By
Vern Edwards
on Thursday, May 4, 2000 - 01:29 pm:
All:
Thanks for all your great responses. I apologize for not
responding recently. I'm helping out at the ranch this week;
we've been branding calves and moving cows. We're a long way
from everything and I don't have ready Internet access at the
house. But I had to come into town this morning (60 miles away)
and I discovered that a young couple has opened an internet cafe
here! I can't get over it.
I'll read your responses. Good work everyone.
Vern
By
Eric Ottinger on
Wednesday, May 3, 2000 - 12:43 pm:
Linda,
I hear you. However, the only consistent rationale that I can
think of to support a sole source, when you know there is
competition, is to state that only one source can satisfy the
Government's requirement in the time frame required.
This might be acceptable if it is true at the time that you make
your decision. I doubt many of us write the determination for
the option exercise six months in advance.
For obvious reasons, I wouldn't decide on a course of action
then wait six months so that I can honestly say that I don't
have enough lead time for a competition. I think the GAO would
frown.
However, there might be some grey area situations where you
could obtain competition for a large buy, including all of the
options, but no other offeror would have the tooling,
specialized labor, etc. to do the option at a reasonable price.
In this kind of case you could write a solid J&A.
As for the larger question, I don't like "Heads I win; Tails you
lose" business arrangements. A business can easily lose money on
a Government contract. It isn't a bad thing for a business to
make a profit on occasion; particularly, when the reasonableness
of the price has been validated by competition.
Renegotiating options isn't the same thing as going back to the
Renegotiation Board (Remember that Vern?), but the underlying
philosophy would be the same.
Eric
By
Linda Koone
on Wednesday, May 3, 2000 - 12:07 pm:
Vern:
Maybe the answer to your original question is as simple as
whether you have the authority to negotiate.
You can negotiate under full and open competition -- or you can
negotiate under one of the exceptions to full and open
competition, with the appropriately executed J&A/D&F.
If you are unable to exercise the option under the conditions
set forth in the contract and pursuant to FAR 17.207, then you
negotiate the option under full and open competition, or
negotiate on a sole source or limited competitive basis using an
exception to full and open competition, presuming one exists.
If you can support negotiating with one company and you get the
required approval, then you could negotiate a reduced option
price.
By
Eric Ottinger on
Wednesday, May 3, 2000 - 11:59 am:
Vern,
Here is the exact language out of the Magnavox case--
Magnavox Electronic Systems Company, (Nov. 02, 1988)
"An agency is not permitted to negotiate with the awardee to
reduce the option price stated in the contract if price
competition for the option quantity is available. Varian
Associates, Inc., B-208281, Feb. 16, 1983, 83-1 CPD 160, aff’d
in relevant part sub nom Department of the
Army--Reconsideration, B-208281.2, July 12, 1983, 83-2 CPD 78."
...
"We do not object, necessarily, to an agency attempting to
negotiate for a lower price than that stated in an option.
Where, however, the facts indicate that a competition likely
would result in the lowest price obtainable, the agency should
conduct such a competition rather than negotiate on a
sole-source basis. Varian Associates, Inc., B-208281, supra.
Here, we think that based on the pricing information available,
the Navy should have concluded that a competition for additional
sonobuoys likely would have resulted in a lower unit price for
the additional units than the $214.30 negotiated with Sparton on
a sole-source basis. ..."
Eric
By
Kennedy How on
Wednesday, May 3, 2000 - 10:46 am:
The (FFP) supply contracts we
generate would have 100% Options, which means the exercise of an
option would effectively double the quantity. The reason why
we'd inquire about price breaks is because often times, there is
a price change for quantity (usually in raw materials). Our
practice is to check to ensure we are getting a reasonable
price. Also, these contracts are a result of full and open
competition.
Realistically, the contractor has 3 choices. He could tell us
there is no price change (whether there is or not), lower the
price so it's Win/Win for him and the Government, or lower it
all the way so his profit stays the same as what was he
calculated at original award.
