By
Eric Ottinger on
Monday, April 17, 2000 - 03:59 pm:
All,
"Ask a Professor" came up with an answer, sort of. Since it
appears that nobody knows, I would say that we are all equally
correct.
http://askaprof.deskbook.wpafb.af.mil/normal/
qdetail2.asp?cgiSubjectAreaID=4&cgiQuestionID=5601
"I agree with you that there appears to be no clear answer to
this issue at the current time. It appears to be an open
question of law. I have reviewed cases involving the "Christian
Doctrine" but none of them appear to address this issue either.
Litigation over the issue (before the Board of Contract Appeals
or U.S. Court of Federal Claims) may conclusively answer this
issue some day. If you deny the equitable adjustment request,
then you may give rise to a claim which may ultimately decide
the question through litigation. To speculate on the law or how
the courts may ultimately resolve this matter goes beyond the
scope of this forum."
Eric
By
Eric Ottinger on
Thursday, March 2, 2000 - 12:44 pm:
I put “Christian” into the
search for the Ask A Professor site. I note that one of our
number has appealed our controversy to another forum. I predict
this will put the good Professors into a “do loop” and it will
be a while before we see an answer.
http://askaprof.deskbook.wpafb.af.mil/normal/
qdetail.asp?cgiQuestionID=5601&Search_Text=Christian
I found the following snippet interesting.
“Can a Contractor wonder if the Government's Contracting Officer
may use the Christian Doctrine as a means to get a clause into a
contract "IF" it was left out? Yes. Could this be overturned in
Court? Yes!”
I think this supports my argument that only a judge has the
authority to determine whether the Christian Doctrine applies to
a contract. The rest of us can allow for some “litigation risk”
uncertainty if it suits our purpose.
Eric
By
Eric Ottinger on
Thursday, March 2, 2000 - 11:30 am:
Going back to an earlier post,
Linda asked whether there was any need to do a modification. It
did cross my mind that a letter from the Contracting Officer,
citing the statute and informing all of the contractors that
payment will be henceforth by EFT, would be one option for her
to consider.
This would do for the instant case. However, we should keep in
mind that ACOs, auditors, payment office personnel, TCOs, etc.
will regard the written contract as holy writ. Generally, we
should be careful not to give them opportunities for confusion.
Regarding consideration, I can make numerous pragmatic arguments
to the effect that (putting aside the clauses where litigation
has established that the Christian Doctrine does appy) there
will be very few cases where you can’t justify consideration (or
an equitable adjustment, if appropriate). Mostly, you don’t know
for sure whether the Christian Doctrine applies. That little bit
of “litigation risk” should be enough, in most cases, to justify
anything that you need to do.
(In the instant case, the statute is pretty forceful but the
Treasury Department Regulation leaves plenty of room for a
waiver.)
Breaking these into categories suggested by the case law—
Cases where the cost impact is in the area of contingencies.
That is: termination costs, anticipated profits.
I think the cases generally support a “no cost” approach.
Cases where the cost impact is “system” impact (i.e. CAS).
Pragmatically, you can assume that even if the clause has been
improperly omitted from one contract, you will probably find the
clause in another similar contact. This is a good opportunity
for benign neglect or nominal consideration.
Cases where the Government makes a determination and the
determination is subsequently reversed by whoever (e.g. the wage
rate and transportation cost cases cited).
The Christian Doctrine doesn’t really apply.
Cases where there is a significant impact on a “direct cost”
cost element.
I didn’t notice any and I’m not sure that I am going to worry
about this very much. If it comes to it, I will let my Counsel
earn his/her pay.
Eric
By joel on Wednesday, March 1,
2000 - 05:55 pm:
John, it depends on the specific
situation. Each instance is usually unique. Your example
indicated that the Government took a unilateral credit. The
Christian Doctrine or "reverse Christian Doctrine" or whatever
you want to call it doesn't mean the Government can make
automatic, unilateral price adjustments. One must review the
facts of the case.
(A price adjustment normally involves a "change" or an action
under some other clause or contract term. The Christian Doctrine
doesn't involve any
"change" to the contract.) Happy Sails!
By
John Ford on
Wednesday, March 1, 2000 - 03:09 pm:
Joel, the appeals boards and
courts recognize the reverse of the Christian Doctrine. If a
clause is prohibited, either by statute or regulation having the
force and effect of law, such as the FAR, it is read out of the
contract as a matter of law. Adopting Vern's argument, since the
clause is not in the legal contract, as contrasted to the
written contract, from the beginning, because it was prohibited
from the beginning, what is there to adjust and what would you
negotiate? Is it your position that the government has an
entitlement to a price reduction? If so, on what basis?
By
Eric Ottinger on
Wednesday, March 1, 2000 - 02:57 pm:
Joel,
I agree, but I didn't intend to express any opinions. I should
note that the message cited was mostly verbatim out of Court
opinions.
I don't believe that the Christian Doctrine has any application
to solicitations.
Eric
By
joel hoffman
on Wednesday, March 1, 2000 - 12:48 pm:
John- In the case you presented
(your Wednesday, 1 March, 9:53AM post), the Government included
an extraneous clause. I believe the Government should not
unilaterally adjust the contract in attempting to remove the
clause. This has nothing to do with "Christian." It is clearly a
change to the contract requirements. If it reduces the cost of
performance, it is because the Government wants to change the
terms of the contract. The Government should negotiate an
equitable adjustment under the Changes clause.
Eric - Re: your Tuesday, 29 Feb, 5:04 post. I agree that the
Christian Doctrine is not intended to be broadly applied to all
missing items from an RFP or IFB. For instance, wage rates are
one area in which the FAR specifically provides procedures for
including the correct wage rates, classifications and fringe
benefits in the RFP/IFB. The FAR also explains what to do in the
event they were omitted, superceded or when incorrect rates have
been included. Those procedures involve issuing a change to the
contract to incorporate the correct rates/classifications, etc.
If the corrected rates or labor classification (e.g., Heavy
Constructiuon vs. Highway vs. Residential, etc.) affect the
Contractor's costs, an equitable adjustment is required. I've
often dealt with those situations.
Anyway, I find it hard to believe that there is a case where the
Government tried to simply include corrected or new wage rates,
citing the "Christian Doctrine," then denied a request for an
equitable adjustment! This reveals some ignorance in the
workings and effect of wage determinations on the bidding
process.
Finally... Vern - hey I love you too, man! I wasn't really mad.
We apparently were looking at the same solution to your
hypothetical situation from different approaches. Hopefully mine
doesn't give the Contractor the impression that I'll pay him to
"go away" (avoid a claim).
Happy Sails! Joel
By
Eric Ottinger on
Wednesday, March 1, 2000 - 11:55 am:
Getting back to basics, I
understand that a Court has the authority to apply the Christian
Doctrine. I’m not sure that a Contracting Officer has that
authority. (Which is not to say that the Contracting Officer
doesn’t have authority to fix the problem in the contract.)
The Christian Doctrine is punitive. The Contracting Officer gets
slapped for ignoring the law and for ignoring the written
direction from his superiors. The Contractor gets slapped for
being foolish enough to be a party to this improper behavior. At
that point the Court can’t and won’t do anybody any favors.
A Contracting Officer, trying to clean up after an error has
been made, isn’t a Court and I doubt he is under any particular
obligation to punish either himself or the contractor.
My only conclusion from this is, that although the Court is
bound to be inflexible and not give either party any more or
less than what the contract says, when the Court applies the
Christian Doctrine, the Contracting Officer is not required to
approach the problem in the same punitive way that the Court
would. The Contracting Officer can be more flexible because
there is no need to punish either party, yet.
(I guess a Contracting Officer is always free to punish himself,
albeit that may get a little strange. I am beginning to doubt
that a Contracting Officer should punish the Contractor for the
Government’s error.)
(The Court is obliged to put the clause in because (1) the
clause implements the law and (2) the Contracting Officer had no
authority to ignore the policy direction from his higher
authorities. However, the Contracting Officer, acting before the
Court gets involved, is mostly concerned with complying with the
law and he may choose to do a one-time deviation (with the
necessary approvals) and put somewhat different language into
the contract.)
We usually assume that the proper thing for the Contracting
Officer to do is to the same thing that a Court would do in the
same circumstances. It appears to me that this is an exception
to that rule.
Noting that no one styled Esquire had been brave (or foolish)
enough to jump into this discussion, I remembered that three of
them had published an article on the Christian Doctrine, readily
available at the Venable web site.
http://www.venable.com/tools/hightech/christndoc.htm
John,
Going back to your February 25 post, the lawyers at Venable
distinguished the situation where the Government made a formal
determination at time of contract award, which was subsequently
reversed; from the situation where the Government failed to make
a determination. In the first instance the contractor may be due
an equitable adjustment; in the second, probably not.
I think the cases that you cited fit the first model.
Regarding your most recent post, we already know that the Courts
apply the Christian Doctrine in a way that tilts toward
protecting the Contractor when the Government ignores it’s own
policies.
Vern,
I asked for a case where the Court negated something explicitly
negotiated between the parties without some consideration for
the Contractor. It turns out that the case is “Christian!”
(I wonder if a Court would distinguish a case where the parties
both intended to subvert written policy from a case where the
parties were simply in error. Would an honest but erroneous
interpretation of current policy be similar to the determination
which is subsequently reversed.)
Getting back to Linda’s issue, I think I would cite the law but
I would not make any reference to Christian. The simple fact is
that DoD, by law and Treasury Department Regulation, is no
longer allowed to pay by any means other than EFT (with a few
common sense opportunities for a waiver.)
Since this should be a Win/Win I would proceed unilaterally on
that basis until some contractor hands me a cogent objection.
Eric
By
John Ford on
Wednesday, March 1, 2000 - 09:53 am:
Let's put the shoe on the other
foot for a while. I wonder what everybody thinks the outcome
should be in a reverse Christian situation, i.e., where the
government has wrongfully incorporated a clause in a contract.
Under this hypothetical situation, the clause requires the
contractor to do something it would not otherwise be required to
do under a proper contract, thus increasing its cost of
performance. This increased cost is built into the contract
price. The government discovers its mistake post-award, deletes
the clause from the contract and unilaterally reduces the
contract price to reflect the decreased cost of performance to
the contractor. Does the contractor have a meritorious claim for
a restoration of the contract price?
By
Eric Ottinger on
Tuesday, February 29, 2000 - 05:04 pm:
All,
I put "Christian Doctrine" into the CCH and did a word search.
There were 80 hits. More than half of these were duplicates or
cases where the judge decided that the Christian Doctrine did
not apply.
Christian Doctrine cases don't seem to be very numerous.
Herewith a few snippets touching issues we have discussed.
