By
Anonymous
on Tuesday, November 28, 2000 - 01:14 pm:
Subpart 36.602-3(c) lists one of the functions of an A-E
Evaluation Board as follows:
"Hold discussions with at least three of the most highly
qualified firms regarding concepts and the relative utility of
alternative methods of furnishing the required services."
My questions to the above reference are as follows:
1. The reference doesn't make mention of "meaningful"
discussions, but shouldn't such discussions be "meaningful"?
What's to prevent a board from just holding discussions for the
sake of meeting the discussions requirement.
2. Should discussions be such that what's discussed with one
firm should be discussed with all others? I personally believe
that discussions should be tailored to each firms strengths,
weaknesses, or other factors worthy of discussion as found on
their SF-254/255's. If identical questions are asked, what you
ask may not be relevant to all firms. It circles back to if
"meaningful" discussions are what is required. Identical
questions or sample problems are good only if they are used to
obtain a firms response to a situation. This brings me to my
next question.
3. Under IDIQ type A-E contracts is it a good practice to allow
firms to provide responses to sample task orders? That is,
Government provides sample task, firms demonstrate how they
would handle order, and Government rates firms on how well they
handle the order. I've always thought this technique, when used
in A-E IDIQ acquisitions, allows one to more effectively "rate"
firms on something a little more concrete than just what's on
paper. Also, if this is a good practice to use should it be
limited to just the firms included in discussions or with all
responsive firms?
By
joel hoffman
on Tuesday, November 28, 2000 - 05:41 pm:
Anon, FAR 36.602-1 is entitled "Selection Criteria". It says:
"c) Hold discussions with at least three of the most highly
qualified firms regarding concepts, the relative utility of
alternative methods and feasible ways to prescribe the use of
recovered materials and achieve waste reduction and
energy-efficiency in facility design (see Part 23)."
Is this is what the "discussions" you referenced are for?
Anyway, I researched the FAR, DFARS and Engineer Far Supplement
36.6 as well as Engineer Pamphlet 715-1-4 "How to Obtain
Consideration for Architect Engineer Contracts with the Army
Corps of Engineers". Although this Pamphlet only applies to the
COE, it is an excellent outline of the process. It can be found
under "Engineering Pamphlets" at "TECHINFO", accessible through
"http://www.hnd.usace.army.mil/"
The guide states that "interviews" are held "with the 3 most
highly qualified firms", prior to ranking them. (This is often
done after a "pre-selection" process determined a list of the
highly qualified firms, then the most highly qualified firms are
determined.) Interviews will include "similar questions about
their experience, capabilities, organization, quality management
procedures and approach for the project."
I presume this includes the required discussions referenced
above.
I also presume that you could ask them similar questions about
an approach to task orders and you could discuss their SF254/255
information.
EP 715-1-7 are the internal COE guidelines for A-E selection and
contracting. It is also viewable at the samr Website.
Hope this helps you! Happy Sails! joel
By
Anonymous
on Wednesday, November 29, 2000 - 04:57 pm:
FAR 36.602-3 is entitled "Evaluation Board Functions" it
says...
"(c) Hold discussions with at least three of the most highly
qualified firms regarding concepts and the relative utility of
alternative methods of furnishing the required services."
It's virtually the same statement you quoted, but it is found
under evaluation board functions (36.602-3) and not selection
criteria (36.602-1). It also doesn't make any reference to
efficiency, waste reduction, and recovered materials.
The reason for my initial inquiry is due to a comment made by an
engineer recently appointed to serve on an A-E evaluation board.
The engineer, incidently, previously worked for DOD. The comment
made was that all A-E's included in discussions must be asked
the same questions or be provided the same material. Evaluation
boards cannot ask different questions of firms included in
discussions. I told him this wasn't true. In order to provide
some back-up to my response I was trying to find out how much of
the "discussion" (or negotiations or exchanges) references in
Part 15 are applicable to A-E discussions as provided in Part
36?
FAR 36.606 "Negotiations", says the following about negotiations
"(a)...Negotiations shall be conducted in accordance with Part
15...".
