really help a lot. But without seeming to be too much of
a pest, I have one more question. If the contract must be TFD'd
due to failure to deliver, and there is no chance of
reprocurement, how could LD's or actual damages be assessed?
By
bob antonio on Thursday, October 18, 2001 - 10:01 am:
Anonymous:
You state you have a "vegetative planting requirement" for a
"specific species of plant to be grown under stringent
conditions." Has the plant been successfully grown before and
provided in the timeframe of your requirement?
By
joel hoffman on Thursday, October 18, 2001 - 11:16 am:
Anonymous, I don't understand the
statement: "there is no chance of reprocurement". Are you saying
that this is a temporary requirement - if it isn't there when
needed, there is no future need for the landscaping?
...or it is a permanent requirement, but is one which can't wait
until the next planting season, using temporary ground cover in
the meantime?
If the plantings could be delayed until the next season, "TFD
damages" would be the increased cost to reprocure next year,
plus any temporary erosion control plantings required. However,
I find it difficult to agree that you can TFD the whole contract
for this, unless it is a real significant portion or purpose of
the project.
Rather than TFD after the contractor fails to meet the
requirement (assuming you don't want to be innovative and write
into the RFP the performance based payments approach I
described), you can order a deductive change to delete the
requirement. The credit for the change would be the savings to
the Contractor from not having to meet the contract requirements
during the next planting season.
Another alternative might be to include liquidated damages
provision in the contract - the administrative cost per day to
keep the contract open, plus an allowance for additional cost to
the owner for not meeting the date - temp plantings for erosion
control? The basic contract should include the former, anyway.
The latter could be an LD specifically associated with delays in
plant establishement. happy sails! Joel
By
Kennedy How on
Thursday, October 18, 2001 - 11:56 am:
Joel,
I'm wondering if what he really means is that all of the
previous work will go for naught if the landscaping isn't done
in time. Basically, it sounds to me like those terraces will be
washed away if the contracted-for ground cover isn't in place.
You are then paying for work that won't be permanent, because
nature will take it's course.
I can see why somebody would not want to pay X millions for
something, have the contractor default, and lose whatever has
been provided to date, because what was provided will be gone by
the next year. However, I'm not sure if you can get away with
not paying for something the contractor has already done, but
I've heard of T4Ds that were initiated even though the
contractor had partially completed part of the contract.
Kennedy
By
Anonymous
on Thursday, October 18, 2001 - 12:20 pm:
In the last five years we've had
about 5 contracts for vegetative plantings. With the exception
of a contract terminated about a month ago, all have been
strictly vegetative. Out of the five contracts, one has been
successfully completed. Probably due to a longer planting period
than the others. Most of the contracts have a planting window of
2 to 3 months (6/1-7/31 or 6/1-8/31).
Also, all have been awarded from sealed bids. I guess it's time
to begin making awards on factors other than price alone, i.e.,
past performance, technical capability, contingency plans, etc.
This is an extremely new and unique business (planting native
marsh plants in extremely remote areas of marsh only accessible
by boat). Most of the companies who grow and/or plant have been
recently formed just to handle the government's requirements.
By
Anonymous
on Thursday, October 18, 2001 - 12:26 pm:
An observation: If the situation
is as Kennedy describes above I would say this is a case of not
coupling work properly in the requirement. In a situation where
all previous work is at risk due to a final stage requirement it
would be wise to couple that finishing touch with the basic
work.
In this case whoever built the terraces should have been on the
hook to provide that last bit that preserves their work.
I've long been aghast and wryly amused at the "business sense"
that sometime applies to division of work into separate
contracts. It gets too little attention in my view. It is an
analytical skill, even an art, that when done badly results in
delivery of something that fails.
I first ran into this when seeing delivery of a large and urgent
CB type radio order -- entirely forgetting the special frequency
"crystals" upon which all depended. Fairly expensive little
boxes sat on shelves while an entire operation had to do
expensive work arounds. Someone had decided to order them from
somewhere else and that had gotten lost in some SNAFU.
