By Anonymous on Monday, August 12,
2002 - 11:10 am:
Could someone please help me
understand how you could have defective pricing (under the Truth
in Negotiations Act) in a cost-reimbursement contract? TINA
applies to cost contracts unless an exemption applies, and I'm
trying to figure out why.
For example, doesn't TINA generally require that cost or pricing
data be submitted prior to the date of agreement on "price"? Is
there really any such agreement in a cost contract?
And let's say that the offeror has cost or pricing data that
indicates that its cost to manufacture an item is really $10 and
not the $12 it has proposed but the offeror neglects to furnish
this cost or pricing data prior to award. If the Govt does a
post-award audit and discovers the data, has there been a TINA
violation? (A CAS violation maybe, but where's the TINA
violation?) The contractor gets paid its actual allowable costs,
not the amount it estimated in its proposal, so how has the
failure to disclose the undisclosed data affected the contract
price? In order for the Govt to recver damages under TINA it has
to prove that failure to discose the cost or pricing data caused
the contract to be overpriced, and I can't figure out how the
nondisclosure causes the Govt to pay anything more than it would
have paid had the data been disclosed.
I apologize if this is a dumb question - I must be overlooking
something.
By Vern Edwards on Monday,
August 12, 2002 - 11:46 am:
TINA requires that firms disclose all of the facts that they
have in their possession that could affect the government's
analysis of their cost estimates during contract negotiation.
The purpose of the law is to put the government on the same
informational footing as the firms with which it negotiates when
price is not established through competition or set by law or
regulation.
As originally drafted, TINA would have applied only to incentive
contracts. But Congress decided to apply it to all types of
contracts after DOD objected that application to only incentive
contracts would make defense firms wary of incentive
arrangements.
The negotiation of the estimated cost for a cost-reimbursement
contract affects the negotiation of fee, whether fixed fee or
incentive fee. It also affects funding decisions and program
decisions that depend on funding. Thus, policy states that when
competition, law, or regulation do not determine costs or
prices, firms must provide the government's negotiators with all
of the facts that may affect their decisions during the
negotiation of costs and fees.
By AnonYmus on Monday, August
12, 2002 - 12:35 pm:
Vern did an excellent job of answering the question, but I'd
like to add a bit more.
Lots of people think that a cost-plus type contract has no limit
on the amount of costs that the contractor will be reimbursed.
This is not true, of course.
The negotiated estimated cost is fixed unless subsequently
modified. If a contractor is going to overrun but fails to
notify the C.O. timely (see 52.232-20, -21, & -22) then the
contractor may not get the extra costs reimbursed.
So TINA would apply. If the estimated cost was inflated because
of a failure to provide cost or pricing data, then the gov't.
has been harmed.
One more point: A number of cases have stated that a
contractor's failure to disclose leads to a (rebuttable)
presumption that the cost has been inflated.
By Anonymous on Monday, August
12, 2002 - 03:21 pm:
I'm still not sure I understand. Maybe a hypothetical situation
might help.
Assume an offeror submits a cost proposal estimating that it can
perform the work for $950,000. Negotiations occur, and the
parties agree on a fixed fee of $50,000. The contractor had in
its possession, but did not submit to the Govt, cost or pricing
data indicating that it probably could perform the work for
$850,000.
The contract is awarded and the contractor performs the work,
incurring $850,000 in cost. It is paid the $850,000 plus the
$50,000 fee for a total of $900,000.
DCAA does a post-award audit, finds the undisclosed cost or
pricing data, and alleges defective pricing. What should the
Govt recover?
Surely not the $100,000 diference between the disclosed and
undisclosed data, because the contractor never received the
$100,000 benefit. I guess Vern would say that the failure to
disclose might have led to excess profit, but that seems like it
would be very difficult to prove (have there been any board
decisions on this theory?). Assuming that the Govt could prove
that it would only have negotiated $40,000 profit instead of
$50,000 if the undisclosed data had been disclosed, would there
be any other damages?
By joel hoffman on Monday,
August 12, 2002 - 04:18 pm:
Using your example, the Government would seek the difference in
'fee', assuming a fee based on $850k vs a fee base of $950k, in
a defective pricing action.
