By
Eric Ottinger on
Tuesday, May 23, 2000 - 12:20 pm:
Joel and all,
I thought the following Washington Post story provides an
interesting real world situation to illustrate some of the
issues that we were discussing.
http://www.washingtonpost.com/wp-dyn/articles/A45748-2000May21.html
It is interesting and encouraging that some of the workers had
enough of a sense of right and wrong to blow a whistle.
Eric
By
Vern Edwards
on Thursday, April 27, 2000 - 09:29 am:
Eric:
Thanks for the response.
Vern
By
Eric Ottinger on
Wednesday, April 26, 2000 - 04:46 pm:
Vern,
To answer the question that you asked.
Q: “Now guys, I didn't ask for a criticism of
firm-fixed-unit-price contracts; I merely asked for a taxonomic
analysis of the type based on pricing arrangement. Because if
they can be considered "firm-fixed-price," then DLM may be able
to buy tariff services under FAR Part 12.”
A: Yes. Probably. I think you can have FFP with some adjustment
provisions. See what your lawyer thinks.
Bob,
Great analysis.
Joel,
I don’t think there will be a big problem paying for the dirt by
the yard for “cultural” reasons. Construction workers are hard
working and lazy. They will work very hard until they get the
job done, at which point it is Miller Time or at least time for
a break. I doubt any construction worker would want to keep
digging just to make a bigger hole, and I doubt that any sane
supervisor would ask him to. (Lawyers on the other hand will be
beavering away at 2:00 o’clock in the morning, running up those
“billable hours,” if you let them.)
Correct me if I am wrong.
Regards to all,
Eric
By
Vern Edwards
on Wednesday, April 26, 2000 - 02:29 pm:
Joel:
I agree with you. I used a bad example.
Vern
By
Vern Edwards
on Wednesday, April 26, 2000 - 02:12 pm:
Bob:
What a thoughtful, logical analysis! Thankyou.
Vern
By
joel hoffman on Wednesday, April 26, 2000 - 01:34 pm:
Bob, et al:
Actually, if the excavation for the hole can be reasonably
estimated, it should and probably would normally be priced on a
lump sum basis, not unit priced. I forgot to mention this
earlier. Happy Sails!
By
bob antonio on
Wednesday, April 26, 2000 - 11:57 am:
Vern:
Approaching this from a bidder's perspective, I have a hole to
dig. I expect the subject material to be consistent with the
geography or with the description provided by the agency. I have
100 days, the measurements of the project, and the agency's
estimate of cubic yards to be moved. I am also aware of the
variations in FAR 11.702. These are the parameters with which I
will build my bid.
Assume my on-site analysis affirms the agency's estimate of
cubic yards. I calculate my costs and desired profit for the
project based on the agency's estimate but I am congnizant of
FAR 11.702. Since the project will be bid on a cubic yard basis,
I convert my project bid to this format. However, my unit price
is my desired project price.
Now for FAR 16.202-1. There are four key items in it. These are:
(1) a price that is not subject to any adjustment on the basis
of the contractor's cost experience in performing the work; (2)
contractor has maximum risk and full responsibility for all
costs and resulting profit or loss; (3) provides maximum
incentive for the contractor to control costs and perform
effectively; and (4) imposes a minimum administrative burden
upon both parties.
Looking at your example, I consider the first three parts of FAR
16.202-1--as I expressed them-- to be satisfied. However, we
have an administrative burden. What is a "minimum" burden?
Should it be the same administrative burden related to the
acquisition of a computer at a firm-fixed price? There are
firm-fixed price construction contracts that require a great
deal of monitoring but they are firm-fixed price. So I would
look at the minimum administrative burden related to the
industry for this work. If the agency and contractor agree to
the minimum administrative burden for the industry in
determining how to measure the cubic yards moved, I consider the
contract to be a firm-fixed price contract using the description
in FAR 16.202-1.
In your second scenario, my opinion is the same.
