By
Steve Cohen on Tuesday, February 15, 2000 - 12:10 pm:
Joel, I would agree it can be an
item of negotiation. Whatever is reached as the agreement should
be stipulated in the subsequent contract. Both customer and
contractor should know before the contract is signed what will
be expected and what are the deliverables. The contract should
be able to be read without such a substantial issue being in
question. In this case there definitely seems to be a breakdown
in the communication process.
The contract in question, being some kind of Requirements or
Indefinite Delivery contract, I am guessing already has labor
categories and rates so the negotiation probably consists of
reaching an agreement on labor mix and labor hours plus
materials. The government, at that point, has the obligation of
telling the contractor what materials it will negotiate and what
materials it won't. If it pays for materials it expects to be
delivered, other than in the end product, it should establish a
CLIN
and ensure the proper clauses are included. If the basic
contract doesn't provide for delivery of CAP it could be argued
it is outside the scope. Especially on this type of contract
where the orders are suppose to be issued unilaterally by the
customer with the basic contract controlling the scope.
I do believe it unreasonable of the contractor to think he could
continue to propose the same tools
over and over again representing them as a new purchase in their
cost proposal. What can be
done is handle their cost as a capital depreciation indirect
cost to an overhead accout which is perfectly acceptable. This
could have easily been explained to him by the contracting
officer during their fact-finding or negotiation. It seems
rather odd such a basic issue continued to fester through
multiple orders.
It is difficult to fathom that when a five year business
relationship is entered into that communication between the
parties is so terrible. You find yourself in Option Year 2 and
communications have totally broken down. When you have a small
business in an 8(a) program I would expect the government to
facilitate and educate rather than become an obstacle to better
understanding. Let us all hope this isn't the typical business
relationship between government contracting officers and their
contractor
business partners. Maybe it is....what do you think?
Steve
By
joel hoffman on Monday, February 14, 2000 - 04:01 pm:
Steve Cohen,
As I stated in my January 13 post, I believe the issue is more
related to the reasonableness of the proposed cost for formwork
and other supplies. I believe that "1 time use" of forms, saw
blades, etc. are being proposed for each wall and that the
Government negotiator disagrees - feels that they can be
re-used.
However, if the Contractor insists on the Government paying for
100% new forms and supplies for each wall, with zero salvage
value to the Contractor, I see nothing wrong with the negotiator
insisting that the Contractor agree to turn over all the scrap
forms and supplies to the Government. Shouldn't be a problem if
this is the truth.
FYI - When I worked for the COE in Saudi Arabia, back in the
80's, I required contractors to turn in a sand wash plant as
well as pre-cast paver molds, after discovering that the
Government paid full purchase price with zero salvage value for
this construction equipment in a couple of changes. It wasn't an
unreasonable request and they did.... Happy Sails! Joel
By
Steve Cohen on Friday, February 11, 2000 - 10:48 am:
Steve,
Just an idea, since you are an 8(a) contractor and "can't make
any money" on your contract, you may want to discuss your
predicament with SBA SADBUS or SBA contracting officer. They may
be able to help you by better defining your contract requirement
which could lead to more accurate cost proposals and greater
profit opportunity. They could also act as an intermediary
between your company and the end user Contracting Officer.
Also, under a fixed price arrangement, unless there is a
deliverable line item for "residual materials" or any other
item, you are only required to deliver the end item which are
the walls, minus any materials, equipment, tools, etc. (known as
Contractor Acquired Property or CAP if to be delivered to the
government), to manufature them. I agree with you concerning the
SOW "Technical Description" which is a typical government
"boiler plate" statement placed in their construction contracts
that
requires the contractor to provide this, that, and the other
thing (all the material, tools, equipment) to complete the SOW
requirement. It has nothing to do with delivering those items
under the contract. Good Luck!
Another Steve
By
Vern Edwards
on Thursday, January 13, 2000 - 07:31 pm:
Joel:
I agree entirely with your great analysis.
Vern
By
joel hoffman
on Thursday, January 13, 2000 - 04:12 pm:
Vern, based on my experience, I
perceive this to be a price negotiating problem, not a contract
interpretation issue. I think the solution lies in each party
trying to understand and meet the other's needs. Happy Sails!
