By
Mary Thompson on Wednesday, November 08, 2000 - 02:02
pm:
Need advise,
I was given a CPFF contract to close out, there are several
delivery orders that were issued under this contract, some
issued in 95, 97 and 98 with O&E and ACI funds. My predecessor
failed to notify the govt of limitation of funds and in closing
out some of the Orders I discovered my company incurred cost
exceeding the funding value of the D.O. I know that the Govt is
not obligated to pay for any incurred cost exceeding the D.O.
value. I though maybe with ACI appropriated funds I could
transfer from surplus funds to those overrun Orders. Have any
one every experience this type of problem. Is there any hope for
recovering overrun cost?
Any reply would be greatly appreciated.
By
Eric Ottinger
on Wednesday, November 08, 2000 - 02:29 pm:
Mary,
What is the contract!!!!
If you have a CPFF term or completion contract, the "delivery
orders" should not be considered contracts and the LOF should
apply to the entire contract, unless there is specific language
in the contract which would limit expenditures for individual
orders.
(A "delivery order" under a CPFF contract is a contradiction in
terms. But strange things are done.)
Eric
By
Anonymous
on Wednesday, November 08, 2000 - 02:47 pm:
You cannot use ACI funds to pay O&E bills or vice versa.
By
Vern Edwards
on Wednesday, November 08, 2000 - 05:03 pm:
Eric:
Couldn't you have an IDIQ contract that calls for the
manufacture and delivery of custom products under CPFF clauses?
I realize that it would be unusual to have a CPFF contract for
supplies, but it would not be illegal or impossible. In what way
would it be a contradiction in terms?
By
Eric Ottinger
on Wednesday, November 08, 2000 - 05:13 pm:
Vern,
Sure,
You could have a definite CPFF order under an ID/IQ vehicle.
No way you can have an indefinite ID/IQ under a defintite CPFF.
However, strange things are done.
In any case the LOF either applies to the CPFF as a contract or
the order as a contract, not both. (Albeit, there may be other
Ts & Cs which limit the funding available for each order.)
Eric
By
joel hoffman
on Wednesday, November 08, 2000 - 05:28 pm:
Well, we are planning to issue an RFP for a $500-800 million
CPAF, ID-IQ, Systems Contract to
design-construct-systemize-train-operate-close/remove a Chemical
Weapons Demilitarization Facility, pretty damn quick. Is this
"no way"? Happy Sails! joel
By
Vern Edwards
on Wednesday, November 08, 2000 - 05:48 pm:
Eric:
Maybe Mary has an IDIQ contract with CPFF clauses or a CPFF
contract with a completion line item and an IDIQ line item.
By
Eric Ottinger
on Thursday, November 09, 2000 - 12:46 pm:
Joel,
Let’s eliminate completion type which would be really illogical.
If the term form is intended, FAR 16.306 (d)(4) “The term form
SHALL not be used unless the contractor is obligated by the
contract to provide a SPECIFIC level of effort within a definite
time period.”
(I guess you could argue that CPAF is entirely a different
animal. I don’t believe it. But, it would be an interesting
argument.)
Which is the overarching vehicle?
A definite order under an indefinite ordering vehicle makes
sense. An indefinite ordering vehicle under an overarching
definite vehicle strikes me as Alice in Wonderland.
However, quoting Robert Service, “Strange things are done… "
Vern,
Separate line items with different contract types are
effectively separate contracts with different terms and
conditions.
Again, what is the contract? To what does the LOF apply?
Eric
By
joel hoffman
on Thursday, November 09, 2000 - 02:04 pm:
Eric, if we are speaking about my systems contract, it is a
CPAF, task order contract with an overall scope of work, in
several phases, which cannot be totally definitized due to
several reasons. The Government will provide design criteria for
the systems contractor to complete the design, then build,
systemize, operate and remove. The work will be issued through
task orders.