I don't see any other direct damages from the scenario you
described. I don't believe that consequential damages (e.g.,
loss as a result of another unfunded requirement, because the
excess funds were used for the inflated obligation) are covered
by TINA, but will do some research.
happy sails! joel hoffman
By seen it happen on Monday,
August 12, 2002 - 05:07 pm:
The comment in Vern Edward's post about how the analysis process
"affects funding decisions and program decisions that depend on
funding" raises another feature of cost contracts for me. I'm
not sure it is formally stated, but some working with these
contracts agree they are much more in line with a co-operative
effort or partnership than other contract types. A high level of
trust and honesty is very important.
Some things are appropriately kept in confidence on both sides
in general or during particular stages. That said, deception, by
either side, in a cost contract can be particularly poisonus and
have expensive results. Consider the example (try it at
$8.5/$9.5 or $850/$950 million though) where the government's
independent cost estimate is more closely aligned with the
contractor's real estimate and the contractors dishonest cost
proposal is thrown into the budgeting process.
One of the ugly times in an agency comes when one vital program
requires more funding than expected and other, less important
ones, are cut to meet its new requirement. No amount of victory
celebration at coming in "under estimate" a year or two down the
road will restore other programs that lost vital funding and
were reduced in scope -- perhaps even cancelled -- due to the
contractor's early dishonesty. In fact, one result can be
bitterness within the agency toward those who supported the
program having the false celebration. It leaves behind a form of
cancerous rot. In my opinion such a contractor should suffer
real pain, not a slap.
By Vern Edwards on Monday,
August 12, 2002 - 05:16 pm:
The defective pricing clause (FAR § 52.215-10)says that the
government is entitled to a cost reduction if any cost under a
cost-reimbursement contract was increased due to defective
pricing.
Defective pricing could be related to any direct or indirect
cost. Thus, for example, if the government agreed to an
estimated cost based on a proposed subcontract price, and the
subcontract was defectively priced, the government could seek a
reduction in the estimated cost and the fee. If the government
actually reimbursed the contractor based on the defectively
priced subcontract, then the government might be entitled to a
reduction in the prime contract estimated cost and the fee, to
recovery of the excess amounts paid to the prime, and to
interest and a penalty.
By anonconorig on Monday,
August 12, 2002 - 07:23 pm:
Seenithappen:
I too have seen this happen and you are correct. Something I am
trying to resolve with my company also. As my father, who spent
23 years in the Navy and 15 more years as a program manager gave
me sage advice. " You may think you 'won' the first time around
but loe unto you for any future business." Memories are long for
most.
By seen it happen on Monday,
August 12, 2002 - 09:01 pm:
Much the same can happen with other contract types as far as a
project needing more than expected. The point to me is that a
cost contract is different. The government is assuming cost risk
in particular. It hopes to select a real partner in minimizing
those risks. In an ideal situation it finds one that will work
co-operatively not only to handle its cost, but to help point
out undue cost drivers in government actions. Such partnerships
exist and are a pleasure to work with. I've seen that too and
remember those days as being on my personal "profit" side. We
did good things together and we made lasting progress.
A contractor that will, in this more trusted environment, play
games with these matters is much like a cheating spouse. The
poison spreads from the couple to family and friends. Anonymous
seemed to doubt damage done. Vern Edwards explained the bare
facts and mentioned the budget process. The damage, as explained
in my earlier opinion, often goes well beyond those more direct
ones.
By Eric Ottinger on Tuesday,
August 13, 2002 - 09:33 am:
All,
It is a truism that the only thing that is really negotiated on
a cost type contract is the fee. Strictly speaking, the only
thing that the government is going to recoup, in the way of
defective pricing for a cost type contract, is the extra fee.
The fee is the issue. Generally, if there is more cost there
will be more fee. In DoD we use weighted guidelines. If you put
more cost into the weighted guidelines the result will be more
fee.
The obvious exception is a situation where the fee is set by
competition. Under the current rules, defective pricing
shouldn’t apply to a competitive contract. (This was not always
true in the past.)
AnonYmous is missing a big point. The government is not required
to fund a contract beyond the estimated cost. Equally, if the
government chooses not to provide the additional funding, the
contractor is not required to keep working beyond the estimated
cost. If the government does decide to provide funds, the
contractor is required to keep working on a cost/ no fee basis.
