By
Eric Ottinger
on Tuesday, January 02, 2001 - 01:08 pm:
In the January issue of
“Contract Management” there is an interesting case regarding
Limitation of Cost and ID/IQ contracts with Task Orders: “Marine
Design Technologies, Inc.” ASBCA 43142, 43914, 99-1 BCA 30,224
(January, 1999).
Each task order had a separate LOC.
The contractor’s business base was shrinking, the actual
overhead rate was increasing. The contractor waited for the
audit report before providing notification to the PCO.
The ASBCA decided that the overrun was allowable for some of the
earlier task orders because the contractor had no particular
reason to anticipate the rate increase before these task orders
were complete. The overruns on subsequent task orders were not
considered allowable because the contractor should have seen the
rate increase and provided notification while the task orders
were ongoing.
This seems like a pretty straightforward application of the
foreseeability rule to me.
Robert D. Witte comments, “Ordinarily, limitation of cost is
inviolable … Seldom do courts or boards substitute their power
for that of the authorities who do the acquisition.”
This ties back to Mary Thompson’s inquiry regarding LOF on an
ID/IQ with CPFF orders.
For LOC/LOF purposes, each order under an ID/IQ is separate
contract. Depending on the circumstances during the period of
performance for each order, overrun costs may be recoverable on
some orders but not on others.
By
John Ford on
Tuesday, January 02, 2001 - 02:47 pm:
Eric, I hope you are not relying
on this case to support your last paragraph. The Board applied
the LOC clause to each order because there was a clause in each
of the contracts at issue that explicitly made the LOC clause
applicble to each DO issued under the contracts. The Board did
not hold as a universal truth that each order under an IDIQ
contract is to be treated as a separate contract for LOC/LOF
purposes or for any other purposes. In this regard, the language
of the LOC/LOF clauses refers to the "contract" not to "orders"
under the contract. Moreover, FAR Part 16 does not state that
each order under an IDIQ contract is to be treated as a separate
contract. It does say orders under a BOA are to be treated as
separate contracts though. Finally, there is an earlier ASBCA
case dealing with withholdings under T&M contracts that says
that each DO under an IDIQ contract is not considered a separate
contract. If you have some other authority to support your
statement, please share it with us as it would be most useful
and would eliminate the need to use special clauses such as
those used in this case.
By
Eric Ottinger
on Tuesday, January 02, 2001 - 03:46 pm:
John,
Could you provide the ASBCA cite. Was this before or after FASA?
We went around this issue in an earlier thread in the previous
“Water Cooler.”
“Contract” is defined under FAR 2.101 Definitions.
““Contract” means a mutually binding legal relationship
obligating the seller to furnish the supplies or services
(including construction) and the buyer to pay for them. IT
INCLUDES ALL TYPES OF COMMITMENTS THAT OBLIGATE THE GOVERNMENT
TO AN EXPENDITURE OF APPROPRIATED FUNDS and that, except as
otherwise authorized, are in writing. In addition to bilateral
instruments, contracts include (but are not limited to) awards
and notices of awards; job orders or task letters issued under
basic ordering agreements; letter contracts; ORDERS, such as
purchase orders, under which the contract becomes effective by
written acceptance or performance; and bilateral contract
modifications. Contracts do not include grants and cooperative
agreements covered by 31 U.S.C. 6301, et seq. For discussion of
various types of contracts, see Part 16.”
Note particularly, that funds are obligated by the order under
an ID/IQ.
FAR 16.501-2(c) allows the orders under an ID/IQ to be any type
under Part 16. Part 16 is “Types of CONTRACTS.” If the order is
a “contract” as defined in FAR 2.10, and each order has a
contract type and everything that goes with the contract type
(like an LOF or LOC), how can we conclude that the order is not
a contract.
If I can risk a side comment, I think it is interesting that we
are even debating this issue.
Eric
By
John Ford on
Thursday, January 04, 2001 - 04:46 pm:
Eric, the ASBCA case was before
FASA. I cannot remember the name of the contractor only that it
began with an S.
The definition of contract does not appear to cover orders under
IDIQ contracts. Thus, I don't find that helpful. As I mentioned
before, the ASBCA decision you commented on was based on
specific language in the contracts involved that made the LOC
clause applicble to individual orders. It did not rest on a
universal truth that each order under an IDIQ contract is to be
treated as a contract. So far as I have been able to tell, no
board or court has held that they are.
If they are, it seems to me that it would have been unnecessary
for the FAR to say orders under BOAs are to be treated as
separate contracts. If IDIQ orders were intended to be treated
in the same way, the FAR would have said so. Silence on this
point indicates that they are not.
Turning to the definition of "contract" in the FAR, it expressly
mentions BOA orders, but does not mention IDIQ orders.
From what you have said, I take it your statement is based only
on your interpretation of the FAR instead of board or court
decisions or an express term of the FAR directing that such
orders be treated as individual contracts.
We are discussing this because this point is not clear, and I
believe many agencies are resorting to the practice of including
special clauses like the one in your case. As I stated in my
earlier post, if you have some authoritative pronouncement that
such clauses are unnecessary, it would allow for their
elimination.
By
joel hoffman on
Thursday, January 04, 2001 - 05:31 pm:
Eric, You appear to be using the
FAR 2.101 definition of "contract" to base your argument that
each task order on an IDIQ contract is a "separate contract."
Then, it must follow that every "bilateral contract
modification" is a separate contract, for the same reasons. I
don't think anyone here believes that a bilateral contract
modification is a "separate contract." Is there another source
for your belief? Happy Sails! Joel
By
Eric Ottinger
on Friday, January 05, 2001 - 09:54 am:
Joel,
Good Point.
We agree that a FASA task order/delivery order is a “contract”
as defined in FAR 2.101 It is a, “mutually binding legal
relationship obligating the seller to furnish the supplies or
services … and the buyer to pay for them.” Also, each order
obligates “the government to an expenditure of appropriated
funds.”
Further, FAR 2.101 includes “…; orders, such as ….”
The ID/IQ ordering vehicle is a “contract” by this definition
because the seller is obligated to furnish and the buyer is
obligated to pay for the minimum.
(However, the idea that we obligate ourselves to acquire a
minimum quantity of dollars always makes my head hurt. But we
do, frequently.)
The order under the ID/IQ is also a “contract” by this
definition. We can have a "contract" under a "contract."
An ID/IQ is an “indefinite” vehicle and a CPFF is a definite
type of contract. (See MUSCHANY ET AL. v. UNITED STATES; ANDREWS
ET AL. v. SAME., (Feb. 05, 1945) “Congress, by changing the
original prohibition in the act from one outlawing any
“cost-plus” system of contracting so as to expressly authorize
use of a “cost-plus-a-fixed-fee” form of contract, indicated it
did not care how the contractor computed his fee or profit so
long as the fee or profit was finally and conclusively fixed in
amount at the time when the Government became bound to pay it by
its acceptance of the bid.)
(See also, FAR 16.306 (4) “The term form [of CPFF] shall not be
used unless the contractor is obligated by the contract to
provide a SPECIFIC level of effort within a DEFINITE time
period.”)
The idea that a specific contract can be definite and indefinite
at the same time seems illogical to me, to the point of
absurdity.
A contracting officer who writes a CPFF contract with indefinite
characteristics is skating on very thin ice for the reasons
cited in Muschany.
Part 16 isn’t mix and match; pick a few clauses from column A
and pick a few clauses from column B. However, I am sure that
some offices have done exactly that.
Eric |