By
Linda Koone
on Thursday, May 25, 2000 - 08:40 am:
Linda:
Thanks for sharing the details that led to the original
discussion on re-negotiating options.
The pressure from competition between agencies for sales can
really test the integrity of the contracting offices involved.
Presuming both agencies are bound by the same regulations, if
one agency can re-negotiate an option, then logically, the
second agency should be able to do the same.
The integrity issues surface when the first agency's actions
can't be supported by regulation.
Very interesting. . . I hope you find the answer that you need.
By
Joel Hoffman
on Thursday, May 25, 2000 - 07:23 am:
In my last post, I meant to
refer to a volunteered price "reduction", not a volunteered
price "increase" . To clarify, I was referring to Linda Koone,
not Linda Magazu.
I thought that Linda K. split this thread off an earlier one.
The other thread had focused on discussion concerning other than
the idea of a "voluntary" price reduction offered on an
unexercised option.
As it turns out the case Vern alluded to, at the beginning of
the other, original thread, never dealt with a purely voluntary
act by a contractor.
Linda Magazu and Vern, your case wouldn't fit within the
criteria I discussed in my analysis in this thread,so my
comments aren't germaine to your frame of reference. Happy
Sails!
By Joel Hoffman on Thursday, May
25, 2000 - 06:56 am:
This isn't a case concerning a
"voluntary price increase." I thought Linda originally split
this thread off the earlier one specifically to distinguish
between a volunteered price increase and a pressured or
requested price reduction. If that isn't the case, I apologize.
My comments only apply to volunteered price reductions.
Happy Sails!
By
Linda Magazu on
Wednesday, May 24, 2000 - 07:53 am:
What a great exchange of
ideas/opinions and thankyou to each and every one of you who
participated (constructively that is) in this discussion. Mr.
Hoffman, you may need to go back to another forum topic "Can a
contracting officer renegotiate option prices without a new
competition" to understand where this all began. It's not as
simple as you make it out to be. Linda K, the original question
did not get lost by your posing another question, it just took a
slightly different direction which also relates to the original
topic.
I am the contracting officer who first went to Vern Edwards
because I value his opinions and knowledge of contracting
issues. Vern decided to post my question to generate some
discussion. Here's some background as to what kicked this off:
The contracts are for supplies & firm fixed price indefinite
quantity types. You have two agencies (1 DoD/1 non-DoD) buying
like requirements where an agreement required both agencies to
combine their buying power when entering into contractual
arrangements. Some of the current initiatives overlap each other
(i.e, original requirement was not joint and the contract is
still active) so the other agency may go out on their own to
acquire the same item in that instance.
The options involved are to extend the term of the contract not
to purchase additional quantities (i.e., base year plus four
additional one-year option periods). The option prices are
evaluated prior to award and determined to be fair and
reasonable. For the sake of example two offerors compete, one
has an on-going contract with the one agency (non-DoD) but loses
to the other (DoD). The contract with the non-DoD agency is
coming up for renewal, who is aware of the price awarded by the
DoD agency and pulls in their contractor and demands a lower
price than what the DoD agency received from the competitor or
they won't exercise the option (bargaining).
I had wondered if it was a violation of CICA to renegotiate a
price with a contractor after the ground rules (low price) were
set forth during the initial acquisition. The other agency has
put pressure on the other to reevaluate the situation and
reconsider whether to exercise the option when a lower price is
available, but it's how that price was obtained (back to the
negotiation table) that bothers me. DoD facilities are under
tight budget constraints so why not just go with the other
agency if the price is lower (we lose a customer and sales). All
of you gave me some very interesting ideas and I'm going to look
at the Magnavox case and especially into Exception 7 since
according to the figures presented, DoD is the highest user.
I hope you continue to keep the discussions through ARNET going,
they really do help stimulate the thought process. Pay no
attention to worthless comments such as "Joe Blow's". Eric you
responded to that reply very eloquently but I think "Joe" just
needed to vent. I'm sure he learned something from the
discussion as well, he just won't admit it! Thanks again, I
value your input.
By Joe Blow on Thursday, May 11,
2000 - 07:31 pm:
Mr. Hoffman,
You said it, brother! No wonder the government can't get
anything done.
