By
Anonymous on Tuesday, April 01,
2003 - 07:49 am:
I awarded a contract with a basic period of 1 Jun 02 -
31 May 03 with four one-year option periods. My customer wants
to change the period of performance to coincide with the fiscal
year (1 Oct - 30 Sep). Is this allowed? If so, or not, is there
a FAR citation I can reference?
By
Vern Edwards on Tuesday, April 01,
2003 - 08:56 am:
Yes, it generally is permissible to restructure the
periods of performance, or to make them longer or shorter. To
the best of my knowledge, the FAR does not address this matter;
such change is more a matter of contract law than procurement
statute or regulation. I do not know of any procurement statute
or regulation that prohibits restructuring a contract
performance period. See FAR Subpart 11.4 for a general
discussion of delivery or performance schedules. Any two parties
that make a contract can agree to change it.
In practice, you will have to negotiate the change with the
contractor, who may be affected in serious and costly ways. You
cannot impose the change on the contractor; you must persuade
the contractor to agree. This may entail compensating the
contractor for any cost impact.
You must also take fiscal law into account. What funds did you
obligate on the contract? What funds will you use in the new
performance periods?
By
joel hoffman on Tuesday, April 01,
2003 - 10:52 am:
Vern, I have two questions. You said, "You cannot
impose the change on the contractor; you must persuade the
contractor to agree." If so, would the supplemental agreement be
outside the authority of the "Changes" clause, because changes
are actions which could be unilaterally directed?
Would such a modification, if there is no other operable clause,
thus be considered outside the scope of the contract? I know
we've discussed this before. I'm not clear when a mod is within
or outside the authority of the Changes clause or outside the
KO's authority, without further justification or exemption from
competition.
Technically, the Changes clause only seems to cover unilateral
changes. Many changes are never issued unilaterally, yet still
considered "changes", executed pursuant to the Changes clause.
I've been under the impression that if one can't direct the
scope of the change or unilaterally make the equitable
adjustment, it isn't a "change", thus requiring another clause
or other authorization to execute. I guess it's safe to say that
there is some implied authority to make bilateral changes
"within the scope of the contract" and that they are normally
executed pursuant to this clause. Correct? happy sails! joel
By
FormerCO4AF on Tuesday, April 01,
2003 - 10:57 am:
Vern,
Do you think Anonymous needs to ensure they do not exceed the 5
year limitation set forth at FAR 17.204(e)? (Unless an award
term is used)
What about clause 52.217-9 -- Option to Extend the Term of the
Contract? Specifically para c...
(c) The total duration of this contract, including the exercise
of any options under this clause, shall not exceed ___________
(months)(years).
By
Vern Edwards on Tuesday, April 01,
2003 - 11:51 am:
Joel:
In answer to your first question: Yes, the supplemental
agreement would be outside the authority of the changes clause.
None of the changes clauses permits the contracting officer to
unilaterally restructure the basic and option periods of
performance.
In answer to your second question: No, I do not think that the
change would be outside of the scope of the contract, defined as
"all work that was fairly and reasonably within the
contemplation of the parties at the time the contract was made."
See: The Government Contracts Reference Book, 2d ed., by
Nash, Schooner and O'Brien. A change of the type that Anonymous
wants to make -- to bring the periods into line with the fiscal
year -- would not alter the scope of the contract. An
extension of the total period -- i.e., adding performance --
would be outside of the scope of the contract.
Finally, you must distinguish between a change ("modification")
and a change order. The parties to a contract can change
it at will. The changes clause is an agreement between the
parties that one of them, the customer, can make certain kinds
of changes unilaterally. However, the parties could choose to
make those changes bilaterally, without recourse to the changes
clause, if they so desire. They can also make changes not
covered by the changes clause.
Technically, changes are called "modifications." See FAR §
43.103. There are two types: bilateral and unilateral. Bilateral
modifications, called "supplemental agreements," include (a)
supplemental agreements to definitize unilateral mods, (b)
supplemental agreements to definitize letter contracts, and (c)
supplemental agreements to make other changes that the parties
agree to make. Unilateral modifications include (a)
administrative changes, (b) change orders, and (c) other
unilateral changes.
Many people have come to think that the changes clause is what
authorizes the parties to make changes. Not so. All that the
changes clause does is authorize the government to make certain
kinds of changes unilaterally -- to order them. The
parties do not need a clause to authorize them to to change
their contract by mutual agreement; the power to make a contract
includes the power to change ("modify") it.
FormerCO4AF:
In restructuring the period of performance the parties cannot
extend that period so that the government buys more services.
That would be a new procurement, beyond the scope of the
existing contract, that would require new competition. This must
be distinguished from a situtation in which the period of
performance is extended to give the contractor more time to
complete a project, which is not a new procurement and does not
change the scope of the contract.
Vern
By
Anonymous on Tuesday, April 01,
2003 - 11:57 am:
Thanks for your answers.
By
joel hoffman on Tuesday, April 01,
2003 - 08:22 pm:
Thanks, Vern for the reality check/ basic review.
happy sails! joel
By
jlessig on Wednesday, April 02,
2003 - 01:07 pm:
Vern - In a case like this, what authority would you
cite in Item 13 of the SF-30.
By
Vern Edwards on Thursday, April 03,
2003 - 11:04 am:
jlessig:
The same authority as was used to enter into the contract in the
first place.