By
Ophelia on Friday, May 17, 2002 - 01:54 pm:
I'm new to this field, but I often hear the term,
"Milestone," yet I cannot find it in the FAR or DFAR's. What's
up with that??
By
Anon on Friday, May 17, 2002 - 02:31 pm:
Milestones are normally locally promulgated, you may limit
yourself to just a few such as PR acceptance, solicitatiion
issue, receipt of offers, award...or you may have many, synopsis
date, solicitation issue, receipt of offers, conclusion of
initial evaluations, start discussion, receive revised offers,
final source selection decision, etc, etc.
By
Eric Ottinger on
Friday, May 17, 2002 - 02:38 pm:
Ophelia,
Think of a milestone as a small deadline on the road to the
final deadline.
For instance, if you are building a house, "Completing the
foundation" would be a milestone.
Eric
By
Ophelia on Friday, May 17, 2002 - 02:47 pm:
Thanks, Anon and Eric for the information. I sort of
understand the term, but I'm wondering why the term is not in
the FAR? It seems to be widely used.
Anon, we recently won a contract and attempted to have a
milestone called "contract award." The customer would not accept
it as a legitimate milestone.
Another question: is a contractor obligated to agree to
milestones?
Thanks again.
By
Eric Ottinger on
Friday, May 17, 2002 - 03:02 pm:
Ophelia,
It is more of an industrial engineering or program management
term than a contract term.
However, there has recently been a push to use "milestone
billings" in preference to "progress payments."
"Milestone" is one of those words that everyone uses and no one
thinks about very much.
There are some contract clauses that may require the contractor
to systematically track progress on the contract. In this sense,
the contractor may be obligated to agree to milestones.
Eric
By
Ophelia on Friday, May 17, 2002 - 03:08 pm:
Thanks, Eric.
By
joel hoffman on Friday, May 17, 2002 - 03:44 pm:
Ophelia, a contractor is only obligated to agree to comply
with the terms of the contract. If a milestone is a contract
condition, the Contractor must meet the milestone.
On the other hand, if you are negotiating a new contract,
technically the other party is an offeror, and no - they don't
have to agree to the milestone; they can try to negotiate.
However, eventually, the owner and offeror must mutually agree
on the contract terms, in order to seal the deal and award the
contract. happy sails! joel hoffman
By
Ophelia on Monday, May 20, 2002 - 01:21 pm:
Thanks, Joel.
By
Vern Edwards on Tuesday, May 21, 2002 - 10:20 pm:
Ophelia:
The term milestone does appear in the FAR. See FAR §
32.904(d)(1)(i). Also, see FAR Subpart 32.10, Performance-Based
Payments, specifically, FAR § 32.1004(a)(1), which describes a
milestone as a "specifically described" event. The term appears
in DFARS, too. See DFARS § 207.105(a)(1)(C) and (D).
By
AnonymousMe on Thursday, May 23, 2002 - 10:16 am:
FAR Part 7.105 also includes a list of milestones for the
acquisition cycle.
By
Anonymous
on Friday, May 24, 2002 - 09:56 am:
Ophelia is apparently a contractor ("we recently won a
contract and attempted to have a milestone called 'contract
award.' The customer would not accept it as a legitimate
milestone.").
The FAR § 7.105 milestones are largely internal government
milestones that may be transparent to the contractor. The
milestones mentioned in § 32.904 with reference to payment are
more likely to be imposed on the contractor through
Departmental, agency policy or program management, not the FAR.
A few, such as weapon system live fire test requirements, are
imposed by law.
Joel is correct. A contractor is only obligated to follow the
contract requirements. I'd expand on that a bit from my
perspective as a program office type. Some milestone activity
will be imposed through the contract (shame on the PMO if not)
while others may remain internal. A contractor must perform as
specified for those directly imposed; however, I think a wise
contractor will also stay tuned to internal milestones they know
about.
Milestones are essentially decision points. Do events at this
milestone measurement warrant a particular action? Do we
continue this contract? Do we move to production? Do we install?
Do we decide this is a lost cause and wind down? Even if not a
contractor-government milestone they will often have an effect
on the contractor's well being. It is to a contractor's benefit
to be aware of these decision points and make the outcome
positive.
Ophelia does not say, but I suspect she is involved in a
contract that is asking the contractor's input on effective
milestone definition and scheduling. Before the reforms of the
early 1990s the effective tool of milestone use had become so
formalized and ritualized that they were being identified with
waste as often as effective program management. They were dog
and pony shows often attended by executives on a road trip. They
tended to be ritualized with dress up, "head tables," very
formal schedules, luncheons and predictable outcomes. Some
milestones were making little sense.
One reform effort that made sense was to involve the contractor
in defining logical milestone content and scheduling. I saw that
work well. I also saw it "captured" by those used to the old way
and made into what was legitimately associated with useless
waste. A contracting shop may not be fully aware of programmatic
milestones. They will differ somewhat depending on what is being
done. For example, software development milestones may have no
bearing at all on another type of development. The company's
program manager and staff had better be fully up on appropriate
milestones for the program type. Failure to do so will likely
result in those decision points resulting in negatives all
around. |