I don't see why a CPFF completion form would be "illogical", had
we not decided to use an incentive approach (CPAF). Each task
order can include a description of the scope of work by stating
a definite goal or or target and specify an end item, product or
result. In each case, the systems contractor will define the
scope through design, construction, systemization plans,
technical approaches, studies and reports, etc.
In fact, this would be the appropriate form of CPFF, if that
contract type had been chosen - not the term form.
Happy Sails! joel
By
Eric Ottinger
on Thursday, November 09, 2000 - 03:09 pm:
Joel,
First, I am glad that you agree that CPFF (or CPAF) can be a
tasking contract. There are some authorities who seem to be
oblivious to this fact.
However, since FASA, the term “Task Order” can only be used for
indefinite quantity contracts.
FAR 16.501-1 Definitions.
““Task order contract” means a contract for services that does
not procure or specify a firm quantity of services (other than a
minimum or maximum quantity) and that provides for the issuance
of orders for the performance of tasks during the period of the
contract.”
However, the terms “task assignment” and “technical instruction”
are commonly used for tasks under a CPFF term contract.
FAR 16.306 Cost-plus-fixed-fee contracts.
“ The completion form describes the scope of work by stating a
definite goal or target and specifying an end product.”
If you can’t fully specify the end product at the start of the
contract I would say that you have a UCA or a contract type
other than a completion contract. I can’t see how a CPFF
completion type would be appropriate for a contract “which
cannot be totally definitized.” However, you could write
separate contracts for each phase or definitize a separate line
item for each phase. (Note, that I am not considering CICA
issues here.)
Getting back to Mary’s issue. To what does the LOF apply? Does
she have one LOF at the level of the overarching contract
vehicle, or several LOFs, one for each cost type order?
Eric
By
Mary Thompson on Thursday, November 09, 2000 - 06:18 pm:
Let me first thank you all for taking the time to address my
problem. In reading your responses I have learned a great deal,
as I am yet a novice, hopefully this will help paint a clearer
picture of the situation.
Anonymous,
I agree that ACI and O&E funds can not be intermixed with one
another, based on the Anti-Deficiency Act, but what I really
want to know is can ACI funds, which is multiyear funds, be
transferred from (the same pot of money but different years)
year to year and if so what is the duration. With that concept,
staying with the same type of money can O&E money be transferred
from one order to the next.
Eric and Joel,
I’m not sure what you mean by “what is the contract” but here is
a stab – I’m looking at the SOW, and it calls for engineering
and technical service. The contract itself is an ID/IQ, cost
reimbursement, with LOF. According to the contract it states
each D.O. “Delivery order performance (CPFF term and completion
delivery orders)” and sites the FAR clauses for both provision.
There is not additional T&Cs in each DO, as the main contract
governs each. Each order states the one LOF that is applicable
to hours.
I hope this helps, you all have, and again I thank you.
By
Vern Edwards
on Thursday, November 09, 2000 - 09:09 pm:
Mary, Eric, and Joel:
This thread started with Mary saying that she has to close out a
CPFF contract under which several "delivery orders" were issued.
This prompted Eric to say, first, "A 'delivery order' under a
CPFF contract is a contradiction in terms," and then, "No way
you can have an indefinite ID/IQ under a definite CPFF," and
then, "An indefinite ordering vehicle under an overarching
definite vehicle strikes me as Alice in Wonderland."
Joel then said that he has a job which must be done in phases
"which cannot be totally definitized... . The Government will
provide design criteria for the systems contractor to complete
the design, then build, systemize, operate and remove. The work
will be issued through orders."
This prompted Eric to say, "If you can't fully specify the end
product at the start of the contract I would say that you have a
UCA [undefinitized contractual action?] or a contract type other
than a completion contract. I can't see how CPFF completion type
would be appropriate for a contract 'which cannot be totally
definitized.' However, you could write separate contracts for
each phase or definitize a separate line item for each phase."
The exchanges between Eric and Joes don't have anything to do
with Mary, and I think that they reflect a big misunderstanding
between Eric and Joel.
