By
C MERCY on
Monday, August 28, 2000 - 10:50 am:
IN ADDITION TO OTHER CITED REFERENCES ONE MAY CONSIDER THE
REMEDIES UNDER FAR 50-302-3
WHAT DID CATCH MY ATTENTION WERE THE PRACTICES MENTIONED IN MR
HOFFMANS 8/23 2:32 MESSAGE. DIRECTING CONTRACTORS TO
PERFORM,UNDER ANY PRETEXT,WHICH HAS THE EFFECT OF INCREASING
COSTS,AND DOING SO WITHOUT FUNDS IS PROHIBITED UNDER THE ANTI
DEFTCENCY ACT. AND DOING SO WITH THE HOPE THE JUDGEMENT FUND
WILL PICK UP THE TAB IS A FALSE ECONOMY. IF THE FUND IS USED THE
TREASURY BILLS THE BENEFITING DEPARTMENT WHO MUST REIMBURSE
USING CURRENT YEAR FUNDS. THIS MAY NOT ONLY HURT THE AGENCY
SPENDING PLAN FOR THE CURRENT YEAR BUT MAY ALSO LIMIT THE
ABILITY TO HAVE USED PRIOR YEAR FUNDS UNDER THE THEORY OF
ANTECEDENT LIABILITY. I WOULD CERTAINLY NOT ENCOURAGE THIS
PRACTICE.
COMMENTS OF 8/23 2:32
By
Kennedy How on
Monday, August 28, 2000 - 12:39 pm:
I wasn't able to find RMTC online, but from the quickie
synopsis that Joel posted, I can say that our activity worried
about this a lot, especially when it came to getting IT
equipment. I remember 4-5 years ago, there was only one person
authorized to order this stuff on an IMPAC card, and while we
(the requirer) called around locally to find what we needed,
there wasn't a 100% guarantee that the cardholder would go there
to actually buy it (sometimes, they had a source that was
cheaper). Things got a little better when we had more
cardholders available, and it was relatively simple to call the
Big Few computer stores and find something locally available
RIGHT NOW.
As far as Vern's post regarding ratification and disputes as
alternative actions, I have a tendency to agree with this. It
has been my experience that most contractors we deal with, they
are somewhat wary of "No CO authorization", and they tend to not
go off on the say-so of somebody not normally in a position to
make some kind of decision. Certainly, there are those who ARE
in a position to decide, and be in a position to request that
the CO initiate the appropriate contractual action. Normally
speaking, it is rare that a CO WILL NOT effect some kind of
contractual action; inasmuch as he would normally do so if the
direction came down IAW established procedure. I can't think of
any reason why the CO would not, in the course of normal
business conduct.
From that standpoint, it would seem to me that for those
occasions that have a problem with timing, it would be only a
matter of time before contract coverage would be accomplished.
Thus, it would never get to the disputes stage.
I've been in many program-level meetings with the contractor, at
the Contractor's facility, as a representative of the CO's shop.
Our working relation with the PM was very good, and while the
PM's made the decisions affecting hardware, there were those
times where there needed to be CO authorization. I did not have
CO authority, but the business relationship was such that I knew
what the CO wanted, and didn't want, and I was entrusted by the
CO to make good business decisions, inasmuch as the CO would
eventually have to sign off on a PCO letter. Furthermore, if I
had reservations, I said so, and I knew the CO may also have
them; at that point, the contractor would not be as eager to get
going until a CO position was provided. Maybe that's implied
authority, but the CO entrusted some of his Contract
Administrators to do this. And, the Contractor certainly picked
up on that, in that we were good for what we said.
By
joel hoffman
on Monday, August 28, 2000 - 04:25 pm:
C Mercy - Agree with your August 28, 2000 - 10:50 am,
concerns about the ignorant - or worse - philosophy of a certain
Agency, that the Contractor could be directed to perform work,
not in the contract, then the KO should simply deny the claim or
REA, forcing a claim. The "judgement fund" would alledgedly be
used to fund settlement of the denied claim, after a Board or
Court would find merit in the Contractor's claim.
To clarify, most of their requested actions dealt with requests
for equitable adjustments by contractors, due to errors and
ommissions in the existing scope of work. However, in many
cases, the work had not yet been done, prior to the issues being
raised. It had the same effect as telling a contractor to
perform "new work."
And - to reiterate - we never honored such harebrained requests.
Happy Sails!
By
Ramon on Monday, August 28, 2000 - 10:29 pm:
Joel, would you have been able to resist such pressure if
exerted strongly from within your agency? I noticed that much
earlier you mentioned an independence that "is sometimes good,
in that it reduces abuse" in relation to forestalling such
manipulations.
That is why I think separation of powers, at least for the
larger more complex acquisitions, is a good idea. It helps ease
the undue pressures and subject actions to more impartial
examination. It does not have to be extremely time consuming
when designed well. We are just used to seeing poor examples.
Though no system can eliminate these things entirely, that
independence from undue internal influence tends to keep
everyone honest.
By
joel on Tuesday, August 29, 2000 - 08:52 am:
Ramon - to answer your question - yes, I would have been able
to resist the pressure, even if it came from within my own
agency - but I may not be typical of most people. I will say
that my Chief's of Contracting have usually stood up to do the
"right thing" to our Generals, as well as local Commanders
within our agency, when necessary - but that, too is rare. Since
we don't have any major weapons systems procurements and
resulting pressures, I suppose we can blow our own horns
concerning integrity. Regardless of what you may hear out of the
Washington Post, the COE still maintains very high ethical
standards.