APPLICATION OF CHRISTIAN DOCTRINE:
US-FED-CLAIMS, 43 CCF 77,445, Gold Line Refining, LTD. v. United
States, (Mar. 25, 1999)
8“It is well-settled that applicable provisions of the FAR are
incorporated into every federal government procurement contract
and have the same effect as if they were set forth in the
contract itself.” MAPCO, 27 Fed. Cl. at 407-408. Moreover, under
the “Christian Doctrine,” set forth in G.L. Christian and
Assocs. v. United States, 312 F.2d 418, 160 Ct. Cl. 1, reh’g
denied, 320 F.2d 345, 160 Ct. Cl. 58, cert. denied, 375 U.S.
954, 84 S. Ct. 444, 11 L. Ed. 2d 314 (1963), the “court may
insert a clause into a government contract by operation of law
if that clause is required under the applicable federal
administrative regulations.” General Eng’g & Mach. Works v.
O’Keefe, 991 F.2d 775, 779 (Fed. Cir. 1993). The Christian
Doctrine applies to mandatory contract clauses reflecting “a
significant or deeply ingrained strand of public procurement
policy.” Id. The doctrine also applies “to incorporate less
fundamental or significant mandatory procurement clauses if not
written to benefit or protect the party seeking incorporation.”
Id. at 780.
PRICE ADJUSTMENT FOR ADDING CLAUSE WHEN OMISSION WAS NOT MERE
ADMINSITRATIVE OVERSIGHT:
ASBCA, GOV-CONT 85,665 , BellSouth Communications Systems, Inc.,
(Sep. 27, 1994)
Labor--Price Adjustments for Changes in Wage
Determinations--G&A, Overhead, and Profit. As part of a price
adjustment for a modification adding Davis-Bacon Act clauses and
wage determinations for construction work included in a supply
contract, the contractor was entitled to recover indirect costs
allocable to the increased direct costs of the modification and
a reasonable profit because, under applicable FAR and DFARS
provisions, an equitable adjustment for an increase in mandated
minimum hourly wages and fringe benefits necessarily makes
provision for increased overhead and general and administrative
costs and for a reasonable profit, unless these factors are
expressly excluded by some pertinent contract provision. The
applicability of FAR Part 31, FAR Subpart 15.9, and DFARS
Subpart 215.9 made it unnecessary to apply or analogize to
Service Contract Act clauses expressly excluding indirect costs
and profit from price adjustments for changes in mandated
minimum wages under service contracts.
Interpretation of Contracts--Incorporation by Law--Davis-Bacon
Act. The Christian doctrine did not require that the Davis-Bacon
Act clauses and wage determinations be read into a contract from
the time of award, because a determination must be made by the
government that a particular contract is covered by the Act
before the contract is subject to the Act. Before award, the
contracting officer determined in good faith that the contract
was not covered by the Act. That determination was concurred in
by the Department of Labor and was not reversed until three
years later. Thus, this was not a case in which the Act was
clearly applicable at the time of award and in which the
omission of the required clauses and wage determinations was a
mere administrative oversight.
SUBSEQUENT MODIFICATION INCLUDING CLAUSE UNDER CHRISTIAN
DOCTRINE:
US-CT-APP-1, GOV-CONT 83,735 , Riggins & Williamson Machine Co.,
Inc., (Jan. 01, 1979)
Mistake not mutual; Christian doctrine incorporated wage
determination.--
A request for extraordinary contractual relief, alleging a
mutual mistake of a material fact in the implementation of
revised wage determinations, was denied for claims on two
contracts because under the Christian doctrine a modification
incorporated the determination into the contract. Both contracts
were subject to the minimum wage requirements of the Service
Contract Act. A required clause relating to fringe benefit
changes was incorporated by reference into one contract, but the
other neither included nor made reference to that clause. Since
the contract without reference or incorporation was executed
first, the contractor maintained that it had no notice of the
provision. However, a subsequent contract modification reflected
the parties’ agreement that the required clause was to be
included in the contract from its inception under the Christian
doctrine, which holds that required provisions are incorporated
into contracts by operation of law even though not expressly
included or referenced therein. In addition, the contractor
failed to prove that it suffered actual losses under the
contract sufficient to permit amendment of the contract without
consideration.
CHRISTIAN DOCTRINE DOESN’T APPLY WHERE MATTER IS EXERCISE OF
JUDGEMENT:
EBCA, GOV-CONT 93,145 , K.L. Conwell Corporation, (Apr. 06,
1988)
A subcontractor’s motion for reconsideration of his claim that
had been dismissed on the ground that he was not in privity of
contract with the government (88-2 BCA 20,597 ) was denied
because there was no requirement in law that a flow-down
Disputes clause be incorporated in the contract. The
subcontractor was dealing with a prime contractor who acted as a
purchasing agent for the government. If a flow-down Disputes
clause had been included in the contract, it would have provided
one of the indicia that the subcontractor was in privity of
contract with the government, which in turn would have permitted
the subcontractor to appeal his claim to the board. However, the
decision of whether or not to include a flow-down Disputes
clause is an act of discretion. The Christian doctrine, that is,
the rule that contract clauses that are required by law are
treated as though set out in the contract, does not apply to
those clauses whose incorporation is a matter of the exercise of
judgment.
DEEMED TO BE PART OF THE CONTRACT EVEN THOUGH OMITTED
DELIBERATELY
US-CL-CT, 38 CCF 76,360 , S.J. Amoroso Construction Co., Inc. v.
The United States, (July 02, 1992)
Interpretation of Contracts--Incorporation by Law--Intended
Omission.
Even if the government and a contractor intentionally included
in a construction contract the Buy American clause applicable to
supply contracts, the contractor was bound by the terms of the
clause designed for construction contracts, because the
construction clause was required by regulations that had the
effect of law. Under the Christian doctrine, a contract clause
required by law is deemed to be part of a contract even though
omitted. The doctrine applies even if the omission was
deliberate; the parties have no latitude to form a contract
contrary to procurement laws.
DELIBERATELY OR NEGLIGENTLY DOESN’T MATTER:
US-CT-APP-FC, 39 CCF 76,603 , S.J. Amoroso Construction Co.,
Inc. v. The United States, (Dec. 17, 1993)
As an initial matter, Amoroso contends that the Christian case
is inapplicable because in that case a clause was inadvertently
omitted whereas in this case clause 79 was intentionally
substituted for clause 34. 3 This distinction, as the Claims
Court held, is irrelevant. Application of the Christian doctrine
turns not on whether the clause was intentionally or
inadvertently omitted, but on whether procurement policies are
being “avoided or evaded (deliberately or negligently) by lesser
officials.” G.L. Christian & Assoc., 320 F.2d at 351. The
Christian doctrine “guard[s] the dominant legislative policy
against ad hoc encroachment or dispensation by the executive”
and prevents “hobbl[ing] the very policies which the appointed
rule-makers consider significant enough to call for ...
mandatory regulation” Id.; see also General Eng’g., 991 F.2d at
779. Moreover, the Christian doctrine echoes Supreme Court law
that the United States is neither bound nor estopped by its
agents who act beyond their authority or contrary to statute and
regulations. See Federal Crop Ins. Corp. v. Merrill, 332 U.S.
380, 384 (1947); see also Yosemite Park & Curry Co. v United
States [25 CCF 82,500], 582 F.2d 552, 558 (Ct. Cl. 1978); Porter
v. United States [20 CCF 83,041], 496 F.2d 583, 590 (Ct. Cl.
1974).
Eric
By
John Ford on Tuesday,
February 29, 2000 - 12:59 pm:
To All: For an interesting
recent case on the Christian Doctrine and how things can get
snarled up when trying to apply it, see Empresa de Viacao
Terceirense, ASBCA No. 49824 decided on 23 Feb. Interestingly
enough, no T4C clause was incorporated in the contract. The
government later incorporated a T4C clause and terminated the
contract for convenience. The contractor appealed. Without going
into great detail, the government incorporated the wrong clause
and the Christian Doctrine did not apply to the clause
incorporated by the government.
As regards Vern and Joel's latest discourse, how about a DoD
contracting office without a copy of the DAR? That actually
happened years ago. Another observation, small inexperienced
contractors are frequently more difficult to deal with than
large experienced contractors who know the rules.
By
Vern Edwards
on Tuesday, February 29, 2000 - 10:23 am:
Joel:
Think of me as a compassionate conservative.
Vern
(Sorry, I couldn't help myself. I love ya, Man!)
By
Vern Edwards
on Tuesday, February 29, 2000 - 10:15 am:
Joel:
I don't think you are a foolish, heartless idealist. I think
you're tough, but that's okay. I have taken the same stance that
you have on occasion. In short, I don't have a problem with what
you've said, but I wouldn't share that opinion in every case.
Hard-won and bitter experience has taught me that sometimes it's
better to settle than to litigate on principle.
I hope you realize that my example was just that--designed to
illustrate a point. I wouldn't give an FPI(F) contract to such
an inexperienced firm. But agencies have and do, and I can
provide you with specific examples.
I do what I call "charity" work for my state government,
advising small businesses who have or want government contracts.
I wonder if you would be shocked to know how many small (and
large) businesses that I have encountered who have contracts
above the simplified acquisition threshhold with the Department
of Defense, and who don't own a current copy of the FAR and who
have never heard of the DFARS, much less the service-level FAR
supplement.
In any event, if I were actually standing in front of your
soapbox, I would applaud and offer to buy you a beer, even if I
wouldn't always stick to my guns.
Vern
By Joel on Tuesday, February 29,
2000 - 10:05 am:
Before I get a lecture from
anybody about FPI-FT contract types, I don't have a fundamental
problem in increasing the firm target cost by $5,000. That is -
if it was because both parties realize that applying the missing
clause in question will cost the Contractor more than they both
originally bargained for when they negotiated target price and
firm ceiling. If so, this is a reasonable solution.
But that isn't the reason Vern cited in the example below for
the "price increase".
According to the example, the decision was simply based on
avoiding the hassle and expense of making a decision and
defending the POSSIBLE consequences from an ignorant contractor.
THAT reason makes my stomach turn, because it is short sighted,
thus "penny wise and pound foolish."
Happy Sails!
By joel hoffman on Tuesday,
February 29, 2000 - 08:59 am:
Ok, Vern. This example struck a
RAW nerve. This is one reason the Government routinely ignores
existing performance requirements and pays extra taxpayer money
to obtain compliance. I don't have any sympathy for the
Contractor in the example.
The Contractor sought out Government work, in a program which
offers essentially non-competitive opportunities to
participants. The Government didn't twist its arm to accept this
million dollar plus business opportunity.
No body in their right mind should offer a contract of the more
complex contract type (FPI-FT) in your example, if they are
dealing with a firm "that doesn't even own a copy of the FAR."
