By
bob antonio on Tuesday, November 07, 2000 - 06:13 am:
The Comptroller General (CG) and
the U. S. Court of Federal Claims (COFC) are the dominant forums
for bid protests. However, since March 1999, less than 400
formal decisions have been issued. There are quite a few that
are dismissed. The COFC has issued 6 decisions for the
protesters. Three of these have been decisions that turned
around Comptroller General decisions. Counting the decisions for
the government, there are only a few handfuls of COFC decisions.
I cannot remember the resolution of the District Courts issue
but one of the reasons supporting them was that the COFC
justices could not travel out of town to hear cases. Maybe they
still ride in horse and carriage. Other organizations are using
the electronic media. However, it appears that Federal Courts
and U. S. Attorneys are just now discovering the internet.
How many forums for bid protests are needed and advisable?
Can their response time be improved using electronic media? Or
are they doing a fine job right now?
By
Joel Hoffman
on Tuesday, November 07, 2000 - 09:48 am:
Bob, I've been involved in
approximately 80 source selections. I have been protested three
times, 1 GAO protest, 1 GSBCA protest and 1 Agency protest. In
each case, the protests were groundless and eventually we
prevailed. In the meantime, critical projects or service
contracts were held up. On a couple of our other projects
(someone else's source selection), despite prevailing in the
decision, the US taxpayers were stuck with millions of dollars
in delay costs, as a result of our inability to issue notices to
proceed. Somebody needs to be looking out for the public, as a
whole, in balance with the rights of individual firms. I can't
justify in my own mind how the American taxpayer was served by
us paying $8+ million dollars in delay costs on one contract (we
prevailed in the protest) - not to mention that the delay cost
money could have been used to fund one or more other critically
needed Air Force construction projects.
I think there are enough forums - we don't need to make it
easier to file frivolous protests. Thank God, the GSBCA no
longer has a stranglehold on protests involving "FIP" resources.
The protesters had their system practiced to a tee. Within
minutes of notification of award to the competition, they had
filed a protest - we were delayed over a year on one project.
When the protestor didn't like the verdict, they went to court.
The protestor's attorney admitted he made a living filing
frivolous protests. He was very sad when the Brooks Act was
repealed.
Yes, there are valid grounds for protest and yes, there are bad,
pro-Government GAO decisions. However, we don't need to make it
easier to stop a project, waiting for resolution of a protest.
That's my opinion. Happy Sails! Joel
By
Vern Edwards
on Tuesday, November 07, 2000 - 10:58 am:
Bob:
Protesters currently have four choices of forum: they can
protest (1) to the agency, (2) to the GAO, (3) to the Court of
Federal Claims, and (4) to the federal district courts.
Congress should act to keep protests out of the federal courts.
The courts have better things to do.
By
bob antonio on Tuesday, November 07, 2000 - 11:20 am:
In a protest, the probable
outcome is defeat for the protester. However, if a protest is
sustained, a protester has a shot at a procedural remedy or bid
and protest costs. One procedural remedy may be to reopen
discussions and apply the principles of the decision. I wonder
how many such remedies resulted in a different awardee. On the
other hand, the awarded cost of bidding and pursuing a protest
soothes some of the successful protester's pain.
I believe Vern's opinion that Courts should be eliminated from
the process has merit since they deal with few protest issues.
Here is a possible solution and I think at least some of it was
mentioned here before. The awarding agency issues an initial
decision. That decision may be appealed to the CG.
Now, who should have the authority to award bid and protest
costs in a sustained protest?
Any other ideas?
By
bob antonio on Tuesday, November 07, 2000 - 11:46 am:
I forgot to mention one thing. A
study needs to be done to see if the procedural remedies result
in different awardees to a signficant percent. If they do not,
the protest laws need to be changed to prevent the protest forum
from having an effect on the instant procurement. The protest
forum should be limited to the award of bid and protest costs.
With that limitation, our attorney friends would still have
clients, a disappointed offeror could still make its point, and
the protest forum could continue to provide guidance.
By
Ramon Jackson on Tuesday, November 07, 2000 - 11:59 am:
Costs to the taxpayers in delays
due to trivial protests are not trivial. I like Bob's idea about
preventing a protest from having an impact on the instant
procurement. I'd also approve of a penalty for a protest
determined to be trivial.
What fixes in law might be desirable to better balance things
between the firms' and public's interests?