I think that Joel has a CPFF completion type contract for a
chemical demilitarization project with clearly defined
performance objectives, but which must proceed in phases based
on a design-build-operate-dismantle basis.
The contractor must design a system, then build it, then operate
it to do the demilitarization work, then dismantle the system
and go home.
The contract says that the contractor must obtain the
government's approval before proceeding with each phase of the
work. Thus, the contractor must obtain the government's approval
of its final system design before it can build the system. After
building the system, the contractor must get the government's
approval of it as built before it can begin the demilitarization
work. Finally, the contractor must receive the government's
approval of the demilitarization work before it can dismantle
the system, collect its fee, and go home.
Joel's agency is using what it calls "task orders" to authorize
the contractor to proceed with each phase. Each such order
specifies the performance objectives for the next phase of the
project based on the work done in the previous phase.
Joel -- Am I close?
This kind of thing can be done under a performance-based CPFF
completion contract (or CPAF completion contract) with an
estimated cost, or a ceiling cost, or even a "guaranteed
maximum" cost. It is also possible to use a progressive pricing
scheme, pricing the work as you go along, but such schemes have
CICA implications. Fixed-pricing isn't out of the question, but
it's risky.
Such a contracting approach is not a contradiction in terms,
Alice in Wonderland, or illogical. Such contracts must be
administered with great skill lest the government's approval
process unduly delay the contractor and lead to cost overruns
and demands for additional fee.
If I have this right and if there has, in fact, been a
misunderstanding between Eric and Joel, then I suggest that it
was due to loose use of terminology.
By
Vern Edwards
on Friday, November 10, 2000 - 11:12 am:
Mary:
Here is your most recent statement of your question:
"[W]hat I really want to know is can ACI funds, which is
multiyear funds, be transferred from (the same pot of money but
different years) year to year and if so what is the duration.
With that concept, staying with the same type of money can O&E
money be transferred from one order to the next."
I'm not sure that I understand that question, but I'm going to
take a stab at answering it anyway, as follows:
Appropriated funds can be obligated at any time during the
year(s) for which they are available, whether the funds are
annual (one-year) or multiple-year. As a general rule, if
the government obligated funds on an order, but the contractor
did not use all of the money, then the government can deobligate
the excess funds and reobligate them on a different order, as
long as it does so within the year(s) for which the funds were
available for obligation. This is true of both annual and
multiple-year appropriations.
My authority for making those statements is the General
Accounting Office publication, Principles of Federal
Appropriations Law, Second Edition, Vol. II, p. 7-52, which
says:
"Funds deobligated within the original period of obligational
availability are once again available for new obligations just
as if they had never been obligated in the first place.
Naturally, any new obligations are subject to the purpose, time,
and amount restrictions governing the source appropriation."
On the other hand: "Funds deobligated after the expiration of
the original period of obligational authority are not available
for new obligations."
WARNING: The agency that hired your company may have
internal policies that further regulate deobligation and
reobligation.
But this answer does not resolve your real problem, which is
that your company exceeded a limitation of funds without
notifying the contracting officer and getting his or her
approval to continue working. What you really want to know is:
"Is there any hope for recovering overrun cost?"
Mary, that's an entirely different question. If the
contract applied the Limitation of Funds clause to individual
orders, and if your company exceeded the limitation on an
order without obtaining contracting officer approval, then the
government probably doesn't owe your company any money.
So even if the government can deobligate excess money from one
or more orders and reobligate those funds to cover the excess
spending on another, it may not be willing to do so.
The point that Eric has been trying to make is that the standard
language of the Limitation of Funds clause applies to the entire
contract and not to individual orders. If the government
intented to apply the clause to individual orders, then it
should have said something in the contract to that effect.
Is there a clause in your contract that indicates that the
Limitation of Funds clause applies to individual orders? Do
individual orders state the funding limitation applicable to
them? If the answer to those questions is yes, then you are
facing a potentially more complicated problem than funds
availability.
