By James S on
Thursday, June 15, 2000 - 10:01 am:
Thanks Joel,
By the way the toilet seat and hammer were "explained" to the
Packard Commission in 1986 and I was present for the
explanation. Both were logical and valid costs. The toilet seat
was simply a crashworthy item - meaning that in the event of a
crash or hard landing the toilet and its contents would not
become missles within the cargo bay! Think about it and in what
location the toilet was!!
In the case of the hammer, the
contractor had a process of adding a % of the order on top for
material handling. This cost however was not allocated on the
basis of cost, but on the "quantity". In the same order as the
hammer were major components and the ordering surcharge was
applied by dividing the total by the number of items being
bought and that amount added to each item's cost. Thus the
hammer absorbed the handling costs for much more expensive
items.
An interesting reaction to this
was provided by Herb Stein, Economist and banker. He remarked
that we not only live by the sword, but by accounting rules. In
some cases the accountants are mystified that citizens "just
don't understand"! Reporters however, and some politicians, love
it!
I still would like to have some written guidance, GAO, OFPP or
other references to help. These "requirers" have the ear of my
bosses!
By
joel hoffman
on Thursday, June 15, 2000 - 06:45 am:
James, another thing to consider
from a good business judgement standpoint is to not overextend
the level and extent of subcontracting involved in too broad a
scope of work. As you said, you need to consider the grouping of
supplies and services involved.
Aside from the fact that we probably used MILSPECS to buy the
toilet seats for the Lockheed C-5, Galaxy - one reason they cost
$600 each was due to markups on subcontracted parts. Same with
bolts and everything else.
Too broad a scope of work overextends the amount of
subcontracting with associated, unnecessary prime contractor
costs (a buyer gets involved; the prime has to run all
subcontracts and supply purchase orders through its accounting
department for payment,etc.; the shipping department may get
involved)and markups, additional delays, etc. The prime turns
into a supply and service broker. Your cost really goes up.
You definitely don't want a broker, simply to avoid separate
contracts for distinct lines of service or supplies.
Since you are charged with using good business judgement and
this is an obvious argument, it might help you in your
meeting......
By the way, I flew in both C-5a's (built in the late 60's and in
the C-5b (built in the early 80's) for several years and the
toilets and lavatories never had any running water, though
supposedly plumbed for water!!!
Happy Sails!
By James S on Wednesday, June
14, 2000 - 04:03 pm:
I found the references but they
do not help much in arguing. I can't get excited about having
concrete tests done in a lab on the same contract I get aluminum
alloys out of a specialty metals catalog.
The problems can be illustrated thus:
If I was buying copier leases for an office I could argue easily
to have an "on demand" repair service for the copier. It would
be somewhat of a stretch to add copier paper which is generally
available but say that I could argue that the delivery of paper
could occasion a copier "tune up" to improve performance. I
start having problems when I also buy drinking water, cups and a
cooler on the same contract and then when I add just about
everything that I could want for my office like pencils, binders
and furniture it starts again looking somewhat logical.
It seems to me that the driving factor in my example is the
"natural" grouping of items from a single type of source (office
supply stores), or a single technology (like copiers and copier
services, toner. paper etc.)
My requirers have made their "natural group" themselves! and
what their several different organizations use for their jobs.
But the mix is getting wide, services, products, on-site work,
tools to do work etc. Their comments are "it is logical to group
all the things we need together, from several sources and select
what we need when we need it". Apparently for their preferred
items of one type they would choose from one award and for
another type of item they might choose from another.
To accomodate this diversity I'd have to have provisions that
are "ordered" on each order - like access to our facility,
shipping info or packaging needs for our remote offices.
This doesn't seem to be feasable - since to use my example, they
might buy copier paper from one awardee and toner from another
because it "performs" better. My comment is that if we made a
multiyear version of this I could sleep for three years and wake
just in time to solicit a follow on!
I have another meeting next Monday and I'd like to have some
plan/rationale for my groups.
By
Vern Edwards
on Wednesday, June 14, 2000 - 12:26 am:
James:
To the best of my knowledge DOD has not issued guidance in
reaction to the Valenzuela letters. It probably thinks that the
current guidance is adequate but that the Air Force and Army
simply went too far.
The Valenzuela matter was about a services contract, but I think
that the GAO's position applies equally to contracts for
supplies.
I don't know of any restrictions with regard to you helping
companies get together to form teams. Keep in mind that if you
slap too many different supply requirements together under one
contract the GAO may react unfavorably if someone protests. Make
sure you develop a sound rationale for your acquisition
strategy, one that takes all relevant policies into account.
Vern
By James S on Tuesday, June 13,
2000 - 10:52 pm:
Thanks Vern - just like an
automatic encyclopedia! I'll look these refs up tommorrow. If
this is a GAO opinion, has OSD or OFPP issued any guidance
regarding scope that could help me explain this situation?
Is it tied to services or to products?
We have needs from specialty metals to electonics to testing and
the number of bidders who can do it all is probably limited, but
teams could.
Are there restrictions in the assistance we can provide to the
public to assist in these players getting together or finding
each other?
By
Vern Edwards
on Tuesday, June 13, 2000 - 06:01 pm:
"Valenzuela" refers to two
letters from the Comptroller General to the Secretaries of the
Air Force and Army warning them not to issue solicitations for
IDIQ contracts with excessively broad work statements. The
citation for these letters is as follows: Letters to the Air
Force and Army concerning Valenzuela Engineering, Inc.,
(B-277979, December 9, 1997), dated January 26, 1998. (The
letter to the Secy of the Army is an attachment to the letter to
the Secy of the Air Force.)
The letter to the Secretary of the Army stated the issue as
follows:
"Statements of work that are too general provide insufficient
information for prospective offerors to decide whether to submit
a proposal or what to offer to best meet the agency's needs.
Also, inclusion of broad categories of work in one statement of
work constitutes a form of bundling, since different kinds of
work (or tasks in different geographical or technical areas) are
combined into one procurement, and an overly broad statement of
work can unjustifiably diminish competition just as bundling
does, by deterring businesses, particularly small businesses,
from competing for a contract, notwithstanding their ability to
perform some of the work at issue. See National
Customer Eng'g, 72 Comp. Gen. 132 (1993), 93-1 CPD ¶ 225;
Airport Markings of Am., Inc., et al., 69 Comp. Gen. 511
(1990), 90-1 CPD ¶ 543. Provisions or conditions that restrict
competition (such as bundling) are permitted only to the extent
necessary to satisfy the contracting agency's needs. 10 U.S.C.
2305(a)(1)(B)(ii); National Customer Eng'g, supra."
By James S on Tuesday, June 13,
2000 - 05:47 pm:
In an attempt to build an IDIQ
we are getting some homoginized requirements that after some
negotiations with users have become quite broad. It is to be a
multiple award contract and thus tasks will be competed but one
attendee to Monday's meeting quoted a "valenzela" case where the
GAO railed about the scope of a solicitation being so broad as
to be unbiddable and thus non competitive. Can anyone help me
locate this? Is there some way to levy some specificity out of
my requirers and not let them say put in everything and say
"we'll define things in a delivery order". I feel myself getting
pushed into a much too open ended a situation.
|