I was looking at FAR Part 17.20x again, and I noticed the blurb
about informal price analysis 17.207(d)(2). While you could say
that the current price IS NOT advantageous based on a price
reduction, that price reduction only applies to the current
contractor, because the reduction is predicated on adding on to
the quantity already on contract. Which is why we ask.
I apologize now for drifting further off-topic; I can see lots
of permutations over this.
Kennedy
By
Eric Ottinger on
Wednesday, May 3, 2000 - 10:06 am:
Linda,
I should have said--
Voluntary offers to discount the price would be nice, but I
question whether such would ALWAYS be voluntary in any way but
the form.
The instances that you cite are of course the interesting ones.
I think the need for closure is the most important principle. We
shouldn't reopen these things unless the circumstances are
really compelling.
However, I can see where it would be hard to turn down a real
Win/Win.
I can imagine circumstance where a renegotiated option and a J&A
would do (i.e. You make your decision at a point when you don't
have the necessary lead time for a competition). But I would not
recommend strategizing to do that. You would have to tell a fib
at some point.
Eric
By
bob antonio on
Wednesday, May 3, 2000 - 09:22 am:
Vern:
This is the way I would approach it if I stumbled over this
procurement. However, there are unmentioned variables in your
example, eg. value of items etc. So you must follow the
assumptions and fill in some facts along the way.
I assume that the option is for priced items and the option
prices were a part of the original competition. If this is the
case, I view it as a "fairness" issue and then a potential full
and open competition issue. I think the sequence of events has
at least some significance.
If I approach this as a full and open competition issue, I would
want to determine whether there were other offerors in the
original procurement. Your example states that it was
competitive so I assume that there were competitive prices and
items. In my mind, there now is the potential for competition
under the option from the original offerors also.
When should the contracting officer discuss revised prices with
the option contractor? If I were the contracting officer, I
would want the other agency's contract in my hands and I would
share it with the requiring activity. Suppose the requring
activity agrees that the other agency's item is the same item
available under the option. The contracting officer must make a
determination if the exercise of the option is most advantageous
to the government.
Suppose the contracting officer finds the option is not the most
advantageous deal for the government. This business decision
will be evaluated on its reasonableness. Assume the decision is
reasonable. Then there is no option to be exercised. End of
contractual relationship in my view.
Suppose the contracting officer begins negotiations with the
option contractor. On what basis? On what agreement? Will this
be a sole-source negotiation? Will the other agency's contractor
be invited for a limited competition. Will the offerors on the
original procurement be invited to submit offers? These would be
my opening questions of the contracting officer.
By
Linda Koone
on Wednesday, May 3, 2000 - 09:19 am:
Eric:
I've actually had instances of voluntary price reductions for
options.
The contractor has simply sent a letter offering to reduce the
option price. An obvious attempt to lure us into exercising the
option, but totally unsolicited from me.
By
Eric Ottinger on
Wednesday, May 3, 2000 - 09:06 am:
Vern,
Short answer. I believe that GAO meant Part 15 competitive
negotiation when they said that it would be OK to renegotiate.
The Magnavox case cites the rule from the Varian case in
unambiguous terms.
I will try to provide more specifics later.
Joel,
The GAO grounded the Varian case in the FAR language regarding
options. This is the basis for saying that options must be
exercised consistent with the terms of the options. The FAR has
a long list of situations where the price may vary for some
reason. Otherwise, it is pretty clear that the price of the
option should remain fixed.
We do have mechanisms where contractors can improve their offers
(e.g.. technology refreshment.) Also under task order
competitions, an offeror can bid lower for the Task/Delivery
Order than he/she did for the initial competition.
However, I don't think this would be a good general policy for
the reasons that I stated. As a rule we value aggressive
negotiations, but we also value closure.
Voluntary offers to discount the price would be nice, but I
question whether such would be voluntary in any way but the
form.