I very much agree with Anonconorig and Seen I Happen. Some
people seem to think that the concept of past performance was
invented recently. In the real world a contractor who refuses to
play straight, and causes large problems for the customer, is
always going to have a problem getting follow-on contracts. And
this has always been true.
Of course, going into a big project both sides tend to be
overoptimistic. But that is another issue. It seems to be a
constant that large projects will often overrun egregiously.
This is true on both the government and the private side. This
kind of mutual folly is, of course, a different issue from the
intentional low-ball.
Eric
By joel hoffman on Tuesday,
August 13, 2002 - 10:08 am:
Eric, Two questions and two comments...
I'll have to do some research, but when did "defective pricing"
(assuming that you are referring to the Truth In Negotiation
Act)apply to competitive contracts?
You said: "In the real world a contractor who refuses to play
straight, and causes large problems for the customer, is always
going to have a problem getting follow-on contracts. And this
has always been true." By "the real world", were you referring
to private and commercial contracting?
Most states and local governments, as well as the federal gov't
(when using IFB procedures) end up with the same trouble makers,
time after time. A "non-responsible bidder" determination is
extremely difficult and time consuming. The flexibility allowed
by a best value, trade-off, RFP process does allow us to choose
another firm. However, the Government's extensive use of
negotiated acquisition for other than major weapons and systems
contracts or overseas contracts is relatively recent. Lowest
price bidding had been the preferred method for much acquisition
for quite a while and still is predominant in public
contracting.
We should all remember that the TINA defective pricing clauses
were designed as administrative tools, within the contract, to
help recover certain negotiated costs as a result of "defective
pricing", without having to prove malice or criminal intent to
deceive the Government's negotiators. These clauses are most
effective as an administrative tool, not as an accusatory tool
or as a punishment. happy sails! joel
By Vern Edwards on Tuesday,
August 13, 2002 - 10:16 am:
"In the real world a contractor who refuses to play straight,
and causes large problems for the customer, is always going to
have a problem getting follow-on contracts. And this has always
been true."
I don't know what "real world" that quote refers to, but in the
real world that I know every single one of the government's
major contractors has been nailed for defective pricing, and
worse, but they're still getting contracts.
By Vern Edwards on Tuesday,
August 13, 2002 - 10:29 am:
Joel:
In the past, some components of the Department of Defense
required offerors to submit and certify cost or pricing data
even when a contract was awarded through competitive
negotiation. For many years, some DOD contracting offices felt
that adequate price competition was not present when technical
factors were weighed more heavily than cost or price in a source
selection.
I'm serving as an expert witness in a case involving a contract
awarded in the early 1980s, in which the contractor has been
charged with defective pricing and false claims, even though the
government solicited and received competitive proposals. The
U.S. attorney's position is that the government's request for
cost or pricing data was justified due to the fact that adequate
price competition did not exist in light of the fact that
technical factors were weighed more heavily than price.
As an Air Force contracting officer in the 1970s and 1980s, I
was routinely required by senior staff to demand cost or pricing
data in competitive negotiated acquisitions, based on the notion
that there adequate price competition did not exist when
technical factors were weighed more heavily than price or cost.
By AnonYmus on Tuesday, August
13, 2002 - 10:36 am:
All,
This is a red-herring argument because the contractor's actual
costs are irrelevant to a defective pricing determination.
That's why they call it "cost OR PRICING data."
Defective pricing occurs when contract PRICE is increased
because the contractor failed to submit accurate, current or
complete cost or pricing data during negotiations. Vern's 1st
post is wrong, or at least not complete.
A cost reimbursable contract price is composed of two pieces --
estimated cost and fee. If either piece is increased because of
defective pricing, then the contractor is liable. Doesn't matter
what the contractor's actual costs will be; only matters what
was disclosed during negotiations.
