By alexreb on Thursday, September
05, 2002 - 03:53 pm:
I have a question concerning weather delays on service contracts
for removal of debris from channels. But first a little
background to lay the groundwork for my thinking.
When awarded a construction contract a contractor is responsible
for the work until acceptance made by Government. If a storm
event occurs and damages work prior to Government acceptance the
contractor may be entitled only to time. Unless otherwise stated
in the contract, contractor is not entitled to monetary
adjustment for storm related damages to construction work under
the control of the contractor, prior to acceptance.
That is the stance we take for storm damages that occur during
construction contracts. But what about service contracts for
debris removal. Would the same tenant apply?
We have a situation where a contract was awarded for channel
debris removal. The work was being accomplished due to a storm
event. A second storm event caused more debris to be introduced
into the channel that the contractor was removing debris from.
Under our current contract, is the contractor now responsible
for the removal of debris caused by the second storm, as well as
the debris from original storm?
By Harley Hartley on Friday,
September 06, 2002 - 07:31 am:
I would ask this question first: Is it fair to expect the
contractor to remove this additional debris for no additional
compensation?
Here are some other questions:
1. Was the original contract based on an estimated quantity or
an actual quantity?
2. Did the contractor prepare its offer based on the quantity
present at the time of offer?
All the hurricane debris removal contracts I've awarded were
based on estimated quantities and most (if not all) included FAR
52.211-18 (yes, I know it's a construction clause), so we made
award based on an estimated quantity but paid based on actual
quantity.
By Vern Edwards on Friday,
September 06, 2002 - 08:54 am:
A service contractor is entitled to a time extension if delayed
by unusually severe weather. See FAR § 52.249-8, Default
(Fixed-Price Supply and Service) (APR 1984), and FAR §
52.249-14, Excusable Delays (APR 1984). The mere fact that there
was a severe storm is not sufficient to entitle you to more
time; the storm must have been an instance of "unusually" severe
weather.
However, the government does not have to compensate you for the
additional cost you must incur due to the weather event, unless
you have a special clause in your contract to that effect. The
government did not cause the weather event, the weather event
was not a breach of contract by the government, and I do not
know of any standard FAR clause that requires the government to
compensate you for weather-related cost increases.
By alexreb on Friday, September
06, 2002 - 09:41 am:
My response to your first question would be that it depends. If
you go back to my original question concerning debris removal as
part of a construction contract, the only type of relief the
Government can provide is usually time (from 52.249-10 Default
FP Const.). The clause at 52.236-2 Differing Site Conditions,
which was included in the contract, may come into effect, but I
believe weather is usually outside the scope of that clause if
the event that causes a differing site condition occurs during
contract performance.
To answer your other questions, it was a fixed price contract,
one job lump sum; contractor to remove all debris from Point A
to Point B. And yes, the contractor's offer was based on the
debris present at the time of the offer.
By Anon on Friday, September
06, 2002 - 11:23 am:
Have enough storms at appropriate intervals and you'll have a
Sisyphean situation. Vern's correct about the weather, was the
second storm of an unusually severe nature. Did the SOW actually
state removal of all debris present at the time the offer was
submitted? If so, as a contractor, I would argue that I have
performed the original requirement, subsequent debris
accumulation is a matter for another procurement.
By Harley Hartley on Friday,
September 06, 2002 - 11:36 am:
I defer to Mr. Edwards' superior knowledge but I don't think it
would be fair to make the contractor remove the additional
debris without additional compensation if the contractor can
show additional costs associated with removing the additional
debris.
By Vern Edwards on Friday,
September 06, 2002 - 11:59 am:
Harley, et al.:
What's fair depends on what the parties agreed to and how they
allocated risk. For instance, did the contractor agree to remove
a certain amount of debris at a unit rate, did it agree to
remove a certain quantity of debris for a lump sum, or did it
agree to clear the channel to a certain depth for a unit rate or
a lump sum? When did the storm occur -- in the middle of the
operation, or after the debris had been removed or the channel
had been cleared but before final acceptance?
If the parties knew what they were doing, then they should have
contemplated the possibility that a new storm (even an ordinary
storm) would bring new debris into the channel and allocated the
risk appropriately. If they didn't reach agreement on the
allocation of risk, then the thing may end up being decided by
lawyers.
There is no universal rule about how such things get done. The
parties have to decide how they want to do it and write it down.
By joel hoffman on Friday,
September 06, 2002 - 12:15 pm:
I'm out of the office, but you are correct Alexreb, that the
Differing Site Conditions clause would not provide relief. I
think there is some discussion about similar situations in Nash
and Cibinic's Administration of Government Contracts (weather
deposited shoals, stumps, etc. are not a differing site
condition, because the condition occurred after contract
performance started.)
As Vern said, relief depends on how risks were allocated between
the parties in the contract.
happy sails! joel
By alexreb on Friday, September
06, 2002 - 12:55 pm:
We thought the same principle applied to service contracts as it
does to construction contracts, but just wanted some input to be
sure. Does anyone know of any case law dealing specifically with
service contracts on this issue?
By Harley Hartley on Friday,
September 06, 2002 - 12:56 pm:
As always, Mr. Edwards is right on the mark. In this specific
case raised by alexreb I wonder, however, what the Government's
position would be if the second storm, rather than adding to the
debris in the channel, had cleared some or all of the existing
debris from the channel.
By Anon on Friday, September
06, 2002 - 01:00 pm:
Why was this determined to be a Services Contract? I looked at
the definition of construction in FAR Part 2...
"Construction" means construction, alteration, or repair
(including dredging, excavating, and painting) of buildings,
structures, or other real property. For purposes of this
definition, the terms "buildings, structures, or other real
property" include, but are not limited to, improvements of all
types, such as bridges, dams, plants, highways, parkways,
streets, subways, tunnels, sewers, mains, power lines,
cemeteries, pumping stations, railways, airport facilities,
terminals, docks, piers, wharves, ways, lighthouses, buoys,
jetties, breakwaters, levees, canals, and channels. Construction
does not include the manufacture, production, furnishing,
construction, alteration, repair, processing, or assembling of
vessels, aircraft, or other kinds of personal property.
(my emphasis added)
By joel hoffman on Friday,
September 06, 2002 - 02:54 pm:
Harley, if it were my contract, I would terminate it for
convenience if "the storm had cleared all the existing debris"
from the channel, but if the storm had merely reduced the
debris, I'd probably not do anything.
Anon, this type of work is probably a service. Alexreb's post
reads like the work simply involves cleaning the channel of
debris deposited by a storm. Alexreb didn't mention any repair
or alteration to the channel.
Alexreb, if the contract scope of work specifically describes
the work as clearing debris deposited by a specific event, there
might be grounds for a change, based on the fact that there is
now debris from more than the specified event. happy sails! Joel
By Anon on Friday, September
06, 2002 - 03:09 pm:
Okay, I just thought that cleaning a channel would entail
dredging. On the eastern shore of MD contractors are brought in
by communities after big storms to clear away excess silt, etc
to reopen boating channels. This work is done by dredging
companies. I presumed this work was of a similar nature.
By joel hoffman on Friday,
September 06, 2002 - 03:24 pm:
Anon, if so, you are correct that it would be a construction
contract. Depends on the size of the channel and the type of
equipment used. A minor operation, using using "snagging"
equipment without any silt excavation, is probably a service.
happy sails! joel
|