By Naddi on Thursday, September
12, 2002 - 06:15 pm:
(Late means after the decision document has been drafted)
I have a Question about an RFP amendment to section B of a
services contract very late in the selection process. The
offeror was going to need to work with another contractor doing
a parallel but different effort for about 8 months. Due to slips
and integration problems we are now looking at 10 a month task
(Firm Fixed Price CLIN). This effort would represent less than
2% of the total contract. We were hoping to award without
discussions. No one has any facts but the opinions are:
1: We need to do an amendment
2: We need to negotiate with the offerors on this topic, and we
should be able to limit discussions to this topic.
3: Just award the contract and negotiate later
4: We need to open discussions on each and every weakness.
(unfortunate because the prices are good and we are awarding on
strengths of real value)
I've got all these opinions but not a single fact. Can anyone
help a long time lurker? The only half way relevant case I found
was a change in the past performance rating after the decision
document was signed. It was interesting but not that relivant,
also it never addressed if the offeror had a chance to rebut the
bad past performance.
Naddi
By Vern Edwards on Thursday,
September 12, 2002 - 07:00 pm:
You can issue an amendment and solicit revised proposals based
solely on the amendment, then award without discussions.
Alternatively, you can establish a competitive range, then issue
an amendment during discussions and solicit revised proposals
that reflect the discussions, including the amendment.
If you award and then modify the contract there is a
possibility, though perhaps remote, that one of the other
offerors might. If one of them did, then you could have trouble
if the GAO decides that you entered into the contract with the
intent of modifying it after award. The GAO does not like to see
that and has sustained protests when it has caught agencies
doing that under some circumstances. See: Hoechst Marion Roussel,
Inc., Comp. Gen. Dec. B-279073, May 4, 1998, and Falcon
Carriers, Inc., 68 Comp. Gen. 206, B-232562, January 30, 1989.
In Falcon, the GAO said:
"If the integrity of the competitive bidding system is to be
maintained, agencies may not award contracts with the intention
of significantly modifying them after award; rather, an award
must be based on the requirements stated in the solicitation.
Ingersoll-Rand, B-225996, May 5, 1987, 87-1 CPD ¶ 474; American
Television Systems, B-220087.3, June 19, 1986, 86-1 CPD ¶ 562.
If we find that the competition for the contract as modified
would be materially different from the competition originally
obtained, then we generally will conclude that the award was
improper and recommend resolicitation under revised
specifications. Ingersoll-Rand, B- 225996, supra."
Whether the GAO would consider your modification to be
significant is anybody's guess.
By Vern Edwards on Thursday,
September 12, 2002 - 07:02 pm:
The first sentence in the third paragraph of my last post should
have read:
If you award and then modify the contract there is a
possibility, though perhaps remote, that one of the other
offerors might protest.
By formerfed on Friday,
September 13, 2002 - 07:59 am:
Naddi,
If I were in your position, I would folow Vern's first option -
issue an amendment, get revised proposals, and award without
discussions.
You know who the respondents are. You can do an amendment
including email or verbal notification and ask for revisions
within a very short time frame. You add just a few days to the
award schedule and save yourself the possibility of a sustained
protest which really sets you back.
Good luck.
By Eric Ottinger on Friday,
September 13, 2002 - 11:46 am:
Naddi,
I would follow the direction in the FAR to the letter.
Vern is correct insofar as the Comp. Gen. would like to see an
amendment to the RFP if the change in the requirement if is
significant. But it is clear that you do not regard this as a
significant change. All other things being equal, it doesn’t
appear that there is any way that this would change the
selection.
Before the Part 15 Rewrite, the FAR cautioned against reopening
discussions to correct small mistakes in the RFP. This was
consistent with a policy of discouraging multiple rounds of
discussion. The Part 15 Rewrite is not so concerned with
multiple rounds of discussion.
FAR 15.206 Amending the solicitation.
(a) “When, either before or after receipt of proposals, the
Government changes its requirements or terms and conditions, the
contracting officer shall amend the solicitation.”