Joel
By
Steve Welch on Thursday, January 13, 2000 - 04:10 pm:
Joel,
Right on. I believe your last post is very close to what is
going on. I believe that the difference is that we do not put in
100% of the material that might be used each time but some, I
believe, reasonable %.
Again I think the solution is to agree on what that pecentage
each time and define material disposition before hand.
By
joel hoffman
on Thursday, January 13, 2000 - 03:37 pm:
Steve, I believe I understand
the problem(s). I perceive this:
The Government negotiators want a detailed proposal from you for
proposal analysis and negotiations.
The Government negotiators balk at contingincies in any
proposals to cover minor items you might overlook or to cover
normal contingencies.
If you aren't allowed to identify a cost as a "contingency", you
feel you must cover yourself other ways, e.g. by including
enough for new formwork, etc.
The negotiators note that you and they have previously
negotiated prices on the basis of "one-time use", rather than
"x" times for formwork, etc.
The negotiators then noticed that you have been reusing some of
the formwork, etc. Therefore, they feel that one-time use
pricing is no longer valid. They don't want to continue to
negotiate "one time use" prices and want the benefit of the
re-usable supplies on future task orders.
While I would probably agree with you that you still own the
supplies, I would agree with the Government negotiator that they
shouldn't have to pay for all new supplies on subsequent tasks
if that isn't your actual, usual practice.
This is because forward pricing of non-competitive task orders
or changes are supposed determined on the basis of the
Contractor's probable COST, not necessarily market prices or
"market value". I would qualify this to say that small task
order proposals need not necessarily be analyzed using extensive
"cost analysis" techniques.
However, a good Government negotiator would still use judgement
based on his or her knowledge of your actual practice in
negotiations. I would probably agree with them that it is
unreasonable for you to insist on including pricing for
non-representative costs in your proposals.
The Government's insistence that you list every nut and bolt in
the proposal to justify costs might or might not be reasonable.
If we are talking about small task orders, 1) it is a lot of
paperwork, 2) you ought to be able to negotiate agreed unit
prices for repetitive work items, then use them in future
proposals to save needless effort and expense on both sides and
3) small tasks inherently involve higher risks in accurately
pricing the work - you miss a few details and lose money, small
delays or cost overruns will cause a loss, etc. The Government
negotiator probably ought to recognize this "risk" and allow
some flexibility in areas within the proposal - such as allowing
a higher allowance for profit and/or allowing lower productivity
rates to cover the hiccups which inevitably occur. Most
published productivity rates are based on large quantities.
Anyway, I would agree with not paying for one time use of forms
and supplies when you can use them several times - I would try
to negotiate some reasonable factor with you. I would also try
to be responsive to your other concerns, so you don't have to
bear an unreasonable risk or be buried in paperwork for
repetitive tasks, which could make use of agreed unit pricing
techniques.
I used to negotiate agreed pricing for repetitive work, keep it
in a book and my contractor would use it in his proposals, too.
Saved us both a lot of work and we were both comfortable with
the rates.
Is my understanding of the problems somewhere near the actual
situation? Happy Sails! Joel
By
Vern Edwards
on Thursday, January 13, 2000 - 02:29 pm:
This thread is a big heads up to
all who enter into fixed-price task order contracts under which
materials costs may be significant.
If there is any possibility that individual orders may produce
significant and useful residual inventory (materials, parts,
tooling, etc.) that could be used on future orders, then the
contract (or individual orders under the contract) should
address the issue of ownership and disposition.
By
Steve Welch on Thursday, January 13, 2000 - 12:28 pm:
Vern,
You are very close to the truth. I was not here during the
previous contract (which was a cost plus fixed fee). I hear that
it was abused by both parties and the CO determined that the new
contract would be much different. I do not believe that I am
adding to each task the full amount of each of these items and
then using some large subset of the residual materials and
pruchasing a small subset of new materials.
It always seems that no matter how detailed we make our
technical evaluation, we forget to include enough labor and
materials. We feel we are in a lose lose situation, we are
obligated to provide the product, but we can't make any money.
