By
Anonymous on Monday, April 14, 2003
- 03:34 pm:
BACKGROUND: The Government competitively awarded a
contract for services with a performance period of 90 days firm.
The contract also includes the FAR clause 52.217-8 Option to
Extend Services and specifies “the Contracting Officer may
exercise the option by written notice to the Contractor within
20 DAYS of contract conclusion.
QUESTIONS:
1. The Government is past the 20 days notification limitation
i.e. it is now 18 days until contract conclusion. I assume that
since we did not give written notice within 20 days of contract
conclusion in accordance with the clause, we have lost the
UNILATERAL right to exercise an option using the authority of
this clause.
However, the Contractor is willing to continue performing for us
and to discuss an agreed upon period up to and including the 6
month period described in 52.217-8.
He also understands that if we mutually agree to a lesser period
than the 6 months (let’s say 45 days), the Government will
consider its unilateral rights under the clause to be restored
upon execution of the option (i.e. the Government will again
have its right to extend unilaterally up to 6 months total (or,
for an additional 135 days (180 days (6 months as per the
clause) – the 45 days as bilaterally agreed).
Is this assessment correct?
2. Understanding that before the Government can exercise any
option(s), it needs to address the requirements identified in
FAR 17.207 including the requirements of Part 6, is it
acceptable to use FAR 52.217-8 as the authorizing clause to
exercise the option?
By this I mean that some of my colleagues consider the use of
the clause to be appropriate only in instances “in extremis”,
whereas I say that any time “continuity of operations is
required” and there is a significant “potential cost of
disrupted services”, this clause is the way to go (again only
once all requirements with regards 17.207 and Part 6 have been
sufficiently addressed).
Any thoughts?
By
Phil C. on Tuesday, April 15, 2003
- 08:26 am:
My thoughts to answer your questions:
To address the 2nd question, I disagree that 217-8 is the way to
go “anytime continuity of operations is required and there is a
significant potential cost of disrupted services.” I think 217-8
should only be used as a “stop-gap” measure, if due to
circumstances it’s the tool the KO has available to get the
required service provided. Moreover, if repetitive use of 217-8
is occurring the activity and /or contracting office have some
fundamental problems such as; statements of work/performance
which do not accurately reflect how long a job will take, and
poor practices to have follow-on contracts awarded in a timely
manner to avoid using 217-8 to extend services.
It seems by continually using 217-8, a band-aid is being applied
vice a more lasting solution. I’d prefer to exercise the option
by using 52.217-9 (extend term) or similar agency clause. I
think 217-9 provides a better opportunity for continuity of
service via the use of base and option periods. Of note, the
potential for 5 years with a base and options periods being up
to 1 year in duration. Also, the Govt should be able to realize
overall lower costs (decreased Govt and possible lower
contractor).
If using 217-8 as the go to method, the KO is then awarding,
extending for 6 months, awarding, etc. I think there are better
alternatives. Of course, 217-8 has its place as a stop gap
measure if circumstances arise. In the situation described,
217-8 is the tool for the KO to use.
I agree that the Government has lost its unilateral right to
exercise the option to extend services. Reviewing Formation of
Government Contracts by Cibinic and Nash, Third Edition, on page
1271 it’s stated “The Government must exercise options in a
timely manner and in exact compliance with the option terms”. In
the situation described, its 18 days before end of the
performance period and the option mod has not been issued. Thus,
I think the Govt. no longer has the unilateral right as 217-8 of
the contract prescribed a 20 day period.
Possibly the meaning of “timely” is different from what I’m
thinking. If so, this could rightfully allow the KO to
unilaterally exercise the option at 18 days or less. I’d feel
more comfortable exercising the option via bilateral
modification, so that I’d have the contractor’s agreement in
writing and don’t have to worry about an REA down the road. In
this case, being the contractor appears willing to stand by his
original pricing, a bilateral mod would be easy enough to
execute. However, if the opposite were true, the contractor
saying too bad its past 20 days, then I’d be looking harder for
a way do extend the term unilaterally.
If the option period of the bilateral mod is going to be less
than 6 months, the maximum time period permitted by FAR
52.217-8, I would obtain the contractors agreement to give the
government the unilateral right to exercise the remaining
portion of the “unused” portion of the 6 month period.