By
joel hoffman on Friday, November 10, 2000 - 05:31 pm:
This is Mary's thread, so I won't belabor my point. I thought
I knew what kind of contract that Army's OSC is going to issue.
It is an indefinite quantity contract, CPAF type. Every scope of
work will be issued through task orders. first, there will be a
"management task". Then, the rest of the work will be added by
individual tasks. When I said that the work cannot be "definitized",
I meant that it could not be accurately estimated for FFP type
task orders, because there are too many variables. That's all. I
thought Eric was saying it is improper to have a CPFF or CPAF
completion type, indefinite quantity contract. --- back to Mary.
Happy Sails!
By
Vern Edwards
on Friday, November 10, 2000 - 07:46 pm:
Joel:
I think that Eric did say that a CPFF completion type contract
is inconsistent with an IDIQ contract. But I should let him
speak for himself.
I thought that you had a completion type contract with an
ordering provision to authorize the performance of the work in
phases. It appears that I got that wrong. I now understand you
to say that you have a "completion type, indefinite quantity
contract." In that case, I agree with Eric that the terms of an
IDIQ contract seem to be inconsistent with the terms of a
completion type contract.
Oh well, who knows?
By
joel hoffman on Friday, November 10, 2000 - 10:46 pm:
????
"16.501-2 General.
(c) Indefinite-delivery contracts may provide for any
appropriate cost or pricing arrangement under Part 16."
I believe our Design-Integration contract (active since circa
1985) is a CPFF ID/IQ. This is the A-E services contract under
which 7 of the Chem-Demil, Incineration plants have been
designed.
Our Chem-Demil umbrella contract for all work in Russia is
either CPAF or CPFF and is ID/IQ.
Didn't know we couldn't do this. The Acquisition Plan for the
Russian contract was approved at DOD level. Don't know if there
was such a thing as an acquisition plan back in the 80's. I
wasn't in this program, then.
Happy Sails!
By
Vern Edwards
on Saturday, November 11, 2000 - 09:22 am:
Joel:
The issue isn't the pricing arrangement per se. The issue is the
notion of a contract which calls for the contractor to complete
a project, but under which the government promises only to buy a
minimum quantity of services, which is all that the government
promises to do under an IDIQ contract.
By the way, I didn't say you couldn't do what you're doing. I
don't think this is a regulatory issue. I think its an issue in
business logic.
I can see calling for completion of a project in phases with
written authorization required prior to the initiation of each
phase, which is what I thought that you were doing on your demil
job. But I think that the appropriate instrument for that is a
contract that calls for a mutual commitment to the project. It
seems strange to say that the contractor is required to complete
a project under a contract which requires the government to buy
only a minimum quantity.
While I don't think it makes business sense, I don't think it's
illegal. I believe that the IRS is using that approach on its
modernization contract and that the GAO has gone along with it.
I know of one other agency that is planning to use the approach.
By
joel hoffman
on Monday, November 13, 2000 - 08:47 am:
I understand. Thanks. Happy Sails! Joel
By
Eric Ottinger
on Monday, November 13, 2000 - 12:03 pm:
All,
You can have goose in a flock but you can’t have a flock in a
goose. You can have a house in a subdivision but you can’t have
a subdivision in a house.
You can have a cost type order (or fixed price or T&M, etc.)
under an ID/IQ, but I can’t imagine an indefinite, min/max ID/IQ
under a definite, cost type contract.
It Mary has an ID/IQ with ten CFAF orders, there should be ten
separate LOF ceilings, which seems to be the case.
As I think Vern is well aware, it is somewhat of an
oversimplification to say that the overrrun will not be funded
if the notification was not provided in a timely fashion.
(I should note that I have had more frustration with government
people and contractors who think that quantum meruit requires
the Government to fund every overrun, no matter what the
circumstances might be.)
