By
joel hoffman on Wednesday, December 12, 2001 - 11:57 pm:
I've been researching the subject
question and need some advice (concerns only DOD competitive
RFP's). I don't want to get into discussion concerning the
wisdom or folly of using additives, et al on RFP's, vs. Options,
etc., yet. I'm going to start a separate thread to cover that
topic.
Additives/Deductives/Alternates are only discussed in DFARS at
236.213-70 Additive or Deductive Items.
http://farsite.hill.af.mil/VFDFARa.HTM
This guidance only covers IFB's. There is also a
DFARS Clause 252.236-7007 Additive or Deductive Items, again
written for use in IFB's.
My question is, if there is no coverage of this topic in FAR for
RFP's, if I follow the guiding FAR principle below, can I assume
that I could use the concept of Additives/Deductives and
Proposal Alternates in a DOD RFP?
(1.102 -- Statement of Guiding Principles for the Federal
Acquisition System:
d) The role of each member of the Acquisition Team is to
exercise personal initiative and sound business judgment in
providing the best value product or service to meet the
customer's needs. In exercising initiative, Government members
of the Acquisition Team may assume if a specific strategy,
practice, policy or procedure is in the best interests of the
Government and is not addressed in the FAR, nor prohibited by
law (statute or case law), Executive order or other regulation,
that the strategy, practice, policy or procedure is a
permissible exercise of authority.)
Gotta go to bed. Tomorrow, I'll start another thread which
discusses questions concerning Options vs, Additives, et al on
construction contracts. Thanks for your assistance. happy sails!
joel
By
Vern Edwards on Thursday, December 13, 2001 - 05:55 am:
Joel:
I think that your guiding principles thinking is sound and that
you can use additive items in an RFP. I found four GAO decisions
in which DOD agencies used additive items in an RFP:
1. ADT Security Systems, Inc., B-249932, 1993 (Army).
2. Northeast Construction Co., B-234406, 1989 (USAF).
3. Honeywell, Inc., B-225684, 1987 (Army).
4. TEK, J.V. Morrison-Knudsen/Harnischfeger, B-221320;
B-221320.2, 1986 (Army).
None of the protests was about the use of additive items, but
the decisions state that the agencies did use such items in
their RFPs.
By
joel hoffman on Thursday, December 13, 2001 - 08:35 am:
thanks, Vern happy sails! joel
By
J. Moore on Thursday, December 20, 2001 - 07:08 am:
Joel:
We've had the same discussion here and concluded as you did that
the guiding principles would allow us to use additives/deductives
in a RFP. We also concluded that it doesn't make much sense to
use them though. I'll look for your new thread and encourage
those in my office who discussed this to jump in. Who knows we
may change our thinking.
By
joel hoffman on Thursday, December 20, 2001 - 02:19 pm:
J, I got tied up with travel and
a bunch of other stuff, so haven't pursued the thread concerning
the appropriateness/advantages and disadvantages of using
options or alternates in negotiated procurement.
The reason I was interested in options was because one of my
former office's attorneys recently provided some legal guidance,
severely restricting their use on construction contracts. I
haven't been able to find such restrictions in writing and can't
find much regulatory background on option use in construction,
unless the option is for a severable extension of time or
renewal. I checked FAR/Supplements, the GAO Redbook, what I
could decipher in the DFAS 37 Series regulations, all my old
sources, like "Briefing Papers", Nash and Cibinic, made a Web
search, etc. FAR 17-2 isn't directly applicable to construction
contracts, but doesn't prohibit their use, either.
The attorney basically said that all options must be severable
(e.g., you can't use an option for an upgrade from a shingle
roof to a tile roof), whereas an alternate can certainly be used
for an upgrade;
The attorney said that all options are treated like separate
contracts, requiring current year funding, not original year
funding, etc. (thus cannot be considered in-scope for purposes
of using otherwise expired funding. I thought I could find some
related guidance under the bonafide needs rules, but was
unsuccessful.
Does anyone have any sources which might shed light on this?
I thought one could use options similar to
additive/deductive/alternates, with the advantage that the
option was available for a specified period after original
contract award.
Thanks. happy sails! Joel
NOTE: This is the beginning of
a second thread started by Joel. It is added here to save
space.
By
joel hoffman on Thursday, December 20, 2001 - 04:12 pm:
An attorney in my former office
recently provided them some legal guidance, which severely
restricts use of options in construction contracts. I'm
interested in any background guidance or regulations concerning
what we can use options for in construction contracts, both bid
and negotiated.
I haven't been able to find such restrictions in writing and
can't find much regulatory background on option use in
construction, unless the option is for a severable extension of
time or renewal.
I checked FAR/Supplements, the GAO Redbook, what I could
decipher in the DFAS 37 Series regulations, all my old sources,
like "Briefing Papers", Nash and Cibinic, made a Web search,
etc. Please note that FAR 17-2 isn't directly applicable to
construction contracts, although it doesn't prohibit their use,
either.
The attorney basically said that all options must be severable
(e.g., you can't use an option for an upgrade from a shingle
roof to a tile roof), whereas an additive alternate can
certainly be used for an upgrade.