As a recent ASBCA decision (Lockheed Martin d/b/a Sanders -- Feb
2002) recently quoted:
"In McDonnell Douglas Helicopter Systems, ASBCA Nos. 50447 et
al., 00-2 BCA 31,082 at 153,465, we set forth the burden of
proof for defective pricing appeals:
In defective pricing cases the Government bears the burden of
proof on three elements--1) that the information in dispute is
“cost or pricing data” under the Truth in Negotiations Act, 10
U.S.C.A. § 2306a; 2) that cost or pricing data was not
meaningfully disclosed; and 3) that it relied to its detriment
on the inaccurate, noncurrent or incomplete data presented by
the contractor. As to the third element, once nondisclosure is
established a rebuttable presumption arises that a contract
price increase was a natural and probable consequence of that
nondisclosure. Sylvania Electric Products, Inc. v. United
States, 479 F.2d 1342 (Ct. Cl. 1973). However, “[t]he ultimate
burden of showing the causal connection between the incomplete
or inaccurate data and an overstated contract price remains with
the Government.” Grumman Aerospace Corporation, ASBCA No. 27476,
86-3 BCA 19,091 at 96,494."
Eric,
I acknowledge your point. I tend to take the contractor's view
of the world, which revolves around the risk of not getting paid
for all costs. Your point, which is more from the Government
customer's view, revolves around providing sufficent funds to
accomplish the SOW. Both points are valid, I think, but
including yours does make for a more complete answer.
By AnonYmus on Tuesday, August
13, 2002 - 10:38 am:
Erratum -- I meant Vern's 2nd post, where he discusses cost
reduction for increased costs. That's not the correct
interpretation -- should be a "price" reduction for increase to
negotiated contract "price."
By joel hoffman on Tuesday,
August 13, 2002 - 10:43 am:
Thanks for the information, Vern. Our Federal Publications' and
West Publishing's "Briefing Papers" on TINA are missing. There
are a couple of good, comprehensive articles on TINA, there.
happy sails! joel
By Vern Edwards on Tuesday,
August 13, 2002 - 10:46 am:
AnonYmus:
Please read FAR § 52.215-10, Price Reduction for Defective Cost
or Pricing Data (Oct 1997), paragraph (a):
"(a) If any price, including profit or fee, negotiated in
connection with this contract, or any cost reimubursable under
this contract, was increased by any significant amount....
(3)... the price or cost shall be reduced accordingly and the
contract shall be modified to reflect the reduction."
Now, where was I wrong?
By AnonYmus on Tuesday, August
13, 2002 - 12:56 pm:
Vern,
You were wrong because your answer was misleading or, if you
prefer, incomplete.
Read the original question in the thread again. We are inquiring
into whether, or to what extent, defective pricing can occur on
a cost reimbursable contract. You replied,
"The defective pricing clause (FAR § 52.215-10)says that the
government is entitled to a cost reduction if any cost under a
cost-reimbursement contract was increased due to defective
pricing.
Defective pricing could be related to any direct or indirect
cost. Thus, for example, if the government agreed to an
estimated cost based on a proposed subcontract price, and the
subcontract was defectively priced, the government could seek a
reduction in the estimated cost and the fee."
As I pointed out, the government is entitled to a price
reduction for any increase in price. Actually, the remedies
include:
1. Dollar for dollar downward price adjustment
2. Refund of any overpayments with interest
3. An additional amount, equal to the amount of the price
overstatement (not mandatory)
Vern, you are usually right on the money. In this case, however,
you were slightly off.
Sorry, but I have to stick to my guns on this one.
By AnonYmus on Tuesday, August
13, 2002 - 01:08 pm:
Let me add some more on TINA, for those who might be interested.
There's a great pamphlet out, kind of dated, but still
excellent. It's called "Living with TINA: A Practical Guide to
the Truth in Negotiations Act" and was authored by Clarence
Kipps and John Lloyd Rice. It's available from the Washington
Legal Foundation.
Here's a relevant quotation:
"Under TINA, the "significance" of undisclosed facts is relevant
to two considerations. Facts are cost or pricing data if prudent
negotiators would reasonably expect those facts to affect price
negotiations significantly. ... Where there is a TINA violation,
the Government is entitled to a price adjustment to exclude "any
signficant sums" by which the contract price was increased
because of defective cost or pricing data. 10 USCA 2306a(d). ...