I would ask whether the overrun was foreseeable. I would ask
whether the overruns and underruns wash. If Mary’s problem is
simply a question of reallocating the funding that has already
been obligated on the ID/IQ, that might be a reasonable thing to
do.
I think Joel’s arrangement is de facto a firm cost type contract
with several options, which haven’t been negotiated. However,
since the FAR frowns on unpriced options, the ID/IQ approach is
a pragmatic workaround. I don’t question that it is a sensible
business arrangement for the work that he has described.
Per Vern, “The point that Eric has been trying to make is that
the standard language of the Limitation of Funds clause applies
to the entire contract and not to individual orders. If the
government intended to apply the clause to individual orders,
then it should have said something in the contract to that
effect.”
Au contraire. Each order should be treated as a separate
contract and there should be an LOF ceiling in each order.
However, If I were Mary, I would take a hard look at the
contract and the orders, to see exactly what the contract says.
Vern,
My controller friends tell me that since the M account fiasco,
the rules have been rewritten. It is no longer proper to fund
previous year overruns out of current appropriations. For a
previous year, it is possible to deobligate unused funds off of
one contract (or order) and reobligate the same funds on a
different contract (order) to cover an overrun. I have relied on
the expertise of our Government comptroller types to advise me
in these matters and Mary should do the same.
In short, I think the answer to the her question is a tentative
"Yes", but she will need some expert help to get this sorted
out.
Eric
By
bob antonio on Monday, November 13, 2000 - 12:24 pm:
Eric:
I believe you have it just about correct on the deobligation.
However, I believe it goes into an "expired" account and cannot
be reobligated. It is available for expenditure under the
circumstances in this piece of legislation.
"Sec. 1553. Availability of appropriation accounts to pay
obligations
(a) After the end of the period of availability for obligation
of a fixed appropriation account and before the closing of that
account under section 1552(a) of this title, the account shall
retain its fiscal-year identity and remain available for
recording, adjusting, and liquidating obligations properly
chargeable to that account."
The law is at
http://www4.law.cornell.edu/uscode/31/1553.text.html
By
Eric Ottinger
on Monday, November 13, 2000 - 12:38 pm:
Bob,
If the satute says that the funds will be available for
"adjusting", I believe that might cover Mary's situation.
This is not an area where I have any particular expertise.
However, I would note that we could get into some situations
where it would be very inequitable if the Government didn't have
some freedom to make "adjustments."
I believe the funding would lose its identity (i.e. funding
line) and it would be reobligated under a new funding line. If
you mean, that you can't reobligate exactly the same funds, that
would be correct.
However, the cognizant authorities may view Mary's ID/IQ as one
big contract (notwithstanding my arguments) for this purpose,
and they may not find it objectionable to shift some of the
funding from one order to another order.
Eric
By
joel hoffman
on Monday, November 13, 2000 - 01:19 pm:
I'm not sure about your particular contract but am familiar
with DOD type one-year appropriation O&M funded, contract
limitations. On an O&M funded contract, the original year
appropriations must be used for in-scope changes and
modifications, unless no longer available. Expired O&M funds
remain available for in-scope changes/modifications, until all
such funds are exhausted. Thus, one usually cannot use current
year funding, for example, to fund fund changes or overruns on
those contracts - until all of the original year funds are
exhausted, even if they are "expired funds".
By
joel hoffman on Monday, November 13, 2000 - 02:11 pm:
Bob, is this the Statute covering my situation? Happy Sails!
Joel
By
Mary Thompson on Monday, November 13, 2000 - 04:02 pm:
All thanks ever so much for your expertise:
Vern,
Yes, me over all question is “Is there any hope for recovering
overrun cost”.
