|
|
|
HOME | CONTENTS | DISCUSSIONS | BLOG | QUICK-KITs| STATES |
Search WWW Search wifcon.com |
Does one J&A=one Mod? |
|
---|---|
By
Elenaor Summers on
Thursday, June 22, 2000 - 10:53 am:
Thanks very much for the input -
Vern you are correct, this was not a case of exercising options,
nor, as John suggests would it have been appropriate to use the
"Changes" clause. These are indeed new quantities of a number of
different configurations which were not initially anticipated,
based on changes in the Navy's requirements. I'm not really sure
an option would have been completely appropriate since the Tech
Code didn't have a real tangible basis for their estimates,
although hindsight being 20/20 we perhaps should have gone that
way. At the time we were under a real time crunch (the typical
thing - no one defines the requirement until they are threatened
with losing their funds - plus I was getting ready to go out on
maternity leave), so I plead guilty to possibly not having
crystal clarity in all aspects of my thinking. By John Ford on Thursday, June 22, 2000 - 10:06 am: I agree with Vern. Additionally, this is not a change under the Changes clause. We often use the term "within scope" too loosely. The Changes clause permits changes within specified parameters or areas. It does not confer a general authority to make any change deemed desirable. As such, it is generally impermissible to acquire additional quantities of supplies using the Changes clause. Finally, based on the fact you had sufficient funds to buy some of the widgets you needed, but not enough to buy all you needed, was it possible to have awarded an IDIQ contract? By Vern Edwards on Thursday, June 22, 2000 - 12:27 am: Eleanor: By Eric Ottinger on Wednesday, June 21, 2000 - 05:36 pm: Eleanor, By Eleanor Summers on Wednesday, June 21, 2000 - 05:07 pm: We are currently involved in a
discussion at my command regarding J&As (citing exception 1) for
increased quantities under an existing contract. In this case,
the original contract was solicited competitively, but only one
offer was received. The requirement has arisen for additional
quantities of the same type of (quite complex) equipment with
some minor variations. The requirement was synopsized, no
responses were received; the program office had a good feel for
the quantities required, but due to funding constraints would
not be able to buy all the quantities at the same time - they
would be purchased as funds became available. The J&A was
written to support this approach and was approved. Subsequently,
a mod was issued buying the first increment of "widgets". There
is now a contingent arguing that we must write either a class
J&A or a new J&A for each mod that we intend to issue. The legal
argument for this is as follows: "FAR 6.303-1(c) indicates that
the definition of a class J&A refers to the execution of more
than one contract action. Likewise, NAPS 5206.304(c) uses the
plural term "actions" in the context of class J&As; i.e., more
than one contract action. The definition of the word "contract"
includes bilateral contract modifications. FAR 2.101. Given the
above citations, it appears as though the FAR/NAPS instituted
the 'one J&A=one mod' rule." |