The attorney said that all options are treated like separate
contracts, requiring current year funding, not original year
funding, etc. (thus cannot be considered in-scope for purposes
of using otherwise expired funding. I thought I could find some
related guidance under the bonafide needs rules, but was
unsuccessful.
Does anyone have any sources which might shed light on this?
I thought one could use options similar to
additive/deductive/alternates, with the advantage that the
option was available for a specified period after original
contract award.
Thanks. happy sails! Joel
By
Vern Edwards on
Thursday, December 20, 2001 - 05:26 pm:
Joel:
I cannot, for the life of me, think of any reason why you cannot
have options in a construction contract. It may be unusual, but
I don't think it is prohibited. For one example of the use of
options in a construction contract see: J.B. Steel, Inc.,
AGBCA No. 83-232-1 (1986). Options might be especially useful
with regard to finish work. FAR certainly does not preclude the
use of options in a construction contract.
And the business about options having to be severable and and
treated as new contracts--I never heard of that before.
By
Vern Edwards on
Thursday, December 20, 2001 - 05:28 pm:
Joel:
P.S. FAR 17.200 expressly states that the use of options is not
precluded in construction contracts.
By
joel hoffman on Friday, December 21, 2001 - 11:40 am:
Vern, et al, here are some
excerpts from the attorney's written guidance concerning options
in supply, services and construction contracts. I didn't copy
the portion dealing with use and evaluation of options, because
it is simply a repeat of normal guidance. I added the asterisks
for discussion purposes. What do y'all think ?
"Exercise of Options.
a. In order for the Government to be able to exercise an option,
the material terms of the option must be established at the time
the basic contract is awarded. These terms must be clear and
definite, and must require no further negotiation. Any change to
the material terms of the option results in a material or
cardinal change to the contract.
b. Where an essential term is changed, the option can not be
awarded until it is justified in the same manner as sole source
procurement.
c. Material terms include but are not limited to price, time for
exercise of the option, quantity, change in type of work, or
performance period (**1).
d. The option, when exercised, is a separate, stand-alone
contract (**2). It may not supercede, replace, be in lieu of, or
detract in any form or fashion from any of the items in the
"Base Bid" nor from any of the other "Optional Bid Items" that
are set out in the solicitation (**2).
e. The Option must be funded with funds available in the year
that it is exercised (**3). It must comply with the bona fide
needs rule, the limits on funding appropriations, and if for
construction, must result in a complete and usable product. If
for services, it can not be for more than 12 months per option
period."
Also, from a "Question and Answer" document (same source):
"Any change in the essential terms of the option results in a
material or cardinal change to the contract.
In determining what constitutes a material change, the COMGEN
has considered the following factors:
Extent of the change in type of work, performance period, cost
between contract as awarded and as modified, as well as whether
potential bidders reasonably would have anticipated the
modification, and impact on competition (**1)."
Joel's Notes:
**1. Note that the description of material or cardinal changes
is different in the two separate discussions. The first is much
more restrictive than the reference to COMGEN considerations.
The latter says "Extent of the change in...", while the former
implies a ban on ANY bilateral change to the period for
exercising the option.
I understand that one must consider the potential impact on the
original competition, if the parties would try to modify the
terms of an option and I understand that the contract's Changes
clause is inapplicable when exercising an option, because the
Government cannot unilaterally make any changes to the
conditions or content of an option, in awarding it (except for
certain facets, such as Wage Determinations on option periods).
However, I don't see any impact on original competition, if the
Contractor simply agrees to extend the period for exercising the
option. It would appear that an extension is done for the
benefit of the Government. The benefit to the Contractor is
primarily to avoid the hassle of re-proposing and
re-negotiating, if the Government wanted to add the work, later.
We had this discussion, awhile back, but I don't remember it
whether or not it was stated that the Contractor could offer or
could agree, upon request, to extend the period. It would
certainly seem to me that a Contractor could submit an
unsolicited proposal to extend an option period, making the
terms more attractive to the Government, similar to the rules
for late modifications to bids or proposals.
For that matter, I don't understand why there would be any
prohibition against the Contractor submitting an unsolicited
proposal to lower the price of an option or otherwise provide
more attractive terms to the Government.
**2. I can't find anything which supports the statement that all
construction contract options are like stand alone contracts. I
can't find anything which supports the position that a
construction contract option can't be structured like an
alternate bid, as long as all options can be evaluated in
accordance with one of the FAR "Evaluation of Options" Clauses.
The example of the option for a more desirable roof type (tile)
comes to mind. Other examples could be options for more durable
finishes, coatings, heavier duty air conditioning equipment,
etc.
**3. The current year funding rule would appear to conflict with
the appropriation rule that original year O&M funds remain
available for in-scope changes to an O&M funded contract.
Those are problems I have with this guidance. happy sails! joel
By
joel hoffman on Friday, December 21, 2001 - 11:48 am:
Vern, I forgot to thank you for
the AGBCA cite and state that I reviewed it. It dealt with a
case where the option description created a patent ambiguity,
resulting in a difference of opinion on what was required in the
base bid for a cold storage facility.