(b) “Amendments issued before the established time and date for
receipt of proposals shall be issued to all parties receiving
the solicitation.”
(c) “Amendments issued after the established time and date for
receipt of proposals shall be issued to all offerors that have
not been eliminated from the competition.”
The FAR does not allow you to send an amendment to offerors who
have already been eliminated from the competition.
Let’s say the Offeror B reduces his price to the point where his
offer is now the best proposal. If you select Offeror A (your
original selection), Offeror B should protest. If you select
Offeror B, Offeror A is going to very unhappy. Either way,
things can turn really ugly.
You intentions are pure as the driven snow, but shouldn’t expect
offerors to know this. Offerors are always looking for hidden
agendas, even where there are none.
Note: I am assuming that the other offerors are “eliminated from
the competition” at the point where the SSA made a decision. If
I made a different assumption, I would probably reach a
different conclusion.
Eric
By Anon on Friday, September
13, 2002 - 01:07 pm:
I have to laugh at the multiple rounds of discussions. For the
youngsters out there, we (generically speaking) would request
BAFOs (best and final offers) and then there would be a request
for BARFOs (beat and really final offers).
By Vern Edwards on Friday,
September 13, 2002 - 01:15 pm:
It is not true that FAR does not allow a CO to send an amendment
to an offeror that has already been eliminated from the
competition. FAR states to whom an amendment must be sent; it
does prohibit sending an amendment to anyone.
A CO would not lose a protest because he or she sent an
amendment to a firm that had already been eliminated and allowed
that firm to submit a revised proposal. The GAO will not object
to CO actions that are intended to enhance competition.
By Vern Edwards on Friday,
September 13, 2002 - 01:17 pm:
I should say that the GAO will not object to an action that is
designed to enhance competition as long as the action is not an
express violation of law or regulation.
By Eric Ottinger on Friday,
September 13, 2002 - 04:39 pm:
Naddi,
Look at --
NV Services, (Feb. 25, 2000)Comptroller General Decision , No.
B-284119.2, February 25, 2000
“…the allegation that an agency awarded a contract with the
intent to modify the scope of work concerns pre-contract award
actions in violation of FAR §15.206(a), which requires that the
solicitation be amended, even after receipt of proposals, to
reflect the agency’s actual requirements. The appropriate
standard in reviewing these pre-contract actions is not whether
the subsequent modification is within the scope of the original
contract but whether the changed work could significantly affect
the competitive positions of offerors such that the RFP should
have been amended. United Tel. Co. of Northwest, supra, at 10.
Here, it should have been apparent to NASA that increasing the
scope of the contract work by approximately 6 percent could
affect the offerors’ respective proposals.”
“Nevertheless, we do not find that NASA’s failure to modify the
RFP prejudiced NVS. As the protester was instructed at the
hearing, see Tr. at 16-17, our Office will not sustain a protest
unless there is a reasonable possibility of prejudice, that is,
unless the protester demonstrates that, but for the agency’s
actions, it would have had a substantial chance of receiving
award. McDonald-Bradley, B-270126, Feb. 8, 1996, 96-1 CPD 54 at
3; see Statistica, Inc. v. Christopher, 102 F. 3d 1577, 1581
(Fed. Cir. 1996). To establish prejudice, NVS argues that if
NASA had revised the RFP to reflect this additional work, this
would have resulted in revised proposals that would have
affected both the technical and cost evaluations. Protester’s
Post-Hearing Comments at 5.”
If I read your scenario correctly, you are talking about a
stretch out from 8 months to 10 months without really changing
the amount of work to be done. I would not be surprised if the
successful (so far) offeror would be willing to give you this
with no change in contract price.
Eric
By Naddi on Monday, September
16, 2002 - 09:44 am:
Hi again
Yes it would be a increase of a few months, but only for a very
small part of the effort. We tried to be clever and set up as
many FFP tasks in advance as we could. The cost for this task
may increase by more than 20%. However, it will be a small part
of the contract (less than 2%, it might be 10% of the FFP CLINs).
