By
newbie on Wednesday, February 26,
2003 - 02:42 pm:
Hi - I'm looking into how our agency can use
award-term contracting. I've read several articles on it,
including Vern's. What I can't find is much discussion on the
legality of contracting for extended periods of time, say the 10
years for which many award term contracts are written. Does this
vary by agency? Is the FAR 5-year limit only on multi-year
contracting, so as not to apply to options? Or is the limit in
period of performace 5 years, inclusive of options, unless your
agency is authorized otherwise (I know part of our agency has
congressional authority to enter into "5+5" contracts, for a
total of 10 years).
Thanks!
By
Linda Koone on Monday, March 03,
2003 - 07:45 am:
Newbie:
Since nobody answered your question, I'll take a stab at it.
(1) The FAR restricts multi-year contracts to 5 years unless
otherwise authorized by statute [FAR 17.104(a)].
(2) FAR 17.204(e) restricts the length of multiple year
contracts (contracts with options) to 5 years unless otherwise
approved in accordance with agency procedures. This restriction
doesn't apply to IT contracts and some classes of contracts,
such as service contracts, may be otherwise restricted by
statute.
The contract length, based on the restriction at FAR 17.204(e)
does vary from agency to agency.
By
Anonymous on Monday, March 03, 2003
- 11:14 am:
I've attended some presentations on award term. As I
recall, the contract term limit is still there, but they get
around the length by stating that the award term (extension) is
part of an award, and therefore can go beyond the term limit.
To my thinking, this argument does not hold water as it would
imply that the terms of the contract would end with the contract
period, (so what are the contract terms during the award term
period?)
I'll wait for the courts to solve the issue.
By
Vern Edwards on Monday, March 03,
2003 - 01:23 pm:
I haven't responded sooner because newbie said he'd
read my stuff. I addressed the issue of maximum length in the
monograph that I wrote for NCMA, Award Term Contracting: A
New Approach for Incentivizing Performance.
The use of an annually-funded award-term incentive does not make
a contract a multi-year contract as defined by FAR §
17.103 (see 10 U.S.C. § 2306b and 41 U.S.C. § 254c). Contracts
with award-term incentives are multiple year contracts, which
are not multi-year contracts. Thus, the five-year limit referred
to in FAR § 17.104(a) does not apply to annually-funded
contracts with award-term incentives.
The five year limitation on the length of the total of the basic
and option periods which appears at FAR § 17.294(e) does not
apply to contracts with true award-term incentives, because
award terms are not options. If a contract provides for award
options, instead of award terms, then the five year limit does
apply. However, agencies may waive that limit in accordance with
their internal procedures.
The Department of Labor has interpreted the five year limit on
contracts covered by the Service Contract Act, mentioned in FAR
§ 22.1002-1, to mean that no single term of the contract may
exceed five years, but that each option or award term is a new
contract for purposes of the Act. See 29 CFR § 4.135. Thus, this
limitation does not prohibit the use of award-term incentives.
The five year limit in FAR § 16,505(c) on ordering periods for
task order contracts for advisory and assistance services does
apply to contracts with award-term incentives.
By
Anonymous on Monday, March 03, 2003
- 03:12 pm:
Vern
Is there any case law to back up your argument? I don't question
your interpretation of the letter of the law, but I would like
to see a court decision on the intent of the law before I accept
your argument.
By
Vern Edwards on Monday, March 03,
2003 - 03:46 pm:
Anonymous:
To the best of my knowledge there have been no court decisions
of any kind about award-term incentives.
Keep in mind that the courts and the GAO become involved when
there is some kind of dispute, either between the government and
a prospective or disappointed bidder or between the government
and its contractor. It is unlikely that you are going to see a
court decision about limits on the number of award terms an
agency can include in a contract. Prospective bidders are not
likely to protest the inclusion of an award-term incentive in a
contract since they stand to gain if they win. A disappointed
bidder is not likely to succeed in a protest about that since
any such protest would probably have to have been filed before
the closing date for receipt of proposals, but that is not
likely for the reason that I just gave. Finally, a contractor is
not likely to go to court because an agency has included too
many award terms in a contract.