If the post planting season survival of these terraces depended
on the these precise plantings or an emergency alternative those
should have been in the critical path for the basic contract.
By
bob antonio on Thursday, October 18, 2001 - 12:42 pm:
Anonymous:
If a contractor cannot produce and is faced with a firm-fixed
price contract, a termination for default, and liquidated
damages, it very well may become defensive. Regardless of the
clause or provisions in a contract, something physically or
financially impossible to do is a defense in court.
A one in five success rate is not very good and you mention that
the successful one had more growing time. In constructing the
requirement, I would consider this potential defense.
By
Anonymous
on Thursday, October 18, 2001 - 01:35 pm:
I've talked to my technical folks
and they say there is nothing that can be temporarily placed on
the terraces to protect them from the environment until the next
planting season. The terraces are built in shallow brackish
water and the only plants that could survive are those
acclimatized to salt-water conditions. One of the "stringent"
growing requirements happens to be a thirty-day salt hardening
proceess that all plants are required to go through in order to
be ready for the environment in which they are to be planted.
We have discussed including language that would invoke an
automatic termination. Something that states that prior to the
contractor beginning terrace construction operations the plants
must meet a specific requirement by a stated date. If the
requirement isn't met by that date the contract would be
terminated for failure to perform. This would take out the
chance of the Government having to pay for completed terraces.
Reprocurement is possible, but work under the new contract would
be delayed until the next growing and planting season. It would
involve accessing damages (actual) throughout the year until the
work was complete. If there's nothing wrong with that then maybe
were fine.
By
Anonymous
on Thursday, October 18, 2001 - 01:43 pm:
The prime contractor will be
responsible for supplying the plants, building the terraces and
planting the plants. The prime contractor will most likely be a
heavy construction firm who will build the earthen terraces.
There will probably be two subcontractors, a nursery that will
grow and transport the plants and a planter who will place the
plants on the terraces.
By
Vern Edwards on
Thursday, October 18, 2001 - 02:19 pm:
Why is everybody focusing on
writing clauses to nail the contractor in the event of failure.
Why isn't everybody discussing how to prevent the failure in the
first place?
In the very first message in this thread Anonymous asked:
"Therefore, what can a C.O. do to ensure that the contractor
meets the critical time requirements of the contract? Also, what
action can the Government take if the contractor doesn't have
the plants planted by the end of the planting time?"
The first question is the most important one, and the answer is
not to write specification language and contract clauses!
The answer to the second question is simple: terminate for
default.
Anonymous, you and the contractor have to discuss this problem
openly, decide together on how to deal with it, and then to work
together to make sure that your plan works. If the work is to be
subcontracted, then include the subcontractors in the
discussions.
By
Anonymous
on Thursday, October 18, 2001 - 02:24 pm:
Placing the burden on the prime
makes me feel a lot better when the planting is actually the
vital completion phase. It appears in this case that if the
prime's subs don't perform the prime has not delivered anything.
Part of the purpose of a fixed price contract is to place the
risk on the prime. Do so. Until delivery is made, ie., a
completed terrace that includes the vital planting
consider it a non delivery. What would you do if you had bought
a truck load of computers FFP and they never showed at your
facility? This should be treated much the same way as far as I'm
concerned.
Now, if the thing is such that no contractor in their right mind
would take the risks perhaps you've picked the wrong contracting
method. This does not sound as if it is experimental or that
risks are so ill defined that this is the case.
As someone pointed out, one of the best defenses against such
non performance is proven past performance and a sound plan in
evidence before selection. Since the growing of the plants
necessary for completion is critical path for delivery those
plans must be part of the critical selection consideration.
If you've already selected and in real trouble the treatment
would seem to be as with any other contract where it has become
evident the contractor has failed to deliver as required. That
does not help get your delivery, but there should be little
question the contractor failed to deliver as promised. They
simply did "things" yet failed to perform.