By
joel hoffman
on Thursday, May 11, 2000 - 07:06 pm:
I'm sorry, folks. I can't
believe how y'all have taken what does not appear to be overly
complicated and convoluted it into an in-depth analysis of
exceptions to competition.
Is there guidance out there other than a GAO admonishment to
compete where it appears that the Government can be better
served by competition?
Are you saying that procurement professionals, supplemented by
subject matter experts can't conduct some market analysis,
combined with analysis of cost to compete and delivery
requirements, to determine whether or not the public would best
be served by competition?
Is your frame of reference supply contracts for something that
has widely varying prices on the market? Maybe I missed
something. But you seemed to have dismissed any room for
discetionary judgement and automatically assumed that you must
justify not publicly competing against a voluntary price
reduction offer. Happy Sails! Joel
By
Kennedy How on
Thursday, May 11, 2000 - 12:40 pm:
Gee, I was off sick for a couple
days since I last posted, and look what happens! What a good
discussion!
I think the reason why we're all discussing this subject back
and forth is that we all, deep down, want to accept what, to
everybody else, is a good sense decision. Namely, there is a
possibility that we can get something for a lower price, and we
desperately want to take advantage of that, because we're
entrusted with the public funds. But yet, we hesitate, because
we're afraid we'd violate some rule or regulation. And, absent
clear permission, we won't do that. And, when it gets out that
we didn't take advantage of this, we get pilloried, from the
press all the way to Congress, who put us in this position in
the first place.
Anyway, back to the topic: For an option, I would have problems
using Exception 1, only one source, especially if the original
contract was full and open competition. As our activity is
conservative by nature (management), we'd not be able to really
tailor this exception, to something like "Only this source can
give us this price". In my example, the price reduction is over
the entire base + option quantity. Nobody else can do this
except for the current contractor. I could recompete, but I'd
only recompete the option quantity, and I seriously doubt I
could get a price equal or better than the current contractor's
price (after reduction), for the reasons cited.
Exception 7, Public Interest, appears to me to be more
appropriate. If I'm entrusted with the public funds, and the
contractor is volunteering something in the public's favor, I
don't think I'd be overly happy if I couldn't see my way clear
to accept on behalf of the public.
We're supposed to make good BUSINESS decisions. If the decision
to be made doesn't fit under any of the other 6 Exceptions, then
the catch-all is the last resort; it gets us past that hurdle.
(oops, real work is interrupting!)
Kennedy
By
bob antonio on
Wednesday, May 10, 2000 - 01:44 pm:
Vern:
Here is the answer to who used Exception 7, 688 times during FY
1999.
FY 1999
DoD..........491
NASA.........108
DOE...........27
USDA..........25
DOI...........23
DVA...........10
DOT............2
HHS............1
DOC............1
By
Linda Koone
on Wednesday, May 10, 2000 - 01:06 pm:
Vern:
That doesn't surprise me, at least not from our perspective.
But remember, exception 1 applies for DoD, NASA and the Coast
Guard when the requirement can be satisfied by one or a limited
number of sources.
It's not unusual for us to have competition and use exception 1.
It's just limited competition.
I'll watch for more information from you.
By
Vern Edwards
on Wednesday, May 10, 2000 - 12:51 pm:
Linda:
At this time I don't know who is using the exception. I have
ordered a report and will let you know the answer when I get it,
probably next week. DOE is probably one of the sources, but it
would not account for 688 actions.
Another interesting statistic is that about 22 percent of
reported FY99 obligations were procured without any
competition under Exception 1 (only one source).
By
bob antonio on
Wednesday, May 10, 2000 - 12:40 pm:
Linda:
At most, there are a handful of management and operating
contracts ending each year. I do not think they are included in
the FPDS in regard to CICA. If they are, I would assume that
they are classified as one of the first 6 exceptions. However,
the Secretary of Energy does approve every sole-source
management and operating contract procurement. The signature may
not be on the J&A itself but it is in the package.
By
Linda Koone
on Wednesday, May 10, 2000 - 12:00 pm:
Vern:
They are interesting (and surprising) statistics.
Are the exception 7 contracts coming from DOE as Bob suggests?
If not, what agency is using this exception?
By
bob antonio on
Wednesday, May 10, 2000 - 08:04 am:
Vern:
Several years ago, DOE changed its philosophy for competing its
facility management contracts generally referred to as managment
and operating contracts. It now uses a combination of the DOE
and CICA process. However, these are DEAR contracts and not FAR
contracts. Authority for them is included in DOE's authorizing
legislation and FAR 17.6. Below is the excerpt from the DEAR.