If I hadn't been assigned to my present program, which will
remain nameless, I'd definitely agree with you that separation
of powers can be a good idea (previous experience). In our case,
it is a disaster. The PCO is in one Command, the PM in another,
and we are the ACO's for the FFP construction portion of several
near billion dollar systems contracts and are COR's on CPAF
design-construction portions of a couple of others. The Systems
Contractors, and the PM have zero clue about the differences
between FFP and CPAF and the PCO's seem to have little FFP
experience and NO construction experience.
I just erased two paragraphs, so will now shut up!
Happy Sails!
By
Kennedy How on
Tuesday, August 29, 2000 - 12:11 pm:
Ramon,
To interject here, that's been a topic of discussion amongst
some of us long-timers here at my activity. I know that some of
those contracts types were resistent to the "teaming" concepts
put forth by those who believe that a cohesive unit consisting
of PMs, Acquisition, Engineering, etc. promotes streamlining and
less bureaucracy. Rather, they tend to be skeptical about just
what the ramifications are of a GS-13 CO who reports to a Bird
Colonel, or One Star in the ratings chain. While some here decry
the continued independence of the acquisition community (citing
the same as, perhaps, "not being a team player" or "a law unto
themselves"), much can be said about maintaining an
independence, in order to forestall exactly what Joel alludes
to.
By
Anonymous
on Friday, September 01, 2000 - 12:59 pm:
This is a humbling experience for me and I hesitated to post
this message. However, this seems like a great forum.
I am working on a claim for additional charges resulting from
expedited shipping. The contractor filed the claim timely and I
have requested and obtained additional information since the
claim was filed.
Here is the situation: The Government awarded a lease of
computer equipment for multiple locations in September 1999. The
computers were required to be installed and operational by
11/19/99 to comply with Y2K specifications. A protest stopped
performance of the lease. The stop work was lifted approximately
one month after award, but the delivery date could not be
changed. The contractor has claimed the difference between its
regular shipping costs and expedited costs. The contractor did
not consult with me prior to incurring these additional costs.
The contractor's position is that I was aware of the need for
expedited shipment.
I have consulted with other contracting officers internally and
there is no consensus among us. I know this may be elementary to
some of you, but I have been wrestling with this claim and would
really appreciate any assistance.
By
joel hoffman
on Friday, September 01, 2000 - 04:28 pm:
Dear Anon, First, you need to consult your legal advisor. The
following is only requesting more info, since you asked for
advice in this forum.
What clause is the Contractor "claiming" the adjustment under?
(e.g., 52-242.17 "Government Delay of Work", 52-233.3 "Protest
after Award"?)
The Protest After Award Clause provides an adjustment where the
protest delay causes an increase in costs to complete the
project, provided that the Contractor notifies the Government
within 30 days of the end of the protest delay - The CO can
extend that period, if the Government was not prejudiced by the
Contractor's failure to notify sooner. When did the Contractor
notify the Government of the extra cost needed to meet the
inflexible completion date? If more than 30 days, were you
prejudiced? What would you have done, if notified sooner? Happy
Sails!
By
Vern Edwards
on Friday, September 01, 2000 - 04:35 pm:
Unless you know something that you haven't told us, you owe
the contractor the money. Pay up.
I'm assuming that the contract was a fixed-price supply
contract. You awarded the contract, then stopped the work for
one month, then cancelled the stop order without changing the
delivery date. By definition, you accelerated the work when you
did not change the delivery date after you cancelled the stop
work order. If the stop work order increased the cost or time
required to perform the contract work, then the contractor is
entitled to an equitable adjustment to the contract price, the
delivery schedule, or both, assuming that it notified you within
30 days after you cancelled the stop work order or it expired.
See FAR 52.233-3, Protest After Award, which is required in all
fixed-price supply contracts.
The fact that the contractor didn't notify you in advance of the
increase in costs does not take you off the hook.
Don't wait too long to pay. The contractor is earning interest
on the claim.
By
joel hoffman on Friday, September 01, 2000 - 04:35 pm:
Dear Anon, you already said the "claim was timely filed" -
but what did you mean by this? Also, when were you
constructively or actually aware that the units would have to be
shipped, using more expensive, expedited procedures? Before or
after the cost was incurred? Happy Sails!
By
Joel on Friday, September 01, 2000 - 04:40 pm:
Agree with Vern that there is no requirement to notify you
before incurring the costs, per the clause, if you are the
reason for the acceleration due to a protest - and the cost was
necessary and reasonable. Happy Sails!
By
joel on Friday, September 01, 2000 - 04:55 pm:
Vern - I was too quick to express unequivocal agreement with
you. The Clause does require the Contractor to notify the Gov't
within 30 days of the end of the protest delay. If they waited
until the stuff was already shipped - after that period, they
might have prejudiced Anon's ability to do something else -
though I doubt it - if there was no relief available.
By
Vern Edwards
on Friday, September 01, 2000 - 05:07 pm:
Joel:
We still agree. I mentioned the 30 day notice requirement in my
post. Note that the clause allows the CO to consider the claim
even if filed late, as long as its filed before final payment.
I assume that the decision not to change the delivery date was
made after the cancellation or expiration of the stop work
order.
By
joel hoffman on Friday, September 01, 2000 - 05:14 pm:
Anon, did we help you or confuse you? Happy Sails! Joel
By
Vern Edwards
on Friday, September 01, 2000 - 05:59 pm:
Joel:
Let's have some fun with this.