Although I suppose that a lawsuit from some other party is
possible, I consider it highly unlikely. Who would sue? So those
of you who can't accept my reasonable interpretations of the
regulations until a court or the GAO affirms them are likely to
be in limbo for a very long time. Meanwhile, agencies are using
award-term incentives.
By
FormerCO4AF on Monday, March 03,
2003 - 06:32 pm:
Anonymous of 3:12 pm.
Personally I wouldtake the lack of court rulings and protests as
a sign of industry acceptance to the process.
I agree with Vern. If a contractor protests and wins he/she
loses on any future opportunity with award terms.
Talk about biting the hand that feeds you.
By
Vern Edwards on Monday, March 03,
2003 - 07:35 pm:
I just searched the active listings at
FedBizOpps and got 11 pages of hits for "award term." I checked
more closely and found 24 separate acquisitions with award term
incentives in just the first four pages.
Agencies planning to use award term incentives included:
Air Force Education and Training Command;
Army, White Sands Missile Range;
DOD Missile Defense Agency;
Naval Facilities Engineering Command;
Naval Surface Warfare Center, Dahlgren Division;
Air Force, Air Force Materiel Command;
Naval Surface Warfare Center, Port Hueneme;
Army, Fort Hood Directorate of Contracting;
Army Infantry Center, Fort Benning;
U.S. Corps of Engineers, Kansas City Civil Works;
Military Traffic Management Command;
NASA Ames Research Center;
Army, Fort Riley Directorate of Contracting;
Navy, Military Sealift Command;
DOD Education Activity;
Navy, Space and Naval Warfare Systems Center;
USAINSCOM;
Department of Transportation, Coast Guard;
Army, Fort Campbell Directorate of Contracting; and Defense
Threat Reduction Agency.
The acquisitions were for a variety of services, including base
maintenance, IT operations and support services, advisory and
assistance services, technical support services, aircraft parts,
ship defense systems engineering, motor pool operations, dining
facility operations and management, herbicide application,
project office support, aerospace testing and facilities
operations and maintenance, custodial services, school
maintenance, care and training of marine mammals, grounds
maintenance, and nuclear technology support.
Several of the acquisitions would permit the contractor to earn
up to 15 years of renewals by providing excellent performance.
By
newbie on Monday, March 03, 2003 -
10:40 pm:
Thanks for everyone's input. Vern, I did read your
writings on the topic, but I guess I still am unsettled on the
issue. Here's why:
"Thus, the five-year limit referred to in FAR § 17.104(a) does
not apply to annually-funded contracts with award-term
incentives."
What if we're not talking about annually funded contracts? I use
multi-year money and incremental funding on CR contracts... what
if I wanted to incrementally fund a two-year award term? Would
the multi-year limit apply then?
"The five year limitation on the length of the total of the
basic and option periods which appears at FAR § 17.294(e) does
not apply to contracts with true award-term incentives, because
award terms are not options. If a contract provides for award
options, instead of award terms, then the five year limit does
apply. However, agencies may waive that limit in accordance with
their internal procedures."
But what's the other option? If award terms are not options,
then they are either:
1. continuations of current awards; or
2. new awards.
If they are continuations of current awards, then the multiple
year limit on the base plus option periods would seem to apply.
The intent of this part of FAR seems to be to limit the total
time -how can we say that award terms aren't part of the total
time of an award? If the award terms are awarded under a
contract, they are part of that contract, and I would think they
would be subject to applicable time limits on that award. If
award terms are new awards... well... I just don't think this
holds water.
"The Department of Labor has interpreted the five year limit on
contracts covered by the Service Contract Act... Thus, this
limitation does not prohibit the use of award-term incentives."
Their interpretation only deals with contracts subject to the
SCA. Right?
What about service contracts not subject to SCA, with one or
multi-year money, in incrementally funded CPAF contract
arrangements, subject to the 5-year limit and not subject to any
agency exception on time limits?
Thanks, everyone.
By
newbie on Monday, March 03, 2003 -
10:43 pm:
Also, thank you for the active listings of activities
using award terms. I think DoD has different authority regarding
time limits - and almost all of those listings were DoD. I
wonder if they are using this authority to justify the award
term arrangements, or if they are just ahead of the curve in
implementing this relatively new incentive.