If I remember correctly, the DOE J&A is processed according to
DOE policy but looks much like the FAR J&A. Regardless of the
exception selected to support a sole-source procurement or
extension, the Secretary of Energy will sign the J&A. The data
on obligations for these contracts makes its way to the FPDS but
I do not know how or if the use of exceptions is recorded since
they are not really CICA contracts. These contracts, under their
various monickers, receive annual obligations in the $13 billion
range. A new 5-year procurement or extension could be valued
from about $1 to $6 billion. Some are smaller. Since they are
all signed by the Secretary, they could be considered to be
exception 7 J&As regardless of any other designation.
"917.602 Policy.
(a) It is the policy of the Department of Energy to provide for
full and open competition in the award of management and
operating contracts, including performance-based management
contracts.
(b) A management and operating contract may be awarded or
extended at the completion of its term without providing for
full and open competition only when such award or extension is
justified under one of the statutory authorities identified in
FAR 6.302 and only when authorized by the Head of the Agency.
Documentation and processing requirements for justifications for
the use of other that full and open competition shall be
accomplished in accordance with internal agency procedures."
By
Vern Edwards
on Tuesday, May 9, 2000 - 07:47 pm:
Bob and Linda:
Some interesting statistics:
According to FPDS, in FY99 agencies used the public interest
exception to CICA (Exception 7) 688 times for procurement
actions worth $2.9 billion. Agencies used the only one source
exception (Exception 1) 46,363 times for actions worth $39.8
billion.
The average dollar value of an Exception 7 procurement was
$4,226,890, while the average dollar value of an Exception 1
procurement was only $859,315.
Exception 7 ranked fifth in usage among the seven CICA
exceptions when ranked by dollars obligated, ahead of the
national security (Exception 6) and international agreement
(Exception 4) exceptions; it ranked sixth when measured by
actions, ahead of only the international agreement exception.
The second most frequently-used exception was authorized or
required by statute (Exception 5), which was used 39,005 times
for actions worth $8.3 billion, which averaged $212,648.
By
bob antonio on
Tuesday, May 9, 2000 - 03:22 pm:
Linda:
When I taught second-guessers (auditors in this case), I always
talked about exception 7 a bit. It is the only exception that
provides the opportunity for a politician to stick his/her neck
out and then squeal on himself/herself to other politicians.
That is at least one reason it is rarely used.
In the 1980s, I remember doing an extensive legislative history
of CICA. The first 6 exceptions come right out of the
Comptroller General's bid protest playbook. You should find
congressional reports stating that. However, the reason for
exception 7 is vague, if not blank. I remember trying to find a
clear explanation for it and I could not. If I remember
correctly, exception 7 was added in a House and Senate
conference and little was noted in the conference report.
However, you can imagine exception 7's birth in a give-and-take
environment. It probably went something like this.
Do the first 6 exceptions cover everything? I don't know. Well,
what if we missed something? We need a 7th as a catch-all. What
do we call it? How about "public exigency." (I believe that was
an exception to formal advertising prior to CICA) What does
"public exigency" mean? I don't know. How about "public
interest?" What does that mean? I don't know but it sounds
better. If it is easy to use, the contracting officers will
start using that one instead of "only one." ("only one" was the
most-used exception to formal advertising.) If the head of the
agency has to sign it, it will not be abused. Make sure the
authority cannot be delegated. Good idea. How about a special
reporting provision when it is used. Good idea. There you have
it. It is designed to be used; designed not to be abused; and
almost impossible to use. A mongrel's mongrel.
I will respond to your other questions later.
By
Linda Koone
on Tuesday, May 9, 2000 - 02:11 pm:
Enjoyable comments from all! I'd
like to clarify that my scenario is purely hypothetical, but at
the same, well within the realm of possibility.
Some responses to some specific questions:
Vern: Couldn't I consider exercising the option to be a form of
consideration? I have other options - I'm not obligated to use
the option to fulfill my requirement using the option.
As for stepladder pricing based on quantities and periods of
time, we sometimes do include these. Often the responses we get
to the stepladders are so crazy that you'd rather pull your hair
out than weed through the mess! Some folks just don't get it.