The attorney agrees that options in construction contracts are
allowable; the extent of restrictions on their use is what is at
issue.
P.S. Is there any particular reason that the term "exercising an
option" is used, in lieu of "awarding an option"? Seems that if
each option is a separate contract, "award" would be
appropriate. happy sails! joel
By
Vern Edwards on
Friday, December 21, 2001 - 12:43 pm:
Joel:
I think I understand why your attorney has taken the position in
paragraph d. of his opinion. It's because he's worried about how
to evaluate option prices during the competition. He's thinking
that the GAO requires the evaluation of option prices and if the
option is used to modify the base bid item it could result in
payment of a higher price than offered by another bidder.
Suppose the base bid item requires installation of plastic pipe
and the option provides for changing the material from plastic
to copper. On what basis would you decide which bidder is low?
If the option is for additional work, then you can just add the
option amount to the base bid item. But if the option would
supercede, replace, or be in lieu of the base bid, you could
have a situation wherein one bidder is low on the base bid and
another is low on the option bid. Which one do you choose? If
you choose the bidder that's low on the base and then decide to
exercise the option, what have you done to the competition?
Most options are for additional quantities or an extension of
the period of performance. They are severable from the basic
contract and can be evaluated by adding their prices to the
basic contract price. But an option that alters the
specification is either/or--you go with the base bid or the
option bid, but not both.
Make sense?
If that's not his rationale, then I'm stuck.
By
joel hoffman on Friday, December 21, 2001 - 01:50 pm:
Vern, From what I'm told,
evaluating the options isn't the problem.
In IFB's, they use one of the "Evaluation of Options" clauses,
usually the one which provides for evaluation of base plus all
options, to determine the lowest bidder.
On RFP's, it is done similarly. Plus, in RFP's, we can also
analyze the advantages and disadvantages between offerors
(trade-offs).
If one offer isn't the lowest overall, but its combination of
base plus desired option(s) falls within available funding,
while the overall low offeror's doesn't, this can be considered
an advantage in the trade-off analysis, etc.
I'm not aware of those evaluation methods being a problem for
them. As far as I know, the root cause is that someone has an
extremely conservative outlook on contracting issues.
Thanks for your time. happy sails! joel
By
John Ford on Tuesday, December 25, 2001 - 05:58 pm:
Joel, I'm stuck on his rationale
as well. As for options being seperate contracts, we have to ask
for what purpose or in what context are we speaking. For
contracts subject to the SCA, the DOL considers options to be
separte contracts. However, from a FAR perspective options are
not considered separate contracts, but merely modifications to
an existing contract with the option(s)and basic contract
forming a single contract. See for example, Penn Enterprises,
Inc. ASBCA No. 52234.
Turning to the funding issue, I believe you have misinterpreted
what he says. He said you have to use funds current a the time
the option is exercised. That is quite different from saying you
have to use current year funds. For example, if you have multi
year appropriations, you can obligate those funds on an option
in any year that they are available for obligation. Thus, if you
are using a three year appropriation, you could use FY 2000
funds to fund an option in FY 2002. Also, for O&M funds, at
least for DoD, they expire at the end of each fiscal year.
Therefore, if you awarded a contract in FY 2001 using FY 2001
O&M funds, I doubt you could use those funds to exercise an
option in FY 2002. In this regard, options are treated
differently from other modifications where the "relation back"
rule is applied to determine the appropriate funds to be used on
the mod.
By
joel hoffman on Friday, December 28, 2001 - 11:01 am:
Thanks for your input, John. The
O&M original year funding is the only funding issue I meant to
question. Do you have a source for the interpretation that
original year funds would not be available for a non-severable
type option (e.g., an option for tile roof, in lieu of basic
shingle roof, where only enough funds were available at award
for the shingle roof, but a tile roof would match the
surrounding buildings)?
I understand that options for additional quantities or for new
periods most likely couldn't use original year funds, but some
options are for original needs for which funding wasn't
available at award. It seems that those should be treated like
any other in-scope mod on an O&M or other "expired" funding
source contract. What do you think? happy sails! joel
By
John Ford on Monday, December 31, 2001 - 10:22 am:
Joel, in the hypothetical you are
posing, I wonder if you really have an option or is it just a
change with a different label placed on it? If the option is in
the nature of a change as you have described it, use of O&M
funds would appear to be proper. However, if the option is for
additional quantities of work in a later period, I do not think
you could use O&M funds once there period for obligation has
expired.
By
joel hoffman on Monday, December 31, 2001 - 10:45 am:
Thanks, John. I would agree with
that scenario. I'd assume that each option has to satisfy the
bonafide needs rule for the proposed funding source. I just
wondered if you or anyone else has found any reg, covering
appropriations or otherwise, which would restrict any and all
options to current year funding. Apparently not. happy sails!
joel
By
joel hoffman on Monday, December 31, 2001 - 12:15 pm:
To clarify, my question concerns
an O&M funded contract. I understand the idea of "funds current
at the time the option is exercised", regarding multi-year
funds, etc. happy sails! joel
|