By
Vern Edwards on Monday, March 03,
2003 - 11:49 pm:
newbie:
See FAR § 17.104: "Multi-year contracting is a special
contracting method to acquire known requirements in quantities
and total cost not over planned requirements for up to 5 years
unless otherwise authorized by statute, even though the total
funds ultimately to be obligated may not be available at the
time of contract award."
Under an award-term contract the agency does not acquire
services in advance of funding. Award-terms are conditioned upon
a continuing need and availability of funds. The contractor
earns entitlement to an award term, but the term does not go
into effect unless the government needs the services for another
year and funds are available. If there is no requirement
or if funds do not become available, there is no cancellation
charge.
You say that if award terms are not options, then they must be
either continuations of current awards or new awards. You then
conclude that if they are continuations, then the option
limitation in FAR § 17.204(e) applies. That's a non sequitur.
The option limitation applies to contracts with options. Award
terms are not options. So, the option limitation does not apply.
And why can't award terms be new awards? Why doesn't that hold
water? In any event, whether award terms are non-option
continuations of an existing contract, an entirely new thing, or
new awards, the five year limitations in FAR Subparts 17.1 and
17.2 do not apply.
Now I have explained this to you as well as I can. A number of
agencies have been using award term incentives since 1997. Their
use of award term incentives has been widely discussed. There
has been no outcry from Congress, the IGs, or the GAO. Why,
then, are you so bound and determined to find them in violation
of non-applicable five year limitations?
You remind me of the people who in 1994 swore that the
evaluation of oral presentations in source selection was
"illegal" and would result in an overwhelming number of
sustained protests. You also bring to mind the people who in
1987 thought that fixed-price contracts with award fees were
illegal because they weren't mentioned in FAR, and the ones that
said the evaluation of past performance was too subjective to be
permissible.
There are a lot of things wrong with award term incentives,
newbie; I'm increasingly inclined to think that they are not a
good idea. But I do not believe that they violate any statute or
regulation.
Here's a final thought: If you're convinced that award term
incentives violate FAR, then don't use them.
By
Anonymous on Tuesday, March 04,
2003 - 08:32 am:
Vern:
Can we stick to the issues and not browbeating to try to win
people to a point of view?
Does anyone have an idea why the FAR puts a 5-year limit on
contracts? If we can ascertain the reason for the limit, then I
may be more comfortable in skirting this FAR induced limit.
Anonymous of 3:12 pm
By
Vern Edwards on Tuesday, March 04,
2003 - 10:12 am:
Anonymous:
Congress established a five year limit on multi-year contracts
because it did not want DOD to make commitments beyond its
five-year defense plan. Multi-year contracting originally was
available only to DOD and for the acquisition of supplies; it
has since been made available to the civilian agencies and for
the acquisition of services.
I don't know why FAR (not Congress) put limits on contracts with
options. It might be for similar reasons or because of the
difficulty of pricing beyond five years. Keep in mind, however,
that the limitation on contracts with options is neither
statutory nor absolute. Agencies may waive it and several of
them have.
The five year limit on contracts covered by the SCA reflects the
determination that contract wage determinations should be
revised at least that often in order to reflect prevailing wages
and fringe benefits.
The five-year limit on the ordering period of contracts for
advisory and assistance services reflects Congress's dislike of
those contracts.
If you understand the history and background of multi-year
contracting and read the regulations carefully, you'll see that
the policy is about contractually obligating the government in
advance of funding, with provision for payment of cancellation
charges, which is not what a properly written award-term
incentive does. The idea behind multi-year contracting is to
enable contractors to obtain the benefits of long term
commitments and economies of scale, which they can pass on to
the government. If a contractor is going to manufacture a
product for which quantities are authorized and funds
appropriated annually, and the agency's long-term plan calls for
five years of production, the contractor can get better prices
from suppliers of parts and components by insuring them against
production breaks. Multi-year contracting is designed to enable
the contractor to enter into long term agreements with its subs,
by contracting in advance of funding with provision for the
payment of cancellation charges. If the government wants a
contractor to build a facility in which to provide a service,
like space launch preparation services, and the facility will
take more than one year to build, the government must allow the
contractor to make long term commitments to its subcontractors,
notwithstanding annual authorization and appropriation. That's
what multi-year contracting permits. See FAR § 17.105-2.