Suppose that the stop work order issued after the protest
expires on September 15. On September 30, the contractor
requests an equitable adjustment in the form of a change in the
delivery date from November 19 to December 19, but does not
request an adjustment to the contract price. The CO informs the
contractor that the requirement is such that he cannot change
the delivery date. The contractor says nothing more, delivers on
November 19, and submits a claim for more money due to
acceleration of the schedule.
The CO says: Hey! The stop work order expired on September 15,
so you had until October 15 to make your claim for any increase
in time or costs resulting from the stop work order. I won't
pay.
The contractor's lawyer then says, Hey! The increase didn't
result from the stop work order; it resulted from your refusal
to give my client more time. The stop work order didn't
accelerate the work. Your refusal to extend the schedule
accelerated the work. If you had extended the delivery date my
client would not have asked you for more money. The 30 day
deadline in the Protest After Award clause does not apply to
this claim. Pay up!
What would you do?
By
joel hoffman on Friday, September 01, 2000 - 11:21 pm:
Vern,
Sorry, I'm at a disadvantage, having left work for the weekend.
I will have to re-read Nash and Cibinic on the all necessary
conditions for a successful "acceleration" claim (changes
clause). Also, I noted a difference between the construction
contract and supply contract changes clauses, earlier when
checking out FAR clauses. I believe the Supply contract clause
didn't specifically mention constructive changes, whereas the
clause for construction contracts does. If this was a
construction contract, I'd say there was acceleration under the
changes clause. We also recognize impacts from delays in
starting the project due to Protests. Let me read up on it.
By
Linda Koone
on Tuesday, September 05, 2000 - 09:53 am:
I believe the CO has to pay up!
Assuming from the stated scenario that the contractor's request
for a delivery extension in order to perform at the contract
price was legitimate, the CO's denial seems to be a breach of
contract. The Protest after Award clause appears to 'guarantee'
such an adjustment.
The contractor asserted its right to an adjustment under the
clause within the prescribed timeframe. It may have been wiser
to request either a delivery extension or a price adjustment but
failure to do so, in my opinion, doesn't negate the inital
assertion to a contract adjustment.
But, I could be wrong and there's always the Disputes clause!
By
Kennedy How on
Tuesday, September 05, 2000 - 10:07 am:
Let me throw out another little twist here. Are we saying, by
the 30 day notice provision, that a contractor is allowed to
submit a notice of possible increase in cost to perform? Perhaps
the contractor thought he COULD perform without incurring
additional cost, but as time came closer, he discovered that
expedited shipment is the only way to meet the contractual
delivery schedule.
I'm not certain what a CO would do when he gets this kind of
notice; it's more of a "heads up" of a claim of sorts, once the
time actually arrives. Certainly, a contractor can't submit a
claim of increased costs to perform until he actually incurs
those costs, and that usually happens after the fact. In a
borderline case, we might well put it aside, telling the
contractor to try to perform without using expedited delivery,
and revisit it later.
To reply to Vern's situation, my gut feeling is that I would be
inclined to pay up. There is no reason to ask for more money as
well as ask for a contract extension at the same time. I also
believe that we might well have put the contractor in an
impossibility of performance situation, if we did not provide
him with an adequate period of time to perform as the terms of
the contract specifies.
Kennedy
By
Anonymous
on Tuesday, September 05, 2000 - 10:51 am:
I appreciate both of you taking the time to offer your advice
and opinions concerning my dilemma.
You have posed these questions:
"What clause is the Contractor claiming adjustment under?"
In filing its claim, the contractor cited "41 U.S.C. 605(c), as
amended by Section 907 of the Federal Courts Administration Act
of 1992, PL 102-572 (October 1992), the Federal Acquisition
Regulation (FAR) 33.207 ... "
The contractor had VERBALLY stated that it would do "whatever it
takes" to get the equipment to its destinations on time to meet
the November 19 deadline. There was no written commitment by the
contractor to meet the deadlines at the original price. The
contractor did not request an extension, either. The contractor
did not notify the Contracting Officer, either verbally or in
writing, of the expectation of additional costs associated with
the delay of performance prior to incurring those costs.
"When did the contractor notify the Government of the extra cost
needed to meet the inflexible completion date?
I was not aware of the additional costs until January, 2000. The
units had been shipped in October and November, 1999.
If more than 30 days, were you prejudiced?
Delivery date could not be changed because the Government
required new computers in order to be Y2K compliant. If I had
been prejudiced, it would have been in favor of the contractor.
What would you have done, if notified sooner?"
If I had been notified sooner, I might have been able to obtain
additional funds from the end user to finance the costs of
expedited shipping.
"I'm assuming that the contract was a fixed-price supply
contract."
The "contract" is a competed lease under a Federal Supply
Schedule.
"First, you need to consult your legal advisor."
I have consulted my Legal Counsel. Counsel's opinion is that the
Government DOES NOT owe money to the contractor because the
contractor failed to obtain approval for the additional costs in
advance.
It is my position that we do owe the contractor money. I
understand it is the Contracting Officer's decision, but, as
usual, there are unique circumstances. The Government would have
to pay out of the agency's funds, then collect from another
agency, its customer, which does not agree with the additional
costs. I have personally audited the documents submitted for the
claim and can substantiate a portion of the amount. The bottom
line as far as I'm concerned is that the GOVERNMENT owes the
money to the contractor.
Again, I thank you for the time you are taking to offer your
advice and opinions.
By
joel hoffman
on Tuesday, September 05, 2000 - 11:48 am:
The situation is somewhat different than I understood from
previous posts.
Nash and Cibinic's "Administration of Government Contracts", 3rd
Edition, discuss the requirements for "Acceleration" under
"Constructive Changes" (Chapter 4, Section IV, 3.
