By
julie a. talley on Monday, February 04, 2002 - 02:46 pm:
A contracting officer issued a
solicitation for maintenance dredging with a performance period
of a base year and one option year. At award, and on the SF 1442
block 21 the Contracting Officer accepted the line items for the
total base year and one option year. The amount in block 22 is
for the total base year and option year periods. This was
discovered at the post award conference. Legal opinion at the
time stated that in fact the entire contract period (the base
and option year) were awarded at the same time by virtue of what
was written in blocks 21 and 22 SF 1442. The Contractor and the
Contract Admin office worked under this assumption.
It has now been requested that the contract be terminated for
convenience, as there is no requirement for the second year.
Services were only performed during the base year.
My question is "do I really have a period of service to
terminate"? Did we legally exercise the option? None of the
regulatory requirements of FAR 17.207 were met to exercise the
option year?
By
Vern Edwards on Monday, February 04, 2002 - 03:20 pm:
Julie:
If all that happened was that the CO cited the line items and
amount for both the basic and option periods on the SF1442, then
in my opinion he/she did not exercise the option and doesn't
have to terminate the option period. However, in order to answer
your question with confidence I would have to see the contract
and accompanying documentation. I'm assuming that there are no
damning facts and that there were no oral or written
communications that might be construed as evidence that the
Government did, in fact, exercise the option. I'm a little
worried by what you say about the contract admin. office and the
contractor working under the assumption that the option had been
exercised. What does that mean in practical terms?
Generally, contracts with options have clauses that say what the
CO must do to exercise an option. Did the contract include the
clause at FAR 52.217-9? If so, did the CO give the contractor
the required preliminary notice of intent? Did the CO ever
communicate by written or oral notice that he/she was, in fact,
exercising the option?
Saying that the basic and option periods were "accepted" doesn't
necessarily mean that the Government exercised the option.
Whenever a CO awards a contract that includes an option he/she
"accepts" the option; that's how the Government obtains the
right to exercise it. But it doesn't follow that accepting the
offer of an option is the same as exercising it.
If you have given us all of the relavent facts, and all the CO
did was cite both line items in SF1442 block 21, and insert the
total of the basic and option period prices in SF1442 block 22,
then I would say that he/she did not exercise the option
thereby. I would prepare a unilateral administrative change to
the contract changing the amount in block 22 and, if necessary,
the accounting and appropriation data in block 23.
Having said all this, you say the CO got a legal opinion that
the option has been exercised. If that's so, then you should
probably go with it.
By
joel hoffman on Monday, February 04, 2002 - 03:59 pm:
Julie, were all the funds
obligated with the initial contract award? If so, what type
funds were set up for year two - annual or two year?
I don't think CW annual funds can be obligated for future year
dredging, can they? If not, the award would be improper and must
be voided for year two, correct? happy sails! joel
By
Anonymous
on Tuesday, February 05, 2002 - 08:22 am:
Julie,
If the contract accepted all the line items and the funding was
obligated for base and options was the provision 52.217-4,
included in the solicitation? Assuming the funding is
non-expiring why would they need the options in the first place?
If the provision was not included then where was the
contractor's notice of option award.
By
julie a.
talley on Tuesday, February 05, 2002 - 03:13 pm:
Anonymous - No, the solicitation
did not include 52.217-4. The only notice the contractor
received was a verbal statement from the Contracting Officer
stating that by virture of block 21 and 22 being completed for
the full contract amount the option had in fact been exercised
at award.
By
Vern Edwards on Tuesday, February 05, 2002 - 03:43 pm:
Julie:
Just out of curiosity: In light of the fact that the contracting
officer told the contractor that the option had been exercised,
why are you raising the question now? Does the contracting
officer now wish to renege?
By
joel hoffman on Tuesday, February 05, 2002 - 04:53 pm:
Vern, unless the funds cited for
the option year dredging were current for the option period, I
don't think they can be used, can they? Maintenance dredging
contracts are usually set up to handle each year's shoaling
requirements. Bonafide Needs rule, similar to options on a
janitorial contract, I would think. Anyway, that is a
consideration which Julie's COE apprpriations law attorneys
should sort out. If the funds were improperly cited, the award
of the option may be invalid. happy sails! joel
By
Vern Edwards on Tuesday, February 05, 2002 - 06:01 pm:
Joel:
I don't know the answer to the funding question in this case. If
the appropriated funds were not available to cover the option
period, and the contracting officer exercised the option without
funds, wouldn't that be a violation of the Anti-Deficiency Act?
This relates to the thread on IDIQ minimums. The creation of an
obligation and the recording of that obligation (which many
people refer to as "obligating funds") are different things.
Recording an obligation when, in fact, there has not been one,
does not give rise to an obligation. And an obligation is an
obligation whether properly recorded or not. I think that
exercising an option creates an obligation. If the option is
exercised without funds, then the CO has violated the
Anti-Deficiency Act. Right?
So, if the funds were from an annual appropriation and were
available to cover only the basic year, but were recorded to
cover both the basic and the option years, then they were
improperly recorded, but the exercise of the option created an
obligation nonetheless. If there were no funds to cover the
obligation, then I think we have an Anti-Deficiency Act.