By
John Ford on
Tuesday, November 07, 2000 - 03:33 pm:
Although Vern and Bob have
advocated for keeping the courts out of the protest arena, there
are mechanisms available there to deter frivolous
protests/suits. One is the ability of the COFC to award attorney
fees to a prevailing party in certain cases. This includes the
government. Thus, if the government could recover attorney fees
from a protestor this might deter some of them. The second
mechanism is the imposition of costs against an attorney if the
attorney does not make a good faith inquiry into the merits of
an action (s)he brings. Charging attorneys the government's cost
of defending frivolous protests could act as a deterrent.
Finally, court rules also allow a party to recover some of its
litigation costs if it offers to settle a matter, the offer is
rejected and the other party ultimately recovers less than what
was offered in settlement. The losing party in this situation
gets to recover the costs it incurred after the settlement offer
was rejected.
By
C MERCY on Tuesday, November 07, 2000 - 03:49 pm:
Requiring protest to the agency
first is the right way to start this reform. Secondly require
protestors to post a bond along with their admin or judicial
appeals, as in civil cases(which these are after all is said and
done). If a protestor is sustained and there is a remedy other
than B&P costs then it is so ordered. If not, than the forum in
which the appeal is heard can order B&P expenses. No
anticipatory profits however.Suggestatiopns that the matter be
further studied are clearly correct. As an aside I remember
losing almost 500K in delay expenses in which the protestor was
never an interested bidder.
By
joel hoffman
on Tuesday, November 07, 2000 - 03:53 pm:
John, don't count on it. There
seems to be an inbred tolerance by GAO and the Government
agency's attorneys of misconduct by the protester's attorneys.
In my last protest, we discovered that the unsuccessful
offeror's (read: "protester") attorney illegally taped the KO's
debriefing without her knowledge. This came out when the
protester included a transcript of the debriefing in the protest
file. Despite the KO's anger, nothing was done by GAO.
The next problem was an obvious violation by the attorney of the
"protective order". A protective order is issued to keep the
attorney from disclosing protected information submitted by the
Government, such as specific information in the winning
proposal, names of source selection officials, names of
references contacted for past performance information, etc.
The protester's attorney filed an amended protest, asserting
that a reference wasn't qualified, due to the nature of her
specific job duties, as it relates to the incumbent (the
"protester"). Not only was she well qualified, the attorney
didn't contact anyone in the Government to determine what her
duties and qualifications were - the very detailed info came
from the protester!!!!!! I insisted that action to impose
sanctions be taken, our attorney's reluctantly agreed,
complained to GAO - and NOTHING came of it.
You may remember that the Contract Disputes Act also contains
provisions in case of false, frivolous or pumped up claims, HA
HA HA HA HA HA HA HA HA!
Happy Sails! Joel
By
joel hoffman on Tuesday, November 07, 2000 - 03:59 pm:
In my opinion, adding a step to
require an Agency protest, first, just adds another step, more
delays, ties up more agency resources and can result in
questionable decisions - depending upon the qualifications of
the agency counsel assigned to resolve the protest.
In a GAO protest, our local attorney's can ask for assistance.
In an agency protest, the folks they usually get advice from are
the ones deciding the agency protest! Happy Sails! joel
By
Vern Edwards
on Tuesday, November 07, 2000 - 08:20 pm:
Bob, Joel, John, Ramon, CMERCY:
Guys--Are protests really that much of a problem?
Notwithstanding the occasional horror story like Joel's, it
seems to me that the GAO does a good job. It decides protests
pretty quickly using relatively informal procedures, and it's
leading the way with time-saving procedures like ADR and
electronic filing. Some of its decisions are goofy, but not too
many.
The number of protests filed with GAO has been declining
precipitously. There were 1,220 protests filed with GAO in in FY
2000, down 13 percent from FY 1999, making for eleven straight
year of decline! And that's 1,220 protests out of millions of
contract actions if you include small purchases, and over
400,000 actions over $25,000. (See Federal Contracts Report,
October 31, 2000.) It doesn't strike me that protests are a
significant problem for the government at large, even if a
protest does loom large in the mind of a CO who has to deal with
it.
As I have said in another thread, requiring firms to protest to
agencies first isn't going to cut it. The typical protester
already distrusts the agency, that's why it filed the protest.
Joel's right--unless the agency decides to see things the
protester's way it's going to appeal any denial, so making
protesters file with the agency first will do little more that
increase the paperwork and the delay. Any agency that wants to
settle a protest after it's been filed with GAO can do so
easily.