Based on everyone responses I’ve been busy reading the main
contract and each delivery orders and here is my discovery:
The Coast Guard awarded an ID/IQ cost reimbursement contract
that states among other things, that delivery orders will be
issued as cost plus fixed fee term and completions. The main
contract does quote the Limitation of Funds clause, but does not
state that it’s applicable to individual orders. Strangely
enough, there are provisions in the main contract that spells
out organizational conflict of interest for “Preparing Work
Statements”, “Obtaining Access to Proprietary Information”, and
“Preparing Specifications” and it states very clearly that these
items are “applicability of this clause will be established on
individual delivery orders”, so does this mean that the LOF
clause is applicable to each order regardless if the delivery
order states it? In checking each order some of them incorporate
the LOF clause in the order and modification(s) and some don’t.
For those delivery orders that do not incorporate the LOF clause
we have overruns.
I am still investigating each order to see if any of the
overruns were foreseeable. Inclusively, the overruns and under
runs will wash and in fact when its all said and done there will
be funds to de-obligate.
I’ve experience a situation were the contracting office
de-obligated funds from one delivery order to cover overruns of
another order. I’m aware that it depends on the agency and the
relationship with the agency and contractor (I was brought on
only to close out the contract and therefore have not
established a relationship with the CO and the way this look,
not a good start).
What I’m fighting here is a contracting specialist who is
discussing with her legal department the choice of paying for
overruns. According to her legal dept. they say it’s
inappropriate and illegal to transfer funds that was used or
appropriated for a specific task to another task (but in
reviewing some of the orders it states for instance: D.O 005
begins upon the expiration of D.O. 01). Which to me mean that
the tasks are related to each other and/or at less funds from
D.Os 01 and 05 can be transferable.
Eric and Bob,
What you stated, “It is no longer proper to fund previous year
overruns out of current appropriations…. and re-obligate the
same funds on a different contract to cover an overrun”. Eric
Bob, “… it goes into an “expired” account and cannot be
re-obligated” is precisely what the Contracting Specialist is
saying. She indicated that when she de-obligate the funds from
the under run order that the funds will be lost and that its no
way to save the funds to obligate them to the overrun orders. I
am hoping to find some FAR clause or legal terminology that will
support my request to transfer funds. Thanks Bob I will check
out site provide.
Again, Much appreciation To All!!!
Mary
By
joel hoffman
on Monday, November 13, 2000 - 05:44 pm:
Mary, This is an appropriations law issue, not a FAR issue. I
suggest you have your attorney check 31 U.S.C. para. 1502(a).
Your Resource Management folks should also be familiar with the
procedures.
I took the following quote from the Judge Advocate General's
School, U.S. Army 145th Contract Attorney's Course Deskbook
(Jul/Aug 2000).
" Expired funds retain their 'fiscal year identity' for five
years after the
period of availability. During this time, the funds are
available to adjust existing obligations, or to liquidate prior
valid obligations but not to incur new obligations."
I don't know what Department you work for, so the US Code
reference may vary
for Civilian vs. DOD.
Happy Sails! joel
By
joel hoffman
on Monday, November 13, 2000 - 05:50 pm:
Mary, the above cite from the Army's JAG Deskbook clarifies
my earlier statement that expired funds remain available until
exhausted - they remain available until exhausted or up to five
years after period of availability, whichever comes first. Happy
Sails! Joel
By
bob antonio on Monday, November 13, 2000 - 06:45 pm:
Joel and Mary:
I was not following this thread closely. However, I saw you
discussing appropriations. The law is at 31 U.S.C. 1551 to 1558.
The law is here:
http://www4.law.cornell.edu/uscode/31/ch15.html
Basically, if money is deobligated beyond its fiscal year, it
goes into the "expired account" with its identify. It keeps its
identify because of the old problems with the "M" accounts. It
cannot be reobligated. However, it can be used to pay off
appropriate expenditures until it is closed. The specifics are
in the law that I cited. The Red Book discusses this clearly at
about Part 5.
By
joel hoffman
on Monday, November 13, 2000 - 08:34 pm:
Assuming several things here, from what I read:
1. Mary's contract had a limitation of funds clause.
2. The Government failed to place a limitation of funds on
individual delivery orders, which use different type funding,
thus erroneously allowed overruns in some appropriations, while
others have underruns.
