By Anonymous
on Thursday, October 11, 2001 - 01:00 pm:
Assume gov't suspended a
contract, which later turns out to have been a breach. For a
while thereafter, both parties continue to act within contract,
and contractor requests modifications of contract. Gov't
declines to make requested modifications, and directs contractor
to perform. Based on denial of modifications, contractor then
says "That's it. This contract is at an end." Gov't sends
appropriate notice of breach and opportunity to cure letters,
finally terminates contractor for default, and determines
damages. Contractor appeals CO's determination of damages on
many counts, one of which is that the gov't's termination for
default was invalid because gov't breached first. Anyone have
some general case law citations holding that gov't's prior
breach does not preclude it from terminating contract for
contractor's breach?
By
Dave Barnett on Thursday, October 11, 2001 - 02:12 pm:
Interesting...I don't have any
case law at hand but how long a time elapsed from the gov't
breach until the subsequent event (contractual trauma) occurred?
If a short time, the contractor could claim forbearance; if a
significant time, the gov't could claim the contractor waived
his contractual rights vis a vis the gov't breach. I suspect
forbearance is the case here.
That's one take, on the other hand, possibly the request for
modifications was the contractor's assertion for consideration
for the gov't breach. Accordingly the contracting officer should
proceed with the contractor in resolving the matter via the CDA,
requiring a proper claim, asserting a sum definite, yadda yadda...
With little knowledge of all the circumstances, as a KO I would
first consider the gov't breach immaterial to the instant breach
(based on KTr waiver of its contractual rights)in order to win
the battle. Realistically, I think you're looking at a T4C in
lieu of a T4D. If the contractor and the program are deemed
important enough and to keep the good will between both parties,
try to resolve under the CDA provided the KO reinstates the
contract via a supplemantal agreement citing an improper T4D
(you know, the old WHEREAS, the gov't improperly terminated
contact Yadda Yadda and WHEREAS the contractor agrees to
continue performance as established under contract Yadda Yadda,
now THEREFORE contract Yadda Yadda is in effect and all rights
and obligation thereunder assume to the respective parties, etc
etc). No matter what, you need your agency counsel in on this
one.
And if you reinstate, does this open the door for another claim
for the period of suspension due to an improper termination
action? If so, suggest a global settlement on all outstanding
claims.
Bottom line, how hard do you want to fight this battle? And are
you prepared to take the hits?
By
Linda Koone
on Thursday, October 11, 2001 - 02:33 pm:
Anonymous:
You may want to read
Thomas & Sons, ASBCA 51874.
The Govt breach was settled via modification prior to the
contractor breach,(although contractor claimed it wasn't), which
may be different from your situation. However, it may point you
in the direction of other relevant cases.
By
Anonymous
on Thursday, October 11, 2001 - 05:42 pm:
To Dave Barnett:
additional info, change mind? its a timber sale contract. gov't
suspension due to injunction during env. suit re: consultation
with FWS. During inj., agency refunded 85% downpayment as per
contract. During inj. also, market for pulpwood component of the
contract tanked. (contract had small am't of pulpwood, loss of
market did not prevent performance of cut and remove x amt.
pulpwood, nor did it make contract non-performable) after
injunction lifted, gov't requested reinstatement of downpayment,
contractor requested modification deleting sale of pulpwood.
Deletion of requirement to cut and remove pulp not at all in
gov't best interest, and less expensive to have company removing
and selling sawtimber in exact same area remove the pulpwood at
same time than trying to get someone to come in and remove it
after.
After gov't says no, won't remove pulpwood component, and by the
way, replace your downpayment, purch. says "that's it, I
consider this contract at an end." Major amount of sawtimber not
cut, gov't reappraises, resells, loses money, assesses damages
in co decision, purch. appeals to Board of contract appeals.
during same time and in same contract in fed.claims court, judge
just rules the gov't breached contract by not consulting in
first place. purchaser now argues in front of Board of contract
appeals that the gov't's breach resulting in suspension means
gov't's termination for default is invalid. ???? more think?
to Linda Koone: thank you, I will check the case out!