Most "trivial" protests are simply reflections of the fact that
many firms just do not understand the contracting rules and COs
often do a lousy job of explaining them in plain English. Think
about the debates that we have about the rules, and we get paid
to understand them.
I say let well enough alone. Get the courts out of it (the
district courts are going away soon, anyway) and let the GAO do
what it's been doing since the 1920s.
By
Vern Edwards on Tuesday, November 07, 2000 - 08:33 pm:
In case you haven't got ready
access to FCR, here are the GAO FY 2000 protest statistics:
Cases
filed |
1220 |
Cases
closed |
1275 |
Went to
decision |
306 |
Sustained |
63 |
Sustain
rate |
21% |
ADR used |
144 |
Hearings |
54 |
The peak year for GAO protests was 1989; it received more than
3,300 in that year.
By
Ramon Jackson on Tuesday, November 07, 2000 - 09:13 pm:
Vern, the statistics you mention
are interesting. What may be missing is the more difficult
collection and analysis of drag effect. What is the cumulative
annual cost of delay? It is a difficult problem, but probably
significant.
One example (and I'll reserve comment on the government's
"wisdom" in doing things this way) would be a technical
development and delivery with interrelated efforts under
separate contracts. How many large scale, complex efforts have
seen fairly significant impacts beyond the particular effort hit
by a protest? We probably don't even know and dollar estimates
are probably not collected against a protest cost estimate. I've
seen the horror stories of something like a domino effect, but
they are stories, not data.
While I have little patience with agency ineptness that often
opens the protest door, too many offerors see the protest as a
low risk stop work order while they try for another bite. Some
seem to treat protest as a bit of punishment for not choosing
them or any other slight they think they suffered.
Standard risk assessment might show the penalty is moderate and
occurance rate low so protest. I think perhaps the risk level
should be raised so that it shows clearly on their screens as
they consider such action. Let them do some of the same sweating
the agency does on protest risk. The balance could be changed by
either changing likleyhood of damage or severity of damage. A
firm policy that a protest on weak grounds will result in
payment of some of the government's costs would therefore avoid
the more draconian punishments sometimes muttered in dark
corners by government people faced with significant delay in
projects.
By
joel hoffman on Tuesday, November 07, 2000 - 09:53 pm:
Vern, I agree with you that GAO
does a pretty good job. My pessimism was primarily in response
to John's idea that something could be done to penalize
frivolous protests.
I would like to see a higher standard established to invoke an
automatic stop on the awarded contract, considering the low
"sustained" rate. Too much waste when contract performance is
held up. The winner often loses key personnel who may have been
a factor in the selection. Pricing of key commodities are very
time sensitive. Contractors can typically only lock in on price
quotes for one to two months. Oh, well. Protect the rights of
one firm at the expense of the majority and the taxpayers. Happy
Sails!
By
bob antonio on Wednesday, November 08, 2000 - 08:17 am:
Vern:
Here is the issue I wanted to discuss.
1. I was asking whether a CG or COFC recommendation for
corrective action makes a bit of difference. For example, if a
forum recommends that discussions are reopened, does it result
in a change in the award. Probably not. However, this needs to
be analyzed to determine if the suggested remedies produce
results. If nothing changes after the recommended action is
taken, we end up with more process without a result.
2. If the CG's and the COFC's remedies produce no results,
should something change. If so, what change is necessary. If we
keep the status quo, we must accept the fact that the result is
to produce process and not results.
3. If we have these two organizations and the district courts
making recommendations that delay the award process with no
results, are all of these forums needed. If not, which one(s)
should remain.
4. Here is one possible change based on a finding that
recommended actions produce no results in procurements. First,
we keep the current agency process. Maybe we have a contracting
officer decision similar to a dispute. We need an appeal forum
but only one. That forum may award bid and protest costs only
and may not affect the award. There are no stays in the award
process and there are no recommeded actions for the instant
procurement.
By
Vern Edwards
on Wednesday, November 08, 2000 - 09:30 am:
Bob:
I do not know of any study of the effect of protest corrective
actions. I have often wondered how many times a successful
protester has gone on to win the contract. To the best of my
knowledge, no one keeps track. There were 63 sustained protests
in FY 2000. It may be possible to find out what happened by
calling the protesting firms or their lawyers. It may also be
possible to find out by checking FPDS or CBD award information.