Others don't want to put the effort into various pricing
schemes, knowing that we are as likely to issue a partial (or
full) termination as we are to exercise the option. But, in
theory, I agree that this is a good idea.
Bob: You're sounding like an auditor! Actually you've made good
points.
I'll give you the benefit of the doubt that your suggestion to
use exception 7 was meant to make us all refresh our memory on
what this exception is and who approves it. (Wouldn't it be fun
to explain to the Secretary why we're taking up his time to
pursue a new procurement instead of using the option simply
because the contractor wants to give us a better price for the
option quantity?)
I take it you would not endorse using the option, even if
supported by a J&A, to procure the new requirement for 97 units.
I still believe that an argument could be made that the J&A
gives you the authority to negotiate, whether it be the option
price or a new procurement. Using the option relieves the need
for synopsis providing that the synopsis for the original
solicitation included the option.
Also, I believe an argument could be made that testing the
market would be unnecessary since the time between the award of
the contract and the exercise of the option was short enough to
determine that the option price is the lowest price obtainable
or the more advantageous offer. Do you agree?
Eric: Good analysis of "Joe's" comments!
(I guess it's a good idea to permit people to participate in
this forum anonymously, but I have to admit, it's a bit like
receiving an unsigned letter--somewhat annoying)
But "Joe" is right. It really shouldn't be that difficult to
accept a reduced price!
By
Eric Ottinger on
Tuesday, May 9, 2000 - 01:13 pm:
Joe,
I'm not sure how you got into this highly select, immensely well
trained, extremely intellectual discussion group.
However-- Stop by often. We need you.
Thanks,
Eric
By Joe Blow on Tuesday, May 9,
2000 - 01:05 pm:
Oh, for pity's sake! Linda, just
take the *&@!!! price reduction, mod the K, and get on with
life. I bet you got hundreds of PRs to process. By the time you
go through all those exception and memos you'll have spent the
money you save. What are they gonna do? Shoot you for saving
money?
What's the matter with you people?
By
bob antonio on
Tuesday, May 9, 2000 - 12:04 pm:
Eric:
Thank you. I think you see what I see in exception 1. There is
some room to work.
In the very remote event that I may have to look at this
contract sometime in the future, I am necessarily vague.
By
Eric Ottinger on
Tuesday, May 9, 2000 - 11:32 am:
Bob,
Excellent analysis.
I would go straight to Exception 1. The only thing that I would
consider viable would be: “(ii) Supplies may be deemed to be
available only from the original source in the case of a
follow-on contract for the continued development or production
of a major system or highly specialized equipment, including
major components thereof, when it is likely that award to any
other source would result in (A) substantial duplication of cost
to the Government that is not expected to be recovered through
competition, or (B) unacceptable delays in fulfilling the
agency's requirements. (See 10 U.S.C. 2304(d)(1)(B) or 41 U.S.C.
253 (d)(1)(B).)”
To make a dumb point, this will only work if it is the truth. In
Linda’s situation where the contractor has the production line
set up and she is adding 97 units to the production run, it is
probable that award to anyone else would result in a very
substantial “duplication of costs.”
Eric
By
bob antonio on
Tuesday, May 9, 2000 - 08:53 am:
The Magnavox case is 1988.
By
bob antonio on
Tuesday, May 9, 2000 - 08:47 am:
Linda:
Kennedy, this should answer your question too. If I came acrosss
your example after it happened, this is what I would do. My
viewpoint is to see that fairness and integrity are maintained
in the procurement process. A bid protest may result in the same
or a different conclusion.
In your option, you have an agreed upon option quantity and
price. The option terms were part of the original competition.
There are several scenarios that I can think of now.
You have the requirement for 97 items and your option allows you
to acquire 100 items at the agreed upon price and quantity. You
believe you can obtain a better price than the option price from
the option contractor. You now go through the process of
exercising the option. There are clear procedures you must
follow. Part of those is to check to see if the market
conditions have changed. I would look in your contract file
documentation to see how you checked the market. I would check
to see if you contacted the competitors to the original
competition. If you did and it was for clarification that the
market conditions are the same, I would see no problem. I am
trying to determine if the original competition remains intact.