By
joel hoffman on Thursday, October 11, 2001 - 11:41 pm:
Anon, please explain what the
breach was... I'm slow, sometimes. I don't believe a suspension
of work, imposed by a court injunction, is a "breach." Of
course, I'm not familiar with the specific terms of this
contract, either. happy sails! joel hoffman
By
Anonymous
on Friday, October 12, 2001 - 06:29 pm:
Joel - you ask the key question -
the agency didn't think the suspension of work imposed by a
court injunction was a breach either, ESPECIALLY as the contract
provided for the purchaser to agree to suspend if required to do
so by a court of competent jurisdiction.
The injunction was ordered because the agency and FWS formally
consulted on the LRMPs as amended, not on the original
LRMPs,(since it and FWS had concluded that they did not
adequately protect the owl,) and Dr. Robin Silver et al. argued
that the decision in Pacific Rivers required consultation on the
original LRMPs, as opposed to the amended ones. Despite the fact
that formally consulting on the original plans was stupid since
they were being amended, and thus would have no consequence, the
judge bought the enviromentalists arguments for 17 months.
(Within days after he was taken off the case (retired) the
following judge dismissed the case.)
In our current case,Purchaser's attorney argued that even though
the contract specifically said that the purchaser would agree to
suspension of the sales in the event of an injunction, (and
agreed to a limited type of damages), that the agency
none-the-less breached the contract by "refusing" to formally
consult with FWS on the original plans, thus putting them in the
position where they could be sued, and the Claims Court judge
agreed.
(The truly remarkable part of the whole story is that the
consultation on the original plans (which by then were 3/4 of
the way through amendment) did not result in any modifications
to the contract -- BECAUSE THE CONTRACT HAD ALREADY BEEN
MODIFIED TO MEET THE REQUIREMENTS OF THE AMENDMENTS TO THE
PLANS!!!!!!!!!!!!!) (and, 3 years later, the Supreme Court
agreed that the original LRMP's did not require consultation.)So
the contract was suspended for 18 months for no value
whatsoever, and now the agency has to pay the purchaser
common-law damages for not doing something it shouldn't have had
to do and for which the parties had already agreed on specific
lesser damages!!!!!!!! Kafka could not have written it better.
(you can tell this case really gets my goat!)
By
joel hoffman on Friday, October 12, 2001 - 07:23 pm:
WOW! Happy Sails! joel
By
Dave Barnett on Tuesday, October 16, 2001 - 01:46 pm:
Now we wouldn't think federal
judges had personal axes to grind, would we. What a mess. The
more I thought about it the more crazy ideas came into me head.
If an executive contract is stayed (or suspended by the
judiciary, does a contract exist since one of the key elements
of the contract is "lawful purpose" and the judiciary deems the
contract is not meeting that element (but is correctable hence a
suspension rather than a null and void ruling)? Will the
contractor get greedy and ask for unabsorbed overhead costs due
to a delay caused by a governmental action? I can see why it
gets your goat.
By
Anonymous
on Tuesday, October 16, 2001 - 02:42 pm:
Dave: a shiny penny for you!!! OF
COURSE the contractor is asking for unabsorbed overhead -- the
problem is that the contract only covered the cutting and
removing of timber from federal lands, and the contractor wants
all the lumber mill costs - even though the lumber mill
activities were not at all part of the contract -- some
operators mill their timber, some sell it to others, and in fact
this operator did both! and the cherry inside the chocolate is
the millions of dollars the contractor is requesting for this
little-more-than mom,pop, and the inlaws lumber mill!
By
Vern Edwards on
Tuesday, October 16, 2001 - 04:08 pm:
Anonymous:
By any chance, was the case that produced the injunction
Sierra Club v. Babbitt, 65 F.3d 1502? Was the timber cut to
make way for a logging road?
By
Anonymous
on Tuesday, October 16, 2001 - 04:11 pm:
Vern -- no, it wasn't.
By
Vern Edwards on
Tuesday, October 16, 2001 - 04:20 pm:
Anonymous:
I don't think a court-ordered suspension is a breach of
contract, but it may be a compensable delay. I haven't looked at
the clauses in a timber sales contract in a while, so I don't
remember what provision it made for such events.