See: "Multiyear Procurement: The Different Faces of Congress,"
in The Nash & Cibinic Report, July 1995 (9 N&CR ¶ 40), in
which the professors explained multiyear contracting as follows:
"The 'multiyear' contract is a special type of requirements
contract that obligates the agency to buy designated quantities
of supplies or services for a period up to five years and to pay
cancellation costs if funds are not available to buy the entire
requirement. This permits contractors to achieve efficiencies by
incurring large startup costs with the knowledge that they will
be reimbursed those costs without regard to changing program
requirements."
This description does not apply to contracts with award-term
incentives. Indeed, award-term incentives would be inconsistent
with the goal of multi-year contracting.
The N&CR article usefully discusses the history of multiyear
contracting and its extension to the civilian agencies and to
the acquisition of services. (The statutes say "multiyear,"
without the hyphen; FAR hyphenates the term, "multi-year.") See,
too: Postscript: Multiyear Procurement," in 10 N&CR ¶ 54
(October 1996).
In "Multiyear Cpntracts or Multiple-Year Contracts: There is a
Difference," 13 N&CR ¶ 48 (September 1999), the professors
discuss the on-going confusion over the distinction between
multi-year and multiple-year contracts:
"In multiyear contracts, the Government obligates itself to
place orders if funds are available. Thus, multiyear contracts
can only be used with multiple-year appropriations or when
specifically authorized by Congress. Although multiyear
contracting, either specifically authorized or with
multiple-year appropriations, has been in use since the early
1960s, the term "multiyear" continues to be used to describe any
contractual arrangement covering a period of more than one year.
As a result, considerable confusion has resulted."
The professors go on to explain the difference. And yes,
Anonymous, the professors cite a considerable amount of case law
in their articles.
A contract with a properly-written award-term incentive does not
commit the government in advance of funds and makes no provision
for payment of cancellation charges or termination costs if
funds do not become available. I explained that in my NCMA
monograph, page 2-14:
"The contract should state that cancellation of an award that
has not commenced will not entitle the contractor to any
termination settlement or any other compensation."
I discussed it again on pages 3-12 and 3-13 in my
recommendations about writing an award-term clause:
"The cancellation of any award terms or the voiding of the
award-term incentive for any of the reasons set forth in this
clause shall not be considered either a termination for
convenience or a termination for default and shall not entitle
the contractor to any equitable adjustment or any other
compensation."
Compare that language with the requirements of FAR §
17.106-1(c), regarding the cancellation of multi-year contracts.
I got irritated with newbie for persisting in making an argument
without first doing his/her homework. I shouldn't have let my
irritation show, and I apologize. I have been running into that
kind of thing a lot lately and I'm getting grumpy about it. No
excuse, though.
By
Anonymous on Tuesday, March 04,
2003 - 12:29 pm:
Vern:
I think this is one area where we will disagree.
I agree that prolonging a contract through award term extensions
can be advantageous in the instant case to the government. And
for the government and the winning contractor, I don’t see a
reason for bringing award term to court.
However, I can foresee award term being protested in the future
for various reasons. The following are just mental exercises for
now, but they are the basis for my being wary about award term
contracting.
1) As you stated in your 10:12 post “Congress established a five
year limit on multi-year contracts because it did not want DOD
to make commitments beyond its five-year defense plan.
Multi-year contracting originally was available only to DOD and
for the acquisition of supplies; it has since been made
available to the civilian agencies and for the acquisition of
services.”
A contract may be for 5 years, but if there is an award term
clause, it may be an obligation for more than 5 years (up to 15
according to an earlier post). Granted, this is only if the
funds are available, the program needs to continue, and the
contractor performs well enough to earn the extra time. However,
in awarding the contract, the government is committing itself to
this prolonged period if all 3 items exist. So in essence, DoD
could be committing itself to contracts beyond the 5-year
defense plan.
Personally, I think the terms “multi-year” and “multiple year”,
et al, have sufficed in usage up to the award term era, but will
be re-addressed in the future.
2) In the wider picture of business, from which many of our
regulations arise (SB contracting being but one example), an
award term contract that could last up to 15 years excludes
other businesses from having a shot at those government dollars.