From the losing offerors on the original procurement, you were
told that market conditions remain the same. However, the option
contractor tells you that the additional quantity will affect
its costs and your price. You ask if they will be submitting a
new offer to reflect the changed conditions. They say yes and
they submit a new offer for the 97 units. In my view, the option
is no longer an issue to deal with for the 97 units. You have a
new procurement.
You have a choice--a new competitive procurement or a
sole-source negotiation. You go sole sole-source and use
exception 7. Somehow you get the signature you need and the J&A
is completed correctly with the exact conditions noted. The J&A
shows that this price change was unsolicited and occurred during
your informal analysis of the market in anticipation of
exercising the option. The original competitors to the
competition were contacted and they said there were no changes.
I read Magnavox Electronic Systems Company, B-231795, November
2, 1998. Your price analysis for the item is flawless. You award
the 97 items to the option contractor and modify the contract
for administrative convenience. The option is still intact and
available for future use. What am I going to do with a properly
signed J&A for an exception 7 under conditions that make sense?
I walk away. However, I take note.
OK, the above remains the same but you cannot get the signature
for an exception 7. None of the other exceptions fit quite
right. You go with exception 1. In the J&A, you make a good
argument why its use makes sense. It is a stretch but a good
story. The required synopsis was published and there was no
response. You now modify the contract for the 97 items for
administrative convenience and the option is still available for
the future. Now I look at your exception 1 and I realize it does
not fit perfectly. Your J&A states that you contacted the
original competitors and their situation has not changed. I read
Magnavox Electronic Systems Company, B-231795, November 2, 1998.
Your price anlaysis is flawless. What have you left me? An
opportunity to nit-pic your use of Exception 1. I talk with you
for a few moments to make sure that I understand exactly what
happened. I tell you my concerns with exception 1 but I consider
your actions to be reasonable and I walk away.
However, I review more contracts to see if this situation
occurrs repeatedly. If it does, I look for problems with your
activity's use of options or something else that is related to
the conditions.
On the other hand, if you start negotiating with the option
contractor before you go through the exercise route I may reach
a different conclusion.
I think this covers all the issues.
By
Vern Edwards
on Monday, May 8, 2000 - 04:40 pm:
Linda:
I understand now.
A couple of thoughts:
First, a voluntary price reduction raises the issue of
consideration to make the reduction contractually binding. What
would you give the contractor to seal the bargain? You cannot
give him an additional quantity, since an increase in quantity
under a supply contract is generally considered a change in
scope.
Second, I don't know what I would do in your most recent
scenario, but I know what I would do the next time I negotiated
such a contract. I would negotiate step reductions in unit
prices for options exercised before a specified date or number
of days after contract award.
By
Eric Ottinger on
Monday, May 8, 2000 - 03:51 pm:
Linda,
Actually, I like Vern's idea better. If you only gave up one
priced option, it might be the way to go. However, if you gave
up three or four priced options, it wouldn't be such a good
idea.
Re the J&A, if you have a requirement with a short fuse, the
other offerors may not be able to deliver as quickly as you need
the units, or come anywhere near the price with a short
production run.
Re Varian, although my logic sounded good to me, it sounded a
bit like the logic that GAO rejected in Varian.
For whatever it is worth, I think these were step ladder pricing
competitions. The low cost bidder at one quantity might be the
high cost bidder at a different quantity. I think the GAO was
particularly irate because the agency was playing stupid when it
had current prices in hand from a very recent competition.
Eric
By
Linda Koone
on Monday, May 8, 2000 - 03:29 pm:
Eric: What authority would you
use on the J&A? Also, I'm not sure I follow your reference to
Varian. As I recall, that involved an offer of a lower price
from a company that was not the successful offeror.
Vern: We're still operating in the FFP, system stock
replenishment mode in many cases. We include options in our
contracts to reduce leadtimes in case other requirements emerge
within the option period. But we can't predict with any degree
of certainty whether another requirement will emerge. We've had
more than a few options expire without ever being exercised.
In the scenario that I painted, the 97 units would represent the
option quantity, not be in addition to it.
By
Vern Edwards
on Monday, May 8, 2000 - 02:57 pm:
Linda:
Perhaps the right thing to do would be to obtain new competition
for the option quantity and the additional 97 units instead of
exercising the option or adding the 97 units to the contract.
Increasing the quantity under the contract would be an increase
in the scope of the contract that would require new competition.