In making both determinations, courts and boards state that
signficance is not measured as a percentage of contract price or
by the dollar value shown by undisclosed data but refers to the
logical connection between the data and the issues negotiated.
See Sylvania Elec. Prods, Inc. v United States, 202 Ct. Cl. 16,
479 F.2d 1342 (1972) ... (etc.)"
There's a lot more. As I said, it's a great resource.
By Vern Edwards on Tuesday,
August 13, 2002 - 01:25 pm:
AnonYmus:
What are you talking about?
Suppose that a prime contractor negotiates a sole source CPFF
contract with the government with an estimated cost of
$100,000,000. Suppose further that the estimated cost included
$15,000,000 for a sole source FFP subcontract for a
noncommercial item. Both the prime and the sub submitted and
certified cost or pricing data.
The subcontractor performs and the prime pays the sub the
$15,000,000 and seeks and obtains reimbursement from the
government. Subsequently the government's auditor finds that the
subcontract was defectively priced (the sub's cost or pricing
data were not accurate, complete or current) and that the
subcontract price should have been $10,000,000. The contracting
officer agrees.
Pursuant to FAR § 52.215-10(a), the government is entitled to a
reduction in the cost that was increased due to the sub's
submission of defective cost or pricing data. The prime must
repay the excess $5,000,000 plus simple interest. If the
contracting officer finds that either the prime, or the sub, or
both, knowingly submitted defective data, the the prime must pay
a penalty.
Are you saying that what I have just described is not a case of
defective pricing?
Are you saying that the "cost reimbursable" was not increased
due to the defective pricing?
Are you saying that the defective pricing clause does not
entitle the government to a reduction in the amount that it
reimbursed the prime for the payment that it made to the sub,
and to a refund of the excess amount with interest?
Have you read the defective pricing clause? Did you see the part
that says that if any "cost reimbursable" was increased due to
defective pricing then the "cost" shall be reduced accordingly?
In what way was my answer misleading or incomplete? In what way
did I mislead? What was missing?
By Vern Edwards on Tuesday,
August 13, 2002 - 01:33 pm:
AnonYmus:
You have quoted Kipps and Rice out of context. The quote appears
on page 15 of their pamphlet, in the section entitled,
"Significance is not necessarily measured by monetary value."
The defective pricing clause says that the government is
entitled to a reduction when defective pricing caused the price
or a cost to be increased "by any significant amount." Kipps and
Rice cited court cases which held that what is a "significant
amount" is not determined on the basis of percentage of contract
price or dollar value. That has nothing whatsoever to do with
the point that I have been making.
By joel hoffman on Wednesday,
August 14, 2002 - 08:19 am:
Federal Publications and the West Publishing Company have
published several "Briefing Papers", which are comprehensive
reviews of many of the administrative and legal issues
concerning of TINA. The articles include recommended guidelines
for contractors to stay out of trouble with TINA. Here are three
of those issues:
#89-11 November 1989 "Truth In Negotiations Act/Edition III"
#93-08 July 1993 "Subcontractor Cost or Pricing Data/Edition II"
#95-08 July 1995 "Impact of FASA on The Truth In Negotiations
Act"
I read where KO's routinely required Cost or Pricing data for
competitively negotiated contracts, despite the exemptions for
such circumstances. The alleged reasons were various, e.g.,
perceived lack of competition, requiring certification of C&P
submitted for "price realism" analysis, etc.
Thanks for advising me about the first and last articles, Vern.
happy sails! joel
By John Ford on Sunday, August
18, 2002 - 11:34 am:
As someone with a little experience in the realm of defective
pricing, I would like to comment on Vern's 13 August post. A
close analysis of the elements of a defective pricing claim and
a false claim under the False Claims Act leads to the
unfortunate conclusion that they are very similar. This has lead
to assertions by DoD IG personnel that every defective pricing
allegation should be investigated as a possible false claim. It
also can lead to situations where private bounty hunters bring
specious qui tam suits against contractors. If the government
personnel with whom the Department of Justice coordinates on the
claim are not that familar with defective pricing, or worse yet,
view the claim as an accusation that they did not do their job
properly, thus motivating them to cover themselves by blaming
the contractor for deceiving them, you can easily have the
situation where a mere disagreement on the significance of data
or an inadvertant mistake leads to a serious suit against the
contractor. From what Vern has said about this particular suit,
I find the government's position reprehensible and wish him well
in this matter. I hope he can educate the AUSA and other
government personnel as to what TINA required and what is a true
false claim.