Are we dealing fairly with the rest of the market by reverting
to a sole source for the award term? (I know I’m going to get
hammered for citing “sole source”, but that is the impression I
have, even though the contractor has earned it.)
3) Are we raising the bar to contracting with the government, or
maybe slamming the door in the face of improvement? If a company
builds a better mousetrap, how long before the government will
get it due to being licked in to an award term contract? (I
would like to think that this is not a valid argument, but
perception is enough for a legislative representative to make
waves.)
For the time being, I accept award term contracting, but will
keep my ear to the rail as I believe the protest train will come
eventually.
Anonymous of 3:12 pm
By
Vern Edwards on Tuesday, March 04,
2003 - 12:58 pm:
Anonymous:
I'm not sure that we disagree. Here is what I wrote in an
article published at Wifcon in February 2002:
"The award-term incentive is an unproven idea, far too new for
anyone to make any claims about its effectiveness or success,
and so professionals should greet award-term 'success stories'
with skepticism. Nevertheless, FY 2001 witnessed increased
interest in and application of the idea. No regulations have
been promulgated to govern its use and official guidance is
skimpy, at best; significant issues of law, policy and practical
application are unresolved. Contracting offices that have
decided to use award-term incentives in their contracts are
learning as they go, borrowing from each other and improvising.
A review of some of their solicitations, award-term clauses, and
award-term plans suggests that those offices have not been as
thoughtful and as thorough as they might have been. More
importantly, continued expansion in the use of award-term
contracts could result in a significant restructuring of some
segments of the contract services market as requirements are
effectively withdrawn from the market for ten to twenty years at
a time. It is not clear that such a significant restructuring
would be in the best interests of the taxpayers. Thus, if
interest in and use of award-term incentives continues to grow
during FY 2002, the Office of Federal Procurement Policy should
find out what is going on and determine what, if any, regulation
is needed."
While I don't share some of your notions about multi-year
contracting and multple-year contracts, I do share your concern
about the continued expansion in the use of award-term
incentives.
Vern
By
Vern Edwards on Tuesday, March 04,
2003 - 06:39 pm:
For more background on multi-year contracting (as
opposed to multiple-year contracts), see the Comptroller
General's letter to the Administrator, Small Business
Administration, B-152766, 43 Comp. Gen. 657 (April 3, 1964).
The Comp. Gen.'s letter shows that new and unorthodox
contracting methods are often attacked as being illegal and/or
anti-competitive. People in government seem to be inherently
conservative, and often have a hard time accepting new ideas. In
this case, the SBA claimed that multi-year contracting, which
was not then authorized by statute, was illegal,
anti-competitive, and hurtful to small businesses. The GAO
disagreed.
Here is how the Comp. Gen. described multi-year contracting, as
authorized by ASPR § 1-322 (capitalization as in the original):
"AS PRESENTLY CONSTITUTED PARAGRAPH 1-322 DEFINES MULTI-YEAR
PROCUREMENTS AS A METHOD FOR COMPETITIVE CONTRACTING FOR KNOWN
REQUIREMENTS FOR MILITARY SUPPLIES, IN QUANTITIES NOT IN EXCESS
OF PLANNED REQUIREMENTS FOR 5 YEARS SET FORTH IN, OR IN SUPPORT
OF, THE DEPARTMENT OF DEFENSE FIVE YEAR FORCE STRUCTURE AND
FINANCIAL PROGRAM, EVEN THOUGH THE TOTAL FUNDS WHICH ARE
EXPECTED ULTIMATELY TO BE OBLIGATED BY THE CONTRACT ARE NOT
AVAILABLE TO THE CONTRACTING OFFICER AT THE TIME OF ENTERING
INTO THE CONTRACT. UNDER THIS METHOD, CONTRACT QUANTITIES ARE
BUDGETED AND ACCOUNTED FOR IN ACCORDANCE WITH THE PROGRAM YEAR
IN WHICH EACH QUANTITY IS AUTHORIZED. IT WOULD NOT BE USED WHERE
FUNDS COVERING THE PROCUREMENT ARE LIMITED BY STATUTE FOR
OBLIGATION DURING THE FISCAL YEAR IN WHICH THE CONTRACT IS
EXECUTED. IT WOULD BE USED ONLY WHERE COMPETITIVE PROCEDURES
ESTABLISH THAT REDUCED UNIT PRICES WOULD RESULT OVER ANNUAL BUYS
BY REASON OF THE ELIMINATION OF REPETITIVE, SUBSTANTIAL,
START-UP COSTS."