Maybe I'll do it if I have time.
My own belief is that successful protests (i.e., sustained
protests) rarely change the outcome of source selections; I am
personally aware of only one or two cases in which they have. I
think that in most cases a sustained protest merely provides the
protester with procedural relief: re-consideration of its
proposal, inclusion in the competitive range, another round of
discussions and revised proposals, etc.
One argument that has been made in favor of the protest system
is that it keeps agencies honest, whether or not it changes
outcomes for protesters. A couple of economists advanced that
argument in a paper a few years ago. I have a copy of it
somewhere and if I can find it I'll post the reference here at
wifcon.
I might add that the delays resulting from protests are nothing
compared to the delays occasioned by poor acquisition process
execution by government agencies. I still see agencies taking
two and three years and longer to plan and execute acquisitions
for no other reason than simple incompetence. And talk about
costs--my industry friends tell me that agency exchanges with
industry [RFIs, DRFPs, presolicitation conferences, preproposal
conferences, RFP amendments (before and after receipt of
proposals), etc.] are costing them a fortune. I see agencies
going through two or more rounds of draft RFPs. These things
cost agencies money in two ways--first, the government
ultimately pays a large part of industry B&P costs through
indirect cost allocations; second, they raise administrative
costs and delay contract award.
Although I have no data, I believe that the inability of many
agencies to get their acquisitions off the ground in an
efficient and effective manner is a much bigger problem than the
cost of the protest system.
By
bob antonio on Wednesday, November 08, 2000 - 09:56 am:
Vern:
You mention 63 sustained decisions by the CG. Check this page of
the site
http://www.wifcon.com/protestsGAOcount.htm
When I was keeping score on the "Protests" page, I found that
there was a significant difference between the CG's numbers and
this site's numbers. So I contacted GAO's bid protest unit
several times to try to figure out the discrepancy.
Those 63 decisions may include more than one decision on a
procurement. For example, if separate protests are filed for
being excluded from the competitive range and for not receiving
meaningful discussions, that is 2 protest decisions at GAO.
Wifcon.com only considers a printed decision. So the 63 is
actually probably 50 written decisions on procurements in which
one or more decisions were rendered.
I agree with you and think that things can always be improved.
In my line of work, the status quo is always suspect. It doesn't
matter if it is a tweak or a major issue. We need constant
review and improvement. It is the only way we progress.
By
Ramon Jackson on Wednesday, November 08, 2000 - 10:14
am:
Vern, I agree -- with a vengence
you might say. I reserved comment about agency wisdom allowing
multiple contract dependencies to continue. Sometimes it is
difficult to avoid and part of that might be blamed on budget
process, but mostly it is lack of desire or ability to plan,
integrate and execute effectively.
The hidden cost of the blundering run up to the obvious
acquisition actions we most often talk about is probably huge.
It is not necessary to swirl to such extent, but it apparently
is almost the rule rather than exception. If every agency were
required to account for every hour and ODC in those swirling
run-ups to take off I suspect there would be general shock.
I believe Bob has put his finger on the real problem. What is
the purpose of the protest process if nothing changes? Using it,
as your economists thought to keep agencies honest is certainly
a blunt and rather useless tool where more precision is needed.
Let's take the case of a really sloppy acquisition. Punishing
taxpayers, end users, and other firms doesn't keep the
government honest. At best it is point focus on what is probably
a systemic problem. I once knew of a high level individual,
apparently largely responsible for an earlier protest, loudly
stating he didn't want to live through another while doing
things that could bring that about despite warnings. Due
investigation and removal or other penalties for those
responsible for the mess might have long term effect. At least
the worst offenders won't be around for deja vu all over again
(wasn't that a Yogi saying?) -- and again.
Possibly Bob's #4 with addition of authority by the appeal forum
to take direct action on those who made the government less than
"honest" would be useful. The only legitimate reason for
overturning a selection in my view is when the selection process
has damaged the taxpayers, not one of the firms.
By
John Huckle
on Wednesday, November 08, 2000 - 12:05 pm:
Maybe this should be the start of
a separate thread, but Vern makes a statement that his industry
friends say agency exchanges with industry during the
solicitation process [RFIs, DRFPs, presolicitation conferences,
preproposal conferences, RFP amendments] are costing them a
fortune. I don't doubt it. Anyone know of any studies on this
point?
By
Vern Edwards
on Wednesday, November 08, 2000 - 12:50 pm:
John:
Let me elaborate about what I hear from industry.
