|
|
|
HOME | CONTENTS | DISCUSSIONS | BLOG | QUICK-KITs| STATES |
Search WWW Search wifcon.com |
Variation in Estimated Quantity (FAR 52.211-18) | |
---|---|
By
Julie A.
Talley on Wednesday, January 02, 2002 - 05:20 pm:
The intent and purpose of FAR Clause 52.211-18 Variation in Estimated Quantity, is to allow for a degree of difference in the Government's Estimated Quantities with set percentage variances. Has a COR who by allowing a Contractor to perform above the established variance, 100% in this case, without a KO's approval or modification to the contract set himself for a possible unauthorized commitment. Does anyone interpret this clause as to allow a Contractor to exceed the estimated quantity by this much without prior approval of the KO? By joel hoffman on Wednesday, January 02, 2002 - 05:45 pm: Julie, the intent of the construction VEQ Clause, 52.211-18,
is NOT to "allow for a degree of difference" between the actual
and estimated quantities. It is only intended to describe the
conditions under which either party may ask for an adjustment to
the unit price, if the actual quantity of a unit-priced item
varies by more than 15% from the estimated quantity. The clause
also allows for a time extension, due to the variances. The
Clause does NOT place a limit on authorized work for payment.
The prescription for the clause says to use the clause WHEN
a fixed price construction contract is contemplated that
authorizes a variation in the estimated quantitiy of unit-priced
items. The key is that somewhere else in the contract a
variation is allowed. By Vern Edwards on Wednesday, January 02, 2002 - 08:18 pm: Julie: By Mary C on Thursday, January 03, 2002 - 02:26 pm: Anytime the estimated quantity is exceeded by 100% I would say there is a problem that needs to be looked into and a contract that needs to be modified. Do we even have the money to pay for this additional work? I believe the COR had a responsibility to bring the descrepancy in the estimated quantity to the KOs attention as soon as it was noticed. By Vern Edwards on Thursday, January 03, 2002 - 02:39 pm: I agree that the COR should have notified the CO that something was wrong, but I don't think that failure to do so constitutes an unauthorized commitment. Moreover, the CO should be proactive about keeping tabs on contract performance. I was a construction contracting officer for the Air Force and for the Department of Energy, and unless the estimated quantities are very small, so that a 100 percent overrun could happen very quickly, I can't imagine not finding out about a potentially significant variation in quantity early in the game. By joel hoffman on Thursday, January 03, 2002 - 03:47 pm: I can see where the KO, on a COE construction contract, would
not be aware of an overrun, unless or until it becomes a
problem. A Resident Engineer is usually the ACO. Mary and Julie,
your District should have SOP's regarding management and
administration of unit priced quantity overruns. USACE put out
policy several years ago on contract administration procedures
and the PM should have been fully informed to ensure that
adequate funding has been arranged. You can view our Center's
contract admin SOP's for estimated quantity variations at
Chapter 2, Section 15 of our Contract Admin Plan (similar to the
Mobile District's SOP), based on USACE guidance. If your
Distict's ACO's are authorized to execute Admin Mods, the KO
might not be aware of quantity overruns - unless it becomes a
problem. By joel hoffman on Thursday, January 03, 2002 - 04:48 pm: I spoke with Julie, this afternoon. We agreed that the
problem concerns the COR's action beyond his contractual
authority, in directing some additional unit-priced contingency
work, beyond the amounts currently funded in the contract. The
contract is written to allow the KO to order the contingency
work, at the unit prices established for such contingency work,
but not the COR . Since the additional work will require funding
beyond that available in the contract, the COR should not have
ordered the work. The contract contemplated contingency work but
only provided enough funds (quantity) for one time need for
this. We agreed that the actual work performed was not a change. |