By
Ramon Jackson on Tuesday, July 25, 2000 - 12:02 am:
Vern,
I'd certainly agree on the SCA issue. Good management tracks and
anticipates wage trends. In fact, for grossly underestimating
out-year cost based on known trends, an award fee reduction
might be in order under a management criterion in some
contracts! Quality of cost estimates, realistic projections and
"no surprises" should be something of award fee interest.
Ramon
By
Vern Edwards
on Monday, July 24, 2000 - 08:17 pm:
Ramon:
I agree. I think that J. Inman and I believe that it would be a
poor business decision to assent to an increase in a
contractor's fee merely because the Dept. of Labor has increased
the SCA wage rates, because the contractor would not have done
anything that would warrant such an increase. The increase in
fee would not would not reward the contractor for additional
effort.
However, the external mandates that you mention might require
additional contractor effort and thus might justify an increase
in fee, even though an agency program manager might not see the
benefit of it.
I don't think that compliance with the SCA is one of those
mandates. Offerors should anticipate SCA wage rate increases and
price their option year proposals accordingly.
By
Ramon Jackson on Monday, July 24, 2000 - 05:51 pm:
Vern,
You raise an interesting point here that may fall more into the
general category of reasonable behavior than rules and
regulations.
Prohibition of fee based on percentage of cost is a reasonable
effort to prevent a contractor from increasing profit by
inefficient or intentional additions to cost. Where the cost is
driven by an external mandate it would seem reasonable in many,
though probably not all, cases to adjust fee.
For example, considering that fee in part reflects reward for
effective mitigation of risks, it would seem a contractor
meeting a mandate issued during the contract from external
forces to reduce pollution throuch actions that increase cost
might be well deserving increased fee for doing so well and cost
effectively. All else aside, reaction to a legitimate government
directive -- at any level -- that changes cost could most fairly
be treated as a government directed change order even if the
agency, Department, or even government holding the contract did
not directly issue the order provoking the change. Knee jerk
"not my change" seems a good way to damage long term
effectiveness.
It would seem that a contractor presenting evidence of a changed
legal requirement that changes cost should have a change
proposal fairly and reasonably considered by the contracting
agency and a fee adjustment based on the normal process of such
changes.
Thoughts?
By
Vern Edwards
on Monday, July 24, 2000 - 03:15 pm:
J. Inman:
While I, too, would not willingly increase a contractor's fee
because of an increase in Service Contract Act wage rates, I do
not agree that doing so would create a
cost-plus-percentage-of-cost (CPPC) contract.
A CPPC contract is one that includes a contract term that makes
some element of the contractor's compensation a function of the
contractor's cost experience, so that as its costs increase its
compensation increases accordingly. A key attribute of of a CPPC
contract is the fact that the cost impact on the government is
not known at the time of contract award.
In Julie's case, she might be making an improvident business
decision by agreeing to increase the contractor's fee because of
an increase in the Service Contract Act wage rates, but in my
opinion she would not be violating the prohibition against CPPC
contracts, because (1) the contract itself does not make the
contractor's fee a function of its costs and (2) the parties
would know the size of the increase in fee before they sign the
contract modification. Moreover, an increase in fee under those
circumstances would not motivate the contractor to be
inefficient, because it would not entitle the contractor to
further increases in fee due to further increases in cost.
By
J. Inman on Monday,
July 24, 2000 - 11:11 am:
No, you should not increase the
fee because of an increased cost element -- if you did, you
would create a cost-plus-percentage-of-cost contract, which is
specifically forbidden. The contractor and Government agreed
that $xxx was the estimated cost to do a job, and agreed that $yyy
was an appropriate fee for the job. If circumstances prove that
the estimated cost cannot be met (either overrun or underrun),
the fee is still payable at the same agreed-upon amount. If the
contractor anticipated an underrun, would it ask for a reduction
in the award fee pool? No. Similarly, it cannot ask for an
increase in the award fee pool because of an overrun.
Note: This philosophy applies where there is no change in the
work statement -- a government-directed change in work, up or
down, may be a valid reason to adjust the fee. But where the
only matter at hand is an increased cost element, no change in
fee is warranted.
By
Vern Edwards
on Friday, July 14, 2000 - 02:34 pm:
FAR Subpart does not prescribe a
SCA/FLSA price adjustment clause for use in cost-reimbursement
contracts. (But see my parenthetical comment at the end of this
post.) This is probably because the Allowable Cost and Payment
clause covers the contractor for SCA/FLSA increases. However,
the parties should adjust the estimated cost of the contract to
reflect SCA/FLSA increases in order to avoid the appearance that
the increase is a cost overrun.
When awarding a cost-reimbursement contract you should include a
special contract provision to the effect that the parties will
adjust the estimated cost to reflect SCA/FLSA increases, and
that the contractor should not include any amount in an option
year estimated cost to cover such increases, but that there will
be no adjustment to fee. It will be up to the contractor to
decide whether or not to propose higher fees in the option years
in anticipation of the higher estimated cost.
You could tailor the clause at FAR 52.222-43 for that purpose by
changing "price" to "estimated cost."
(The clause matrix in FAR Subpart 52.3 in my Commerce Clearing
House edition of the FAR indicates that the clause at FAR
52.222-43 is required-when-applicable in cost-reimbursement
service contracts, so does the matrix at the Air Force FAR Site,
but not the matrix at the GSA website. Go figure.)
By
Julie A.
Talley on Friday, July 14, 2000 - 11:51 am:
Is a contractor entitled to
additional award fee under a CPAF Service Contract when wage
determination rates are increased?
FAR 52.22-43 Fair Labor Standards Act and Service Contract
Act-Price applies to fixed priced service contracts. Paragraph
(e) of the clause states any adjusmnents will be limited to
increases or decreases in wages and fringe benefits. It goes on
to state the increases or decreases shall not otherwise include
any amount for G&A costs, overhead, or profit. This is great if
you have a fixed price service contract, but what about a CPAF
conract?
If the increased labor rates increase the CPAF contracor's total
estimated cost, and the total estimated cost is the base for the
award fee, is he entitled to additional award fee? The
contractor is paid G&A on his actual cost, therefore paying G&A
on the increase is understood, but I'm not convinced he's
entitled to additional award fee. Can anyone help?
|