Can you tell us the name and date of the Claims Court case that
you mentioned on Oct 12--the one in which the judge agreed with
the contractor's lawyer about the government breach?
By
Anonymous
on Tuesday, October 16, 2001 - 04:27 pm:
Vern - Precision Pine & Timber,
Inc. v. U.S., Ct. Fed. Cl. No 98-720C, decision issued July 30,
2001, Judge Damich. are you gov't or private practicioner? (I am
agency counsel, working through DOJ.)
By
Vern Edwards on
Tuesday, October 16, 2001 - 04:38 pm:
Anonymous:
I'm a private practitioner, and a layman.
By
Anonymous
on Tuesday, October 16, 2001 - 04:45 pm:
Vern -- p.s. I like your idea of
not a breach but a compensable delay. We've already lost on a
motion for reconsideration, and weren't planning appeal since
the record and briefing didn't provide all info available, and
am not sure how we would go about this argument. The purchaser
wanted breach because then they were not constrained by the
contract's enunciated damages. How are you thinking to argue
compensable delay?
By
Vern Edwards on
Tuesday, October 16, 2001 - 06:25 pm:
Anonymous:
So what happened was that the Forest Service awarded a bunch of
timber sales contracts, but got into a spat about the Endangered
Species Act (ESA) with some environmentalists, who filed suit to
block the timber sales. A U.S. district court issued an
injunction that forced the Forest Service to suspend the timber
sales, which it had the right to do under the terms of the
timber sales contract. The suspension clause limited the
remedies available to the purchaser in the event of such a
suspension.
The "contractor" was one of the purchasers. It filed a suit for
breach of contract, arguing that the Forest Service got into the
spat with the environmentalists because it had acted
unreasonably with regard to its duties under the ESA. It argued
that by acting unreasonably with regard to its duties under the
ESA--which resulted in the district court injunction which
forced the suspension--the Forest Service breached its implied
duty to cooperate with and not to hinder the purchaser, and thus
the purchaser was entitled to breach damages.
The U.S. Court of Federal Claims (Judge Edward Damich) agreed
with this argument, holding that the implied duty to cooperate
and not to hinder included the duty to obey the law, i.e., the
ESA, and thus avoid injunctions and consequent suspensions. The
court also held that the suspensions were not sovereign acts.
The result was that the court granted the purchaser's motion for
summary judgment that the Forest Service had breached the
contract, which means that the purchaser's recovery is not
limited by the terms of the suspension clause.
Do I have it right?
The court's decision is about 50 pages long and includes 24
pages of information and arguments about the Endangered Species
Act which I suspect most of us are in no position to analyze.
Judge Damich has a law degree from Columbia University. He was
appointed to the bench by President Clinton, but he was the
Chief Intellectual Property Counsel for the Senate Judiciary
Committee when Orrin Hatch was the chairman (1995-1998) and he
was appointed to the Copyright Royalty Commission by the first
President Bush. (Dave Barnett: What personal axe do you think
Judge Damich had to grind? Do you know him? Do you know
something about him that the rest of us don't?)
The court's decision makes sense to me, but what do I know? I
don't know anything about the Forest Service's obligations under
the ESA and I doubt that many others at this forum do either,
but aside from that the decision seems pretty straightforward.
Of course, the rest of us at this forum certainly don't have the
information at our disposal that you have. (I assume that you
are one of the USDA lawyers identified in the decision.)
With which of the court's holdings do you disagree? Do you
disagree that the Forest Service acted unreasonably with regard
to its duties under the ESA? Do you disagree that if the Forest
Service acted unreasonably then it breached its duty to
cooperate and not to hinder? Do you disagree with both?
What's the citation for the Supreme Court decision that you
mentioned? How does it affect the decision of the Court of
Federal Claims? What is the Forest Service going to do now?
By
Vern Edwards on
Tuesday, October 16, 2001 - 06:30 pm:
Anonymous:
My compensable delay idea was based on the belief that the
suspension was not a breach of contract. Government purchase
contracts include clauses that entitle the contractor to
compensation short of breach damages in the event of a
government-caused unreasonable delay. But now that I have read
the court's decision I realize that my notion of compensable
delay won't help you.
