By
Anonymous
on Tuesday, December 19, 2000 - 03:07 pm:
What is the standard to apply when calculating an equitable
adjustment for a deductive change?
We have a situation where a change was made to a construction
contract that reduced the quantity of an estimated quantity CLIN
by approximately 50%. The contractor submitted a REA for the
change. The REA was for a share of the cost savings that
resulted from the deleted work. Essentially, the contractor is
saying that he is entitled to share in the cost savings because
he found a way to do the work more efficiently than originally
planned.
I've never seen an approach to a deductive change like this. Is
it proper?
By
joel hoffman
on Tuesday, December 19, 2000 - 05:09 pm:
Anon, who initiated the change to the construction contract -
the Government or the Contractor?
1. If the Contractor initiated the change and the contract is
over a threshold amount of $100k, the Value Engineering -
Construction Clause (52.248-3) is in the contract. There is a
very liberal view held by the Courts and Boards that contractor
initiated changes resulting in savings should be treated as "VECP's",
to the extent possible. Thus, the Contractor would be entitled
to share in any cost savings, plus there would be no reduction
in the contract amount for 'profit'on the cost savings. You
treat it as a deductive change (described below) but do not
include any profit in the gross savings. Then you split the
savings, as prescribed in the clause (usually %55
to Contractor and 45% credit to Government).
2. Now, if the Government initiated the change, AHHHH that's a
horse of a different color, as they say. There are three
approaches to pricing such a deductive change. Nash and
Cibinic's Administration of Government Contracts covers this in
detail. However, here is an outline of some major points. I
won't discuss the third approach, where the work is considered
to be "severable", because it appears to me that this is not
such a case. Deleting 50% of a CLIN quantity probably makes this
a case of "non-severable work".
a. The first method is what I call the "take it off the top"
pricing method. An equitable adjustment for deleting
non-severable work is treated as a "deductive change" under the
Changes Clause.
The credit is generally based on the cost (including directs
plus G&A and other applicable indirects and overheads) that it
would have cost the contractor to do the work, had there been no
change. This cost is adjusted for any costs that are already
expended or will be unavoidable for the cancelled work; also
adjusted for any additional costs which were/will be incurred by
the change to delete the work. Remember, that deducting 50% of a
CLIN might result in the contractor not recouping all of its
mobilization costs or other fixed costs. If so, the credit must
consider these sunk costs.
To the net savings is added an allowance for profit (unless it
is clear that there would have been no profit, had the work been
done). The Government does not pay profit for work not
performed, so the profit allowance is included in the credit.
The contract unit price is only significant in discerning
whether or not there would have been a loss on the deleted work.
Administratively, the mod would include a deduction for all the
deleted work at the unit price, plus an adjustment bid item for
the difference between the value of the deleted CLIN amount and
the equitable adjustment. This will either be a credit to the
Government or a lump sum CLIN, depending upon the amount of the
equitable adjustment.
b. If the deleted work is a very large share of the contract
scope of work, the contractor might successfully argue that the
adjustment should be treated as a "partial termination", rather
than as a deductive change. In that case, you are going to price
the adjustment, using a "bottoms up" pricing method. I would
avoid this method. You essentially start by subtracting the
entire CLIN amount, then allow the contractor allowable and
allocable costs plus profit on the work performed, plus any
costs plus profit, if any on the work not performed. That is an
oversimplification - Part 49 Termination for Convenience
procedures apply - profit is not paid on all costs and there are
many other wrinkles. You might alternatively only start by
subtracting the CLIN amount (quantity times unit price) for the
deleted work, then do the bottoms up procedure for incurred
costs on the deleted work. Unless the deleted work is such a
large share of the contract that it could constitute a cardinal
change to the scope, I would not agree to treating it as a
"partial termination".
I have probably confused you but different pricing approaches
apply, depending upon each situation. Happy Sails! Joel
By
joel hoffman on Tuesday, December 19, 2000 - 05:19 pm:
Anon, after rereading your question, I sense that the
Contractor says it could do the work for less than the unit
price - thus he/she says you cannot take a credit for the full
value of the deleted work. In that case, the first approach I
described would be applicable. If the Contractor can show that
the cost plus profit to complete the deleted work is less than
the contract amount for the deleted work, he/she is right.
The administrative means to show the price change on the
modification is to delete the remaining work under the
applicable CLIN at the unit price, then provide for a lump sum
CLIN for the difference. In short, the Contractor keeps that as
a "windfall".
By
joel hoffman
on Tuesday, December 19, 2000 - 05:26 pm:
Anon, clarification to the last message - I meant you'd use
the first approach under a deductive change, if the Government
initiated deletion would cost the Contractor less to perform
than the contract unit price (I didn't mean that you'd treat it
as a "value engineering change proposal", unless the Contractor
initiated it). Happy Sails!