By Anonymous on Thursday,
September 19, 2002 - 12:45 pm:
What about the time period between when the contractor signs the
certificate of current cost and pricing data and the execution
of the prime contract. Is the contractor responsible to notify
the government if he negotiates a lower price, or can he keep
that to himself. This change is between the prime and a sub, but
the government ultimately pays the higher price.
By Anon on Thursday, September
19, 2002 - 03:25 pm:
First question, have you determined this to be defective cost or
pricing data. Did the contractor know or should have known about
the change in the subs cost/price when the certificate of
current cost or pricing data was signed? Also, since this is
cost reimbursement contract aren't you only going to pay actual
costs (that are allocable, allowable and reasonable) incurred by
the contractor?
By joel hoffman on Friday,
September 20, 2002 - 10:30 am:
12:45 anon, as long as the lower subcontract prices were
negotiated after the effective date of the certificate, the
Contractor does not have to notify the Government and provide a
credit. This assumes that the Contractor didn't have factual
knowledge that the price was going to be lower, at the effective
date of certificate signature. There are some wrinkles, which
take a Philadelphia lawyer to interpret, but that is the gist of
it. The wrinkles relate to the "effective date".
Anon 3:25, on a cost reimbursement contract, the fee basis may
be affected by defective C or P. happy sails! joel hoffman
By Anonymous on Friday,
September 20, 2002 - 11:06 am:
I have not determined this to be defective pricing yet. That is
my question. If, after the date the contractor signs the
certificate but before the contract is actually executed, the
contractor gets a better quote from a sub, is the prime required
to pass this info on to the government. His certificate was
accurate when he signed it. Let us pretend this is a FPIF
contract instead of cost plus. Actually, I don't know that it
matters what contract type it is, the question deals with TINA.
By Anon on Friday, September
20, 2002 - 11:07 am:
Joel, I understand the implications regarding fee vis-a-vis
defective costing, my point is that if at the time of proper
certification the subktrs were set at $500,000 and then
subsequently the subs costs were $300,000, under a cost
reimbursement wouldn't the gov'ts outlay for sub costs only be
the $350.000?
By joel hoffman on Friday,
September 20, 2002 - 11:54 am:
Anon 11:07, yes. The sub cost would be the actual cost. Both
Anons, if there were defective pricing on a FPIF contract, the
Contractor's share of "cost savings" could be inflated, because
the original target cost should have been lower. Plus, the basis
of fee would have been inflated.
Anon 11:06. If the Contractor receives a better quote from a sub
after negotiations are complete and after the certificate is
signed, the Contractor does not have to report this to the
Government. This assumes that the Contractor did not have actual
or practical knowledge that the sub was planning to submit the
lower quote, but was simply holding it off until the prime
signed the Certificate. The circumstances surrounding the better
quote are important.
There are at least three or four "Briefing Papers" available
from West Publishing (formerly published by Federal
Publications, Inc.) which cover this in some detail. See the
July 1993, July 1995, and October 1989 issues. happy sails! joel
By Vern Edwards on Friday,
September 20, 2002 - 12:14 pm:
The contractor certifies that the cost or pricing data were
accurate, complete and current as of the date of agreement on
price. There is no TINA obligation to disclose new data obtained
after price agreement, even if the contractor obtains it before
contract award. Take a look at FAR Table 15-2, Note 1, the last
sentence:
"The requirement for submission of cost or pricing data
continues up to the time of agreement on price, or an earlier
date agreed upon between the parties if applicable."
Underlining added.
However, in my opinion, a contractor who gets new data after
agreement, but before award, showing that a subcontract price
will be lower than a quote disclosed to the government during
negotiations, would be foolish not to disclose that information
to the government. If the government learns of it later, it will
never believe that the contractor did not know of it before
price agreement. If that happens, the result could be months of
investigation and perhaps even a false claims suit or
prosecution. Even if the contractor is cleared, the
investigation will be costly and nerve-wracking.
Disclose! |