I think.
Vern
By
Vern Edwards on Tuesday, February 05, 2002 - 06:04 pm:
Joel:
P.S. Of course, Eric and John appear to have different ideas
about obligations than I do, so maybe they have a thought or two
about this.
Vern
By
Kennedy How on
Wednesday, February 06, 2002 - 12:07 pm:
I read this kinda fast, but it
seems to me that the contract was awarded for the entire amount
(base plus option year) using the current year funding
appropriation (if I understand Joel's comment correct, regarding
annual appropriations). So, to me, as long as the current
appropriation is funded for the full amount, there shouldn't be
any Anti-Deficiency violation here, there is money there behind
the obligation.
That's not to say that somebody isn't spending the money
correctly, spending this year's money for next year's work. I
don't know what the regs say about that, in light of
Construction contracts (I also don't have any experience in this
arena in the hardware contracting world, we just never did it
unless it was a service).
I also don't think that this is Anti-Deficient for the option
period since you don't have the option year fund cite to go
against; the only way you can be short funding is if the current
year appropriation is short. And, it doesn't sound like it is (I
know I usually checked the money pot before award, just to make
sure the total amount at award is present on the funding
document).
Kennedy
By
Eric Ottinger on
Wednesday, February 06, 2002 - 12:18 pm:
All,
Seems to me that if the option was exercised at time of award,
it isn't really an option, it is part of the basic contract.
Do any of our legal brains have an opinion on this point?
Eric
By
Vern Edwards on Wednesday, February 06, 2002 - 12:40 pm:
If
the option was exercised, then the contract period of
performance and tasks include the option work; it is no longer
an option. The contractor is obligated to perform accordingly
and the government is obligated to pay.
If the appropriation was not available for the option work, then
it seems to me that citing it to cover the option was improper.
It failed the purpose test(?).
If the option was exercised, and if the exercise constituted an
obligation, and if there was no appropriation available for the
obligation, then don't we have a violation of the
Anti-Deficiency Act?
It seems to me that the question is whether including the option
item and price on SF1442 exercised the option. In and of itself,
I don't think it did, but the agency's lawyer appears to have
counseled differently. Was he/she right? Do any of the legal
brains have an opinion on that point?
By
joel hoffman on Wednesday, February 06, 2002 - 03:01 pm:
Here are the questions:
My question is "do I really have a period of service to
terminate"?
Did we legally exercise the option? None of the regulatory
requirements of FAR 17.207 were met to exercise the option year?
In only responding to the second question,
1) Improper funding MIGHT have been cited for a future
requirement. Does this VOID the award of the option by operation
of law?
2) Options are awarded all the time with the basic contract
award. What did the RFP say about this, if anything? Did it say
the Government could include the base plus option in the initial
award? Did it say that the Government could award anytime prior
to XXX date? FAR 17.207 doesn't cover dredging, so failure to
follow it probably doesn't negate the legal effect - probably
wouldn't negate it even it 17.207 did apply ( most of the same
requirements apply to options for dredging- it just isn't
covered in FAR!).
happy sails! joel
By
Vern Edwards on
Wednesday, February 06, 2002 - 03:37 pm:
Joel:
An interesting variation on your analysis is this: What if the
contracting officer exercised the option in accordance with the
pertinent contract clauses, but failed to follow the internal
procedures prescribed in FAR 17.207? Would the contracting
officer's failure to comply with the FAR void the otherwise
contractually proper exercise of the option? I don't know if
there is any case law about this, but my own guess is that a
court would not void the exercise of the option just because the
CO failed to comply with FAR 17.207. However, I think you could
make an argument that a court would or should.
I don't think that the otherwise proper exercise of the option
would be void just because funds were not available. If that
were the case, then how could there ever be a violation of the
Anti-Deficiency Act? The Act clearly contemplates the
possibility of obligation in the absence of an appropriation,
doesn't it?
By
Eric Ottinger on
Wednesday, February 06, 2002 - 03:51 pm:
Vern and Joel,
Since the "option" is not really an option and there are no
changed conditions to consider, I don't think there is any
requirement to comply with FAR 17.207.
Eric
By
joel hoffman on Wednesday, February 06, 2002 - 03:56 pm:
Good points.
Many of the points in 17.207 (again, which doesn't apply to
dredging) deal with deferred award of options. I presume the
regs are to ensure that the requirement is still valid and that
the award makes sense, later - falling prices, changing market,
changing technology, current wage rates, etc. So, I don't see
any problem with awarding an option at base award - except for
the funding issues.
Unless Julie's lawyers determine a way to void the award, they
will probably have to T4C. If no work was done, there may be
little or no cost. What you don't want to do is complicate
things and scare the pants off the contractor with all the
formal paperwork included in the termination notice and
settlement. A no cost settlement is quick and easy to write up
and execute.
