By
Jerry Zaffos on
Tuesday, February 1, 2000 - 12:22 pm:
Laurel:
I agree with everything that has been said. But I have a
question for you: Have you asked the contractor for his/her
explanation? The two of you might find that this problem is
simply resolved if you talk it over instead of drawing battle
lines.
By
joel hoffman
on Wednesday, January 12, 2000 - 10:50 pm:
I don't know if you have a
liquidated damages clause or if you have a performance bond
requirement for your task order.
Assuming that you do, you not only have the right, you have the
responsibility to protect both the Government's and the Surety's
rights in the event of a default by with holding retainage from
a Contractor in danger of default. If the Contractor is beyond
the required completion date (and not entitled to a time
extension) you'd best strongly consider retainage from progress
payment earnings, equivalent to the accrued liquidated damages -
and take swift action to issue a show cause letter. You need to
contact your legal counsel, ASAP. Retainage protects the
Surety's interest in the event of default. There are several
management actions you must take to properly terminate a
Contractor in default - so as not to overpay. As the Surety will
be left holding the bag, you have a legal duty to preserve funds
from the contract balance to be made available to the Surety to
pay any assessed L.D.'s and to complete outstanding task order
work.
The premature pay estimate you refer to might be an attempt by
the Contractor to get his funds before you or the Bonding
Company can preserve them. Happy Sails! Joel
By Tom Woods on Wednesday,
January 12, 2000 - 02:18 pm:
One other thought related to
your payment and possible T for D concerns: In addition to
Vern's advice on obtaining clarification of your payment
responsibilities, I would add that it is imperative to do your
homework before you withhold a dime from the contractor.
When you fail to pay the contractor for work performed (which is
what a progress payment is), you are either a) breaching your
contract, or b) asserting an affirmative claim against the
contractor based on some theory of entitlement under your
contract. If you are terminating for default, and you are
concerned about recouping either liquidated damages (if any) or
reprocurement costs, you need to quantify and forecast those
damages/costs to make sure that the amount you withhold from the
contractor is reasonable.
By
joel hoffman on Saturday, January 8, 2000 - 04:26 pm:
Laurel,
What are you referring to by "30 days" vs "14 days"? That sounds
like the Prompt Payment Clause requirement for payment due date
after receipt of the invoice. The separate Payments Clause uses
the term "monthly" (not a specific number of days like 30 or
14),unless the Contracting Officer agrees to more frequent
progress payments.
Once a month is the norm for construction progress payments. Our
Resident Engineers always establish a cut-off date and standard
date for invoice submission with the Contractor during the post
award (pre-construction) conference.
It is good practice to ask the Contractor to submit a draft
invoice to review, markup and return in time for him to formally
submit by the normal invoice date.
Happy Sails! Joel
By
Vern Edwards
on Saturday, January 8, 2000 - 02:02 pm:
Laurel:
I think that most people would side with you and interpret
"monthly" to mean at intervals of 30 days, i.e., 30 days apart.
But I suppose that one could argue that "monthly" means once
within each month, so that an invoice could be submitted on
December 21st and another on January 6th.
But remember that construction progress payments are made "as
the work proceeds" and are based on the contracting officer's
estimates of work accomplished, i.e., net percentage of work
completed acceptably since the previous invoice period. What
period of work does the Dec 21st invoice cover? The Jan 6th
invoice? Did the contractor make progress during those periods?
How much? Is the invoice consistent with the estimate of
progress? Is the contractor entitled to a progress payment?
Is it possible that the Dec 21 invoice covers work done in
November and the Jan 6 invoice covers work done in December?
Perhaps the contractor was late submitting the invoice for
November work, which would explain why the two invoices are so
close together.
Finally, payment procedures are usually discussed during a
preperformance conference, which should have been documented in
the contract file. Was there a preperformance conference and is
there any documentation of a discussion of payment procedures?
What did the CO tell the contractor about invoicing?
Unless the contractor was late submitting its December invoice,
which could explain why the Jan invoice followed the Dec invoice
so closely, the fact that your contractor is invoicing in this
way could indicate that it has cash flow problems. This is
worrisome since you say that it is behind schedule and that you
are contemplating T for D. Have you asked the contractor why it
is invoicing again so soon?
Vern
By Laurel Carelli on Friday,
January 7, 2000 - 01:48 pm:
Hello Vern,
Yes, this project is an individual task order. Each order is
paid for separately by the office who has issued it, on a
monthly basis. The only exception is when the duration of the
contract is less than 30 days, the contractor receives one
payment at the completion of the work.
FAR 52.232-5 is included in the basic contract, and all clauses
in the basic contract apply to each order.
My question is, I just processed an invoice a couple days ago
for this contractor on this task order, and yesterday received
another invoice. It has only been about 2 weeks (15 days I
think) since the receipt of the other invoice. Normally, a month
elapses between invoices, but in this case it hasn't. The clause
just basically states that payments will be made monthly, which
I would take to mean, about 30 days apart. I hope this makes it
clearer. Thanks!
By
Vern Edwards
on Friday, January 7, 2000 - 12:04 pm:
Laurel:
You say that you are having a problem with a "construction"
contractor and that the contract is IDIQ, so I assume that you
are issuing task orders for individual construction projects. Is
that right?
If that's right, does the contract require that the contractor
submit a single, consolidated monthly invoice for all work done
under the contract, or does it allow the contractor to submit a
separate monthly invoice for each task order?
What payment clause do you have in the contract? Is it FAR
52.232-5, Payments under Fixed-Price Construction Contracts,
(MAY 1997)? If so, I think that it could be interpreted to apply
to each individual task order. Does the contract contain a
supplemental clause that requires the contractor to consolidate
its task order invoices into one monthly submission?
I urge you obtain clarification about the proper interpretation
of the contract. Failure to pay a contractor in accordance with
the terms of the contract is a material breach and could have
serious consequences for your agency.
By Laurel on Friday, January 7,
2000 - 09:56 am:
I am currently involved with a
construction contractor who is driving me crazy. Here is my
latest problem with him, concerning payments. The contract that
I am referring to is one of a set of multiple-award, IDIQ
Contracts. There is supplement to the payment provisions that
these are 30 day payments rather than 14 day payments. I don't
know why this is exactly, as I didn't write the master contract.
The payment clauses in the
contract continuously refer to monthly invoices, monthly payment
meetings, etc. etc. I recently processed a payment for this
contractor that was received in this office on December 21. I
received another invoice January 6 for payment. Its my opinion
that the intent of these payment clauses is to pay a contractor
only once in every 30 day (monthly period), however, I'm not
sure about this as the clauses do not seem to get that specific.
Technically, this is a new month, January, and the last payment
was in December. But it has only been about two weeks since the
contractor sent in his last invoice for payment. Does anyone
have a spin on this, or even better, point me in the right
direction where I can see something in the FAR that addresses
this?
I do not want to process this payment right now. This contractor
is way behind, should have been completed actually, and with a T
for D possibly looming, I don't want to pay any more than I have
to.
|