There is a huge difference between this and a typical FFP supply
contract! No contractor should accept such a contract type
without fully understanding the nuances and contract
requirements. Participating in large, complex contracts isn't a
game. It isn't something to be taken lightly. Don't get into the
business if you "don't even have a copy of the FAR!"
To base a decision to pay the dear firm $5000 of my money out of
fear or apprehension of any claim and appeal, especially by such
a firm on that issue is penny wise and pound foolish. I've
called bluffs of much bigger contractors on MUCH more
contensious issues than whether or not they have to certify
"cost or pricing" of subcontractors. "Cost or pricing" data is
really little more than a breakdown of how the firm developed
its costs, to provide some accountability and truthfulness
during negotiations. Please quit overblowing the intent of TINA.
Everyone seems to think there is zero cost or risk to a firm to
pursue an appeal and litigation! Once they hire an attorney, at
their expense, they should realize the fultility of fighting
this particular example. In my experience (I was responsible for
negotiating ALL 8(a) and sole source JOC and construction
contracts for one of the largest Corps Districts for 8 years) a
firm, such as described here, will rarely expend the legal cost
and effort to appeal a decision of the type described here.
Sometimes I wonder who y'all are trying to really save the money
and effort involved in standing up for what is right.
Avoiding claims by shoveling out money ultimately results in
more claims. The firm learns that the
Government has no resolve, even in matters of small dollar
amount or in which the Government thinks it is right. Other
firms quickly pick up on this. Standing up for your rights -
when you are right - sends a signal that the contractor must
know what it is getting into before signing a contract or look
elsewhere.
By the way, the "big, bad Government" is vastly more fair to
contractors than the commercial world, States and
Municipalities, if you take any time to review and compare the
litigated issues in the various court and board decisions.
I'm sorry I got on this soap box but people have no idea what
Pandora's boxes they open by not standing up for their contract
rights. The repercussions extend way beyond the "cost of the
instant defense". Throwing in the towel should be the last
resort.
Ther are many other ways to achieve MUTUAL (Win-Win) success in
controversial matters than simply paying the Contractor to go
away, then not realize he'll be right back on the next issue,
expecting the same reaction. Careful, deliberate communication
with the Contractor to resolve disputes or disagreements is
essential and is the key to long term mutual success, not
dropping an issue to avoid a possible claim.
OK, let me have it for being a foolish, "heartless" idealist!
Happy Sails!
By
Vern Edwards
on Monday, February 28, 2000 - 08:27 pm:
John:
I'm afraid that you have not convinced me that a contracting
officer may reform a contract on the grounds that an agency
insists on interpreting a contract to include a mandatory clause
that was inadvertently omitted.
I'm not sure that a board or court can or would do so. If they
could or would, then do you know of an instance in which a board
or court reformed a contract when invoking the Christian
Doctrine?
That would convince me.
I am not an expert on the Disputes Act. I rely primarily on two
books for my understanding of the Act: Contract Disputes Act
Annotated, by Robert T. Peacock and Peter D. Ting (Washington,
DC: Federal Publications, Inc., 1998), and Government Contract
Disputes, by Peter S. Latham (Washington, DC: Federal
Publications, Inc., 1980). Nothing in those books indicates to
me that contracting officers have the authority that you claim
for them under the Disputes Act.
So I guess we'll will have to disagree. But I'd be grateful to
you if you could produce some authority that expressly supports
your position, because then I would learn that I am wrong, which
is the best education.
I have enjoyed communicating with you on this topic and look
forward to more such discussions.
Vern
By Ramon on Monday, February 28,
2000 - 06:43 pm:
Vern and John's interest in
avoiding litigation have another benefit. The government has
limited its options by being a difficult and often high handed
customer. The taxpayer's money should not be handed out
casually, but neither should their business agent be too joyful
about being able to force some relatively obscure legally
required clause they forgot to mention down the throat of that
inexperienced small business firm Vern mentions.
Doing so will insure the government has fewer options,
particularly in the technology areas where the best really do
not care to deviate from their purely commercial ventures. I'm
not sure "reform" and such has really altered the picture drawn
in the early 1990s showing government was simply not getting the
benefits of that market due to its unique practices and
conditions.
There are issues so important that use of the Christian Doctrine
must be used, but like another government power, war, it should
be reserved for truly important things. While I agree most
companies would love faster payments and cooperate on EFT,
somehow it does not seem to rise to the level of importance to
invoke this thechnique that will indeed seem unfair and leave a
lasting aftertaste. The company will quite likely say "It ain't
American" and tell the government to get lost next time it comes
around looking for goods and services.
By
Vern Edwards
on Monday, February 28, 2000 - 06:02 pm:
Steve:
Suppose that I am a KO and my agency has awarded a $13,000,000
sole source fixed-price-incentive (firm target) contract for
military supplies to an inexperienced small business firm that
doesn't even own a copy of the FAR, much less understands all of
the nuances of government contracting. (That's not as
unrealistic as it may sound.) The contractor submitted and
certified cost or pricing data, and the contract includes the
clause at FAR 52.215-10, Price Reduction for Defective Cost or
Pricing Data.
A few weeks after award the contractor requests a approval of a
$900,000 sole source subcontract and it is then that I realize
that the prime contract does not include the clause at FAR
52.215-12, Subcontractor Cost or Pricing Data, a required
clause.
I tell the contractor that he must obtain cost or pricing data
from the subcontractor. He tells me to show him where the
contract says that. I tell him about the missing clause and he
tells me that I'm right, the clause is missing, and it's not
part of the deal. He tells me that the clause will cost him
money and he doesn't want to accept it.
I tell him about the Christian Doctrine, and give him some cases
and some pages from all the right textbooks. He tells me that he
can't believe that the government can insert a clause after the
handshake and that he doesn't understand all the mumbo-jumbo in
the cases and the textbook. "It ain't American," he says, and
tells me to get lost.
I know that I can win this in court, but I worry about the
effect that a dispute like this will have on contract
performance and about the cost of an appeal. So I give the
contractor a choice-- agree to a bilateral modification to
include the clause in exchange for a $5,000 price increase (I've
verified that we've got the money), or face the prospect of a
dispute and costly appeal which he's likely to lose and which
will result in his having to accept the clause for nothing. I
tell him to consult with a government contracts attorney before
answering me.
He comes back and says that he'll agree. I fill out Standard
Form 30, block 13C, and insert FAR 15.408(d) as my authority and
a reference to see my memorandum for record. (Why not? I've
never known what to put in that stupid block anyway. I wish I
had a nickel for every lunch table debate I've listened to about
what to put in that block.)
I prepare a memorandum for record that tells the whole sad
story, complete with my mea culpa, act of contrition, and a
concluding statement to the effect that I think it's better to
pay $5,000 than to suffer through the almost certainly more
costly process of final decision, dispute, and appeal, not to
mention the possible effect on contract performance.
I take the whole package to my lawyer, tell him the story, and
ask him to give it his blessing, in return for which I'll let
him suggest a better entry for SF 30 block 13. Assuming that I
get the lawyer's blessing, I then go to my boss, confess my
failure, and ask her to back me up or come up with a better
idea.
That's it. The whole thing is jury-rigged to let the contractor
feel like he's gotten something for his trouble, keep
performance on track, and keep us out of court, where we would
probably win, but only after spending a lot more than $5,000. I
have no other justification for what I've done. I confess that
it's not by the book.
This may not be an entirely realistic scenario, but it serves to
explain my thinking.
By
John Ford on Monday,
February 28, 2000 - 04:51 pm:
We are either winding down on
this or starting to take off on another tangent which is common
for bull sessions. Before responding to Vern's questions and
comments over the weekend, I would like to reiterate somethings
I said earlier. I do not think there is a universal answer to
this question. Each situation will have to be judged on its own
merits. Also, as is the nature of these sessions, we sometimes
are not the most careful with the words we use, which results in
a point being missed by others or our positions not fully
understood. That leads me to some of Vern's questions and
comments.
As regards KOs being able to grant equitable relief, that is
somewhat of an overstatment. Certainly KOs cannot grant or
mandate equitable relief such as injunctions, declaratory relief
or specific performance. However, over time, the written law and
common law of government contracts have adopted equitable
principles as a part of that body of law. Through application of
these principles, it is permissible to amend contracts without
regard to the specific terms of the contracts. In other words,
grant relief external to the contract. Examples are reformation
or recission due to mutual or unilateral mistakes, refusal to
enforce contracts because of unconscionability, or relief for
impracticability. KOs have authority to grant much of this
relief although it may be characterized as some other form of
relief, such as a T4C when the action is taken. Another
equitable concept that has been adopted by the common law is
allocation of risk based on fault. Thus, if a wrongful
government act or omission causes a contractor to incur
additional costs, the risk of such increased cost is generally
assigned to the government. This is totally consistent with your
discussion of equitable adjustments in your Sunday message. This
is central to my argument that, in some circumstances, a
contractor may receive compensation for increased costs caused
by incorporation of an omitted clause into a contract.
The rationale for this has been alluded to by others in this
thread. The omission may be the result of a mutual mistake by
both parties in not recognizing the mandatory nature of the
clause to the particular contract, or a unilateral mistake on
the part of the government in not assuring that all requirements
of law have been met before awarding the contract. (The
contractor would only have an obligation to raise a question
concerning an obvious or glaring omission. However, it could
only raise the question, the final decision rests with the
contracting officer. If the contracting officer disagrees, the
contractor must follow the directions of the KO.) In either
event, reformation would appear to be the appropriate remedy.
The contract should be reformed to reflect the bargain the
parties would have reached had they known the true facts. This
includes the price of performing the work. Consideration is not
required in either event. This is not giving away money when
there is no entitlement. It is a well know and accepted
(equitable) practice in government contracts.
A couple of other points. A contract is not void merely because
a clause has been omitted. Contracting officers make mistakes
when acting within the scope of their authority. As long as the
contract was awarded using proper procedures and the KO
otherwise acted within the scope of his/her warrant, the
contract would be valid and not void or even voidable merely
because of the omission of a required clause.
Questions relating to whether a clause is incorporated into a
contract through the Christian Doctrine are disputes relating to
a contract. Such disputes are disputes for which there is no
remedy granting clause in the contract. Because there is no
clause captioned Christian Doctrine, or Mistakes, the appeals
boards and courts have jurisdiction to hear these disputes under
that jurisdictional prong. If these were not disputes relating
to a contract, the boards and courts would have no CDA
jurisdiction and could not hear the case.
Whether I convince you or others, I believe I have a sound
foundation for my situational argument. There is quite a bit of
agreement on this issue, despite the extensive debate over it.