My advice is to call the contractor, explain what happened and
see if they will accept a no cost termination. If so, send the
termination notice and no cost settlement mod to the Contractor
to sign at the same time - saves the Contractor a lot of trouble
and time as well as the Government. It doesn't have to be as
complicated as we try to make it. happy sails! joel
By
Vern Edwards on Wednesday, February 06, 2002 - 04:09 pm:
Joel and Eric:
I agree that a CO can exercise an option simultaneously with the
initial contract award, although I'm not convinced that happened
in Julie's case. But I'm a little lost on the business about FAR
17.207 not applying to dredging and about the option not being
an option.
Joel, I've never done a dredging contract. Why doesn't FAR
17.207 apply to dredging?
Eric, why do you say that the option is not really an option?
Are you saying that since the option was exercised we no longer
have to worry about FAR 17.207? If so, I agree, if, in fact, the
option was exercised. But I think that Julie's initial question
was whether the option had, in fact, been exercised. Based on
what she described, I don't think it had. Do you think that the
completion of SF1442 as she described constituted the exercise
of the option?
Am I off track? Have I missed something?
Vern
By
Vern Edwards on Wednesday, February 06, 2002 - 04:22 pm:
Joel:
One last thought:
If the appropriation was not available for the option work, then
what funds would they use to settle the termination of that work
if the contractor would not agree to a no cost settlement?
Vern
By
joel hoffman on Wednesday, February 06, 2002 - 04:32 pm:
"Except as provided in Agency
Regulations, this subpart does not apply to contracts for (a)
services involving...(including dredging...)" FAR 17.200 "Scope
of Subpart"
There are no separate COE "Agency Regulations" covering options
for dredging that I'm aware of. Options are discussed in the
Army JAG Course materals and other legal references, plus there
are DOL requirements for current wage rates when a deferred
option is awarded and appropriations law references. Most of the
guidance concerns awarding just as stated in teh contract and
requirements for deferred awards. There is little or no guidance
on awarding options at initial contract award. happy sails! joel
By
joel hoffman on Wednesday, February 06, 2002 - 04:37 pm:
Vern, re your last post:
I think they would use current year funding (Hopefully, they are
in the option year.) gotta go pick up my daughter at the store!!
h.s. joel
By
joel hoffman on Wednesday, February 06, 2002 - 04:37 pm:
Vern, re your last post:
I think they would use current year funding (Hopefully, they are
in the option year.) gotta go pick up my daughter at the store!!
h.s. joel
By
Vern Edwards on Wednesday, February 06, 2002 - 04:40 pm:
Thanks, Joel. Some of my students
are laughing at me for not checking the scope section.
Vern
By
joel hoffman on Wednesday, February 06, 2002 - 05:24 pm:
Vern, don't worry too much. Many
people assume that the FAR prescribes procedures for every type
contract option. I run into that constantly. I recently finished
an 'exhaustive' search (it tired me out!)for guidance on options
for construction contracts for an "Ask a Professor" question. My
chief counsel even sent a request out to every COE attorney. I
tracked over 70 lawyers opening the message, without any
response. One of my own, Mr. Steve Feldman, has written a book,
which includes some guidance. I'm at home, so don't have access
to it. happy sails! joel
By
julie.a.talley on Monday, February 11, 2002 - 10:20 am:
Vern,
Hope the follwoing settles some of the Anti-Deficiency issues.
The subject contract falls under 52.232-5001 Continuing
Contracts, IAW the River and Harbor Act. Therefore the contract
does not have to be fully funded. Also O&M non-expriring funds
were used.
My my key question is can you exercise an option "year" when you
don't have a requirment for that year. Awarding two years at the
start for two seperable performance periods does not allow for
falling prices, changing markets, changing technology,
incorporation of current wage rates, etc. and a determination
that we still have a requirement.
At this point we are working on a TforC, but for future
acquisitions I would like to see what legal may have to say.
By
joel hoffman on Monday, February 11, 2002 - 10:26 am:
Julie, now I am clear on the
funding. From your description, I'm pretty sure that you awarded
a contract including base and option. A TFC is appropriate, not
an admin mod. happy sails! joel
By
Vern Edwards on Monday, February 11, 2002 - 10:33 am:
Julie:
Thanks for clearing things up about the funding. Here's what I
think about your key question:
Exercising an option is a contractual act. I think that if you
exercise an option in accordance with contractual procedures,
then you have exercised the option, requirement or not, funds or
not. However, if the exercise of the option was not done in
accordance with statute or regulations then perhaps there is an
issue of whether or not the CO acted within the scope of his/her
authority. If the CO acted outside the scope of his/her
authority, then maybe the exercise of the option is void ab
initio. Who knows?
The thing that I would say about what happened to your
agency--based on your description of events--is that I don't
think the CO intended to exercise the option at contract award,
nor did he/she do so in fact. I don't think that making
reference to the option line item and recording an obligation to
cover the option dollar amount on SF1442 constituted exercise of
the option. It was a mistake. If the mistake had been made clear
to the contractor at the outset and promptly corrected, then
there would be no issue. But it sounds like the CO accepted the
interpretation that he/she was given and interacted with the
contractor as if the option had been exercised. Thus, his/her
behavior may have sealed your agency's fate.
I hope that you get good advice from your legal office. If you T
for C, I hope it doesn't cost your agency too much.
Vern |