Eric
By
Linda Koone
on Wednesday, May 3, 2000 - 09:02 am:
Vern:
There's a recent GAO Decision in which the protestor used the
Varian and Magnavox decisions to support its protest - it's
available at the GPO Access website:
Decision # B-279777
TITLE: Outdoor Venture Corporation, B-279777, July 17, 1998
This case was different from the Varian and Magnavox case in
that the contract was awarded on a sole source basis to maintain
an industrial mobilization base [10 USC 2304(C)(3)], but it
provides a little insight into the Varian and Magnavox cases. In
its decision, the GAO writes:
"The decisions cited by OVC are inapplicable here, since they
involved firms which had competed unsuccessfully for the
original award and which then protested that they could have
offered better option prices than those negotiated without
competition with the awardee Magnavox Elec. Sys., Co., B-231795,
supra; Varian Assocs., Inc., supra. This was true even in
Magnavox, where there was less than full and open competition
for the initial award. In that case, the agency had conducted a
limited competition among industrial mobilization base
producers, and had made its original award decision, in part, on
the basis of low price. Subsequently, the agency modified the
awardee's contract to acquire additional units at a lower price.
We sustained the protest, holding that the additional quantity
should have been competed, because the record showed that
another of the mobilization base competitors may have been the
low-priced offeror, and therefore entitled to the award, had the
agency originally awarded a contract for the increased quantity.
In the current case, there was no competition among industrial
mobilization base producers for the original award; rather, the
agency made award to TBE on a sole-source basis--admittedly at a
price premium--in order to maintain that firm's manufacturing
capacity. Because, as explained above, the sole-source
justification remained valid at the time the option was
exercised, nothing in Magnavox or Varian suggests that a
competition had to be held for the option quantity."
I would agree, in principle, that there is nothing wrong with
renegotiating option prices. But I believe that you need to be
careful when you do it in a competitive environment,
particularly when low price was a factor in the award decision
and you have information that indicates that a better price is
available through competition.
None of the cases involved a best value source selection with
award to other than the low offeror.
Any opinions on whether you may have more flexibility in
negotiating a better option price on a best value source
selection decision?
By joel hoffman on Wednesday,
May 3, 2000 - 08:14 am:
My opinion is based on the
assumption that the option was evaluated at the time of award.
Somehow that sentence disappeared from my text, below. Happy
Sails!
By
Joel Hoffman on Wednesday, May 3, 2000 - 08:10 am:
Eric, I believe there are two
basic reasons the Government can't tinker with or "request" a
change in the contractual, technical, price or time terms of an
offered "option."
First, if the Government expects to retain its unilateral right
to accept or decline the "option", it can't change the terms
that the item was competed under. That is to protect the
contractor.
Second consideration would be to the rest of the competitive
community. The Government might have to recompete the work,
where more appropriate.
(I don'tbelieve that means a contractor can't volunteer a
discount, in order to encourage or allow the Government to award
the work included in the option, if it otherwise would refrain
from doing awarding due to lack of funds or an opinion that the
price is unreasonable.
I feel that the first reason above would no longer be an
obstacle; the Contractor is offering to improve its otherwise
successful offer. I am not aware of any FAR prohibition against
this. It is specifically allowed prior to award - why not after
award?
BUT - if the Government decides to try to negotiate with the
contractor - not simply accept the revised "option" offer - the
unilateral right to award anything other than the originally
offered price is gone.
There was adequate competition the first time around. In my
opinion, the rest of the community already had its chance. So,
why can't the Contractor volunteer to improve its offered terms?
We can continue this line of discussion under another thread - I
really wanted to explain why the Government can't try to change
the terms of the option, and still expect to retain the
unilateral right to award the option.) Happy Sails!
By
Vern Edwards
on Tuesday, May 2, 2000 - 10:24 pm:
Linda:
Good work! But the GAO quote seems to indicate that there is
nothing wrong in principle with renegotiating an option price.
Is that right? (I can't get to my GAO decisions right now.)
Vern
By
Eric Ottinger on
Tuesday, May 2, 2000 - 02:31 pm:
Kudos to Linda,
I did a word search and came up with nothing. Linda is obviously
more persistent.
Magnovox would seem to be of limited help. It would be difficult
in most circumstances to say with certainty that you couldn't
get a lower price with competition.