By
Anonymous
on Wednesday, December 20, 2000 - 11:57 am:
Joel--
It was a Government initiated change. The contractor's REA was
provided as per your example. It showed that the cost plus
profit to complete the deleted work was less than the contract
amount for the deleted work.
I'm confused over this method of adjustment because of my
definition of profit, i.e., what's remaining after all operating
expenses are met. Applying that definition the contractor's
"windfall" would actually be profit on work not performed.
Am I missing something?
By
joel hoffman on Wednesday, December 20, 2000 - 02:43 pm:
Anon- from my understanding of what you said, the Government
initiated a CHANGE to the scope of work, deleting about 50% of
the estimated quantity of a unit priced CLIN on a construction
contract.
In my opinion, the basis of the credit to the Government is the
cost to the contractor had it done the deleted work (had there
been no change) plus an allowance for profit. If this is less
than the contract price, the contractor would keep the
difference. The Government cannot simply deduct the entire
contract price as the credit. Equitable adjustments for Changes
are generally priced on the "cost" impact to the Contractor ,
not on the contract price or "value".
E-mail me with your phone number and I will be happy to discuss
or get more facts. Happy Sails! Joel
Please consider reviewing
By
Anonymous
on Wednesday, December 20, 2000 - 03:01 pm:
Joel--
By "per your example" I meant the first approach you described
for a deductive change due to a Government initiated deletion.
By
Eric Ottinger
on Wednesday, December 20, 2000 - 04:57 pm:
Anon,
A few extra thoughts in addition Joel's excellent answer--
Take a look at the coverage in the CON 210; Government Contract
Law Course which you can access in the Deskbook.
http://web1.deskbook.osd.mil/default.asp
10-3. "The prevailing view appears to be that profit is an
allowable factor, but that the amount of profit will be
determined by the facts in each case. Profit, like any other
factor in an equitable adjustment, is subject to negotiation and
agreement between the parties. The amount will be dependent upon
the character of the work involved; each case must be examined
in light of its peculiar facts. The profit included in an
equitable adjustment need not be related to that established in
the basic contract or in any previous equitable adjustments on
that contract. The test is not whether the change is additive or
deductive (i.e., increases the work or decreases the work); the
character of the change is the determining factor."
You need to distinguish the negotiated profit from the profit
that the contractor actually earns. If the contractor has
achieved some additional profit by performing more efficiently
than the parties anticipated at the date of the handshake, I
don’t blame the contractor for wanting hold on to some of this.
Of course, if I were the contractor, that is the story that I
would tell you. You need to determine what the truth is.
Eric
By
joel hoffman on Thursday, December 21, 2000 - 07:22 am:
Anon, have you or any of your technical people done an
analysis or independant Government estimate (required by FAR if
the action exceeds ($100,000) of what the deleted work would
cost the Contractor to perform? In other words, what is the
Government's estimate of the probable "actual" net savings in
cost plus an allowance for profit? That is the credit you are
due. You are not automatically due the "contract value" of the
contract unit price times the estimated quantity of the deleted
work. Sorry, I don't think I can express it any simpler, myself.
NOW - Please be clear about this. Was the work "deleted" by a
change in the actual scope of work to be performed or was it
merely an underrun in the actual amount of work which has to be
performed - without changing the statement of work?
If there was just an "underrun" in the unit priced work, we need
to discuss a totally different approach to the contract price
adjustment.
By
joel hoffman on Friday, December 22, 2000 - 12:31 pm:
I found this in the Army Judge Advocate General (JAG) School
materials under 'Contracts':
Pricing Contract Adjustments (Clauses which provide for
"Equitable Adjustments")
Pricing Formula.
1. The basic "equitable adjustment" formula is the difference
between what it would have reasonably cost to perform the work
as originally required, and what it reasonably cost to perform
the work as changed, plus a reasonable profit. Pacific
Architects and Eng'rs, Inc. v. United States, 203 Ct. Cl. 499,
491 F.2d 734 (1974) (contractor could not use an equitable
adjustment to convert a loss contract into a profitable one);
Bruce Andersen Co., ASBCA No. 29412, 89-2 BCA 21,872
(deductive change).
3. Deleted work is priced using the costs avoided because the
contractor does not have to perform the deleted work, then add
an allowance for profit to the credit. Anderson/Donald, Inc.,
ASBCA No. 31213, 86-3 BCA 19,036 (measure of deductive change
is costs saved). This generally is the difference between the
estimated costs, and the actual costs, of performing the changed
work. But see Condor Reliability Servs, Inc., ASBCA No. 40538,
90-3 BCA 23,254 (deletion of a loss item). Happy Sails! Joel |