"Acceleration").
Three of the required elements for an acceleration claim
(increased shipping costs in order to meet the schedule)are an
excusable delay ; Contractor notice to the Government of the
excusable delay , and request for extension of time together
with supporting information sufficient to allow the Government
to make a reasonable determination .
From what Anon said, it appears that the Contractor never
requested an extension but merely "stated that it would do
'whatever it takes' to get the equipment to its destinations on
time to meet the November 19 deadline."
It also appears to me that everyone was clearly aware that no
time extension would be granted. From the Contractor's
statement, there probably was an understanding on the part of
the Government that the Contractor had to "accelerate"
performance to meet the deadline, otherwise it could not.
Was there no indication from the Contractor that it would cost
the Government additional funds to meet the delivery date AND
did the Government not understand or assume that there would be
additional cost passed on to the Government?
Of course, if there were no cheaper alternatives available to
meet the schedule and the Government feels that the costs were
necessary and reasonable, what else could Anon or the customer
have done? - Could they have gone somewhere else to meet the
deadline?
Apparently, the customer is simply upset that their providing
agency couldn't meet their delivery dates, without incurring
additional costs.
I think Anon ought to pay the additional cost as a legitimate
constructive acceleration, unless there is something more to
this. Happy Sails! Joel
By
Linda Koone
on Tuesday, September 05, 2000 - 01:27 pm:
Joel:
I'm guessing that most would agree (although apparently Anon's
lawyer doesn't) that the contractor is entitled to some relief
here and it appears that he is seeking it under the Disputes
clause of the contract. If a contractor tells me that it will do
'whatever it takes' to meet an accelerated delivery, I'm going
to ask the obvious question-- 'What do you expect it will take
and is it going to cost me anything?' If you respond in silence
to a statement of that nature, it will certainly be viewed as
agreement by the other party.
I think Anon's difficulty arises from the fact that he can't get
the money to pay the claim and that his/her problem more closely
resembles a violation of the Anti-Deficiency Act.
It's not his/her agency's requirement, why should they fund the
claim? Regulated contracting procedures were followed.
Authorizing the contractor to perform in the face of a protest
is risky business, especially if the protestor prevails
(although, personally, in this case, with a critical, short-term
delivery I probably would have risked it-but then maybe I'm
being a Monday morning quarterback on a Tuesday afternoon!)
On the other hand, the customer isn't going to shell out
additional money simply because of a protest. Are you going to
get that customer's business the next time around? Doubtful.
I think Anon needs to come up with money to pay for the
accelerated delivery or risk additional costs if the issue is
elevated beyond the contracting activity.
By
Anonymous
on Tuesday, September 05, 2000 - 01:39 pm:
Joel,
Regarding your earlier message - I had written an e-mail dated
3/30/00 to the contract administrator for the claimant. I had
said that Legal Counsel advised me that it was incumbent upon
(the contractor) to contact the Contracting Officer and obtain
assurance that the Government would reimburse (the contractor)
for such a large sum prior to performing.
The contractor replied in a letter dated 5/5/00 that the
Government knew that (the contractor) had to accelerate
performance and the government, including the Contracting
Officer, was opposed to schedule slippage, notwithstanding the
knowledge that (the contractor) was accelerating performance.
The contractor also stated that, " ... further delay was caused
by the Government's missteps in issuing a proper delivery order
to (the contractor); ..." That statement arose from the time lag
between the J&A to proceed pending resolution of the protest and
the actual lifting of the stop work order.
In another paragraph, the contractor says, " ... winning
proposal offered a firm fixed price predicated on a much longer
period of performance than (the Government) ultimately provided
due to factors completely beyond (the contractor's) control and
largely within the Government's control (e.g., the Government
could have issued the suspension override weeks earlier,
thereafter the Government could have immediately lifted the stop
work order, the Government could have then quickly issued to
(the contractor) a proper delivery order; ..."
The next paragraph says, "The Government knew all the pertinent
circumstances that required (the contractor) to perform this
contract in a fraction of the time upon which (the contractor)
had based its firm fixed price. Equally important is the
indisputable fact that the government, despite knowing about
(the contractor's) accelerated performance, refused to extend
the time for performance."
Later in the same letter, the contractor says, " ... delays
contributed to the accelerated schedule and to (the
contractor's) added costs of performance."
There is more of the same, but you get the drift. I agree with
the contractor in this case. As I said before, Legal Counsel
does not agree with me. I know the decision rests with the CO,
but I would like to obtain more secure support from Counsel. Do
you have any case law references I might cite?
Again, I appreciate everyone's participation in this discussion.
By
Linda Koone
on Tuesday, September 05, 2000 - 01:58 pm:
Anon:
I'd ask the same question you are asking of Joel from your own
Counsel. Ask for cases supporting their position that the
contractor is not entitled to any relief.
We're just speculating based on the information you've provided.
There may be critical elements that haven't been addressed in
this discussion that causes your Counsel to disagree with us.
By
Ramon Jackson on Tuesday, September 05, 2000 - 02:12 pm:
Linda raises an interesting side issue:
On the other hand, the customer isn't going to shell out
additional money simply because of a protest. Are you going to
get that customer's business the next time around? Doubtful.
A customer victim of incompetence in the contracting
organization would be justified in such attitudes. Protest is
not an unusual risk and often not the result of poor execution
on the contracting organization's part. Customer's
responsibility to fund contract costs, including unforseen
glitches not resulting from negligence in the contracting
organization, should be covered in an interagency agreement.