After reading that I went to Part 15. I found that 15.306(d)
says negotiations are called "discussions". I found that
15.306(d)(1) says discussions should be tailored to an offerors
proposal. I found that 15.306(d), in genreral, goes in-depth on
the subject of "discussions".
Part 36.6 doesn't say too much about "discussions". Since it
says negotiations should be conducted IAW Part 15, I assume one
should go to Part 15.306(d) for guidance.
So how much of the "discussion" (or negotiations or exchanges)
references in Part 15 are applicable to A-E discussions as
provided in Part 36?
By
joel hoffman on Wednesday, November 29, 2000 - 05:44 pm:
Anon, the negotiations mentioned in FAR 36.6 are cost and
price negotiations. We only conduct these negotiations with the
selected A-E firm.
The FAR 15 references refer to the Part 15 price and cost
negotiation guidelines, including cost estimates,
pre-negotiation objectives, audits, technical and cost analyses,
price analysis, price negotiation memoranda, etc.
The "discussions" mentioned in FAR 36.602-3 and 36.602-1 are
called "interviews" in the COE A-E selection guidelines. We
conduct "interviews" with the highest rated A-E firms being
considered for the final selection. The interviews cover the
areas I mentioned yesterday.
The COE guidance says we interview the top three candidates, if
there are three, before ranking them. Then we incorporate the
results of the interview into the competitive evaluation. Then
we rank the top three. Then we select the top-ranked firm to
conduct negotiations with. If we can't reach a fair and
reasonable price with the selected firm, we negotiate with No. 2
on the list and so on.
The COE guidelines say we conduct "similar interviews" with the
most highly qualified firms. Since the interviews are to include
job specific topics, I'm sure you can discuss any concerns you
have with their 254's and 255's. It would be absurd to assume
that the Government isn't allowed give and take discussions
regarding qualifications based selection procedures.
Does this make sense? Does your agency have a supplement to the
FAR? Did you read and interpret the COE guidelines (I know they
don't necessarily apply to your agency - they are COE's
interpretation of the FAR and of the Brooks Act).
I suggest you try this... Tell the "expert" to show you where it
says you have to ask the same exact questions and not one other
question specific to the firm being interviewed, as it relates
to the instant contract or project.
Happy Sails! Joel
By
joel on Wednesday, November 29, 2000 - 05:53 pm:
Anon - I'll clarify by saying that we may interview more than
three firms, if there are more than three "most highly qualified
firms".
I will reiterate that an "interview" must allow for some give
and take discussion. It's dumb to have a one way interview - you
can ask the EXACT SAME questions to each in a letter or using a
video - no need for an "interview."
The key is that you are to ask SIMILAR QUESTIONS plus discuss
job specific information and approaches, etc. Happy Sails!
By
Anonymous
on Thursday, November 30, 2000 - 10:08 am:
Thanks for the clarifications and thanks for your help.
By
Vern Edwards
on Thursday, November 30, 2000 - 10:28 am:
Anonymous:
The discussion rules in FAR Part 15 do not apply to A-E
contractor selections. See FAR 36.601-3(b).
The requirement for "meaningful" discussions applies to the
discussions conducted under FAR Part 15, not to the discussions
conducted in an A-E procurement. The "discussions" mentioned in
FAR 15.306(d) are not the same as the discussions mentioned in
FAR 36.602-3(c). Discussions in FAR Part 15 are discussions in
which the government tells the offerors about "deficiencies" and
"weaknesses" in their proposals. The GAO says that such
discussions must be "meaningful" in the sense that the
government must disclose enough information about the
shortcomings in the offerors' proposals to enable them to make
improvements through revisions. A-E candidate firms do not
submit proposals and the GAO has not appled the meaningful
discussions rule to A-E discussions. See ARTEL, Inc.,
Comp. Gen. Dec. B-248478, August 21, 1992, footnote 2. [The
reference in that case to FAR 36.601-3(a) is now 36.601-3(b).]
As Joel said, discussions in A-E procurements are really
interviews. They are not negotiations.
As a general rule, there is no requirement that you ask all A-E
candidate firms the same questions or provide them with the same
material. Your engineer's assertion that evaluation boards
cannot ask different questions of the firms included in A-E
discussions is simply wrong. It would even be wrong in FAR Part
15 discussions.
|