The FFP tasks be
The notion of just awarding now and cleaning up later was more
an expression of frustration at the way the tail wags the dog
sometime. My desire would have been to send the amendment only
to the selected offeror, but that is a transparently bad idea.
We never established a competitive range, but we did have at
least one non-responsive offeror. It was just that starting
discussions because of this task seemed wrong.
It was not clear to me that we could limit proposal revisions to
the amendment. I don't know why I thought we couldn't as we
routinely issue EN's and limit the response to the topic of the
EN all of the time.
I don't feel that I'm doing the other offerors any favor by
getting them to redo an estimate. Fortunately it really should
be a tiny amount of work, unless they read too much into the
amendment.
Naddi
By Eric Ottinger on Monday,
September 16, 2002 - 10:11 am:
Naddi,
If I read you correctly, you are saying that the impact on the
total cost will be 0.4% (20% x 2%). If the highest estimate for
the additional work is 20% higher than the lowest estimate, the
impact will be less than 0.08% (i.e 0.0008).
I think you are jumping at shadows.
Eric
By Naddi on Monday, September
16, 2002 - 10:26 am:
Eric
Agreed, but is there a reasonable way not to jump?
Naddi
By Eric Ottinger on Monday,
September 16, 2002 - 10:52 am:
Naddi,
I would document the fact that the requirement for the 2 month
slip did not arise until after the source selection decision.
I would send the amendment to the only offeror that "has not
been eliminated from the competition."
Would I be correct if I said that the 0.0008 impact would not
affect the source selection decision?
A sleazy contracting office that wanted to reopen the
competition for some nefarious purpose (presumably because the
wrong offeror is in line for the award) can always find some
tiny "piece of lint" flaw to justify an amendment. That is the
kind of appearance that I would wish to avoid.
Eric
By Naddi on Monday, September
16, 2002 - 11:30 am:
Oh My
I did not even think of that last interpretation. You are
correct that any feasible adjustment will not change the
selection decision. Still it seems a simple choice to negotiate
the change now. I've been making the numbers up, but the
relative magnitude describes my situation pretty closely.
Before this I've never experienced any turbulence from the time
of drafting an SDD till the decision was signed. I never thought
of using an amendment that way before.
Naddi
By Vern Edwards on Monday,
September 16, 2002 - 08:25 pm:
Naddi:
If the change is as negligible as you say it is, you could have
sent out the amendment and gotten the offerors' responses by
now. Instead, you're scheming to find a way to do something that
you're clearly uncertain about and uncomfortable with. Why take
a chance?
Email or fax the amendment to everyone, ask them to email or fax
any price revisions associated with the amendment, look at the
revisions, if any, and then make the award.
It's easy, it can be done quickly, and it's the least
controversial thing you can do.
By Vern Edwards on Tuesday,
September 17, 2002 - 09:04 am:
Naddi:
One other thing:
You said that a decision document has been "drafted". If it
hasn't been signed and notifications made, then nothing is final
and no firm has been eliminated from the competition. Sending an
amendment to everyone would not "reopen" the competition. Don't
worry about appearing to be nefarious.
If you decide to go ahead with an award without amending the RFP
and then mod the contract, just do it. Don't prepare an
amendment and send it to only one firm. The odds of a getting a
protest based on the contract mod are not great, and if you do
get one you can just deal with it, seeing as how you're
confident that the change is not significant.
By Newly Nefarious Naddi on
Tuesday, September 17, 2002 - 01:22 pm:
Appreciate the good words and clear advice. We sent out the
amendment to the responsive/responsible offerors Monday morning.
We are expecting much less than a 1% cost delta, but the ops
folks want some useless materials on the approach (I don't want
it, they don't need it, it'll be here next Wednesday). We gave
the offerors until 25 September to respond. I really wanted to
put a note in one offeror's package saying don't muck-up your
current approach; naturally I didn't. I was really surprised at
Eric's point about “gaming” the system like that. So much to
learn - so few active chat sites.