Another option (too many options), as cited from page 1272 of
Formation of Government Contracts “If a contractor leads the
Government to believe that it can exercise the option without
strictly complying with the clause, it will be estopped from
asserting the strict compliance rule, AmeCorp., GSBCA 5913, 82-1
BCA 15,738”. It seems the government has been in contact with
the contractor and he will continue to perform if the option mod
is exercised before the performance period (contract) ends. The
KO could issue the mod unilaterally and see what happens.
By
Anonymous on Tuesday, April 15,
2003 - 08:49 am:
I don't understand why you can't exercise the option
now. The clause says you can do so "within 20 DAYS of contract
conclusion." You're 18 days from contract conclusion now -- that
sure sounds like "within 20 days of contract conclusion" to me.
BTW, the total extension can't exceed 6 months. You couldn't
extend by 45 days now and then extend again later for an
additional 6 months (at least not without a sole source
justification, as this would be tantamount to a new award).
By
Vern Edwards on Tuesday, April 15,
2003 - 09:20 am:
First Anonymous:
With respect to your colleagues' contentions about exercising
the option under FAR clause 52.217-8, you might want to take a
look at the GAO's decision in the matter of Laidlaw
Environmental Services (GS), Inc.; International Technology
Corporation -- Claim for Costs, B- 249,452, B- 250,377, B-
250377.2, 92-2 CPD ¶ 366. The GAO sustained a protest that
exercise of an option under that clause was an improper sole
source contracting action. The circumstances of the case might
not apply to your situation, but it might be worth your time to
read it.
See, too, Akal Security, Inc., B-244386, 91-2 CPD ¶ 336,
in which the GAO explained FAR § 52,217-8 as follows:
"FAR § 52.217-8 merely provides the agency with a right to seek
up to an additional 6 months of contract performance beyond the
36-month period where exigent circumstances (such as delay in
award of a follow-on contract) create the need for continued
performance. See FAR § 37.111."
By
Anonymous on Tuesday, April 15,
2003 - 01:36 pm:
Vern et al,
Thanks for the information. I appreciate your responses and
their timeliness. Vern, how do you do your research? Is there a
way to find the GAO decisions based on some search criteria I
may be missing? I searched GAO using "52.217-8" and didn't get
any result and "options" resulted in a ton of results that
principally had to do with the evaluation of options at the time
of award...am I missing something, or is there a
reference/research guide you could recommend???
Tx,
Anon
By
Vern Edwards on Tuesday, April 15,
2003 - 02:08 pm:
Anonymous:
I use Westlaw (which costs an arm and a leg). If you are using
the Government Printing Office site, that database includes only
decisions issued after 1994. The decisions that I cited to you
were all older than that. I don't think any GAO decision has
mentioned 52.217-8 since 1992, which is probably why you didn't
find any. The Westlaw database goes back to the 1920s.
Vern
By
Anonymous on Wednesday, April 16,
2003 - 10:05 am:
To Anonymous who initiated this thread,
If your customer requires continued performance, by all means
rely on FAR 52.217-8 to issue a unilateral modification to
extend the existing contract for six months, or the period of
time you reasonable expect it will take your contracting
activity to competitively award a follow-on contract, whichever
is shorter.
Anonymous of April 15th at 8:49 correctly commented that 18 days
from contract conclusion is in fact “within 20 days of contract
conclusion.” Just look up the definition of “within” in
Webster’s. The word means “inside of” or “before the end of”.
Also, compare FAR 52.217-8 with FAR 52217-9. The latter clause
states that the Government may extend the term of the contract
by written notice to the Contractor “within” X before the
conclusion of the contract, provided that the Government gives
the Contractor a preliminary written notice of its intent to
extend “at least” X before the contract expires.
Additionally, a practice tip I recommend is that if you include
FAR 52.217-8 in a contract with a complex schedule or several
option periods, it is helpful to draft the schedule of the
contract to specify what rates will apply at any point in time
that FAR 52.217-8 may be exercised. This is because the plain
language of the clause states the Government may require
continued performance of any services within the limits and “at
the rates specified” in the contract. I interpret this to mean
that “the rates” in the schedule should be clearly “specified”
as a prerequisite to exercising the option(s) available under
the clause.