In my opinion the "contract" between agencies needs as much care
as the contract being considered. Was this perhaps neglected in
this case? Will this interagency aspect encourage action
resulting in added taxpayer expense of litigated, directed
payment?
I wonder anew if the enterprise model for contracting
organizations is sound and in the best interest of taxpayers.
By
Linda Koone
on Tuesday, September 05, 2000 - 02:15 pm:
By the way, I wouldn't use that old 'my lawyer says' ploy in
responding to contractor claims/REAs...
If you are using your Counsel's advice in formulating an opinion
in a contractual matter, then call it your opinion.
If you don't agree with Counsel's advice, discuss it with them
and if it's truly just their opinion and not a reflection of the
regs or case law, then thank them for their opinion, formulate
your decision, and advise the contractor of your
decision.
By
Vern Edwards
on Tuesday, September 05, 2000 - 02:45 pm:
Anonymous:
At this point I am confused about your facts, but I'm not
inclined to re-read everything in order to try to straighten
myself out. It's tough to discuss these things intelligently
when you dribble out new information after each round of
discussion.
I'll sum up my thinking this way: You awarded a contract and
then told the contractor to stop work because you got a protest.
Then, either (a) you lifted the stop work or (b) it expired.
Either way, the contractor had 30 days to request an equitable
adjustment to the price, schedule, or both. As I understand it,
he asked for more time but, for whatever reason, you wouldn't
give it to him. So the contractor delivered as required and then
sent you a large bill for the "acceleration."
As I understand it, your lawyer doesn't want you to pay the bill
because the contractor did not tell you in advance that it would
cost a lot more to deliver in accordance with the original
schedule. I have not heard you say that you dispute the amount
of the bill. The only argument that I have heard you make
against paying the bill is that the contractor did not tell you
in advance that it would cost more.
The contractor was foolish not to have warned you in advance.
But even if it had, what would you have done? Would you have
then granted the extension, even though you told us earlier that
you couldn't? Would you have terminated the contract for the
convenience of the Government, which would have not only delayed
delivery, but would have required you to pay termination
settlement costs and then reprocure?
Pay up, unless you think that the additional amount requested is
not allowable, as provided in FAR 31.201-2. If you want, fuss at
the contractor for failing to warn you in advance and bargain
for a lower amount on "moral" grounds.
By
joel hoffman on Tuesday, September 05, 2000 - 02:48 pm:
Anon, there is some discussion in Nash and Cibinic's
"Administration of Government Contracts" - the cases go both
ways. That would be a good starting point to begin a search.
Linda is right. We don't have enough facts or benfit of the
evidence or contemporaneous knowledge of the circumstances to
provide a full opinion - sorry. Happy Sails! Joel
By
Anonymous
on Tuesday, September 05, 2000 - 03:17 pm:
Thanks to all for your advice and opinions. I will take the
information and proceed to argue my case that the contractor
should be paid.
By
Kennedy How on
Wednesday, September 06, 2000 - 12:21 pm:
Vern,
I think Anon was looking for what might be termed "an easy
answer", from the standpoint that we here have a tendency to
cite experiences or case facts in our other replies. Personally,
I think that was what he was looking for, in the hopes of
gaining some insight as to where he can look for backup to his
position.
It sounds to me that in order to effect a settlement with the
contractor on his "claim", he needs his Legal's concurrance,
which he doesn't have at this time. Our activity is the same
way, while the CO has the ultimate decision authority, we really
would like to have Legal buy-in. I've gone around and around on
things like this in the past, we don't get much done if Legal is
not willing to go along; for whatever the reason. I would be
curious to know exactly what legal precedent Anon's counsel is
citing to support their position. It might be something
technical or procedural, which puts the Government in a superior
position. But, depending on the quantum, or fairness of that
position, the a court may not agree. We've been in a case where
the Government position was thought to be very, very solid, but
the ASBCA ruled on "equity", and found for the contractor.
Linda, I don't think it's an Anti-Deficiency issue at all. No
contracting activity goes in with a fund to cover litigation.
I've settled litigation where no funding existed, we had to
petition Army to get settlement money, based on the facts, and
JAG opinion. We did get the money, and we did settle. I would
expect Anon's agency or customer to do the same.
Kennedy
By
Linda Koone
on Wednesday, September 06, 2000 - 01:02 pm:
Kennedy:
I didn't mean to imply that you have to have funds available to
cover litigation costs.
The situation that was finally described in this thread doesn't
really involve a ratification of an unauthorized commitment. In
my opinion, it is more closely tied to the Anti-Deficiency Act
because I think it was incumbent upon the CO to find out what
the contractor meant when he said he would 'do whatever it
takes' to meet the original delivery schedule after he was
denied an equitable time extension.
My experience tells me that if I can't give a contractor time,
I'm going to have to give him money. I'd better have that money
available or I'm in violation of the Anti-Deficiency Act.
Hope that clears it up for you - and again, it's just my
opinion. Maybe my experience is unique.
Ramon:
I agree that the cost of litigation should be addressed in any
interagency agreement, and really can't say whether that is a
common practice. I would think it would be a difficult issue on
which to reach agreement. As a customer in this case, there's an
argument to be made as to whether there was some 'negligence' on
behalf of the contracting office (e.g., a month to lift the
stop-work order? Denial of an adjustment due to the stop-work
order?)
Who would you put in charge of determining whether the
requirement or the contracting office is responsible for the
litigation costs?
By
Vern Edwards
on Wednesday, September 06, 2000 - 02:05 pm:
Kennedy:
It is interesting that conflict between the contracting officer
and the program/project manager is so frequently discussed, but
not conflict between the legal office and the contracting
officer, which has always been of more concern to me.
