By
Brad Franklin on Thursday, November 16, 2000 - 11:35 am:
I am looking for someone that can give me insight regarding
the effects of DFARS 252.249-7000, Special Termination Costs.
Specifically, in the event of a termination for convenience what
costs would be recoverable against the contract funding and what
costs would be recoverable against the limits specified in DFARS
252.249-7000. My primary concern is the treatment of subcontract
costs. An example may help clarify my question:
Assume the prime contract is T for C'd on January 1. I would
assume that costs incurred by the Prime up to that point would
be recovered against the contract funding; and costs incurred by
the Prime after that point would be recovered against the
termination limitation. Now, assume I flow down the T for C to
my suppliers on January 3, 2 days later. Is it safe to assume
that the costs incurred by the supplier up to January 1 are
recoverable against the prime contract funding notwithstanding
when these costs are billed to the prime? If so, are the costs
incurred by the suppliers between Jan 1 and Jan 3 recovered
against the contract funding or the termination limitation?
Any experience out there?
Thanks,
Brad
By
Vern Edwards
on Friday, November 17, 2000 - 08:07 pm:
Brad:
I believe that the answer to your question depends on whether or
not the contract was fully funded before the termination.
According to DFARS 249.501-70, the Special Termination Costs
clause is for use in incrementally funded contracts. The clause
constitutes an advance agreement about the government's maximum
liability for certain costs that a contractor may incur if the
government terminates the contract; it does not apply to costs
that are not incurred as a consequence of a termination.
The key paragraphs in the clause are (c) and (e). Paragraph (c)
states the government's maximum liability for special
termination costs. Paragraph (e) says that the clause is no
longer applicable after the contract has been fully funded.
Thus, if the contract in your example was not fully funded
before the termination, then the ceiling on special termination
costs would apply to such costs incurred by the contractor and
its subcontractors. If the contract was fully funded before the
termination, then the ceiling on special termination costs would
not apply to such costs.
By
Brad Franklin on Monday, November 20, 2000 - 07:40 am:
Thank you Vern. The contract is not fully funded. Your
question though, drove me to re-phrase my question. Assume the
following: 1.I have a $100m contract that is incrementally
funded to a level of $50m; 2. My Special Termination Cost clause
has a ceiling of $5m; and 3. I receive a T for C when my costs
incurred to date are $30M leaving me with $20M in contract
funding.
Question: If my actual termination costs exceed $5m, can I
recover the difference out of the $20m in excess contract
funding?
My questions is driven by what I thought was the intent of the
clause; i.e., to provide funding over and above "contract"
funding to cover termination costs. If a contractor cannot dip
into the remaining "contract" funding to cover termination
costs, a contractor may be worse off having this provision then
they would be without it.
Thanks in advance for any further insight you can give me.
Brad
By
Vern Edwards
on Monday, November 20, 2000 - 10:08 am:
Brad:
I think that in your scenario you would not be legally entitled
to recover any special termination costs in excess of the $5
million ceiling. Your company has agreed to limit the
government's liability to that amount prior to full funding of
the contract. Since the contract has not been fully funded, the
government is not obligated to reimburse you for any amount in
excess of the ceiling, even though funds remain.
The purpose of the special termination costs clause is to cap
the government's prospective termination liability and exclude
it from the "amount then allotted to the contract" mentioned in
paragraph (f)(2) of the Limitation of Funds clause. By doing
this, the parties avoid the necessity for the contractor to stop
working in order to protect itself when the incurred costs plus
the government's termination liability reach the amount
allotted.
The key to understanding the special termination costs clause is
to take note of the parenthetical phrase in the first sentence
in paragraph (f)(2) of the Limitation of Funds clause, which
says: "including actions under the Termination clause of this
contract... ." Because of that phrase, a contractor must
anticipate the possibility that the government will terminate an
incrementally funded contract rather than continue to fund it.
If that were to happen, the contractor would not be able to
recover any termination costs in excess of the amount allotted.
Thus, were it not for the special termination costs clause, the
contractor would have to stop working at the point at which the
costs already incurred + the anticipated termination costs =
"the amount then allotted to the contract." If it continued to
work past that point it would be taking the risk that it could
not recover the costs that it would incur due to the
termination.
The special termination costs clause does not set up a separate
funding pool for the special termination costs. It merely
excludes such costs from the operation of the Limitation of
Funds clause and limits the government's liability for such
costs until the contract has been fully funded. The clause is
inoperative once the contract has been fully funded, and the
government's liability for special termination costs is no
longer capped at that time.
I suppose that it may be possible for you to negotiate something
with the contracting officer, depending on the circumstances.
But absent any other facts, I think that the special termination
clause pretty well deprives you of any contractual basis for
demanding reimbursement of special termination costs in excess
of the ceiling.
By
Brad Franklin on Monday, November 20, 2000 - 11:29 am:
Vern,
Thank you.
Brad |