In your third scenario, I feel the first three items that I set
forth in FAR 16.202-1 would not be met and it could not be
called a firm-fixed price contract.
By
Vern Edwards
on Wednesday, April 26, 2000 - 09:55 am:
Rose:
I don't think you're being sarcastic. Thanks for your opinion.
Vern
By Rose McWilliams on Wednesday,
April 26, 2000 - 09:36 am:
Vern, I don't mean to be
sarcastic but what is firm in your FFP unit price contract?
Since you have fixed prices but not a firm requirement, I still
think that a Requirements type contract would be better. If you
can't establish a firm requirement for a portion of the overall
effort, then a hybrid contract with some FFP items and some
Requirements type items seems appropriate. In the past, I have
seen Fixed Priced Requirements contracts done as commercial item
contracts, while Fixed Price with Award Fee contracts for
services are not done as commercial items due to the FFP
constraint; I agree that the FFP constraint is a problem.
By Joel Hoffman on Wednesday,
April 26, 2000 - 08:38 am:
Just an aside. I have often seen
individual CLINS within FFP contracts which provide a
pre-determined "dummy" amount for the item, such as "utilities"
or "gasline connection by the XX Gas Company."
The CLIN description and technical specification provide that
the Contractor will arrange with XX Gas Co. to make the
connection. The Government will pay the actual cost to the
Contractor under the "Changes" clause. Although not exactly the
same as a tariff adjustment, the concept is similar. Assuming
that adjustable CLIN is a minor item in the overall FFP
contract, I don't see why DLM can't use a FFP contract type with
a minor CLIN, subject to economic adjustment or whatever. In
fact, I've seen time and material and FP, Level of Effort CLINS
within an overall FFP contract type. Not a problem. Is there a
prohibtion against mixing contract types? The only one I am
aware of is Part 36 not allowing Cost Reimbursible and FFP types
to be intermingled, due to the impracticality of separating
costs between them.
Also one of my reasons for not awarding a totally separate
contract to dig a basement, using unit priced CLIN, for the
building being constructed under a FFP, lump sum basis. Happy
Sails!
By
Vern Edwards
on Tuesday, April 25, 2000 - 07:35 pm:
Eric and Rose:
Keep in mind that requirements, definite-quantity, and
indefinite-quantity are not "types" in the sense of pricing
arrangements. To draw a contrast between an FFP arrangement and
an IDIQ or requirements arrangement is like drawing a contrast
between "a human being" and "a swift biped." There is no
either-or issue; a creature can be both.
The issue here is the pricing arrangement.
Firm-fixed-unit-price contracts are used when it is difficult or
impossible to predict the amount of work that the contractor
will have to do. They are an alternative to cost-reimbursement
contracts and are similar to a labor hour pricing arrangement
except that payments are based on units of output (e.g.
cubic yards of excavation), rather than units of input
(e.g., labor hours). These kinds of contracts are very standard
in both government and the private construction sector.
A firm-fixed-unit-price contract does not compensate the
contractor on the basis of its "cost experience." The
contractor's cost experience is not relevant to the payment
determination. It compensates the contractor for its production.
Eric, a firm-fixed-unit-price contract does provide an
incentive to control costs. I have seen construction supervisors
raise all kinds of hell with equipment operators for inefficient
production. (I'll bet Joel has, too.) The company is getting
paid per unit of production, not per hour, and heavy equipment
rental is expensive. The contractor cannot control how many
units he has to produce, but he can and must control how much
input he uses to produce those units, or he'll go broke.
However, firm-fixed-unit-price contracts are administratively
more burdensome than lump sum contracts.
Now guys, I didn't ask for a criticism of firm-fixed-unit-price
contracts; I merely asked for a taxonomic analysis of the type
based on pricing arrangement. Because if they can be considered
"firm-fixed-price," then DLM may be able to buy tariff services
under FAR Part 12.