The plaintiff's lawyer must have presented a heck of a case.
Vern
By
Dave Barnett on Wednesday, October 17, 2001 - 07:28 am:
Well Vern, I don't know the judge
involved so my comment was rhetorical in nature. But do you
really believe that all judges don't have biases/agendas? If
that was the case then why are some impeached or denied a
position on the bench by the Senate?
By
Vern Edwards on
Wednesday, October 17, 2001 - 09:06 am:
Dave:
I don't have any beliefs regarding "all" judges. I just wondered
what axe you thought that the judge in Anonymous's case had to
grind. I thought maybe you had personal knowledge of the case,
since your rhetorical comment suggested that you felt
Anonymous's agency had been wronged by the decision. Have you
read the Precision Pine & Timber decision? Do you think
that the Forest Service was wronged?
(Actually, in her/his Oct 12 6:29pm post, I think Anonymous
referred to two judges--the district court judge in the
Silver v. Babbitt case, who "bought" the environmentalists'
arguments, and Judge Damich of the Court of Federal Claims, who
made the Precision Pine & Timber, Inc. v. U.S. decision.)
I only joined this thread because I didn't understand what
Anonymous was getting at and wanted to learn more. What I have
learned by reading the Precision Pine & Timber decision
has reinforced my belief that we should try to get all the facts
before we jump to conclusions or offer solutions to problems not
fully understood--a thing that I'm guilty of from time to time.
Vern
By
Anonymous
on Wednesday, October 17, 2001 - 02:58 pm:
Vern and Dave:
Vern your understanding of what happened is correct, but the
confusion is this: the FS still maintains that it did not ignore
its duty under the ESA. After the MSO was listed, the FS in
Region 3 informally consulted with the FWS on the original LRMPs
and regional timber sales, realized there was trouble, and then
modified the timber sales and developed amendments to the
original LRMPs so they would meet the requirements of the ESA as
to the MSO., and the FS and FWS consulted on that. THE FS IN
REGION 3 COMPLIED WITH ITS DUTIES UNDER THE ESA as to the MSO.
However, in a different FS region, the 9th Circuit decided the
Pacific Rivers case, holding that the agency had to reconsult on
all LRMPs each time a new species was listed. That's nice, but
the fact patterns there and here were different. Seeing the
handwriting on the wall during informal consultations after the
MSO was listed, Region 3 immediately began amending the LRMPs
and modifying its contracts to protect the owl, and consulted
formally on those improvements instead.
THe environmentalists sued FS region 3 on the basis that the
Pacific Rivers decision required formal consultation on the
original LRMPs as a technical or procedural requirement, (even
though in reality in Region 3 there was no benefit to formally
consult on the originals given the amendments and
modifications.) Judge Muecke agreed. It is interesting to note
that FWS did not come up with any modifications to the contracts
based on consultation under the old LRMPs -- cause the contracts
had already been modified to meet the much more rigorous
requirements in the LRMPs as amended.
The second point that the FS had been trying to make is that
consultation should not be required on the LRMPs, which are just
theory, and don't provide any information of what specifically
will happen on the ground, but that the consultation should be
held on the specific ations - timber sale contracts, etc., cause
that is where you can determine actual facts regarding how many
owls will be taken, how much of their habitat will be removed,
etc.
FWS agreed with this -- without specific activities - cut trees
in this location, skid trees in that location -- you cannot know
what effects the sale will actually have on the animal or
habitat, and in fact when ordered to consult on the original
LRMPs, actully reviewed the timber contracts vis a vis the LRMPs
so they could quantify actions.
The Supreme Court agreed that consultation is required on
specific actions -- contracts, etc. and not on the LRMPs by
themselves in Ohio Forestry Assn.; unfortunately that was
several years after Judge Muecke ran rampant in Silver v.
Thomas.
Unfortunately Judge Damich did not have the benefit of all the
information regarding the agency's actions and position in
Silver v. Babbit; if he had, I believe he would not have
concluded that the FS breached its opportunity not to hinder.
Hope that explains the problem better.
|