It seems that the solution is to define exactly what we are to
deliver to the customer. We were under the impression that we
were to deliver exactly what is stated in the SOW, no more no
less, for the amount of money listed in the order for supplies
and services.
Where is it stated in the FAR that material not incorporated
into the final product becomes the property of the customer?
There is no line item for saw blades, drill bits, form stakes,
etc. in the contract, I only mentioned them in the technical
description to get a better estimate of our costs. If we put in
X amount of $ for misc. mat'l then we have to define misc.
Clearly the relationship is more valuable than the material. I
guess that we should just submit to the CO wishes and press on.
By
Vern on
Thursday, January 13, 2000 - 11:34 am:
Steve:
Let me speculate about something:
It sounds like your contract is a task order (or job order)
contract for construction services.
Maybe the government has noticed that you are including the
costs of materials for formwork and walls in each order
proposal, but that you are using residual materials (sometimes
called "residual inventory") from previous jobs to get the work
done. They figure that they've already paid for those materials
once and shouldn't have to pay twice if you're going to reuse
them. So now they are claiming that the residual materials
belong to them and that you must reuse them when possible in
order to cut project costs. You figure that the stuff belongs to
you and that you have every right to do what you want with it.
You include the costs of the materials for the formwork and the
walls in each order proposal because they are true costs of
doing the work. Then you economize by using any useful residual
materials on the job.
Am I right about this?
If I'm right, that would explain why they are specifying the job
in such detail and claiming that the residual materials belong
to them. They write the specifications in detail in order to
ensure that you use the residual materials, and their claim
means that they do not intend to pay twice for the same stuff.
If I'm right, you have a problem that the government probably
should have anticipated when they were planning the contract.
They should have included a residual materials or residual
inventory clause in the contract.
I generally agree with Joel's analysis, but I don't know how the
construction payment clause is to be interpreted in your
situation (assuming that I'm right about your situation).
If I have speculated correctly, then despite any legal
interpretations you have a customer relations issue. Surely you
can understand why the customer feels the way it does. What kind
of relationship do you have with the customer? Is the value of
the materials greater than the value of the relationship?
If my speculation is off base, and it very well may be, then I'm
not sure what's going on.
Vern
By
Steve Welch on Thursday, January 13, 2000 - 10:07 am:
Hey guys, thanks for the
responses. I will try to make my case more clear. We are in
option year 2 of our contract. The contract is for one basic
year with 4 one year options. We are not in default. This issue
with materials just came up and was not an issue several months
ago. I do not know what prompted the governemnt to seize our
material.
A little more detail. We build structures that will be tested
using energetic materials (explosives). We receive an SOW that
details the structure to be built. Lets say, a 10 foot high 40
foot long 1 foot thick 5000psi concrete wall with associated
footings and rebar. Lets also say that a plywood sheathed 2x4
wall of the same length and height also needs to be built.
The concrete is GFM and the concrete transit mixer trucks are
GFE. Our company must produce the concrete and plywood walls.
After we receive the statement of work (SOW) we have 10 days to
prepare a cost proposal and deliver it to the government. The CO
then usually requires a breakdown of our costs so that the
construction engineers can better evaluate our proposal. Over
the past few years the cost proposals have become more and more
detailed in order to reduce the number of iterations of
re-detailing the the cost proposal.
We don't believe that the CO can tell us how to build the walls,
if that is not specifically called out for in the SOW. We
believe that the form stakes, saw blades, drill bits, 2x4s and
plywood purchased for the formwork for the concrete wall remains
our property and the 2x4s and plywood purchased for the plywood
walls becomes the property of the government once delivered to
the site or incorporated into the wall.
Progresss payments are and have been made for rebar delivered to
the site and for a percentage of work completed for that month.
I believe that the idea of a firm fixed price job has been
perverted by having to detail each and every subtask, nail, 2x4
etc. required to produce the end product, a concrete wall and a
plywood wall. I could understand if the SOW required us to
purchase concrete form work and then pass ownership of the
formwork over to the government. But this is not the case. Even
if our cost proposal said that we were going to buy 2x4s and
plywood for forming the wall and we later decide that it would
be more cost effective to rent forms this should be of no
concern to the CO if the end product is of equal quality and
produced on time.