By joel hoffman on Tuesday,
April 25, 2000 - 06:06 pm:
Hey, Eric. I told you we
construction types like to keep you off balance! Seriously, if
quantities can be estimated with certainty and there is little
likelihood of adjustments to the scope of work - we are supposed
to use lump sum CLINS to price the work.
Unit priced items are discouraged unless we can't reasonably pin
down the actual quantity. Otherwise, contractors would place
large contingincies in their bids. Thus, (FFP) unit prices with
estimated quantities are established to protect the contractor
and to reduce contingent pricing to the owner.
Although estimated quantities are "specified" they are based on
reasonable but often not precise estimates due to variables
likely to be encountered. The 'specified' quantities are subject
to measurement and payment provisions based on actual quantities
within the defined pay limits for the defined scope of work.
So, reading the entire 36.207 (36.207(a)is explicit; the rest is
implicit), it is clear to me that unit priced work can be FFP.
Happy Sails!
By
Eric Ottinger on
Tuesday, April 25, 2000 - 05:44 pm:
Joel and Vern,
Since I have admitted that I know nothing about construction
contracting and I started off saying, “However, if someone wants
to call it a firm-fixed price for each cubic yard, I wouldn’t
waste time arguing with them.” I would say that I have done such
a good job of waffling that there is no possibility of a
substantial disagreement with anybody.
The arrangement that you describe is not one which, “provides
maximum incentive for the contractor to control costs and
perform effectively and imposes a minimum administrative burden
upon the contracting parties.”
But you might argue that every other arrangement would be even
worse from the point of view of the “administrative burden,” and
I might agree with you.
It could be an “adjustment on the basis of the contractor’s cost
experience in performing the contract” However, this would only
apply if you are buying the hole in the ground rather than dirt
by the yard.
If we are serious about doing a taxonomy, we should look at the
mechanisms and ignore the labels. In this light, I would still
say the closest kin is an ID/IQ with a small range between the
minimum and the maximum.
I get cranky when something is described as FFP and it is
obvious that the contractor isn’t accepting the degree of risk
that you would normally expect for a FFP. Otherwise, suit
yourself.
Eric
By
Vern Edwards
on Tuesday, April 25, 2000 - 05:44 pm:
I asked the question because of
something posted to the thread "Commercial telecom."
Someone named DLM wrote that Ask A Professor had said not
to buy telecom services under FAR Part 12 because they are
tariff-priced and "tariffs are not considered fixed price."
FAR 12.207 says that acquisitions under Part 12 must be FFP or
FFP with economic price adjustment.
As I recall, tariff prices are rates or unit prices set by law
or regulation. The tariff fixes the unit prices for the service,
but what the buyer pays depends on actual usage. That's why I
wanted to get some opinions about whether firm-fixed unit-price
contracts under which payments depend on performance quantities
to be determined after award could be considered
"firm-fixed-price contracts." If firm-fixed unit-price contracts
can be considered "firm-fixed-price," then perhaps DLM could use
Part 12 to buy commercial telecom after all.
I'm not criticizing Ask A Professor in this case, because
I haven't seen the actual question and answer. Ask A
Professor may have had very good reasons for telling DLM
that tariffs are not fixed-prices.
I just wanted to see what others thought about this.
Frankly, I'm not sure myself. I have used sealed bidding many
times to award unit-priced construction contracts with quantity
estimates, and FAR Part 14 restricts the use of sealed bidding
to contracts that will be FFP or FFP with economic price
adjustment.
However, FAR 36.207(a), which describes firm-fixed-price "lump
sum" and "unit-price" contracts, says that unit-price contracts
must have a "specified" quantity of work units. I'm not sure
that an "estimated" quantity is the same as a "specified"
quantity.
I'm inclined to call firm-fixed unit-price contracts
"firm-fixed-price contracts," but I'm not sure that's right.
By joel hoffman on Tuesday,
April 25, 2000 - 05:10 pm:
Vern didn't ask whether a FFP
unit priced contract was the best method. He asked if such a
contract COULD BE a FFP contract. I say it can be.
