|
|
|
HOME | CONTENTS | DISCUSSIONS | BLOG | QUICK-KITs| STATES |
Search WWW Search wifcon.com |
"Liquidated Damages" | |
---|---|
By
joel hoffman
on Tuesday, February 20, 2001 - 08:06 pm:
Here is an unanswered question from "Ask A Professor." Does
anyone disagree with my answer? By Anonymous on Wednesday, February 21, 2001 - 07:43 am: I don't disagree with the way you treat LDs, because I would do the smae thing in your situation. However, I don't believe that is the proper technical answer. LDs are supposed to be payments from the contractor to the government for harm created by contractors delays in performance. In other words, the government incurs some financial harm by the contractor being late, and LDs are a means to compensate. What you are doing is almost like receiving a credit from the contractor to be applied against payments. In other words, the contractor isn't receiving full contract amount. That's not LD, where the payment for harm may not immediatly be due to the contract itself - like the government is paying rent until the contract is finished. LDs properly should be cash payments to the governement and not be confused by contract payments. By joel hoffman on Wednesday, February 21, 2001 - 09:07 am: Anon, where did you learn this? "That's not LD, where the
payment for harm may not immediatly be due to the contract
itself - like the government is paying rent until the contract
is finished. LDs properly should be cash payments to the
governement and not be confused by contract payments." By Anonymous on Wednesday, February 21, 2001 - 10:11 am: I was thinking in general terms and ignored use in construction where LDs are assesssed for fauilure to pay subs. However, in more general use, LDs are used in the situation I described such as the government incurring losses (see examples cited in FAR 11.503(b)). As far as how LD payments are treated, look at the GAO Red Book. I don't have immediate acess to ne right now, but I will look when I get a chance. By joel hoffman on Wednesday, February 21, 2001 - 10:55 am: Anon, My discussion of the subject only concerns construction
L.D's, as described in Subpart 11.5 - damages for late
completion. By Anonymous on Wednesday, February 21, 2001 - 11:21 am: Joel By anon 2 on Wednesday, February 21, 2001 - 11:23 am: Thats anon 2 at 11.21 By Anonymous on Wednesday, February 21, 2001 - 11:31 am: Joel, By joel hoffman on Wednesday, February 21, 2001 - 11:57 am: Anon2, you have valid concerns about actual use of such funds
for additional work. I need to review the accounting and finance
regulation for disposition of retained l.d.'s. By the way, funds
disposition is not determined by the construction offices. In
the past the COE Finance and Accounting offices made the
transactions - now done by DFAS. I beleive that Anon1 and I were
primarily debating the administrative details of "collecting"
the L'D's. However, I did state in my initial post that I
thought the de-obligated funds could be used for other valid
uses. By joel hoffman on Wednesday, February 21, 2001 - 12:02 pm: Anon1 (11:31AM), you may be right about what happens to the funds, even if not directly received from the contractor and that LD's are not a precise measure of the Government's actual damages. I have to review the F&A reg. Happy Sails Joel By John Ford on Wednesday, February 21, 2001 - 12:25 pm: Joel, I think your analysis is correct. If the contractor
does make a payment to the government, it should be deposited
into the miscellaneous receipts account at the Treasury.
Obviously, the agency gets no use of that money. By John Ford on Wednesday, February 21, 2001 - 12:47 pm: I have to disagree with Anon2 (11:21) about the augmentation of appropriations. In the example given, under Joel's scenario, the agency would have retained the $2000 and not paid the contractor. The contractor would only have been paid $98K. This leaves the agency with only the $100K Congress appropriated. Clearly, use of the $2k in this case would not be an augmentation of appropriations. In this case, the contractor pays the LDs by a price reduction in the contract. This same result could have been achieved by the government extending the period of performance after receiving consideration, in the form of a price reduction, for not terminating the contract for default due to the contractor's unexcused delay in performance. This is another way of maximizing your appropriations and ensuring contract performance. By joel hoffman on Wednesday, February 21, 2001 - 01:32 pm: Thanks for the information, John. I have someone researching
AR 37-1 but found this excerpt from Engineer Regulation
37-345-10: Accounting and Reporting - Military Activities CH
1-52 (pages 7-30a to 7-31) Change 39, 29 Nov 85 (1) Some examples of extra costs to the Government are: (a) S&A costs, such as for: added inspection time; replacing
stakes and other marks destroyed by contractor; retesting
materials after failure to meet requirements in initial test;
and review of shop drawing after rejection of initial shop
drawing. (2) Pending final determination by the contracting officer, the amount of damages (actual or liquidated) assessed contractors for failure to complete the contracted work within the time specified by the contract, damages withheld under the terms of the contract should be carried as accounts payable. Upon final determination, accounts payable will be liquidated and damages assessed will be credited to project cost accounts as follows. (a) Damages finally assessed in connection with E&D will be
credited to account 800.4. By anon 2 on Wednesday, February 21, 2001 - 03:30 pm: At the risk of becoming pedantic I know what the practice is within the government I am just trying to say that it is wrong. JF --if you retained 2k and paid 98k technically you owe congress the 2k--it is not available for other projects. JH--I cannot comment on the info provided because it is not fully contextual but my initial reading suggests that the liquidated damages mentioned are related to DB violations not LDs at 52.211.11 However I cannot say for sure. But using LD under DB as an example--if you used retainage to acquire them are they free for you to use? The red book at page 6-108 in the second and third paragraphs make it clear as to how monetary credits (retainage and offset) are to be treated.. And they are treated as cash. And for what it is worth just because we deposit funds to the treasury does not mean we cannot recover them.The reason the procedures are generally not followed is because the amounts involved are small ,by comparison, and therefore do not attract attention. But I hope you will agree with me that it is at least appropriate to know the rule we break. Nes Pas? By Anon 1 on Wednesday, February 21, 2001 - 03:52 pm: Anon 2, By joel hoffman on Wednesday, February 21, 2001 - 11:12 pm: Dear Anon 2, you are slightly correct. There are a myriad of