FAR says that the contracting officer should seek the advice of
specialists in law (FAR 1.602-2(c)), but it does not give
lawyers any authority. They have simply managed to TAKE it.
By
Anonymous
on Thursday, September 07, 2000 - 11:07 am:
In my case, agency regulations require concurrence of Legal
Counsel on the Contracting Officer's decision document for a
claim. Therefore, Counsel may hold the Contracting Officer
hostage.
By
Kennedy How on
Thursday, September 07, 2000 - 11:53 am:
Vern,
I think it's because we tend to be more in sync with our legal
advisors on many issues, and, as such, they tend to bolster our
positions with respect to our "conflicts" with the PM types.
From personal experience, the PM types I've worked closely with
have tried to get the opinions of the legal staff as we go
along; we usually don't have problems in that arena.
Having said that, I'm aware of the various battles we've fought
with the same legal staff, certainly, some have been dumb,
others are more murky in which way is the better way. Usually,
this latter happens when you're on the cutting edge of
something, when you aren't on solid, established precedent,
those are where the philosophical battles are fought.
Kennedy
By
Stan Livingstone
on Thursday, September 07, 2000 - 01:48 pm:
My experiences and observations throughout the Government is
that legal reviews/approvals/concurrences take on a much more
powerful connotation than just providing advice chiefly due to a
lack of uniformly competent 1102s in the workplace. Certainly
there are very bright and qualified 1102's (for example those
than read and participate in this forum). However, there are way
too many people in the series without proper training,
education, and experience. Those people over the years made
outright dumb mistakes. Consequently agency management requires
legal approvals on just about everything significant to avoid
reoccurrences. I think the only solution is showing that we are
educated and trained, exhibit solid business judgment, and can
bring value to the acquisition process. Then, and only then, are
we respected and legal guidance becomes guidance and not
approval.
By
bob antonio on
Thursday, September 07, 2000 - 02:26 pm:
Stan:
From experience, I group legal counsel as--general
(non-contracting) and contracting. The contracting counsel
brings specialized knowledge to the table and it is the most
important for our purposes. Unfortunately, a "general" counsel
often attempts to deal with federal contracting matters.
Years ago, several Justice Department attorneys were
representing the U. S. in a dispute. Prior to court, the
attorneys were looking for someone to explain fixed-price type
contracts. The government lost the case.
By
Stan Livingstone
on Friday, September 08, 2000 - 07:22 am:
Bob,
I agree. Having a good contracting counsel to work with is key
to being effective and doing the job right. There are lots in
the Government but sometimes not enough to go around. The
unfortunate piece is that the legal advise role often has grown
to a legal approver role. In many agencies and offices, you have
to have "legal approval" before even rountine actions such as
administrative mods are signed. It's a shame that our collective
performance over the years allowed that situation to occur.
Stan
By
bob antonio on
Friday, September 08, 2000 - 09:23 am:
Stan:
I looked over the notes on "legal council" and feel that often
contracting officers or heads of contracting activities are
better qualified to render decisions on federal contracting
matters than agencies' "general" counsel. I also feel that the
generalist attorney makes a good advisor on general issues.
The court case I noted involved a legend from the Navy--Gordon
Rule. If you worked in Crystal City during the 1970s and saw a
fellow that looked like Winston Churchil walking around, that
was him. If my memory is correct, he signed a contract
modification, as a special contracting officer, adding $33
million to a FPIF shipbuilding contract. However, the government
claimed that the modification was not valid, in part, due to a
lack of Navy legal review. Prior to working for the Navy, Rule
practiced law at a prestigious D. C. law firm. Additionally, he
authored books on federal contracting. In the Navy he was the
head civilian in the Naval Material Command's contract clearance
office. I believe all Navy contracts over $1 million required
his approval.
Sometimes a requirement for legal review can be absurd. In the
case I noted, Rule was probably more competent than anyone in
the Navy's legal office.
By
Ramon Jackson on Friday, September 08, 2000 - 10:17 am:
Linda, I agree. Ignoring "we will do whatever it takes" in
such context should set off alarm bells. Under these
circumstances the statement demands a question and some fact
finding -- fast! It this context it contains an implied threat.
I know of no solution where agencies get into serious finger
pointing and unethical behavior about responsibility. I've heard
a couple of horror stories about agencies being stuck with
another's just debt on contracts and there seems to be little
defense in such cases.
Written agreement between agencies, including details of cost
allocation, is some defense against ignorance. "Customer"
agencies, who are often involved with the contracting agency
because the contracting scope is beyond their authority,
experience, or ability, often seem to fit this category. The
normal hazards of contracting, protests included, need to be
covered. I recall a big issue one case -- the need for a
government management reserve to cover such emergencies. Working
and negotiating the issues in MOUs, MOAs, ISSAs, etc., before
the "elephants" sign the agreement is itself worth the effort.
It defines issues, understanding gaps and works as an
educational tool at the lower levels. The final form should
capture the real understanding of the staffs involved and
formalizing it with signing.
Like all things worth while it will be work, even heated work.
Doing it the "easy" way early on only makes it much harder in
the long run. Disputes before the fact are generally easier on
all than the wars that can be aftereffects of full blown
interagency disputes. I'm under no illusion this will solve all
problems. I do know leaving it undone or poorly done nearly
assures greater problems.
By
joel hoffman on Friday, September 08, 2000 - 11:16 am:
The FAR requires legal review, not legal "approval". The KO
is required to ensure that all laws are followed, that the
interests of the US are served and to seek legal opinion where
necessary. I don't see how an Agency Supplement can add a
requirement that Counsel "approve" an action. Of course, if the
KO does something that Counsel says is not "legal", the KO has
exceeded their authority.