I hope I have not confused this issue even more. Again thanks
for your comments.
By
joel hoffman
on Wednesday, January 12, 2000 - 11:53 pm:
Having re-examined your post,
Steve, are you stating that the contract includes separately
priced line items for saws, tools, supplies, form work, etc. in
the line item payment schedule? I did not clearly understand
your description of the problem.
Of course, if this concerns a "default", the Government may
seize and use your tools, supplies, equipment, etc. to complete
a defaulted task order. Happy Sails! Joel
By
joel Hoffman
on Wednesday, January 12, 2000 - 11:43 pm:
Steve and Vern,
On the off-hand chance that we are dealing with a default
situation here - under the terms of the contract - the
Government has the right to seize your on-site supplies, tools,
equipment as well as on-site materials to be incorporated into
the work. The Government may use them to complete the contract
work. The Government doesn't obtain title to the tools, supplies
and equipment but CAN hold them and use them.
Otherwise, only materials to be incorporated into the permanent
work become the Government's property. There should be no
separate progress payments for anything but satisfactory,
in-place permanent work and for "stored materials" (to be
incorporated). The Government has the right to require proper
storage of, safe use of, housekeeping,etc. for supplies, tools,
and equipment while on Government property. But the Government
has no ownership rights, per se. Happy sails! Joel
By
Vern Edwards
on Wednesday, January 12, 2000 - 09:38 pm:
Steve:
Has the contracting officer claimed that specific materials
belong to the government? If so, ask him/her what the basis is
for that claim. See if the CO can cite a clause or some other
term of the contract in support of the claim. Then read the
clause or other term and decide if you think that the CO's claim
has merit.
I haven't seen your contract and don't know what it says, but
the CO has to base his/her claim on the terms of the contract.
Vern
By
Steve Welch on Wednesday, January 12, 2000 - 07:15 pm:
I think that one of our problems
is that the Statement of Work does not include the materials.
The materials are only listed in a technical description that
justifies cost. The technical description lists all nuts, bolts,
rental equipment, rented concrete forms, saw blades and other
expendables, labor hours for each sub task etc. We consider this
description as an evaluation tool only, not as a list of
equipment and materials that are to become the property of the
government.
We believe that the end product is what we owe the government
not the tools, materials, and equipment that it took to deliver
that end product. An example might be that in order to provide a
concrete wall we will need to either rent concrete forms or
build forms on site. Once the concrete is placed into the forms,
the forms are removed and returned to the rental agency or the
job built forms are removed and stored for use on other jobs.
Whether that next job is for that government agency or some
private concern.
By
Vern Edwards
on Wednesday, January 12, 2000 - 06:13 pm:
However, one caveat concerning
my last post. The construction contract payment clause at FAR
52.232-5(f), says that material covered by progress payments
become the "sole property" of the government.
Your question didn't mention progress payments, and construction
progress payments usually don't include materials unless they
have been delivered to the construction site, although the CO is
allowed to include the costs of other materials, as well.
So, if you have received progress payments that included
coverage of the materials in question, then those materials
belong to the government. If you have received progress
payments, hopefully you have records for which materials were
included and which were not.
By
Vern Edwards
on Wednesday, January 12, 2000 - 06:06 pm:
I agree with you. Unless the
contract expressly provides otherwise, material that is
purchased by the contractor during the performance of a
firm-fixed-price construction contract and that is not
incorporated into the contract work belongs to the contractor.
By
Steve Welch on Wednesday, January 12, 2000 - 02:29 pm:
I manage a small construction
company with an 8a set-aside firm-fixed-price delivery order
type contract. My question is regarding materials purchased by
the contractor (us) during the construction of the object of the
delivery order. These materials are not the final product but
are necessary for the construction of the final product. Some of
these items include but are not limited to form stakes, 2x4s and
plywood used to make forms for the placement of concrete, etc.
It is our contention that these materials belong to the us and
not the government. What say you?
|