On what basis would you justify a sole source procurement for
the 97 units?
Vern
By
Eric Ottinger on
Monday, May 8, 2000 - 02:47 pm:
Linda,
I'm thinking that I might distinguish the "new" quantity from
the "option" quantity, assuming that the agency will still need
the option quantity after 180 days. I would write a J&A for the
new quantity and negotiate a lower price based on the extended
production run.
However, I should note that this sounds a whole lot like Varian
or Magnavox. The GAO might not be so flexible.
It was my observation when I worked for the Navy that if I
didn't get the requirement negotiated very quickly, the
quantities would change and I would have to redo all of the
paperwork. Your scenario sounds very credible to me.
The Navy had a very firm policy against "unpriced" options, as
does the FAR. I assume that you have ceiling prices for the
options.
Good discussion.
Eric
By
Linda Koone
on Monday, May 8, 2000 - 02:23 pm:
Eric:
I understand what you're saying and presume that your comments
apply to situations when you've evaluated the option prior to
award. And I agree that we shouldn't shake hands with our
fingers crossed behind our back.
Just curious, however. . .what would you say to this scenario--
Let's say I awarded a FFP contract for 100 widgets to the
company who submitted the lowest priced technically acceptable
offer. Delivery will be made in 270 days. The contract has an
option that may be exercised up to 100% within 180 days. Thirty
days after the award, I get a new requirement for 97 additional
widgets. Price history indicates that pricing for this widget is
quantity sensitive, and I'm pretty confident that doubling the
quantity would have a substantial effect on price. If I compete
the new requirement, I'll miss the opportunity to tie the two
production quantities together. Nobody else is in production, so
competitive pricing will probably come in around the current
option price.
Would your advice be to bite the bullet and award at the option
price-- or would you inquire as to whether doubling the quantity
so close to the award date would result in a better option
price?
Joel:
I sole source negotiated procurements, we rarely negotiate the
option price at the time of award-it's often hard enough to
reach agreement on a definite requirement. The uncertainties
(when or if another requirement will arise and for what
quantity)surrounding the option create too much work. It's
easier to negotiate the option when the requirement arises. The
J&A already covers the option quantity for purposes of
negotiation authority.
By
Joel Hoffman
on Friday, May 5, 2000 - 04:19 pm:
The scenario, originally
presented, was a Contractor initiating a purely voluntary price
reduction. The question was, "Can the Government accept a
voluntary price reduction for an option offered by the
Contractor?"
In my opinion, it depends upon the circumstances. Assuming that
the reason for the revised offer is that the Government won't
otherwise exercise its unilateral right to accept or reject the
option, one must look at the Government's reasoning.
This also assumes that the option was initially evaluated in the
overall selection process for award of the contract. I honestly
never dealt with any other evaluation scheme because I think its
better to include the option prices in the overall price
evaluation. There may be circumstances where that is
appropriate.
This also assumes that the option acceptance period is still
open.
In the situation where the Government doesn't have enough funds
to award at the original price, the KO needs to evaluate whether
the Government would be better served by a new, separate
solicitation. Factors to consider are such things as the type of
procurement (supply, services, construction, simple or complex,
simplified or complex acquisition methods) trade- offs between
cost to recompete, time available to meet the Government's
reasonable needs, probable market price obtained by re-competing
and the Contractor's PURELY VOLUNTARY (i.e., not suggested or
requested) price reduction. I ought to be be fairly consistent
with my original pricing basis for award (e.g., was lowest price
the primary consideration or where there other trade-offs).
If such a careful analysis - under the appropriate circumstances
- concludes that it is in the Government's best interests, I'd
probably accept the offer. Nothing in FAR prohibits it; the
language in FAR 52.215-1 states that the Government can accept a
better offer from the otherwise successful offeror, implying
that it is good public policy; I believe I would have satisfied
the GAO in its admonition concerning looking out for the
Government's overall best interest.
Now, if the reason for not exercising the option is that I
originally considered the option price to be unreasonable, I'd
have to take much more into consideration. Depends on the
original basis of award - Trade-off or lowest overall price,
price vs. quality considerations, whether or not the sucessful
contractor's price for the option was the lowest, what the
current market price is, etc. Get's a bit more complicated.
More complicated yet if the original price was reasonable but in
the ensuing period (option price is still valid) the market is
significantly dropping, etc.......