Happy Sails! joel
By
Kennedy How on
Friday, September 08, 2000 - 02:05 pm:
Speaking to the specifics of Procurement Law lawyers (which
we have here at my activity), I am lumping them into those
lawyers who are trained as such.
I think that when a lawyer tells you it's not legal to do
something, those types of opinions/concurrences are pretty cut
and dry. It's where we don't have a law prohibiting something
that's where we get into problems, or where the lawyer is
familiar with past case law which sets a precedent; all because
some contractor was able to hire a sharp lawyer to come up with
some novel reason to find the Government liable.
A few years ago, I wanted to include Liquidated Damages in a
solicitation for GFE. The PMs wanted to hold the contractor to a
delivery schedule, so that the final end item will be equipped
with said item. This item could be considered a safety item in
that it COULD put somebody other than the end item operator in
danger. Our legal advisor told us that we had to quantify the
cost of that danger (human life) in order to make the liquidated
damages provision stick. We could quantify the cost to retrofit,
or to store the end item, but we couldn't quantify the price on
a human life. And because we couldn't do that, we couldn't use
the clause.
If I remember correctly, our legal advisor said that previous
case history has ruled against the Government when this clause
was applied.
Theoretically, we could have gone ahead and put that in anyway,
but if push came to shove in litigation, we would have lost
because our legal advisor will say "I didn't support this then,
I don't support it now." And, the contractor's attorney will
point that out before the ASBCA. When we get to this point,
Joel, it becomes more clear as to why you have legal "approval";
you may not have violated any laws or regs, but the case you
might end up in will be unsupportable.
I say all of this because it's evolved to where one wants the
lawyers on your side from the get-go, because one is gun shy
when you're on the cutting edge (or as Stan says, something
being done by a competent and bright 1102), and there is a
possibility of something blowing up in your face.
Kennedy
By
John Ford on
Monday, September 11, 2000 - 09:05 am:
Bob, I worked for the Navy at Crystal City in the 70's and I
think I remember the case you are talking about with Gordon
Rule. There are some details you forgot to mention in your post.
As you said, Gordon was acting as a Special Contracting Officer
to help NAVSEA clear its backlog of shipbuilding claims. He had
a proposed settlement on a claim, but had no backup or support
for the position he had negotiatied with the contractor. In
essence, he put a rubber stamp on the contractor's claim. NAVMAT
revoked his warrant, but he signed the SF 30 granting the
contractor's claim and mailed it to the contractor anyway.
Shortly thereafter Gordon went into forced retirement.
By
bob antonio on
Monday, September 11, 2000 - 09:59 am:
John:
The case was the CGN 41 and the Virginia class of CGNs--I
believe--and there are a great many details that I left out. If
I remember correctly, Gordon was working for the Deputy
Secretary of Defense and he briefed the Deputy Secretary on the
results of negotiations before signing the modification.
However, he was part of the Navy and there were forces in the
Navy that had their own agenda.
I have a moment by moment account of Gordon's actions at home
and if I remember correctly he still had his special warrant for
a few minutes after he signed the modification. Eventually, the
Court--somewhere around Norfolk and maybe a district
court--decided that the modification was valid. The real story
of this case involves the original signing of the contract for
the three ships with an option for two more ships.
The first time I met Gordon he was dressed in a three-piece
black suit with a watch and chain and a big cigar. All I could
think of was Winston Churchill. Years later, I spoke with one of
his staff members and I told him how I though Gordon looked like
Churchill. The staff member looked at me and said, "He thought
he was Churchill."
The major and even minor players involved in this case were
interesting.
By
bob antonio on
Friday, September 15, 2000 - 06:41 pm:
This is the second part of this popular thread. Several notes
were added to this one from the first thread. Both this thread
and the first thread will remain active until the last note in
this thread is 30 days old. After that, both threads will be
archived.
By
Harley Hartley
on Friday, September 15, 2000 - 02:47 pm:
At the top of this thread John Huckle said something along
these lines: if a contractor continues to perform routine
maintenance services on a contract that has expired, the
additional services should be added to the expired contract
rather than treated as an unauthorized action requiring
ratification. Under the theory that a contract with a specific
performance period is completed at the end of the performance
period and, therefore, no contract exists on the next day, I've
always treated services performed after the end of the
performance period as unauthorized and put them through the
ratification process which is no fun. I am prepared to re-think
my position but would like to know whether the issue has been
addressed by BCA or court. Does anyone know of cases addressing
this point? By the way, this is my first time reading in this
chat room. I haven't so much fun since I used to read letters to
the editor in the Washington Post by and about people who drive
at the speed limit in the left lane on the beltway.
By
Eric Ottinger
on Friday, September 15, 2000 - 03:20 pm:
Kennedy,
The fact that the courts will only support liquidated damages up
to the amount of actual damages is basic knowledge which most
1102s should pick up fairly early. Your lawyer was passing along
some information which your supervisor should have provided.
Here is an excerpt out of the Basic Contracting Course available
in the Deskbook.
"The following are the limitations on its use:
(1) to be used only where time of delivery is important and
actual damages would be difficult or impossible to determine;
(2) rate must be reasonable, i.e., decided on a case-by-case
basis;
(3) rate must bear some reasonable relationship to anticipated
or actual damages;
(4) government must attempt to mitigate its liquidated damages,
making all reasonable effort so as not to delay contractor’s
ultimate performance;
(5) only Comptroller General has power to remit liquidated
damages (41 U.S.C.256a);
(6) mandatory in DoD construction contracts expected to exceed
$500,000, except cost-plus-fixed-fee or where con-tractor cannot
control pace of work (DFARS 211.504)."