It strikes me that I may have taken the Ask A Professor quote
out of context. The person asking the question wanted to know if
it was possible to exercise an option late. The answer said that
it would be all right if done bilaterally. This clearly
contemplates renegotiating something in the option (i.e. the
option exercise date). In short you must excercise in accordance
with the terms, but that doesn't prevent you from renegotiating
such terms before the option exercise.
The GAO imput is interesting, but I think the legal argument
gets to the question of what an option has to be, to be legally
enforceable.
Eric
By
Linda Koone
on Tuesday, May 2, 2000 - 02:04 pm:
Vern:
Sorry to throw a monkey wrench into the discussion. I withdraw
my question.
In Varian Associates, Decision B-208281, Feb 83, (83-1 CPD para.
160), the Comp Gen determined that it was inappropriate for the
Navy to negotiate with the contractor to reduce the option price
where price competion for the option quantity was available.
In Magnavox, B-231795, Nov 2, 1988, 88-2 CPD Para. 431, the Comp
Gen writes about the Varian decision and states:
'We do not object, necessarily, to an agency attempting to
negotiate a lower price than that stated in an option. Where,
however, the facts indicate that a competition would result in
the lowest price obtainable, an agency should conduct
competition rather than negotiate on a sole source basis.'
(Please excuse any paraphrasing due to my scribbled hand-written
notes from the case)
The option pricing was not evaluated at the time of award in
either of these cases as I recall, however.
As far as Eric's discussion on what the lawyers say, I believe
that the Comp Gen has long held that an option should be clear
and definite enough to exercise without further discussion/
negotiation, otherwise it's not an option.
My answer, then, would be that you would not be permitted to
negotiate the option price without first conducting a
competition with other sources.
If the contractor submits the best offer through the
competition, perhaps then it would be acceptable to use this
price as the option price rather than award a new contract.
By
Eric Ottinger on
Tuesday, May 2, 2000 - 01:28 pm:
Vern,
At the risk of quoting the highly suspect Ask A Professor site--
"The general rule is that an option must be exercised in
accordance with its terms."
I have seen this rule in similar form several times and I would
assume that it is the legal rule. An explicit reopener might be
a way around.
I claim no additional expertise. Linda and I may open our own
thread so that we can have fun speculating.
Regards,
Eric
By
Vern Edwards
on Tuesday, May 2, 2000 - 01:15 pm:
Kennedy:
"[A]sked the contractor if he can do any better on price before
exercising the option" sure sounds like negotiating for a lower
price to me.
Vern
By
Vern Edwards
on Tuesday, May 2, 2000 - 01:12 pm:
Eric:
In any dispute half of the lawyers are wrong and I don't know
which lawyers you're talking about. The lawyers can speak for
themselves, for Peet's sake. What do you say?
Vern
By
Kennedy How on Tuesday,
May 2, 2000 - 12:32 pm:
Vern,
I'm not sure if I'm answering the question either, but I know in
the past (and, maybe even now), our activity has asked the
contractor if he can do any better on his price before
exercising the option. The contractor was under no obligation to
change his price, though there were times that he did. The
contracting officer would then proceeded to make the award,
mainly because we had the need for the item, and it wasn't going
to be cost-effective to recompete (which, by the way, I what I'd
seriously consider in the case you give). I don't ever recall a
time where we'd officially attempt to reopen negotiations on any
FFP contract (you say only fixed priced). The only time we even
thought of doing something like that, we required a reopener
clause.
I'll stop here, because I know I'll get even further
off-topic.....
Kennedy
By
Eric Ottinger on
Tuesday, May 2, 2000 - 12:28 pm:
Vern,
I think the lawyers would say that options must be exercised
exactly in accordance with the language in the contract.
Eric
By
Vern Edwards
on Tuesday, May 2, 2000 - 12:08 pm:
Eric:
Are you saying that negotiating a change to the option price is
a bad idea, or are you saying that the law forbids it? If the
latter, is your "no" answer based on statute, regulation, or
common law?