What they say they want in a solicitation is good information
about the requirement, the agency's terms and conditions, and
the evaluation factors and procedures. They say that in order to
respond to a DRFP they have to charge their time to B&P, and
that B&P funding is a scare commodity. They want agency
personnel to keep in mind that reviewing and commenting on
solicitations is not free. It costs time and that time has to be
charged to the B&P account.
They complain that many draft RFPs are issued prematurely,
before an agency has thrashed out its requirements and problems
internally, and that the final RFP is often drastically
different from the draft, not because of industry comments but
because of changes in agency strategy that were driven by other
considerations. They feel that their efforts in such cases are
wasted, but that they cannot afford not to at least review a
DRFP.
They say the same about presolicitation conferences, that they
are often conducted prematurely, with the result that the
agency's final strategy and solicitation are significantly
different from what was described at the conferences.
When I was doing research for the book about award term
contracting that I wrote for NCMA I noticed an interesting
phenomenon--procurements in which agencies issued five or six
CBD announcements about an acquisition over the course of many
months. In these cases the agencies were going to industry while
the acquisition was still evolving internally. On the one hand,
agencies are told to involve industry early, but on the other
they are not told that such involvement can be costly to
industry.
By
John Ford on
Monday, November 13, 2000 - 11:12 am:
Joel, going back to your post of
7 Nov, you should notice that I mentioned vehicles that are
available to the courts. Your response focused on fora which may
or may not have the authority to impose the sanctions requested.
There is no doubt the courts have the power to impose the
sanctions I described, and do impose them. As regards, the CDA
misrepresentation provision, if you check the COFC decisions,
you will find that that provision is frequently used in
proceedings before the court. It is one of what I call the Three
Amigos of suspected fraud. If fraud concerning a contractor's
claim is suspected and can be substantiated with proof, the
government will file at least three counterclaims based on
fraud. These counterclaims are based on the False Claims Act,
the CDA, and the Forfeiture Statute. The courts have
jurisdiction to determine fraud while the GAO and the BCAs do
not.
By
joel hoffman
on Monday, November 13, 2000 - 02:07 pm:
John, I originally responded to
your November 07, 2000 - 03:33 pm post, regarding sanctions for
"frivolous protests/suits." I said I doubted there would be the
will to take such actions. In today's post, you responded,
describing actions taken by courts against those committing
fraud or false claims.
There are huge differences between "fraud", "false claims" and
"false statements", which are criminal acts and the "frivolous
protests/suits", which are stupid acts or simply poor judgement.
Are you aware of any protests involving alleged "fraud"? I
suspect there are very few instances of "fraud", "false claims"
or "false statements" in protests. From my readings, I recall
these issues usually involve matters of differences in opinion
or judgement regarding factual material, rather than arguments
about facts.
I understand that the US Attorney's office must prosecute all
cases of fraud, false statements or false claims (criminal acts)
before the courts. This is something they are very reluctant to
do, unless it is a high profile (politically advantageous)case
or involves a great sum of money AND if they have an air-tight
case. High standards of proof, based on facts, are necessary to
prove fraud. My opinion is based on my experience.
As I said, I believe there are very few cases, if any, of
suspected fraud in COFC protest suits and likewise, in BCA
cases. That leaves "frivolous" issues (weak, groundless,
misinformed, misinterpreted issues?).
If a US Attorney is reluctant to prosecute criminal acts, do you
really believe they or the forums be interested in pursuing
sanctions for non-criminal, "frivolous" protests/suits, if they
were given the authority?
Certainly a BCA must have some authority over broken rules, such
as violations of their own protective orders, don't they (see
the example in my 7 November post where the BCA dropped such a
matter) ? Happy Sails! Joel
By
John Ford on
Wednesday, November 15, 2000 - 05:46 pm:
Joel, my comments about fraud
only responded to your comment concerning the misrepresentation
provision of the CDA. As regards frivolous protests or claims,
the powers granted courts by the Federal Rules of Civil
Procedure and the Rules of the United States Court of Federal
Claims are unique to the courts. What I suggested originally was
that the GAO and the BCAs be given similar powers. As it now
stands, they do not have the ability to impose meaningful
sanctions on either party. The point I was trying to make is if
these fora have explicit powers to levy sanctions short of a
dismissal, it would cause contractors to think twice before
submitting a fivolous protest/claim.
|