As we all know, government procurment still has many unanswered
questions after all these years and we are all voicing our
opinions without any authority on point to support our
"educated" guesses.
By
Linda Koone
on Monday, February 28, 2000 - 03:51 pm:
First, my apologies for asking a
question and then being unable to contribute to the resultant
discussion, especially since I could have saved Vern some of his
effort in researching the origins of the EFT clauses.
What an interesting discussion, though!
When I posted the initial question, my opinion was that the EFT
clauses could be subject to the Christian doctrine. The ensuing
discussion served to strenthen my opinion. But I'm still just
weighing all of the options.
In any event, the discussion on modifications was interesting. I
agree with the position that the modification would be
unilateral and should cite the authority for the clause (i.e.,
PL 104-134 or 33 USC 3222). I wouldn't entertain any discussion
on consideration on behalf of the contractor for incorporating
the clause if indeed, the clause was part of the contract by
operation of law. That, to me, would be analogous to having the
contractor request consideration for complying to a clause that
was clearly called out in the contract but that he/she had
overlooked. Again, this is my opinion if we are talking about a
clause for which the Christian doctrine applies. I don't
disagree with Vern's approach of discussing it first before
issuing the modification. Staying out of the courts, once you've
had the experience, tends to be good advice.
My only question about modifying contracts would be is it
necessary? I can't tell from the cases that I've looked at
whether the CO actually modified the contract, since in essence,
under the Christian doctrine principle, the clause is already
there. A modification signifies a change, which isn't really the
case under this principle.
An interesting thing about the EFT clause (for those of us in
DoD) is that the CCR collects the information necessary to make
EFT payments. As such, contractors should be aware that EFT
payments are a distinct possibility.
I also believe that most contractors would be happy to receive
(dare I say timely) payment from the Government, regardless of
the form (check or electronic). I can't imagine a contractor
screaming about an absent EFT clause when the same contractor
has provided the information that would permit EFT payment and
has been paid via an EFT.
Linda
(Vern: Thanks for the kind words.)
By
Steve Aronson
on Monday, February 28, 2000 - 03:33 pm:
Vern,
I have followed and understand your arguments and why you would
do otherwise in a real situation as a preferred course to
litigating. what I do not understand, and what appears to be
echoed in your earlier submissions to this thread, is upon what
basis would you provide consideration for the contractor
agreeing to insert the text of the clause into the contract
document.
If it is stipulated, consistent with prior discussion, that by
operation of law the force and effect of the clause is already
part of the contract, then inclusion of the text in the contract
document is merely a nicety that does not impact the obligations
of the parties. If the obligation of the parties is not
impacted, upon what basis can the KO provide consideration?
Perhaps, foregoing a claim provides adequate consideration from
the contractor so that the bilateral modification becomes a quid
pro quo...?
By
Eric Ottinger on
Monday, February 28, 2000 - 03:08 pm:
Ramon,
It should be noted that this thread started out with an issue
regarding the transition from traditional payment to electronic
funds transfer. I doubt this is going to discourage many
contractors from doing business with the Government.
(I think we have wandered a long way from that initial question.
Maybe Vern can ask Linda what this was all about.)
I doubt that, in the big picture, many contractors have been
significantly harmed by the process of correcting Section I to
reflect the law at the date the contract was signed.
Usually, when a firm does itself significant harm dealing with
the Government, it is because the firm made the mistake of
underestimating the cost or intentionally low-balled, hoping to
get well in some fashion.
As Vern points out, there isn't much we can do for
self-inflicted pain, because we don't have authority to give the
taxpayer's money away, merely because we feel sorry for the
contractor.
Eric
By Ramon on Monday, February 28,
2000 - 02:18 pm:
Any creep away from limitation
to "significant government interests" would seem to be a clear
disincentive to participate in government contracts. Even
commercial contracts cannot ignore the law, but in government
contracts we have law of a clearly different flavor.
Commercial and government contractors should be responsible for
knowing law on clearly public rules, ie., equal opportunity. It
is something entirely different to expect a business to be fully
up on the arcane government uses of law in its own contracting
for social or other purposes. I keep thinking of a "required"
clause dealing with use of U.S. vessels for shipping -- on a
software contract requiring electronic delivery.
Extension of the doctrine beyond the most compelling situations,
as may have been suggested, would seem to be a very clear signal
to the contracting community that government contracts are
potential poison. As government becomes less of a driving force
in business, extension of the doctrine to less compelling cases
would seem to be a foolish move on its part.
By
Eric Ottinger on
Monday, February 28, 2000 - 11:56 am:
All,
I apologize for giving John a somewhat flippant reply.
However, when the contract is complete and the price has been
changed up and down several times, I don’t think anyone will
have much interest in distinguishing what part of the price is
consideration and what part is equitable adjustment.
Vern, I am glad to see that you are capable of pragmatism.
I prefer Joel’s strictly unilateral approach for pragmatic
reasons. The worst that can happen is that the contractor might
object and it might be necessary to do a subsequent bilateral
mod to bring things to closure. As Joel observes, the unilateral
approach works well almost 100% of the time (assuming that there
is not a significant cost impact).
Joel raised a cogent point. It is impossible to know for sure
whether the Christian Doctrine applies until the issue is
litigated. This uncertainty (however small) should be enough to
justify some consideration.
Eric
By
Vern Edwards
on Monday, February 28, 2000 - 11:24 am:
Joel:
I certainly respect your feelings and opinion in this matter. I
don't think you're wrong at all in what you're saying. But I
will admit that I hate board and court proceedings and will do
almost anything within reason to avoid them.
Ramon:
To the best of my knowledge, there is no rule quite like the
Christian Doctrine in the commercial sector. In general, I doubt
that commercial firms focus on contract texts quite as much as
we do in the government sector.
I don't know to what extent, if any, the Christian Doctrine has
been a disincentive to doing business with the government. I do
know that the government's complex rule system is unattractive
to many fully commercial firms.
Despite all the talk about commercial practices, government
contracting is a world apart from the commercial sector.
By
Ramon on Monday, February 28, 2000 - 11:10 am:
Awareness of outside influences,
in the sense of those outside the actual written agreement, must
be a part of any contract, but is there comparable risk for the
contractor in the commercial world? Is anyone aware of any data
or research into this being a cost driver or a significant
disincentive to participate in government contracts?
By joel on Monday, February 28,
2000 - 10:27 am:
Vern, I would certainly agree
that whether or not the "Christian Doctrine" applies in a
situation is not always a simple determination - usually when a
clause has been updated or when new clauses are added to the
existing myriad.
I do believe, however, that (at least some of) the Government's
attorneys can analyze the statute and/or implementing directives
for a clause and make a determination whether the clause is
effective. I don't believe we have to make a "case" to insert a
clause.
Although I only remember a couple of instances we had to deal
with, neither resulted in a claim. The instance I mentioned
concerning the "Prompt Payment Act Amendments of 1988", affected
about 10 new contracts in Mobile District, back in 1994. The
Payments (construction) clause was revised and a totally new
clause with different conditions for progress payments was
added. Since the directive to issue the admin mods to insert
these two clauses into existing contracts awarded after April
30, 1994 came from our Washington Headquarters COE Counsel
(around June or July 1994), it must have affected dozens of
contracts throughout the Corps. Construction contractors were
(are still?) notorious for using payments due their
subcontractors to improve cash flow and reduce their financing
costs. When we explained that they "now" had to identify any
funds they weren't going to promptly pass on to the subs - and
the Government would "hold" those funds "for them", there was a
lot of wailing and gnashing of teeth! However, nobody submitted
a claim in our District or anywhere else, I'm aware of.
Vern, I guess I'm just tired of the Government administering
contracts without demanding contractually required performance.
Since that's another topic, I won't elaborate here. But it forms
the basis of my opinion that we shouldn't "negotiate" whether or
not the Contractor will comply with an existing contract term.
I do have empathy for contractors who don't know they are
supposed to be contract law experts and have time to read the
Federal Register each day! So I listen and try to work with them
to find a way, WITHIN the contract, to minimize or eliminate the
pain of discovering a "new" clause is being added to the
contract. I don't have much empathy for a contractor, doing
repeat business, when a traditional, established clause is
inadvertantly omitted from a contract document, sloppy as that
may be.
Happy Sails!
By
Vern Edwards
on Monday, February 28, 2000 - 08:53 am:
Joel:
I understand that no consideration or bilateral modification is
necessary! That was my whole point!
I am saying that in order to be practical, I would abandon my
own legal theory in in order to settle the matter without going
to court, if my bosses and lawyer would go along with me. I am
saying that I would prefer to do that than go to court under
those circumstances, even if I thought that I would win. That is
what I meant when I said that I would act like a business
pragmatist.
Only the boards or courts can apply the Christian Doctrine.
Agencies have lost cases in which they've tried to get a board
or court to apply the Christian Doctrine. I don't have a problem
with talking about the Christian Doctrine and the theoretical
limits of KO authority, but then doing something different in a
real life situation in order to stay out of court, as long as my
superiors and lawyer don't have a problem with it. But I
wouldn't blame any KO who would not agree to do what I would do.
If the contractor would go along with letting me insert the
clause into the contract document by administrative
modification, then I would do that.
By joel hoffman on Monday,
February 28, 2000 - 08:14 am:
Vern, I agreed with you all the
way up untill
I(E). After "having said all of the above...", you ignore the
fact that the missing clause is already a contract term. You
then decide to negotiate for Contractor performance of a term
already requiring performance. I disagree. No consideration or
bilateral mod is necessary.
We write a mod to "add" the clause because my agency includes
full text clauses in construction contracts. I don't know
whether we always include full text (Section I) or list the
references in our service and supply contracts, using the
Uniform Contract Format. I've seen it done both ways. i would
still write a mod to add the correct reference to the list.
We prepare an admin mod, because we aren't affecting the rights
of either party, merely correcting the text of the contract
document. Yes, we usually first discuss what we are going to do
with the Contractor. No, it doesn't have to be bilateral. No,
consideration is unnecessary for the mod, as the clause is
effective, as a matter of right.
Happy Sails! Joel
By
Vern Edwards
on Sunday, February 27, 2000 - 02:10 pm:
Eric:
This thread has gotten long and we have covered a lot of ground,
and the nature of these kinds of websites makes it a little
difficult to follow the discussion. Let me try to sort things
out. I warn the casual reader that this is going to be long,
since I am going to try to recap much of the thread.
I. Consideration and equitable adjustment in Christian Doctrine
cases.
I.(A) The Christian Doctrine provides that if (a) a clause is
required by law and addresses a significant procurement issue,
and if (b) an agency leaves the clause out of a contract without
legal authorization, then (c) a board or court will consider the
clause to be in the contract anyway, "by operation of law."