The issue at this time is not whether renegotiation of option
prices is a good idea, sound policy, or good business practice.
The issue is whether or not it is permitted.
Vern
By
Vern Edwards
on Tuesday, May 2, 2000 - 12:00 pm:
Linda:
The option was evaluated at the time of award.
If you don't mind, let's stick to the question of whether or not
a contracting officer can negotiate with a contractor to reduce
an option price without getting new competition. If we entertain
your question about voluntary price reductions at this point
we'll get irretrievably off track.
Vern
By
Eric Ottinger on
Tuesday, May 2, 2000 - 11:59 am:
I think not.
1) I don’t have the exact words. But the lawyers usually say
that an option has to be exercised precisely consistent with the
terms and conditions of the option in the contract.
2) There are several arrangements which explicitly contemplate
negotiating lower prices than the prices specified in the
schedule. If you could negotiate less without such explicit
language, I would assume that there wouldn’t be a need for it.
3) It would set up a scenario where the customer could routinely
demand price reductions from the contractor as the price of not
having another competition. It would invite an ugly sort of
auctioning which would leave the contractor with very little or
no profit.
I think the third is the most cogent argument. Although it would
be a good thing to do in many situations, it would be bad public
policy overall.
One could probably do a comparison between the option prices and
the market prices, determine that the option prices are too
high, ask the contractor for reduced prices, and do a J&A
stating that there is not enough lead time to do a competition
and maintain continuity, thus only the incumbent can provide
continuity of support.
I think this would be legal as long as it conformed to the truth
of the situation.
Linda,
That's the interesting question. I am not sure that the
unilateral offer would always be truely unilateral. Thats the
problem.
Eric
By
Linda Koone
on Tuesday, May 2, 2000 - 10:54 am:
Vern:
I believe the answer to your question might depend on whether or
not the option was evaluated at the time of the award.
If the option was not evaluated at the time of award, then you
would need to execute a J&A prior to exercising the option. This
J&A would give you the authority to re-negotiate the option
price (in my opinion).
If the option was evaluated at the time of award, then I agree
with the other response provided.
Here's a question, however. Can you accept a voluntary option
price reduction from the contractor? What if the contractor
decides to voluntarily lower its option price under the contract
as an incentive to have the option exercised.
Is there a prohibition against the CO acceptance of the price
reduction and subsequent award of the option?
By
Vern Edwards
on Tuesday, May 2, 2000 - 09:42 am:
Roscoe:
Thanks for the input.
Vern
By Roscoe Price on Tuesday, May
2, 2000 - 09:39 am:
Vern,
The Contracting Officer's discretion can get around all parts of
17.207 and allow him/her to exercise at the option specified
rate by determining that even though it isn't the best price
available, it is the most advantageous method of fulfilling the
need.
But,I think that 17.207(f) implicitly prohibits a contracting
officer from re-negotiating the option prices. 17.207(f) states,
in part, "To satisfy requirements of part 6 regarding full and
open competition, the option must have been evaluated as part of
the initial competition and be exercisable at an amount
specified in or reasonably determinable from the terms of the
basic contract . ."
Once the price has been changed, the option is not that which
was evaluated and the CO can no longer make the determination.
Additionally, if you negotiate option year prices for the sole
purpose of making the prices competitive with other known
sources aren't you circumventing competition to the disadvantage
of the company with the better price?
Roscoe
By
Vern Edwards
on Monday, May 1, 2000 - 02:17 pm:
This question was sent to me via
private e-mail. I'd like to get your opinions.
Background:
An agency awards a one-year, single-award,
competitively-negotiated, fixed-price IDIQ delivery order
contract to Company X for a commercial item. The contract
includes an option to extend the contract for an additional
year.
Prior to exercising the option the contracting officer learns
that another agency has awarded a contract for the same kind of
item to Company Y at a lower price. Thus, the contracting
officer no longer thinks that Company X's price for the item is
reasonable.
Question:
Can the contracting officer negotiate with Company X to reduce
its price for the option year without conducting a new
competition? |