different "damage" situations covered by this regulation. This
paragraph of the regulation, among other things, discusses the
disposition of "Liquidated damages", where the contract includes
an LD provision for late completion. It also covers delay
damages where the contract does not include an LD provision, as
well as other types of damages. The COE can only use these funds
to cover the additional costs, such as supervision and
administration (S&A), engineering and design (E&D), etc. when
caused by a contractor - not for additional work. Since
salaries, travel, office space, etc. are strictly reimbursible
costs, they are truely "increased costs" due to completion
delays. The COE isn't funded like an O&M organization or other
standing organizations. By John Ford on Thursday, February 22, 2001 - 10:46 am: Anon2, you say it is important for us to know the regulation we break. I agree. My problem is no one has identified the regulation at issue. On another note, I have a major problem with the idea that retainage and offsets must be treated as amounts to be credited to the misc. receipts account of the Treasury instead of being added back to the appropriation from whence they came. For example, amounts received under the credits cost principle in FAR 31.201-5 and its companion provision in the Allowable Cost and Payments clause, are credited back to their original appropriation and are available for future use to the same extent as are other amounts in that appropriation. Similarly, amounts credited to a contract under the Progress Payments provision when material is transferred from that contract are credited back to the original appropriation. As for retainage, when the government retains fee under a cost type contract, and the contractor does not deliver all that it has contracted for, the retained fee is deobligated off the contract and credited back to the original appropriation. Finally, contract debts collected as an offset under FAR 32.6 go back into their original appropriation account and are treated as other balances in that account. A good example of the operation of credits is the California sales and use tax refund matter of a few years ago. For years, California had improperly been collecting a use tax on property used on government contracts. This resulted in a refund to contractors covering eleven years of taxes. Under the credits cost principle and the Allowable Cost and Payment clause, the government was entitled to a credit for amounts it had paid the contractors for those taxes. The ultimate amount of the refunds would exceed $450M. Because most of the appropriations used on the contracts under which the taxes had been reimbursed had been canceled, the government collected the refunds as lump sum cash payments from contractors and deposited them into the misc. receipts account. However, if the appropriations had still been available, the refunds would have been collected as adjustments to specific contracts and credited back to specific appropriations and retained by the agencies concerned, primarily DoD and NASA. By Anon 1 on Thursday, February 22, 2001 - 12:37 pm: John, By joel hoffman on Thursday, February 22, 2001 - 01:19 pm: "(f) Damages accounted for as above will be treated as an
offset against engineering supervision or supervision and
administration costs, as applicable, and not as a reduction of
contractors' earnings." By Kennedy How on Thursday, February 22, 2001 - 01:48 pm: Anon1, By Anon 1 on Thursday, February 22, 2001 - 02:22 pm: Kennedy, By joel hoffman on Thursday, February 22, 2001 - 02:31 pm: Anon 2, a clarification. Technically, the Corps of Engineers is not an "agency". It is a major command within the Army. True, it is considered a "contracting agency". This year's budget is somewhat over $11 billion, down somewhat from a few years ago, when the cold war military construction portion of the budget was two or three times the current value. The COE has 36,000 civilian and military employees (mostly civilian), not counting "military engineers" and troops. When I started, the number was about 70-75,000 employees, but privatization, commercialization and downsizing hit. Happy Sails! Joel By ANON 2 on Thursday, February 22, 2001 - 03:04 pm: I think we are all in violent agreement but I would like to point out one truth. When we send, iaw appropriations rules, money to treasury we are not hurting our budget in the next FY. In other words doing the right thing does not puinish us in this particular case. ANON 1 2:22 IS RIGHT. By John Ford on Friday, February 23, 2001 - 10:13 am: Anon 1 12:37, I agree that LDs are not credits. My comments
were directed toward the earlier reference to the GAO Red Book
to the effect that retainage and offsets were to be treated in
such a way that they are considered misc. cash receipts. By Kennedy How on Friday, February 23, 2001 - 12:28 pm: I also think we are agreeing violently, but I also think that
some folks may be mistakenly thinking it's all a big shell game
or accounting exercise. I think that part of the problem stems
from the amount obligated vs the amount demanded in payment by
invoking LD. If you don't change the amount obligated, then
there is a case of extra appropriation. There may also be an
erroneous understanding of the practical situation at hand if
the contractor hasn't been fully paid under the contract. Many
folks believe it's more practical to withhold money than to have
a contractor pay it back, because getting a contractor to pay it
back means a dogfight. By anon 2 on Friday, February 23, 2001 - 02:26 pm: KH By joel hoffman on Friday, February 23, 2001 - 03:32 pm: John, This is in response to your 2/23/01 question concerning
funds. Unfortunately, our USACE home page and our server with
the technical documents (ER 37-345-10) is off-line, today. I
will research your question, as soon as I can. By Anonymous on Monday, February 26, 2001 - 09:16 am: I am curious, what is the reportable contract price (at closeout) of the example contract provided by Anonymous on 2/21/01 (11:21)? $98K, $100K, or $102K? By Anon1 on Monday, February 26, 2001 - 09:38 am: $100K. The contractor is paid the full contract price and writes a check for $2,000 in liguidated damages for performing late. |