I.(B) The issue has been raised whether a KO should agree to
increase the contract price if inserting a clause by virtue of
the Christian Doctrine would increase the contractor's cost of
performance. Participants in this thread have referred to such
an increase variously as "consideration" and as "equitable
adjustment."
I.(C) I have taken the position that if (a) the omitted clause
is already actually in the contract by operation of law, then
(b) inserting the clause by virtue of the Christian Doctrine
does not change the contract, but merely acknowledges the fact
that the clause is actually there.
I.(D) I then argue that if (a) inserting the clause by virtue of
the Christian Doctrine does not change the contract, then (b) it
would not be appropriate for the KO to agree to consideration,
to an equitable adjustment, or to any other compensation for the
following reasons:
I.(D)(1) Consideration is needed to make an agreement binding.
However, the contractor is already bound to abide by the clause
by virtue of the Christian Doctrine, so no further consideration
is needed or appropriate.
I.(D)(2) "Equitable adjustment" is a term of art that has long
referred to compensation based on a remedy granting contract
clause. An "equitable adjustment" compensates one party for an
act or omission by the other which a clause states is a basis
for compenstation.
I.(D)(2)(a) No FAR clause authorizes an equitable adjustment for
inserting a clause by virtue of the Christian Doctrine.
I.(D)(2)(b) Inserting a clause by virtue of the Christian
Doctrine has never been considered a constructive change that
would entitle a contractor to compensation under a changes
clause, because it does not change the contract but merely
acknowledges what the contract really says.
I.(D)(2)(c) Since entitlement is a prerequisite to an equitable
adjustment, if the KO agreed to increase the contractor's price
because of a Christian Doctrine clause insertion, then he or she
would giving the contractor more money without justification in
law or contract. He or she would be changing the government's
promise to the contractor without obtaining consideration,
something which KOs may not do except as authorized in FAR Part
50, Extraordinary Contractual Action. (I disagree with John that
KOs can grant "equitable relief" and give the contractor more
money out of a sense of fairness without a basis in contract or
law.)
I.(D)(2)(d) The boards and courts have never treated the
insertion of a clause by virtue of the Christian Doctrine to be
an act that would entitle a contractor to compensation as a
matter "relating to a contract" under the Disputes clause. They
have taken the position that firms wishing to do business with
the government either know or should know the laws and
regulations and assume the risk that an omitted clause will be
read into the contract by operation of law.
I.(E) Having said all of the above, on Feb. 26 I explained what
I would do in real life: I would explain to the contractor that
I had inadvertently left out a required clause and ask the
contractor to agree to let me insert the clause in the contract
document in exchange for consideration. I would try to minimize
that consideration by confronting the contractor with the
possibility that if she wasn't reasonable I would let the board
or court declare the contract void ab initio or insert the
clause by virtue of the Christian Doctrine without giving her a
nickel. I would do this only if my superiors and lawyer agreed
that it was preferable to a dispute and appeal. In short, I
would be a business pragmatist, and try to find a reasonable
solution to the problem. If I can get the bosses to go along
with me, then why not?
II. The distinction between consideration and equitable
adjustment.
II.(A) On Feb. 24, you told John that he was "slicing the
distinction between consideration and equitable adjustment finer
than necessary." You also said, "both terms describe what we
pay, to get what we want. And, because we are the Government, we
should always be equitable."
II.(B) I disagree that John was slicing the distinction too
thinly. The two concepts are very different. To say that
both "describe what we pay, to get what we want" obscures both
the nature and the magnitude of that difference. I also disagree
that we should be "equitable" when it comes to consideration.
II(B)(1) Consideration is what we do, promise, or agree
to give up in order to induce someone to enter into a contract
with us. It only need be "adequate"; it need not be "equitable."
Equitability is always measured on the basis of the impact of an
act or omission; adequacy is not.
See Contracts, 3rd ed., by Calamari and Perillo, pp. 192-195;
Formation of Government Contracts, 3rd ed., by Cibinic and Nash,
pp. 247-258. See, too, Restatement of the Law, Second,
Contracts, 2d, §§ 71 - 81, especially § 79, Adequacy of
Consideration; Mutuality of Obligation, which says:
"If the requirement of consideration is met, there is no
additional requirement of
(a) a gain, advantage, or benefit to the promisor or a loss,
disadvantage, or detriment to the promissee;
(b) equivalence in the values exchanged; or
(c) "mutuality of obligation."
(As a business pragmatist, I would give a contractor
consideration to induce it to promise to abide by a clause that
I had inadvertently omitted, even if I believed I could get a
board or court to insert the clause without giving the
contractor anything.)
II(B)(2) Equitable adjustment is what one party gives to
the other party to compensate it for the impact of an act or
omission. It is a term of art used in government contracting. It
is well-established that an equitable adjustment must, by
definition, be equitable to the impact that the act or omission
has had on the other party. See The Government Contracts
Reference Book, 2nd ed., by Nash, Schooner, and O'Brien, p. 215.
("The basic formula for an equitable adjustment is an estimate
of the difference between (1) what it would have reasonably cost
to perform the work as originally required and (2) what it will
reasonably cost to perform the work as changed.") In this way,
equitable adjustment is similar to damages rather than to
consideration. Your quote from the contract law class merely
points out that what is equitable depends on the facts and
circumstances of each case, and cannot be determined on the
basis of a regulatory formula.
II.(b)(3) In your Feb. 27 post you said, "I haven’t actually
used (or misused) the phrase 'equitable adjustment' in this
thread. The careful reader will note that I never equated
'consideration' and 'equitable adjustment.' However, I did note
that in practice they both equate to price."
This careful reader notes that, in fact, you did use the
term "equitable adjustment" in this thread, on Feb. 24, as I
quoted above. I agree that you neither misused it nor "equated"
it with consideration. However, you did understate the
difference between consideration and equitable adjustment.
Moreover, equitable adjustment does not "equate" to price. An
equitable adjustment may have the effect of increasing or
decreasing a price, but price need not be related to cost (it
may reflect market supply and demand), while an equitable
adjustment to a price must always reflect the impact of
an act or omission on cost.
Having said all of this, I'm sorry if I have read too much into
your response to John. Yes, we're having a bull session. After
all, this site used to be called the "water cooler." These are
the kinds of discussions, arguments, bull sessions, (whatever)
that should be happening from time to time in all contracting
offices. We can learn from these sessions, especially if they
motivate us to read more often and more deeply.
By
Eric Ottinger on
Sunday, February 27, 2000 - 09:52 am:
Vern,
I am confused. I thought you were opposed to consideration.
I am not sure where we differ at this point. On Thursday you
disagreed with me because I thought, that under certain
circumstances, consideration might be needed. You disagreed.
Now, you seem to have come around to the idea that consideration
might be needed.
If the consideration is not for something that the Government
has done unilaterally (since the clause was in the contract all
along), what authority do you have for the consideration.
As I see it (Note: This is pure speculation.)—
1. No consideration is required to comply with the law (which we
all should have known from the start.)
2. Consideration may be required to remove some part of the
contract, to which we had previously agreed, particularly if we
had explicitly negotiated that part of the contract.
3. In most cases, no consideration or nominal consideration
should be sufficient. For instance, changing to payment by EFT.
I haven’t actually used (or misused) the phrase “equitable
adjustment” in this thread. The careful reader will note that I
never equated “consideration” and “equitable adjustment.”
However, I did note that in practice they both equate to price.
I think John’s definition of consideration is a little too
restrictive. I refer the reader to the “Contract Law” course
available in the Deskbook:
“6-1. A fundamental concept involved in contract formation is
bargain and exchange. Each party receives something of value and
gives something of value. "Consideration" is the name given to
the "something of value," i.e., the price paid for a promise.
Actually, a number of things may constitute consideration: an
act, a promise, forbearance, or the creation, modification or
destruction of a legal relation. (Restatement of Contracts,
Section 75.) In a bilateral contract each party exchanges a
promise for a promise. For example, if the Government hires a
contractor to build an airplane, the contractor promises to
build the plane and the Government promises to pay money. Each
promise is the consideration for the other. In a unilateral
contract one party gives a promise as consideration, and the
other party performs without making a promise. The classic
example is an offer to pay $500 to whoever captures a named
outlaw, "dead or alive." In that instance, the offeror is not
asking anyone to promise to capture the
outlaw.
7-1. The concept of "equitable adjustment" is one of the larger
unresolved issues in Government contracting. Although the phrase
appears expressly or implicitly in the "adjustment clauses"
e.g., "Changes," "Government Property," "Differing Site
Conditions," etc., the determination of what constitutes an
equitable adjustment has not been objectively quantified by the
regulation. The term "equitable adjustment" is
construed as a "fair," "reasonable," "just," or "right"
arrangement or settlement. As mentioned above, in Government
contracts this involves a determination as to an adjustment of
the contract price, the period of performance, or both.”
I have no problem speculating about legal theory as long as
everyone knows this is a bull session. However, we should all be
careful not to confuse our readers by using a term of art,
without giving the term an exact definition.
Regards,
Eric
By
Vern Edwards
on Saturday, February 26, 2000 - 12:04 pm:
Eric:
You asked: "Vern, Do you have a case where the Government
explicitly agreed to do or not do something in negotiations then
unilaterally, and without consideration, overrode the negotiated
contract by citing the Christian doctrine. My bet is that you
won’t find one."
No, I don't have such a case. Why should I? The Christian
Doctrine doesn't have anything to do with agreeing to one thing
and then doing another. It has to do with conforming to the law,
knowledge of the limits of KO authority, and the
responsibilities and risks associated with doing business with
the government.
Many seem to find the Christian Doctrine shocking, and can't get
past the seeming unfairness of it. They want to give the
contractor more money if inserting the clause would increase its
costs. And I'm sure that some find my tenacity in pointing to
the limits of KO discretion as an indication that I'm being
unreasonable.
If I was a KO and discovered that I had omitted a required
clause from the contract, I would tell the contractor and show
her the requirement for the clause. I would explain that as KO
it had been my responsibility to include the clause and that I
had left it out through carelessness. I would then explain that
my authority is limited, that by law I cannot leave out a
required clause, and that my action could render the contract
void ab initio or result in the invocation of the Christian
Doctrine.
I would explain to the contractor the courts' position--that she
was presumed to know what the laws and regulation require. I
would give her copies of cases in which the court had invoked
the Christian Doctrine and refer her to appropriate textbooks. I
would encourage her to talk to her lawyer and to tell the lawyer
to call me if he or she had any questions.
I would then ask the contractor to agree to the inclusion of the
clause and what consideration (not equitable adjustment) she
would require to sign a bilateral contract modification in which
she promised to comply with the clause. I would tell her to be
reasonable, because if she asked for too much the government
might declare the contract void or invoke the Christian
Doctrine. If she asked for too much I would negotiate by warning
her that the courts consider it her responsibility to know the
rules and to check solicitations for omissions. I would tell her
that she would have to accept the fact that she can't get
everything she wants.