Finally, though the inclusion an option to extend services for
up to six months in a contract with a performance period of “90
days firm” is curious, if this option exercise clause was
included in a solicitation that resulted in a competitively
awarded contract, then the General Accounting Office is likely
to consider any protest of exercising the option under the
clause to have been filed in an untimely manner. Further, GAO
ordinarily considers option exercises to be matters of contract
administration outside of scope of their jurisdiction.
Finally, if your customer does require continued performance and
you are only exercising the option for the period of time you
reasonable expected it will take your contracting activity to
competitively award a follow-on contract, then even if one
assumes for the sake of argument that the option exercise was
improper, in all likelihood an after the fact J&A could be
generated to document that the Government has a legitimate
requirement for continued service (without any disruption) as a
stop-gap measure until such time as a follow-on contract can be
competitively awarded and the incumbent contractor is the only
responsible source for meeting that requirements within the
timeframes required. GAO routinely accepts documents generated
by the Government after the after the fact.
Cheers,
Ned Kelly
By
Vern Edwards on Wednesday, April
16, 2003 - 10:50 am:
Anonymous:
A couple of observations about Ned Kelly's remarks--
First, "within 20 days of contract conclusion" is strange
language and I'm not sure what the person(s) who wrote it
intended or supposed it to mean. (I'd be willing to bet that
they meant "not later than 20 before contract conclusion.") But
it doesn't matter, since the contractor doesn't object to the
exercise of the option. So, sure, go ahead and exercise the
option.
Second, if the GAO refuses to hear a protest from another firm
about the exercise of the option, it won't be because the
protest is untimely in relation to the original contract award,
but, as Ned indicated, because the exercise of an option is a
matter of contract administration. But don't count on that,
because the GAO has considered such protests in the past when it
felt that the exercise of an option violated CICA. See the cases
I cited, above.
Third, Ned went too far when he said that the GAO "routinely"
accepts documents generated by the government after the fact,
although they often have done so. But if you decide that you
must prepare a J&A based on the unusual and compelling urgency
exception to full and open competition, then FAR 6.302-2(c)(1)
says you can prepare and obtain approval of the J&A after the
option has been exercised "when preparation and approval prior
to award would unreasonably delay the acquisition."
By
Anonymous on Wednesday, April 16,
2003 - 02:37 pm:
Vern,
I agree with your observations.
First, based on the facts presented, the contracting officer
should “go ahead and exercise the option.”
Second, as a procedural matter, GAO will refuse to hear a
protest allegation on jurisdictional grounds (i.e., the protest
allegation involves a matter of contract administration) in
preference to dismissing the protest allegation on timeliness
ground (i.e., FAR 52.216-8 was contained in the competitive
solicitation, so any objection to it should have been filed
prior to the solicitation closing date in order to be considered
timely). It was undisciplined of me to have spoken first of
timeliness and then of jurisdiction. Concurrently, I suspect you
would agree that GAO’s decisions explaining its timeliness rules
are easier to understand than GAO’s decisions explaining the
circumstances under which it will review option exercises.
As an aside, permit me to state here for those without the
benefit of readily accessible GAO decisions that in Laidlaw
Environmental Services, Inc.; International Technology
Corporation--Claim for Costs, B-249452, B-250377.2, 92-2 366
(November 23, 1992) the agency issued a solicitation to procure
Waste Management Services for a specific three month period and
that solicitation did not contain FAR 52.217.8. After soliciting
four sources to participate in a limited competition, the agency
competitively awarded a contract to International Technology
Corporation and on the very same day modified that contract to
incorporate FAR 52.217.8 (which authorizes the government to
extend performance under the contract for a period not to exceed
6 months). In that case, the agency conceded that the 6-month
option was outside the scope of the 3-month contract and
effectively constituted a new procurement. GAO’s rationale for
sustaining the protest was: “In our view, the urgent
circumstances leading to this sole-source contract extension
resulted from the Navy's failure to adequately plan for the
procurement in advance. On the same day it awarded the interim
contract to ITC, the Navy amended the contract by authorizing up
to a 6-month option to extend. Yet the Navy neither provided
offerors with an opportunity to compete for the additional
requirements at that time or during the 3-month interim
contract. n5 Based on the record, it is apparent that the Navy
did not properly plan in advance for its requirements and this
sole-source contract was unjustified. See K-Whit Tools, Inc.,
B-247081, Apr. 22, 1992, 92-1 CPD P 382.”