I would do the basement or other excavation in the sample cited
as a FFP, unit priced contract. In fact, it may be part of a
larger contract to construct the building.
Vern just happened to cite what appears to be a poorly written
contract. One simply describes the required cross-section for
construction with tolerances for overexcavation and establishes
limits for payment on the contractor, so if he excavates outside
the pay lines, it is at the contractor's expense. That is not
particularly difficult to do.
Your method doesn't appear to me to offer any advantage over
mine, if my scope of work is properly written. You still have to
have someone verify by measuring that the quantity you ordered
was actually performed in order to make payment. I can include
this work in an overall contract for the building construction.
Yours is a separate contract I have to administer and coordinate
with the general contractor and its subs for the building
contract.
Just my opinion. Happy Sails!
By Rose McWilliams on Tuesday,
April 25, 2000 - 04:51 pm:
Joel, We don't have a need to
adjust unit prices in Vern's scenario, we need to adjust
quantities, therefore I don't think a FFP contract is
appropriate. I would issue a Fixed Price Requirements type
contract and provide authority for an on-site Govt rep to issue
oral orders specifying the areas/yards to be excavated; since
the Govt rep is on-site, firm quantities can immediately be
ordered and the confirming written order will reflect actual
quantities at the fixed prices contained in the basic contract.
By joel hoffman on Tuesday,
April 25, 2000 - 04:08 pm:
Eric - hint, see FAR 36.207 and
11.702
(FAR 16.202-1 refers to unit prices not total contract price or
estimated quantities. UNIT PRICES are generally not subject to
adjustment due to the contractor's cost experience.)
BUT - - Far 16.202-1 is technically incorrect. See Far 11.702
where an adjustment in unit PRICES is allowable on a FFP
construction contract. We construction types like to keep 1102's
off balance, you know........ (see VEQ Clause at 52.211-18)
Happy Sails!
By
Vern Edwards
on Tuesday, April 25, 2000 - 03:08 pm:
Eric:
Please explain the relevance of FAR 16.202-1 to the questions.
Also, what is your answer to the questions?
By
Eric Ottinger on
Tuesday, April 25, 2000 - 02:54 pm:
Not really disagreeing with
anybody. I certainly don't know anything about construction
contracting.
I am always amazed to see how 1102's debate these issues without
reference to Part 16.
See: FAR 16.202-1 Description.
A firm-fixed-price contract provides for a price that is not
subject to ANY adjustment on the basis of the contractor’s cost
experience in performing the contract. This contract type places
upon the contractor maximum risk and full responsibility for all
costs and resulting profit or loss. It provides maximum
incentive for the contractor to control costs and perform
effectively and imposes a minimum administrative burden upon the
contracting parties.
Eric
By joel on Tuesday, April 25,
2000 - 02:47 pm:
Oops, sorry to answer your
question to Rose. It popped up while I was typing my answer to
your initial question.
We seldom use ceiling caps - suppose we should have, though. We
administratively added funding from contingencies to cover
progress payments to cover overruns. We used management
techniques to keep up with funding overruns. Technically, that's
wrong.
But, I guess the answer is yes, it is FFP, even without a stated
price ceiling - because we did it for years and years. Happy
Sails!
By
joel hoffman
on Tuesday, April 25, 2000 - 02:36 pm:
Yep, its a FFP contract. Of
course, we try to include various controls such as "pay lines"
which are physical limits of payment - over excavation outside
those limits is uncompensated; Government making the actual pay
calculations; defined scopes of work with, no carte blank open
scopes of work, use of Variation in Estimated Quantity clauses,
etc.
A few years ago, after 100 years or so of doing things the same
way, we were told to process admin mods to make the books even
out at the end of the job - and at any time before final payment
when progress payments exceed 100% of the estimated contract
amount - looks bad to see progress reported at "106%" -
especially if they are still working! The final quantities and
contract price had to match the book price and published
contract amount. Okay, sounds good.