Once I had reached a tentative agreement with the contractor [I
would advise her that it was subject to my superiors' (not my
lawyer's) approval] I would go to my superiors and my lawyer,
explain the situation, and ask if they would object to a
supplemental agreement that would include the clause and provide
consideration to the contractor. They might say, "No way, she's
not entitled to anything!" But if they would go along, I would
sign the supplemental agreement, cite the clause prescription on
SF30, and be done with it. If they would not go along, I would
ask if they thought that it would be worth a dispute and appeal
to avoid giving the contractor something (not an equitable
adjustment) for agreeing to accept the clause without making a
fuss. If they still refused to go along with a supplemental
agreement with consideration, then I would ask whether they
thought we should void the contract or rely on the Christian
Doctrine.
I think it's nice that so many of you are worried about being
fair to the contractor. That's appropriate. But KOs are
creatures with limited authority. They can't just do what they
want because they think it's "fair."
And as professionals, we don't have to be lawyers to discuss and
debate the law among ourselves. That's not "practicing law
without a license"; that's trying to educate ourselves about
things like the Christian Doctrine, the difference between
consideration and equitable adjustment, and the difference
between legal and equitable relief. We should try to learn what
we can do before we ask or decide what we should do.
Every contracting officer should have, or have access to, the
books that I've been citing. True professionals don't go running
to their lawyers every time they have a problem, asking, "What
do I do?" They do their homework, fashion what they think is a
reasonable course of action based on what think they know, and
then go to their lawyer to seek professional advice and
counsel. That's how they learn and earn respect. That's how they
rise above the level of procurement clerk.
By
Eric Ottinger on
Saturday, February 26, 2000 - 09:49 am:
For those who haven’t sat
through “The Constitutional and Legal History of England” in
school, when the English found that the common law courts didn’t
always do the right thing, they established separate “equity”
courts. This may or may not have something to do with the
distinction that John is making.
I think we are all starting to practice law without a license. I
really don’t know what logic or theory the law would require, to
allow a Contracting Officer to do the equitable (i.e. fair)
thing. But, I don’t trust a theory which leads to blatantly
inequitable results.
Vern,
Do you have a case where the Government explicitly agreed to do
or not do something in negotiations then unilaterally, and
without consideration, overrode the negotiated contract by
citing the Christian doctrine. My bet is that you won’t find
one.
Eric
By
Vern Edwards
on Saturday, February 26, 2000 - 03:11 am:
John:
An addendum to my last post: The Court of Federal Claims can
grant equitable relief in bid protests. That relief is limited
to bid and proposal costs. You can check this at the Court's
home page at
http://www.law.gwu/fedcl/.
By
Vern Edwards
on Friday, February 25, 2000 - 05:18 pm:
John:
You wrote: "Thus, contracting officers are given the power to
grant eqitable relief to contractors as well as legal relief."
That is not correct.
First, let me explain to some of the readers what equitable
relief means. Black's Law Dictionary defines that term as
follows: "That species of relief sought in a court with equity
powers as, for example, in the case of one seeking an injunction
or specific performance instead of money damages."
Black's defines equity as follows: "Justice administered
according to fairness as contrasted with the strictly formulated
rules of common law... . The term 'equity' denotes the spirit
and habit of fairness, justness, and right dealing which would
regulate the intercourse of men with men... . A system of
jurisprudence collateral to, and in some respects independent of
'law'; the object of which is to render the administration of
justice more complete, by affording relief where the courts of
law are incompetent to give it, or to give it with effect, or by
exercising certain branches of jurisdiction independently of
them."
You read FAR 1.602-2(b) too broadly when you interpret it to
grant equity powers to contracting officers. Neither the FAR nor
the Contract Disputes Act of 1978 (41 U.S.C. 601-613) grant
equity powers to contracting officers. In fact, the boards and
the Court of Claims do not have equity powers. Only the U.S.
District Courts and the Federal circuit courts have equity
powers. (I checked this with my lawyer, Ralph Nash.)
The Disputes Act and the Disputes clause at FAR 52.233-1 require
contracting officers to decide "claims." FAR 33.201 and the
Disputes clause define a "claim" to be "a written demand or
written assertion by one of the contracting parties seeking,
as a matter of right, the payment of money in a sum certain,
the adjustment or interpretation of contract terms, or other
relief arising under or relating to the contract." Underlining
added.
The key phrase in the definition of "claim" is: "as a matter of
right." In order for a contracting officer to grant relief
pursuant to the Disputes Act and the Disputes clause, he or she
must determine that a contractor is entitled to relief, based on
a contract clause, a breach of the contract, or some other
common law rule such as mutual mistake. Note, too, that the
certification of claims required by the Disputes clause requires
the contractor to certify that it believes that the government
is "liable" for the relief sought. A request for equitable
relief is not a matter of right or liability and is not covered
by FAR 1.602-2, the Disputes Act, or the Disputes clause.
If the government has a right to have the contract interpreted
to include an improperly omitted clause by virtue of the
Christian Doctrine, then a contracting officer who agrees to
compensate the contractor for an increase in cost that is
attributable to the clause is agreeing to a contract
modification without consideration. Contracting officers may not
agree to modify a contract without obtaining considertion except
in accordance with FAR Part 50, Extraordinary Contractual
Actions.
FAR 33.205 and 50.102(c) do state that the Contract Disputes Act
of 1978 expanded the relief available from contracting officers.
But that is because prior to the passage of the Disputes Act,
contracting officers and the boards of contract appeals could
only settle claims "arising under the contract." The Disputes
Act of 1978 added claims "relating to the contract." That is why
agencies can now rescind or reform a contract for mutual
mistake. Mutual mistake is related to a contract, and pursuant
to the common law of contracts recission or reformation is a
matter of right when the parties have made a mutual mistake. See
The Restatement of the Law, Second, Contracts, 2d, § 152.
I think that Joel has adequately addressed the cases that you
mentioned.
By
joel hoffman
on Friday, February 25, 2000 - 03:08 pm:
John, I think I confused
applicability of the "Christian Doctrine" with other Government
caused pre-bid/pre-award problems, in my last post.
I've read several cases concerning clauses which were omitted
from the contract documents for one reason or another, in which
the "Christian Doctrine" was applied. From my recollection,
those cases generally involve situations which arose AFTER
contract award, such as when Government terminated a contract
for convenience, then the Contractor claimed a breach of
contract occured, not T4C, because the Gov't left out the T4C
clause. Another situation involved a Contractor which
encountered a differing site condition and the "Differing Site
Condition" clause was missing.
These cases are distinguished from mistakes in pre-bid/proposal
interpretation of various requirements by the Government, which
misled the bidder or offeror in pricing or planning performance.
I believe the situations you discussed - as well as the
hypothetical one I covered in my last post - are based on other
principles than "Christian".
The "Blackhawk Hotel" Case you cited, involved an incorrect
determination by the Government that the Service Contract Act
did not apply to the solicitation/ subsequent contract in
question. Therefore, the contract didn't include the correct
clauses or SCA wage rates. The Department of Labor later advised
that the contract was indeed subject to SCA. When the Government
refused to allow an increase to cover the higher SCA labor
rates, the Contractor refused to perform at higher cost. The KO
"KO'd" the Contractor (T4D). This was a case of out and out
misinterpretation of the correct contract requirements by the
Government prior to bid, directly misleading the bidders, not an
"inadvertantly omitted clause".
In the other two cases you referred to, didn't the Government's
incorrect interpretation directly mislead the bidders? From
experience, I know that applicability of Cost Accounting
Standards (CAS) to a specific contract requires some careful
interpretation. The clauses implementing the Cargo Preference
Act were written by Philadelphia lawyers - probably the same
ones who wrote the Buy America Act implementing regs and
clauses! Were those cases where Government misinterpretation
directly resulted in clauses omitted or simple Government
pre-bid misinterpretation of clauses already in the contract?
(I won't be-labor another line of discussion in yout post but
the cases you referred to more likely involved "mutual mistakes"
not "unilateral mistakes", as you inferred.)
Anyway, sorry I started a tangential discussion about "mutual"
and "unilateral" mistakes. The Christian Doctrine is another
principle. Happy Sails! Joel
By
John Ford on Friday,
February 25, 2000 - 11:17 am:
To All, I think we are facing
the quandry experienced by policy writers in quite a few
instances. We are trying to enunciate rules for all situations
when it is apparent that the outcome should be dependent upon
the facts of the specific case.
Vern, while it is true that contractors are held to constructive
knowledge of what is in the FAR, that does not equate to a
responsibility to ensure that contracts comply with law or
regulations. That responsibility is conferred on the contracting
officer by FAR 1.602-1(b). Additionally, FAR 1.602-2(b) requires
contracting officers to ensure "that contractors receive
impartial, fair, and equitable treatment." Thus, contracting
officers are given the power to grant eqitable relief to
contractors as well as legal relief. (The appeals boards and
COFC have this same power.) This, coupled with the KO's power
under the CDA and Disputes clause to resolve all claims arising
under or relating to a contract, would be the basis for a KO to
grant an equitable adjustment for increased costs due to the
KO's failure to comply with his/her responsibilites under the
FAR. As for a specific case holding that a contractor is
entitled to an equitable adjustment in Christian Doctrine
situations, I cannot give you a case that is directly on point,
but there are some that would support this concept. Blackhawk
Hotels Co., ASBCA No 13,333, 68-2 BCA 7265, where the government
mistakenly told offerors that the Service Contract Act did not
apply to a procurement when it did, is one. Another case (sorry
I cannot give you a cite on this one) involved the situation
where the contracting officer had determined that a contract was
not CAS covered when in fact it was. The government later tried
to apply the CAS retroactively to the entire contract. However,
the ASBCA (and I believe the Court of Claims) refused to permit
this. Finally, we have the situation where the Department of
Defense interpreted the Cargo Preference Act, and its
implementing FAR provision, as not applying to components
shipped to the U.S. for incorporation into end items. Thus,
these components could be shipped using cheaper foreign flag
vessels. However, the Fed Cir held that the Act does apply.
Under these circumstances, contractors received equitable
adjustments to their contracts to reflect the higher shipping
costs of using U.S. flag carriers if they could demonstrate that
they priced their contracts based on using foreign flag
carriers. The common thread in these situations is that the
government made a mistake in interpreting what must be admitted
are not very clear laws and regulations. The contractors all
relied on the government mistake. As a matter of equity and
allocation of risk for a unilateral mistake, the government bore
the financial consequences of its mistaken actions. I would
agree that if a requirement is clear and the contractor is aware
that the government has made a mistake by omitting a mandatory
clause, the contractor should not be permitted to remain silent
and ambush the government at a later date. This again is based
on equity and the implied covenant of good faith and fair
dealing that accompanies every contract.