The letter is historically very interesing.
By
newbie on Tuesday, March 04, 2003 -
11:17 pm:
without doing my homework? your reply didn't bring up
any new unconsidered information, just reiterated your
interpretation of information already in discussion.
My point about the option contract limits was this: if you have
a contract with options, that also has an award-term incentive,
then nothing tells me that the FAR limit at 17.204 would no
longer apply, merely because an award term is part of the
equation.
As for the comment, "If you're convinced that award term
incentives violate FAR, then don't use them," I'm certainly not
convinced they violate the FAR. I'm the one who wants to use
award term in my agency. I'm the first person to look into it or
consider it. If I decide I don't think it is adventageous for
the purchases I make, I won't use it. My objective (stated from
the outset) was to gather information in an effort to advise my
agency of the appropriateness of this type of incentive for the
work we do.
By
Vern Edwards on Wednesday, March
05, 2003 - 12:43 am:
newbie:
I most certainly did bring up newly considered information and
you should by now have all the info you need.
1. I have clearly distinguished multi-year from multiple year
contracts and provided you with plenty of references for the
proposition that the use of award-terms does not make a contract
a multi-year contract and is, indeed, inconsistent with the
objectives of multi-year contracting.
2. I have explained that the five-year limit on contracts with
options is waivable without the need for a FAR deviation. (You
don't need options with an award term contract anyway, and if
you don't have options then the limitation on options will not
apply. Moreover, even if you have options along with award
terms, FAR says that "the total of the basic plus the option
periods shall not exceed 5 years." It says nothing about award
terms, which are not options. So, if you have a one-year
contract with four one-year options and the potential for 15
award terms, the total of the basic and option periods does not
exceed five years.)
3. I have cited authority for the proper interpretation of the
Service Contract Act's five year limitation, which does not
preclude the use of award terms.
4. I have opened your eyes to the possibility that an award-term
is neither an option or a new award (your false dichotomy). It's
not necessarily one thing or the other; it may simply be an
entirely new thing -- an award term.
One thing I did not do was answer your question: " I use
multi-year money and incremental funding on CR contracts... what
if I wanted to incrementally fund a two-year award term? Would
the multi-year limit apply then?"
If by "multi-year money" you meant "multiple-year appropriation"
(see the GAO Redbook, Vol. 1, Ch. 5, page 5-3), then by all
means, go ahead and incrementally fund a two-year award term. If
your funds cover the extent of your contractual obligation, then
you don't have a multi-year contract within the meaning of FAR
Subpart 17.1 and the five-year limit will not apply.
When a contract includes a well-written award term incentive
clause, it says:
"You have the chance to earn award-term contract extensions by
rendering excellent service. If you earn an award term, and if
when the award term is due to commence we still have a
requirement, and if we get money from Congress for the
requirement, then you won't have to compete to continue
performing the contract. The contract extension will be yours as
a matter of right. But if you earn an award term and we don't
have a requirement, or if Congress doesn't give us money, then
there will be no extension of the contract and we will part
company amicably (or not, as the case may be) at no cost to the
government -- not a penny, not a farthing, nothing, nada,
zilch."
(Gee, that would make a pretty good award-term clause.)
Good luck to you.
Vern
By
formerfed on Wednesday, March 05,
2003 - 10:21 am:
Newbie,
One key thing in your task to "advise my agency of the
appropriateness of this type of incentive for the work we do" is
determining if this is the most effective way to incentivize the
contractor. You can get this started when you conduct market
research. Motivating factors to provide exceptional performance
vary greatly from company to company and from industry to
industry. The best way to gather this information is to ask from
your potential offerors.
Another factor is how much your requirement will change over
time. The thing that prompted the five year FAR restriction is
the discovery of many long term overpriced contracts years ago.
These contracts contained excessive prices in the out years due
to many negotiated changes over time that are noncompetively
established. You want to avoid that and the longer the term is,
the more the likelihood.
By
newbie on Friday, March 07, 2003 -
12:06 am:
Thank you Vern, and formerfed.
|