By
Anon2U on Thursday, October 18, 2001 - 09:56 pm:
With a 1 in 5 success rate and
the fact that this is a new planting technique, the risks seem
high. The government is trying to shift all the risk of
non-performance on the contractors. It was stated that the
contractors had been recently formed just to attempt this kind
of work. Evidently they are willing to bid on the contract but
don't realize how much risk they are taking and that they can be
terminated without payment. If they did, I doubt they would have
bid on the project (or their profit would be about 500% to cover
the risk).
By
bob antonio on Friday, October 19, 2001 - 06:58 am:
Anon2U:
Exactly. Vern is correct in stating the contracting officer and
requiring activity should meet with the potential contractors
and subcontractors. The requirement should be discussed to make
sure everyone understands.
It doesn't matter what the requiring office wants if it is
impossible to perform!
Once the contractors and subcontractors believe they can satisfy
the requirement, the contract work should be based on observable
performance and in this case that seems possible. The government
observer should be able to determine satisfaction quickly and
notify the contracting officer immediately so that contract
performance can move forward.
The different stages of the process can be "fenced" in some
manner similar to decision points on a system acquisition. Maybe
using a simple "notice to proceed" from the contracting officer
after certain performance is achieved makes sense. The contract
should be written to match the requirement and performance
should be viewed as a partnership with the contractor team. If
the contractor fails, the government fails.
By
joel hoffman on Friday, October 19, 2001 - 07:13 am:
Anon and Vern, I wasn't trying to
focus on failure. I thought Vern made the point quite well that
this should be best value, with past performance as a critical
factor and some type of plan and interaction during performance.
I was trying to interject some performance based specifications
as an alternative to TFD. TFD should be a last resort.
Performance based specifications REQUIRE both parties to have a
plan to measure performance.
The project has finally been described in some coherent manner,
revealing some of the problems - there has been only a 1/5
success rate, previous award by low bid, temporary plants are
not an option, etc. By the earlier description, I thought this
was a base beautification project to build terraces somewhere or
something.
For this type project, a best value RFP is necessary. Evaluation
criteria could include, for example, evaluation of the offeror's
management plan, key subs, technical approach to the project,
including growing and planting, quality and schedule control,
past performance - especially important for the proposed
nursery, if that has been a problem. I would also ask for a
preliminary, outline schedule with the management plan. If key
personnel would be a discriminator, based on past performance,
I'd ask for the offeror's to identify them.
happy sails! joel
By
Peggy Richter
on Friday, October 19, 2001 - 11:21 am:
If the plants are critical, it
seems to me that you want them FIRST. IE, you want to have the
plants available ahead of time, to ensure they are there ON
time. In other words, is there some way the plants could be
grown and maintained in readiness for transplant ahead of the
date they are actually due? I am not a plant expert, but it
seems to me that if you HAVE to have 3" plants on May 20, then
requiring 3" plants in March and allowing for 5" plants in May
might be technically the better approach. I am NOT trying to get
into a specification thing - the above is an example. If you are
only having one success in 5 tries, it seems that somewhere
someone has gotten too hidebound in the requirements or in how
to get them done or in IF they can be done. If the one success
was with a longer growing period, this should be a clue. There
are a lot of ways to accelerate growing or to have a longer
period for growing. The contracting end of it is to ensure that
you HAVEN'T put in overly restrictive specs or requirements that
would prevent this (think of it as obtaining "long lead items")
and that you HAVE put in language that would at the best reward
"preplanning" and at the worst not penalize it.
You might want to think about using phases wherein if the plants
are not at stage X by date Y the terraces don't GO in, which
would delay performance for a year (or at least a growing
season) but eliminate the higher risk of putting something in
that wouldn't survive the environment because it wasn't
finished.
It seems to me you need to seriously talk to your tech folk. |