By
Vern Edwards
on Friday, February 25, 2000 - 10:29 am:
Joel:
Mutual mistake is one of the most obscure legal doctrines that I
know of. For the benefit of others:
FAR 15.508 says that mistakes disclosed in a contractor's
proposal after award shall be processed substantially in
accordance with the procedures for mistakes in bids at 14.407-4.
FAR 14.407-4 says, in part, that agencies may rescind or reform
a contract when a mistake is discovered after award if:
(1) there is clear and convincing evidence of a mistake, (2) the
mistake was mutual, or (3) if the mistake was not mutual it was
so apparent that the KO should have noticed it.
FAR does not define mistake. The Restatement of the Law, Second,
Contracts, 2d, § 151 defines a mistake as "a belief that is not
in accord with the facts." Black's Law Dictionary defines
mistake as "Some unintentional act, omission, or error arising
from ignorance, surprise, imposition, or misplaced confidence. A
state of mind not in accordance with reality." Black's goes on
to say, "A mistake exists when a person, under some erroneous
conviction of law or fact, does, or omits to do, some act which,
but for the erroneous conviction, he would not have done or
omitted. It may arise either from unconsciousness, ignorance,
forgetfulness, imposition, or misplaced confidence." See, too,
the entry for mistake in Nash, Schooner, and O'Brien, The
Government Contracts Reference Book, 2nd ed. (Washington, DC:
The George Washington University, 1998).
Restatement § 152 discusses mutual mistakes. Cibinic and Nash
discuss mutual mistake in Administration of Government
Contracts, 3rd ed. (Washington, DC: The George Washington
University, 1995), pp. 321-330. Calamari and Perillo discuss
mutual mistakes in Contracts, 3rd ed. (St. Paul: West Publishing
Co., 1987), pp. 379-386.
I have not been able to find a case in which a contractor has
sought to rescind or reform a contract based on mutual mistake
in a Christian Doctrine situation. (There may be some, I just
haven't found them.) If anybody out there does find such a case,
please let us know about it.
A key sticking point is the position of the boards and courts
when applying the Christian Doctrine that the parties either
knew or should have known about the published law or regulation
that requires the clause. That stance deprives the parties of
any claim to ignorance, surprise, imposition, forgetfulness, or
misplaced confidence. Thus, it's hard to argue that the omission
of a clause is a "mistake" in the legal sense, i.e., as defined
by the Restatement and Black's. Moreover, the government's
omission of a clause is more often a matter of carelessness or
rather than forgetfulness, and thus may not be a "mistake" for
that reason.
One type of mutual mistake is sometimes called a mutual mistake
in integration. See the Restatement at § 155. That's when the
contract document does not reflect the actual agreement of the
parties. It doesn't seem to apply in Christian Doctrine cases
because the constructive knowledge rule of the boards and courts
eliminates the "mistake" element.
With regard to ambiguities -- as I said in my last message, the
court will resolve any ambiguity that results from the insertion
of a clause by determining whether the ambiguity was latent or
patent. If the insertion of the clause resulted in a latent
ambiguity, and if the latent ambiguity increased the costs or
time of performance, then the contractor is going to get an
equitable adjustment. If the insertion created a patent
ambiguity, then the contractor is going to get nothing. The
Federal Circuit dealt with that very issue in the General
Engineering & Machine Works case that I cited in my earlier
message. It denied the contractor's claim for relief based on an
ambiguity created by the insertion of the clause, finding that
the ambiguity was patent, not latent.
I don't claim to be certain about all of this. But I'm pretty
sure that you can't claim a mistake (mistaken belief) when the
courts say that you either knew or should have known that the
regulations required the inclusion of the missing clause.
Now, it's usually about this time that somebody says that the
reader should check these things with their lawyer. So I'll say
it: We're just talking here. If you're facing a real situation,
check with your lawyer.
By
joel hoffman
on Thursday, February 24, 2000 - 08:28 pm:
I agree with Vern and Eric. Vern
has pretty well covered the legal principles and what the KO can
and can't legally do concerning mandatory clauses.
Notwithstanding the fact that an omitted mandatory clause is
already a contract term, I suppose it is possible in a sole
source, negotiated contract (detailed cost negotiations)that
both parties could negotiate SPECIFIC TERMS AND COST AREAS
inconsistently with the requirements of an omitted clause. If
such a situation is possible, I believe it constitutes a "mutual
mistake in contract formation." Aren't such situations usually
grounds for reformation of the contract?
For example, on a construction contract, the parties agree that
a specific foreign made control valve of substantial value is
acceptable, and later discover a new Buy America Act provision
was effective at the time of negotiations. The new provision
prohibits use of the foreign made valve and requires the
Contractor to purchase a vastly more expensive American made
valve. Assuming it can be reasonably determined that neither
party was aware of the new clause, I believe a case of "mutual
mistake" could be established, whereby the Government would
allow an adjustment for the increased cost to comply with the
new clause. What do you think?
A unilateral mistake, on the other hand, does not automatically
entitle the mistaken party to an adjustment. As Vern states, the
parties are "presumed" to know the applicable contract terms.
Neither the Government nor the Contractor is guaranteed a "fair"
bargain....
Happy Sails! Joel
By
Vern Edwards
on Thursday, February 24, 2000 - 01:39 pm:
Eric:
You wrote: "To pick the most obvious example, it may have been
explicitly agreed by both parties that we would not include the
clause. I don’t think you can use the Christian Doctrine to
override such agreement without consideration."
I disagree. A KO cannot agree to exclude a clause required by
law unless authorized to deviate. Deviation without
authorization would exceed his or her authority, and the
government generally is not bound by the unauthorized acts of
its agents. See FAR 1.401(b), 1.403, and 1.602-1. The Christian
Doctrine would override any such unauthorized agreement
and, therefore, the KO could not provide "consideration"
for inserting the clause into the contract document. As the
Federal Circuit said, contractors are presumed to know what the
laws require.
If the inclusion of a clause by virtue of the Christian Doctrine
creates an ambiguity in the contract, the proper interpretation
of the contract will depend on whether the ambiguity is latent
or patent. Since the Federal Circuit has held that "government
contractors are presumed to have constructive knowledge of
federal procurement regulations" and should know what clauses
are required in government contracts, a board or court may
decide that any conflict was a patent ambiguity, not a latent
ambiguity. In that case the contractor would not be entitled to
anything. If the ambiguity is latent, then the contractor would
be entitled to an interpretation in its favor. In that case the
contractor might be entitled to an equitable adjustment if some
government act or omission based on a faulty interpretation
constituted a constructive change.
Also, consideration and equitable adjustment are very
different ideas.
Consideration must accompany an agreement. It is
necessary to bind the parties, being the inducement to contract.
See Black's Law Dictionary. The amount of the consideration is
not, per se, important; it need not reflect the impact of any
act or omission. See Calamari and Perillo, Contracts, 3rd ed.
(St. Paul: West Publishing Co., 1987), p. 192-195.
The concept of the equitable adjustment is related to the
concept of compensatory damages. Equitable adjustments and
damages follow an act or omission. They are not inducements,
but forms of compensation. Equitable adjustments and
compensatory damages compensate one party to a contract for the
impact of an act or omission by the other party. The amount of
the equitable adjustment is crucial; it must reflect the impact
of the act or omission. We call such compensation an equitable
adjustment if entitlement is based on a contract clause; we call
it damages if entitlement is based on a breach of contract. (See
the entries on consideration, damages, and equitable adjustment
in The Government Contracts Reference Book, 2nd ed., by Nash,
Schooner, and O'Brien (Washington, DC: The George Washington
University Law School)).
By
Eric Ottinger on
Thursday, February 24, 2000 - 12:06 pm:
John and All,
Just in case you are wondering--
Vern and I did not collude on our previous responses.
Eric
By
Eric Ottinger on
Thursday, February 24, 2000 - 10:46 am:
John,
I see your point but I am not sure that I agree.
(Any smart lawyer who wants to step in here and straighten us
all out is welcome.)
I think you are slicing the distinction between consideration
and equitable adjustment finer than necessary. I don’t disagree
with the distinction that you make regarding usage. However,
both terms describe what we pay, to get what we want. And,
because we are the Government, we should always be equitable.
(I have been hearing lawyers say, “You can’t do this without
consideration” for as long as I have worked in contracting. I
have never understood this to mean that a nominal amount would
be OK vice an equitable amount.)
I think Joel has it right. The Christian Doctrine isn’t
authority for us to ADD the clause. We are merely doing a
clarification because the clause WAS IN THE CONTRACT ALL ALONG.
Normally, there shouldn’t be any consideration.
However, if the contract is logically inconsistent after the
clarification, something must be done to resolve the
inconsistency, which would entail a bilateral modification and
some consideration.
To pick the most obvious example, it may have been explicitly
agreed by both parties that we would not include the clause. I
don’t think you can use the Christian Doctrine to override such
agreement without consideration.
If we are merely correcting a mistake to which both parties were
oblivious at the time of the negotiation I would think the
correction should be done on a no cost basis.
If we are overriding something that both parties explicitly
agreed to, there should be consideration.
(John, I didn’t argue that no consideration is due. I argued
that I would not pay more than nominal consideration if the
contractor is obligated to make the change under another
contract. Otherwise, the taxpayers are going to be paying twice
to obtain the same change.)
Eric
By
Vern Edwards
on Thursday, February 24, 2000 - 10:42 am:
John:
Suppose that a KO omitted a mandatory clause that has cost
consequences for the contractor and that the KO's lawyer says
that a board or court would read into the contract by virtue of
the Christian Doctrine.
I would argue that the contractor is not entitled to an
equitable adjustment. I would go further and argue that the
KO has no authority to give the contractor an equitable
adjustment, even if the clause indisputably would require
the contractor to incur costs that it had not anticipated during
contract formation.
The thrust of the Christian Doctrine seems to be that a
mandatory clause is, in fact, in the contract "by operation of
law" (quoting the Federal Circuit). Therefore, inserting the
clause into the contract document does not change the contract;
it simply acknowledges that the contract document as distributed
did not accurately reflect the agreement between the parties.
(This is why KOs and others have to understand the distinction
betweent the contract, as a matter of law, and the contract
document. The two are not necessarily the same.)
In the case of an omitted mandatory clause the Federal Circuit
has said (in General Engineering & Machine Works v. Sean C.