The contracts are self operating concerning what the contractor
will be paid for. Therefore, to simply adjust the contract price
and individual estimated CLIN quantities to match the actual
payment quantites ought to involve an admin mod (assuming there
is no ceiling price specified or if specified, not exceeded, in
overall obligations). Why? Because the rights of either party
are unchanged. Hey, no problem!
Interestingly, the Army contracting software system, "SAACONS"
(and I believe the new replacement - "SPS") has big problems
dealing with contracts containing unit prices and estimated
quantities.
Well, SAACONS wouldn't accept an "Admin Mod" which revised the
final contract price - whether it be up or down! Then, Army
refused to re-program SAACONS for this quirk. I'd bet a few
beers that SPS doesn't either.
Catch 22 - there is no contract clause to cover such an
adjustment, since it isn't a "change" in anything other than the
administrative adjustment of estimated unit priced CLINS and the
contract price. The contractor was already entitled to payment
for actual quantities of work performed.
So, they came back and said to cite the mod as an "adminstrative
adjustment of unit quantities, pursuant to the Variation in
Estimated Quantity Clause" on the SF30. This was so that SAACONS
could process the mod!!!!!
The VEQ clause has no provision and was never intended to cover
simple adjustments to estimated quantities. In fact, the clause
already says we will pay for actual quantities within the
authorized scope of work! The VEQ clause ONLY provides for
adjustments to unit PRICES, provided certain criteria are met -
not estimated quantities.
The tail often wags the dog in Government contracting..... Happy
Sails! Joel
By
Vern Edwards
on Tuesday, April 25, 2000 - 02:18 pm:
Rose:
So, what's your answer? Is the contract that I described a
firm-fixed-price contract or not?
Let me give you an additional fact: the contract requires the
contractor to complete the work within 100 calendar days after
issuance of a notice to proceed.
By
Vern Edwards
on Tuesday, April 25, 2000 - 01:51 pm:
Eric:
The example that I described is a very common approach to
pricing construction contracts, used by both the government and
the private sector.
By Rose McWilliams on Tuesday,
April 25, 2000 - 01:40 pm:
There's a tendency to get sloppy
with terminology and refer to fixed price contracts as firm
fixed price (FFP) contracts. The difference between the two is
that all FFP contracts have fixed prices but not all fixed price
contracts have firm delivery dates and/or quantities.
By
Eric Ottinger on
Tuesday, April 25, 2000 - 11:57 am:
I’m not quite sure what you are
getting at Vern. However, the folks who keep advocating
something like a T&M and calling it "Firm Priced" give me gas.
What you have described is more like an indefinite quantify
contract.
However, if someone wants to call it a firm-fixed price for each
cubic yard, I wouldn’t waste time arguing with them.
Of course, if there is an opportunity for the contractor to move
dirt, just to move dirt, this contract would create a perverse
incentive. "Firm fixed price" should give the contractor the
maximum incentive to be efficient.
Eric
By
Vern Edwards
on Tuesday, April 25, 2000 - 11:04 am:
If a contract stipulates
firm-fixed unit prices for work and states that the contractor
will be paid on the basis of the actual quantity of units
delivered or performed, is it a "firm-fixed-price contract" as
described by FAR 16.202-1?
For example, suppose that a contract requires the contractor to
excavate a building site and stipulates that the contractor will
be paid the firm-fixed unit price for every cubic yard of
material that it excavates. The contract includes an estimate of
the number of cubic yards that the contractor will have to
excavate and a ceiling price. The contract requires the
contractor to measure and document the number of cubic yards
that it excavates and states that the contractor's measurement
is subject to review and approval by the owner's site
supervisor. Assume that the contractor does not exercise any
control over the number of units to be excavated.
Can such a contract be considered a "firm-fixed-price contract"?
Would your answer be different if the contract did not include a
ceiling price?
Would your answer be different if the contractor exercised some
control over the number of units to be delivered or performed?
|