Naddi
By Eric Ottinger on Tuesday,
September 17, 2002 - 05:23 pm:
Naddi put her finger on the point where I am uncomfortable. What
authority does Naddi have to restrict the proposal revisions to
just ”price revisions associated with the amendment” (i.e. the
adjustment for the additional two months)? It has been my
understanding that the offeror can make whatever changes to the
proposal that the offeror wishes to make.
Vern may be correct regarding the decision document. However, I
would think that if the SSA meets with the evaluation team from
one o’clock to two o’clock and makes a decision during the
meeting, the exact time and date of the decision for legal
purposes would be the time and date of the meeting, not the time
when the SSA signs a piece of paper documenting the decision.
Does anyone have some authority to cite, addressing this issue
one way or the other?
Eric
By Vern Edwards on Tuesday,
September 17, 2002 - 08:21 pm:
The GAO has issued several decisions saying that a contractor
can revise its proposal in any way that it wishes during
negotiations/discussions. However, if an agency has not decided
to conduct negotiations/discussions, I think that it can limit
proposal modifications to those necessitated by an amendment
(see FAR § 15.001 for the distinction between a proposal
modification and a proposal revision).
By Vern Edwards on Wednesday,
September 18, 2002 - 11:15 am:
I would like to comment about the following remark:
"I would think that if the SSA meets with the evaluation team
from one o’clock to two o’clock and makes a decision during the
meeting, the exact time and date of the decision for legal
purposes would be the time and date of the meeting, not the time
when the SSA signs a piece of paper documenting the decision."
A source selection decision is not final until an award has been
made. (It might not be final then.) An SSA can change his or her
mind at any time prior to contract award, even after signing a
decision document, and a higher-level official can overrule a
decision by a lower-level SSA.
As long as the ultimate selection decision is made in compliance
with the FAR and the terms of the RFP and is otherwise
reasonable, it will withstand a protest. The GAO will not
sustain a protest merely because an SSA changed his or her mind
or was overruled. The exact time and date of the decision has no
significance in that regard.
While changing a selection decision might raise suspicions in
the mind of an offeror and prompt it to protest, that
possibility should not deter an SSA from making the decision
that he or she thinks is in the government's best interest.
By Eric Ottinger on Wednesday,
September 18, 2002 - 05:07 pm:
Vern,
Just recently you argued that it was perfectly permissible to
negotiate with just the successful offeror. I agreed. However,
in my view, such negotiations should not be in any way
prejudicial to the other offerors.
Now you are arguing that the determination of the successful
offeror dithers in a state of quantum uncertainty right up to
the point where the contract is signed.
I prefer the answer that you gave in the earlier thread.
Eric
By Vern Edwards on Wednesday,
September 18, 2002 - 08:10 pm:
Eric:
Your notion of there being an "exact time and date of the
decision for legal purposes" has no merit. What legal purpose? A
source selection decision is final when the contracting officer
awards the contract and makes the required notifications, and
not before. Even then the decision might not be final if the SSA,
some higher level authority in the agency, the GAO, or a federal
judge decides that the initial decision was unsound. If you want
to call that "quantum uncertainty," that's okay by me, but
that's the way it is.
I agree that a contracting officer can negotiate with only the
successful offeror after selection and prior to award (like in
the old NASA procedure or the DOD "Four-Step" procedure), but in
my opinion the RFP should announce the possibility that the
contracting officer has reserved the right to do that. Even
then, you have to decide whether or not to amend the RFP if your
requirement changes.
In Naddi's case, I think that the most sensible thing to do was
to amend the RFP, tell the offerors to submit proposal
modifications limited to responses thereto, and then proceed to
decision. The whole process could have been done in a couple of
days and without any serious controversy.
By Anonymous on Friday, October
04, 2002 - 11:29 am:
Done + one week. It still seems a shame to have gotten the exta
documentation from people who were not going to win almost no
matter what they said.
Naddi
By Anon on Friday, October 04,
2002 - 03:21 pm:
Yeah, but you kept the process clean and nobody can say you
didn't afford them a fair opportunity. |