3. Mary needs some funds which would be made available by
de-obligation from one delivery order to fund another order?
4. Mary's contract specialist considers this a new obligation?
I believe that the prohibition on re-obligating funds applies to
NEW obligations. Isn't Mary's case a situation where "the funds
are available to adjust existing obligations, or to liquidate
prior valid obligations but not to incur new obligations?" Of
course, it also depends on when the underfunded task order was
issued - presumably while the funds were unexpired. Happy Sails!
joel
By
bob antonio on Tuesday, November 14, 2000 - 05:20 am:
Here is a tutorial on financial management. Go to the
following page and scroll down.
http://www.wifcon.com/bonafidecontents.htm
By
Eric Ottinger
on Tuesday, November 14, 2000 - 09:21 am:
Mary and All,
By chance Carl Peckinpaugh addressed the overrun issue in FCW
this week. Peckinpaugh cites a few cases, but there a numerous
relevant cases available in CCH and other authorities.
http://www.fcw.com/fcw/articles/2000/1113/pol-carl-11-13-00.asp
My friend in the controller’s office tells me that there is no
distinction between prior year funds that were never obligated
and prior year funds which have been deobligated. It is all the
same, from the point of view of DoD 7000.14-R Chapter 10.
(However, if the deobligated funds are used to cover an overrun,
there will be a new ACRN and a new funding line.)
Notwithstanding the prohibition on new obligations, the prior
year funds can be used for claims and adjustments (including
overruns).
CON 210; Government Contract Law Course Text; (1999 Edition)
“4-7. An expired obligation is no longer available for new
obligations. Under the former successor or "M" Accounts (31
U.S.C.1551 et seq.), obligated balances retained their fiscal
year identity for two years, then were merged into successor
accounts having no fiscal year identity, but retaining purpose
identity, and remaining available indefinitely. Unobligated
balances retained their fiscal year identity for two years in a
surplus account similar to obligated balances. Currently, while
obligated but unexpended balances and unobligated balances
retain their fiscal year identity for five years after their
expiration date, they may not be used for new obligations.
Agencies have a five year window to settle contractor claims and
make other contract adjustments. After five years, obligations
must be satisfied out of current year funds.”
DoD 7000.14-R -- DoD Financial Management Regulation; Volume 3
-- Budget Execution -- Availability and Use of Budgetary
Resources; December 1996
Chapter 10
“C. Title 10, United States Code, section 7313(b), and
applicable appropriation language, permit expired appropriations
available to the Department to be used for new obligations of
appropriations for specific purposes. Those include payment to a
Working Capital Fund activity and payment to a contractor for
unusual cost overruns and changes in the scope of work for ship
overhaul, maintenance, and repair.
1. While expired appropriations may be used in certain instances
for new obligations, these appropriations are not available
beyond the end of the fifth fiscal year following their
expiration.”
Just for clarity-- The Section I “Limitation of Funds” clause
requires a separate full text clause in the contract to
establish to LOF ceiling. I don’t think it matters whether the
Section I clause in is in the orders, but there should be a full
text clause specifying the LOF ceiling in the order. If the
order is fully funded, I would assume that Limitation of Cost
applies.
Eric
By
joel hoffman on Tuesday, November 14, 2000 - 09:47 am:
Thanks, all. The AF "Fiscal Law Tutorial", found at Bob's
link, covers the subject of period of availability well - it
clearly states that adjustments and in scope changes are fair
use of the expired funds. Happy Sails!
By
Vern Edwards
on Tuesday, November 14, 2000 - 06:46 pm:
Mary:
I think that it is significant that some orders incorporate the
LOF clause and some don't and that your overruns occurred on the
ones that don't. Allow me to suggest at this point that if the
amount of money is significant, you should discuss the problem
with a competent government contract law attorney. You need
professional advice.
Vern
By
Mary Thompson on Tuesday, November 28, 2000 - 12:19 pm:
Thanks all for your help in this matter. |