Third, in stating that GAO “routinely” accepts documents
generated by the Government after the fact, I was using the word
“routinely” to denote the “habitual or mechanical performance of
an established procedure” (as opposed to commenting on how
frequently this occurs). I would encourage all who are involved
in contracting work to consult the dictionary early and often.
In addition, I offer these citations in support of the
proposition that GAO has an established procedure of considering
documents generated after the fact by agency personnel (who are
presumed to act in good faith in the absence of convincing
evidence to the contrary):
United Terex, Inc., B-275962.2, 97-1 CPD P 196 (May 30, 1997):
While documents prepared in response to a protest reflecting an
evaluation or source selection rationale may be accorded less
weight than contemporaneous documentation, we consider the
entire record including statements and arguments made in
response to a protest in reviewing an agency's evaluation and
source selection. Solid Waste Integrated Sys. Corp., B-258544,
Jan. 17, 1995, 95-1 CPD 23 at 5 n.4.
LTR Training Systems, Inc., B-274996; B-274996.2, 97-1 CPD P 71
(January 16, 1997): In a supplemental agency report, the
contracting officer furnished a declaration in which he
elaborated upon the reasons for his source selection decision.
n2 Specifically, the contracting officer stated that he reviewed
both SSET reports and the responses received from both offerors
during discussions and conducted his own independent review,
which led him to conclude that despite the SSET scoring, the two
proposals were essentially equal. n2 LTR objects to our
consideration of this declaration because it is not
contemporaneous with the selection decision. However, while we
generally give more weight to contemporaneous records than to
those prepared after the fact, we consider all documents of
record, including explanations for evaluations and selection
decisions furnished in response to a protest. Benchmark Sec.,
Inc., B-274655.2, Feb. 4, 1993, 93-1 CPD P 133.
JJH, Inc., B-247535.2, 92-2 CPD P 185 (September 17, 1992): JJH
takes exception to our considering documents such as Appendix A
because they were not prepared contemporaneously with the actual
evaluation and selection. The protester suggests that such
documentation is not reliable because it merely ratifies an
earlier, allegedly defective, decision that the agency is
seeking to preserve in the face of a protest. Although we may
give less weight to documentation supporting an agency's
original selection that is developed after the decision has been
made, we do consider such documents, along with the entire
record, if they are presented in a timely manner so that the
protester has an opportunity to comment on them. See Aircraft
Porous Media, Inc., B-241665.2; B-241665.3, Apr. 8, 1991, 91-1
CPD P356.
Truth be told, where I went out on a limb was predict based on
existing decisions and the current personnel in GAO’s Bid
Protest Group that GAO would accept a sole source (as opposed to
urgency) J&A generated after the fact and conclude that if there
had been a legitimate basis for a sole source justification,
then the contracting officer’s failure to document in writing
that sole source justification prior to exercising the option is
merely a procedural defect that does not prejudice the
protester. Thus far, to the best of my knowledge, GAO has only
ruled that written justifications that substantially complied
with CICA requirements, but contained procedural defects, did
not prejudice protesters.
In closing, notwithstanding my views on how GAO might rule on
particular facts, I agree wholeheartedly with your views on the
limitations of a contract officer’s authority. FAR 6.302-1(d)
and FAR 6.303 read together require a J&A to be executed prior
to awarding a sole source contract. And, FAR 1.602- 1(b)
prescribes that “[n]o contract shall be entered into unless the
contracting officer ensures that all requirements of law,
executive orders, regulations, and all other applicable
procedures, including clearances and approvals, have been met.”
Regardless of whether a contacting officer’s warrant authorizes
him or her to award contract in “unlimited” amounts, the
standard language on a U.S. Government’s SF 1402, Certificate of
Appointment, states: “Subject to the limitations contained in
the Federal Acquisition Regulation and to the following:
[Fill-in the Blank].” Unfortunately, some U.S. Government
contracting officers do not understand the principles of Agency
Law well enough to realise the express limitations upon their
authority to bind the U.S. Government.
Cheers,
Ned
|