You might do an incentive arrangement instead.
You might determine the value of your "human life" by
determining what life insurance would cost under the
circumstances.
If you wanted to be creative, you might get an advance agreement
from the contractor on the value of the human life.
Eric
By
Eric Ottinger
on Friday, September 15, 2000 - 03:58 pm:
Kennedy,
I should have said "Contract Law" course. I just put
"liquidated" into the Search then went down to the education
hits.
Sorry for any confusion.
Eric
By
Vern Edwards
on Friday, September 15, 2000 - 04:33 pm:
Hartley:
You posed this question:
"At the top of this thread John Huckle said something along
these lines: if a contractor continues to perform routine
maintenance services on a contract that has expired, the
additional services should be added to the expired contract
rather than treated as an unauthorized action requiring
ratification. Under the theory that a contract with a specific
performance period is completed at the end of the performance
period and, therefore, no contract exists on the next day, I've
always treated services performed after the end of the
performance period as unauthorized and put them through the
ratification process which is no fun. I am prepared to re-think
my position but would like to know whether the issue has been
addressed by BCA or court. Does anyone know of cases addressing
this point?"
Let me use an example to answer your question:
Suppose that the period of performance of a contract for
services ends on July 31. The COR asks the contractor to perform
for another week, saying that he will make sure that the
contractor gets paid. Let us assume for the sake of discussion
that the COR had no authority to make a commitment to the
contractor, actual, apparent, or implied, and that the CO did
not know about the COR's action and therefore cannot be said to
have ratified it through acquiescence.
It does not matter whether you add the continued performance to
the expired contract or treat is as a new procurement, it was
done on the basis of an unauthorized commitment as
defined in FAR 1.602-3(a), which must be ratified before the
contractor can get paid.
If John Huckle believed that an unauthorized addition to an
expired contract does not require ratification, then he was
mistaken.
In a different scenario, suppose that the contractor performed
for another week entirely on his own initiative. In that case
there was no unauthorized commitment to be ratified. FAR makes
no provision for making an after the fact award, except to
ratify an unauthorized commitment.
I hope that I have understood your inquiry correctly.
By
Kennedy How on
Monday, September 18, 2000 - 12:21 pm:
Eric,
Yes, we were aware of how the liquidated damages worked, even
though we never really used it. Our office was investigating the
possibilities of using it in response to the PM's request to
look into it as a way to hold the contractor accountable for his
performance.
All of this was in the solicitation writing phase, so we hadn't
gotten to the point of discussions with any offerors yet.
I don't recall what happened eventually; I was put onto a
special assignment (not to exceed infinity) a short while after.
I know we didn't use the LD clause.
Kennedy
By
Anonymous
on Tuesday, September 19, 2000 - 09:39 am:
Although I'm unfamiliar with the case law, I believe the
FAR's plain language grants contracting offices authority to
resolve unauthorized commitments, that arise under or relate to
contracts, under the CDA without a FAR Part 1 ratification.
The content of FAR 1.602-3(b)(5) and its relationship with the
rest of FAR 1.602-3(b) lead to this conclusion. FAR
1.602-3(b)(5) doesn't address whether the ratification described
at FAR 1.602(b)(1) through (3) is required; the regulation
merely provides that unauthorized commitments involving claims
should be processed in accordance with FAR 33.2. FAR
1.602-3(b)(4) also addresses the relationship between the
ratification process and another type of resolution (i.e., GAO
claim process), but in this case there is express language
requiring ratification.
The context of 1.602-3(b)(5) within 1.602-3(b) is also relevant.
If ratification were required, the most logical place for the
language at (b)(5)would within one of the provisions at
1.602-3(b)(1) through (b)(3), all of which describe the
ratification process. Instead, (b)(5) is placed on equal footing
with these provisions and following another provision, (b)(4),
which also addresses the relationship between ratification and
another resolution mechanism.
The most reasonable interpretation of 1.602-3(b) is (b)(1) - (3)
describe the ratification process while (b)(4) and (5) address
whether the ratification process should be used when another
authority also exists. As stated at (b)(4), ratification trumps
GAO process, but CDA trumps ratification per (b)(5).
FAR 33.2 further supports this conclusion. 1.602-3(b)(5) states
"unauthorized commitments that would involve claims subject to
resolution under CDA should be processed in accordance with FAR
33.2." If ratification was intended to be part of the process in
such instances, FAR 33.2 would address it. However, there is no
mention of ratification in 33.2. FAR 33.210 and 33.211, for
instance, place limitations on the contracting officer's
authority to act under the CDA and set forth the contracting
officer's responsibilities under the CDA, but there is no
mention of ratification.
I also believe my conclusion is the best from a policy or common
sense perspective. Unauthorized commitments that arise under or
are related to a contract are likely to be less egregious than
those unauthorized commitments that are unrelated to performance
under a legitimate contract (e.g., unauthorized commitments
unrelated to a contract are more likely to be CICA violations).
From an equity standpoint, vendors involved in unauthorized
commitments unrelated to a contract are generally less deserving
of payment than those who were confused into believing the
unauthorized commitment was actually part of their legitimate
contract. A conclusion contrary to mine results in a more
difficult resolution process (i.e., both Part 1 ratification and
Part 33.2 CDA) for those unauthorized commitments related to a
contract than for those unauthorized commitments unrelated to a
contract, which can be resolved entirely through Part 1
ratification. |