Happy Sails! Joel
By
Kennedy How on Friday,
May 5, 2000 - 10:19 am:
Linda,
I kinda added to the voluntary reduction issue as well, so it's
not all your fault!
Your comment regarding an audit finding is a good one, and I
don't doubt that something like that happened to somebody at
least once over the years. We usually get either activity audit,
or AAA. Sometimes, it's Materiel Command that gets it started,
but just for it's MSCs. It's kind of interesting, because if
it's determined that the informal inquiry is considered to be
"renegotiation", then an audit finding telling us to do that may
be contrary to FAR/FAR Supplement. This kind of situation would
beg for a Bob Antonio point of view.
As far as "negotiations" are concerned, I would say that the
simple inquiry wouldn't fall into that category; I would say
it's a part of the informal analysis. This is a personal view,
because we aren't formally declaring we're doing something. The
option exercise is Unilateral, we're either going to do it, or
we're not going to do it. Plus, I think there is enough guidance
out there which sets out just what is considered "negotiation"
(no specifics, just a feeling based on experience). I think
because it has to do with price, the contracting community tends
to be conservative in their thinking, because for so long, price
was the driving factor, and we went through (and still do, I
guess), a lot of grief when doing something that has to do with
price.
At any rate, as long as we ask, but accept the reply of the
contractor at face value (without further discussions), I don't
think it's negotiating.
If somebody said that if you're going to do this, then we should
recompete, I can make a solid case that this is a total waste of
time and money, and helps nobody anywhere, and you're not going
to get the result you think you're going to get.
Kennedy
By
Eric Ottinger on
Thursday, May 4, 2000 - 05:48 pm:
Linda,
I guess I would say that there is a very fundamental principle
involved. Both sides negotiate as hard as they can for the best
deal they can get. At some point there is a handshake. After the
handshake there should be no more negotiation. The contractor
may lose money or the contractor may make a bit of a windfall
profit. This doesn’t mean the deal was unfair. It just means
that neither party has 20/20 foresight.
We can’t do business efficiently if we are constantly going back
reopening our negotiations looking for a better price. If market
conditions have changed so much that it makes more sense to do
another competition, we should do so. Otherwise, we should
exercise the option in accordance with its terms.
The exception would be certain markets where the technology or
other conditions change radically or rapidly. In these instances
we need some flexibility. But these mechanisms are intended to
adapt the original handshake deal to rapidly changing
conditions.
Now, hypothetically, there may be cases where the contractor
finds that he is making so much profit that it would really be
prudent to give some of it back. Maybe the contractor values the
customer’s long term goodwill more than he values the short term
profits. Maybe he wants to avoid bad publicity. Of course he
wants to give the excess profits back without reopening
competition.
That’s an interesting question.
Eric
By
Linda Koone
on Wednesday, May 3, 2000 - 01:30 pm:
This is an attempt to move the
discussion on 'voluntary' contractor option pricing reductions
to a new thread (if there's any more to be said). Vern's concern
was valid. His original question is getting lost with the
discussion that I created with my question "Can you accept a
voluntary contractor option price reduction?" My apologies,
again.
I agree with Eric on his revised sentence:
'Voluntary offers to discount the price would be nice, but I
question whether such would ALWAYS be voluntary in any way but
the form.'
I would prdict that 'Voluntary' reductions are not as typical as
the scenario described by Kennedy, in which the CO contacts the
contractor prior to exercising the option to see if a better
price is available for the option quantity. Like Kennedy, we
primarily award FFP supply contracts; however, most of ours are
sole source/limited competitive. I think the practice is similar
here in that the CO often 'inquires' about the option price
before exercising it (i.e., informal analysis). And I tend to
believe that this practice may have started as a result of an
audit or some other report that claimed we should be getting
better pricing on follow-on option quantities due to
efficiencies in production and possible reduced material
costs/unit. Does anybody remember a report of this nature?
I also agree with Joel's point that you are permitted to accept
a more favorable modification to an otherwise successful offer
prior to award, so, why not after award?
In my mind, a CO would be hard pressed to find a reason not to
accept a purely voluntary option price reduction, whether the
contract was awarded under competitive or non-competitive
conditions. I suppose the difficulty is in defining the term
negotiation. Is a simple inquiry considered a negotiation?
|