Beverly Wester on Friday, February 09, 2001 - 04:12 pm:
What are the advantages and
disadvantages of a ID/IQ Contract.
By
Eric Ottinger
on Friday, February 09, 2001 - 06:04 pm:
Beverly,
Very short answer--
Advantage: You get all of that flexibility between the minimum
and the maximum.
Disadvantage: Every Task Order is effectively a separate
contract (although I am not sure we all agree on this point.) In
any case, each Task Order must be separately priced and
separately funded (separately closed out, etc., etc.).
Eric
By
Anonymous
on Friday, February 09, 2001 - 10:34 pm:
Most COs know that it is
impossible to protest a delivery order under an ID/IQ so you can
avoid those problems and award to who you want.
You can also avoid the CBD notices and publicity of separate
contracts so it is very hard to track what a CO is doing against
such a contract!
Thus ID/IQs provide a cover for getting away with things!
By
bob antonio on
Saturday, February 10, 2001 - 08:32 am:
Beverly:
Here is the citation in the Federal Acquisition Regulation that
covers Indefinite Delivery, Indefinite Quantity contracts.
http://www.arnet.gov/far/current/html/16.html#16.504
Part 16.5 covers the various Indefinite-Delivery Contracts and
16.504 specifies the process for the Indefinite-quantity
variety.
Here is a brief history of these contracts. Prior to 1994,
agencies used these contracts on a fairly regular basis.
However, in many cases, only one contractor would be selected
from the initial contract competition and all orders were
sole-source to the that contractor. On the other hand, quite a
few agencies did qualify more than one source under the original
procurement and did award their orders on a competitive basis.
In 1994, Congress believed that these contracts were being
abused through a lack of competition for individual orders so it
included changes in a major contracting law called the Federal
Acquisition Streamlining Act of 1994. Here is that original law
http://thomas.loc.gov/cgi-bin/query/z?c103:S.1587.ENR: (To
use this address, you need to highlight the full address
including the colon and then copy and drop it into the address
area of your browser. For some reason, this thing will not
include colons.)
The law and its implementing regulation set a legal preference
for multiple awards under the original competition to try to
ensure competition for the orders; recognize the value of the
administrative convenience of orders vs. new procurements and
frees these orders from the view of external legal forums (bid
protests); allow a streamlined ordering process.
The basic advantages I have found over the years include, (1)
the administrative convenience of ordering vs. new procurements
in the federal process, (2) an opportunity to pre-qualify
sources and work with a limited number of offerors similar to
the private world, and (3) developing a nice ordering process
using current workload and past performance on the orders.
The things to remember which are not really disadvantages
include the following:
1) The contracts to the qualified sources require a minimum
quantity of items to be acquired. On numerous occasions, I have
found agencies forcing work to a contractor to meet a poorly
conceived minimum quantity. So it is necessary to identify a
realistic minimum for the entire procurement and then allocating
parts of it to the potential sources' contracts.
2) The potential sources selected need to be evaluated to ensure
that there is truly more than one competitor available for the
orders. Unless there is more than one potential supplier
available for the various types of work, you will be in a
sole-source position in the award of orders. Things to consider
include the makeup of the original statement of work and lines
of work to make sure that it is structured to result in
competition. The evaluators who evaluate the potential sources
and who develop the statements of work under the original
procurement need to understand that the purpose of this effort
is to qualify more than one potential supplier in the various
areas of work.
3) An ordering process needs to be developed to take advantage
of the administrative convenience this type of procurement
provides. The ordering process should be streamlined and fair.
Any burdensome evaluation process should be avoided.
By
Kennedy How on
Tuesday, February 13, 2001 - 12:21 pm:
Our activity does a lot of IDIQ
contracts for hardware items. It was basically deemed an
efficient way to buy things that we regularly buy anyway, and
have a stable demand for. The downsizing of the Fed Acq force
caused us to revisit having to spend an inordinate amount of
time buying something every 6 months or so, and suffering the
procurement lead times that go along with it.
What we've ended up doing is competetive RFPs for an IDIQ
contract, up to 5 years. This also gives contractors a secure
feeling for the next 5 years, but, on the flip side, the losers
have a while to wait before the next go-around. Once the
contract is in place, when the logistics system says we need
something, a Delivery Order is issued within a short period of
time. Short being way less than the normal procurement lead
times.
Our office has automated this to less than 24hrs, not counting
the time it takes for a manager to approve the buy. This allows
us to reduce lead times to nearly nothing, and to reduce stock
levels, because our contracting action is so short.
In the larger scheme of things, our activity has made it a
policy to award as many long term contracts as is practicable.
Kennedy
By
Anonymous
on Friday, February 16, 2001 - 11:37 am:
How about IDIQ type contracts
with multiple awards for items where the government maintains
strict control over the specifications (for example, purchases
using government drawings)?
Possible? Desirable?
By
Kennedy How on
Tuesday, February 20, 2001 - 12:44 pm:
16 Feb Anon,
That's what our IDIQs are for. We generally buy the "build to
print" stuff here. It's a Government-owned TDP, and all the
potential offerors submit their proposals against that.
Or, are you talking about some other multiple awards? I know DLA
has some big, long term contracts for competetive items; when a
requirement comes up, they do a price comparison and award to
the low, which might not be the contractor who's holding the
IDIQ contract.
Kennedy
By
Anonymous
on Tuesday, February 20, 2001 - 01:55 pm:
Kennedy,
How many awards do you typically do off of one IDIQ? How do you
handle drawing changes in the middle of a delivery? Do you only
award each delivery order to one vendor?
By
Kennedy How on
Thursday, February 22, 2001 - 12:31 pm:
Anon,
Here are the replies:
#1 Generally, our IDIQs are up to 5 years long. We've
historically bought on a 6 month reorder cycle, but because of
mandates to reduce depot stock, we've gone to something closr to
every 3 months. So, you see anywhere from 15-25 orders over the
life of the contract.
HOWEVER, for the tires we manage, it's on a 2 month cycle. These
contracts are only about 2 yrs long, so we're looking at about
12 D/Os. BUT, we also have a process to generate these orders
electronically, but instead of split deliveries, each order is
specific to one location. Since we have 3 locations, we're
looking at about 36 D/Os.
On top of that, we used to do Direct Vendor Delivery, where we
turn an individual requisition into a Delivery Order. In that
case, we've seen up to 15,000 (yes, thousand) delivery orders
against one 2 year contract.
#2 This can be handled the same way as a Waiver/Deviation, or
ECP change. It gets negotiated into the existing spare parts
contract, and priced accordingly. We used to do this a lot when
we bought Bradley and Abrams spare parts, FMC and GD would
submit ECPs which affect spare parts.
#3 This can be done a couple different ways. One order to each
vendor, but we know of a number of cases where there was a split
award, and so, based on quantity split (60/40 or whatever), you
just had to make sure you kept the order quantities close. If
your item has a steady demand, and your buy histories are
stable, you can alternate awards. We know of a DVD contract like
that; split award by percentage. They put in a counter which
kept track of how many were awarded to each, and it directed the
delivery orders appropriately. I don't think we've ever split a
single requirement in two and awarded two delivery orders
simultaneously to two different contractors, i.e., we need
100ea, 60/40 split, 60 to contractor A, 40 to contractor B. You
could do that, I suppose. Depends on what your activity allows
you to do.
Kennedy
|