O'Keefe, Acting Secretary of the Navy, 991 F.2d 775 (1993)):
"[G]overnment contractors are presumed to have constructive
knowledge of federal procurement regulations. General Builders
Supply Co. v. United States, 409 F.2d 246, 250-251 (Ct. Cl.
1969). Thus, appellant should have known that it was required
under federal regulations to maintain separate cost pools,
particularly since the payments clause upon which appellant
would rely is typically used in fixed-price service contracts."
Thus, the clause is in there, whether the contractor consciously
knew about it or not.
Accordingly, since inserting a required clause into the contract
document by virtue of the Christian Doctrine does not change the
contract as a matter of law, the contractor has no claim to
entitlement to an equitable adjustment. And without entitlement,
on what basis would a contracting officer agree to a price
increase? KOs ordinarily cannot grant price adjustments just
because they think it would be "fair" to do so; they have to
have a basis in law or contract regulation. It's always a
"judgment call," but such judgments are not unfettered. That's
why KOs have to have special authority to grant extraordinary
contractual relief. See FAR Part 50.
So under what authority would you give such a contractor an
equitable adjustment to cover the increased costs attributable
to the clause?
By the way, two things:
(1) I am reasoning about this; I can't cite a case to bolster my
argument. I don't know of any case in which a contractor has
claimed that a Christian Doctrine clause insertion constituted a
change to the contract, or sought an equitable adjustment after
a board or court has read a clause into a contract by virtue of
the Christian Doctrine. Maybe someone out there does know of
such a case. If so, I'd like to know about it.
(2) I realize that this would be a hardnosed position for the KO
to take with the contractor, especially if the contractor truly
hadn't known about the clause. But I think that it's important
for KOs to understand the law before they make decisions about
solutions that they think are "fair." This is especially
important because KOs don't have the authority to act on the
basis of their personal notions of fairness. Their authority is
limited to what the law allows them to do. This is why KOs need
special authority to modify a contract without consideration
(see FAR Subpart 50.3).
What do you think?
By
John Ford on
Thursday, February 24, 2000 - 10:13 am:
Eric, you missed my point. My
point is that if an omitted clause would require a contractor to
do something it is not otherwise doing, or obligated to do under
a specific contract, the contractor would be entitled to an
equitable adjustment for its increased effort and cost under
that contract. The amount of the equitable adjustment would
depend on the cost impact to that contract of the new effort.
Don't get consideration and an equitable adjustment confused.
Consideration is a legal concept regarding the enforceability of
an agreement. It need not have anything to do with the value or
cost of work done under a contract, i.e., an agreement supported
by "adequate consideration." An equitable adjustment is a
mechanism to make a contractor whole as a result of government
action. An equitable adjustment is more akin to damages than
consideration.
By joel hoffman on Thursday,
February 24, 2000 - 09:05 am:
Vern, et al.
To answer Vern's question to me, I issue administrative
modifications as follows: (see definition in 43.101), pursuant
to 43.103 (b)(1).
On the SF 30 , check block 13B. (Administrative Changes) and
mark in Block 13E. Contractor is not required to sign and return
the original.......
In Block 14, explain to the effect that this is an
administrative modification to add Clause....... which was
inadvertantly omitted from the contract documents but was in
effect at the time of bid opening and contract award. Sometimes
we describe the directive we received to include the clause.
Mainly an explanation why the mod is necessary.
Been doing it that way for years with no problems.
Happy Sails! Joel
By
Eric Ottinger on
Wednesday, February 23, 2000 - 03:45 pm:
John,
Sure, but most government contractors have more than one
contract. If the contractor is required to make the change by
another Government contract, the additional expense argument is
specious.
This isn't an argument for a unilateral modification, but the
consideration shouldn't be any more than nominal if the
contractor is required to make the change to "its accounting
system or its inspection system" by at least one Government
contract.
Getting back to EFT, if the contractor has more than one
contract, it is unlikely that the clauses have been ommitted
from all of the contracts.
If the contract is truly a "one each," it might be better to
write the waiver and pay by check.
Eric
By
John Ford on
Wednesday, February 23, 2000 - 03:26 pm:
Vern, limiting the discussion
only to the Termination for the Convenience of the Government
clause, I would agree because the T4C clause does not require
the contractor to do something that costs it money or delays
performance of the contract. On the other hand, if the omitted
clause required the contractor to do something such as change
its accounting system or its inspection system, then I believe,
in some circumstances, the contractor would be entitled to an
equitable adjustment to the contract to compensate the
contractor for the additional expenses. In other words, if the
contractor had been required to do this from the beginning, the
cost of these changes would have been built into the contract
price. The government should not be permitted to get a free ride
on this. The equitable adjustment would simply be a mechanism
for putting the parties in the position they would have been in
if things had been done right from the beginning.
By
Eric Ottinger on
Wednesday, February 23, 2000 - 01:18 pm:
Vern,
FAR 43.103(b)(3) is more permissive than I remember. Either my
memory is faulty or it has been rewritten to be less restrictive
Personal Opinion: The SF 30 should be rewritten. But the fellow
who wrote it retired many years ago, nobody knows for sure what
he intended, and there are many other projects with higher
priority.
I think the Statute, which you cited, is a much more compelling
argument than the Christian Doctrine.
I would simply state that, “After January 1, 1999 the statute
doesn’t allow us to pay you by check.” The contractor, if he
isn’t a fool, will want to see the fine print. This would lead
to the Treasury Dept. Regulations which appear to be
significantly more permissive.
I have no idea what the scenario is (which makes this a somewhat
strange discussion), but if the sole source contractor, who only
expects one payment by check, is crackpot genius who thinks EFT
has somehing to do with black helicopters and the “New World
Order,” I don’t think I would get very far arguing the Christian
doctrine. I would be working on that waiver.
Eric
By
Vern Edwards
on Wednesday, February 23, 2000 - 12:38 pm:
John and Eric:
John first:
If the clause is not in the contract (i.e., the legal agreement)
by virtue of the Christian Doctrine, then adding it would
require a bilateral modification and consideration.
However, if the parties agree that the termination for
convenience clause a part of the legal agreement by virtue of
the Christian Doctrine, then inserting it into the contract
document should require no consideration, since the clause is
already a part of the legal agreement and adding it to the
document merely acknowledges that fact. The authority for SF30,
block 13C could be the clause prescription, e.g., FAR
49.502(b)(1).
Do you agree?
Eric:
It is an intriguing notion that FAR 43.103(b)(3) indicates that
a KO could cite the excluded clause as the authority for
unilaterally inserting that same clause into the contract on the
basis of the Christian Doctrine. I agree that it's a good
question for a lawyer. I doubt that there is any case law about
it, but I'm sure that a good lawyer can make up an answer upon
request.
However, I don't know what you mean when you say that you would
agree with the contractor that "this Christian Doctrine suff is
off on a tangent... ." Do you mean that you think the Christian
Doctrine is bad law, or that you think that it doesn't apply to
the Linda's EFT clauses, or both?
By
Eric Ottinger on
Wednesday, February 23, 2000 - 11:21 am:
Vern,.
I wouldn’t worry about Block 13. We do unilateral modifications
which are not really administrative.
“FAR 43.103 Types of contract modifications.
(b) Unilateral. A unilateral modification is a contract
modification that is signed only by the contracting officer.
Unilateral modifications are used, FOR EXAMPLE, TO--
(1) Make administrative changes;
(2) Issue change orders;
(3) MAKE CHANGES AUTHORIZED BY CLAUSES OTHER THAN A CHANGES
CLAUSE (E.G., PROPERTY CLAUSE, OPTIONS CLAUSE, SUSPENSION OF
WORK CLAUSE, ETC.); AND
(4) Issue termination notices.”
I think Joel would use 43.103(b)(3), which doesn’t appear very
restrictive, and use the authority of the clause, which is in
there by virtue of the Christian Doctrine, as sufficient
authority to make sure that the contractor knows what the clause
(which has been in the contract all along) has to say.
(The question of what can be done unilaterally, does seem to me,
to be an issue where we should rely on the advice of counsel.)
If we are going to hypothesize a hard-headed, sole source
contractor who only wants one payment by check, who never heard
of the Christian Doctrine, I would suggest that it would be much
better sit down with the contractor, read the law which says
that we are forbidden to make payments by any method other than
EFT, then read the implementing regulations.
From the point of view of this hypothetical, hardheaded
contractor, this Christian Doctrine stuff is off on a tangent,
and I would tend to agree with the contractor.
Eric
By
John Ford on
Wednesday, February 23, 2000 - 10:52 am:
Joel and Vern have raised an
interesting issue. Assuming that the Christian Doctrine applies
to a clause, how do you implement the Doctrine and evidence the
incorporation of the clause in the contract? Vern's advice about
negotiating with the contractor is sound. The government may be
convinced the Doctrine applies, but the contractor may think
otherwise. Also, the possibility exists that the contractor is
correct. To avoid the possibility of a dispute and the
disruption that would cause, negotiating is always the better
course. Having said that, the next problem is what mechanics
does the government use to incorporate the clause. If the clause
is clearly an admin clause and does not impose any obligations
on the contractor, a unilateral mod checking 13b on SF 30 would
seem permissible. On the other hand, if the clause would impose
obligations on the contractor that effect cost or schedule, it
seems to me the contractor would be entitled to an equitable
adjustment for that impact. Conversely, if the clause reduced
the cost to the contractor, the government would be entitled to
a price break. Thus, in these situations, a bilateral mod would
be appropriate. However, that does not answer the question of
what authority is to be cited for that mod. Sometimes
legislation provides the answer as was the case when FASA
authorized agencies to amend contracts to reflect the
streamlining anticipated by the statute. Generally, I do not
think there is a universal answer to this question. Instead,
theoretically, a detailed analysis of the clause and what it is
intended to accomplish should be done to determine what is the
appropriate authority. In some cases, the Changes clause might
be appropriate while in others it may not. In any event, I don't
think this will be much of an issue for a board or court if the
matter goes to dispute. They will only be concerned with whether
the Christian Doctrine applies.
By
Vern Edwards
on Wednesday, February 23, 2000 - 10:02 am:
Joel:
Lets pursue this. The word "contract" is used in two ways. The
first refers to the legal agreement between the parties; the
second refers to the document that memorializes that agreement,
i.e., the "contract document" that the KO and the contractor
sign. We all know that the legal agreement between the parties
can be different than the contract document. Indeed, that's the
gist of the Christian Doctrine -- that the content of the legal
agreement depends in part on the law and not just on the
conscious agreement of the parties, and thus their document of
memorialization may not accurately reflect their legal
agreement.
Now suppose that a KO has awarded a fixed-price supply contract
and distributed the contract document. The document does not
include the termination for convenience clause, which we know is
a required clause to which the Christian Doctrine applies. A
month after contract award the KO discovers the inadvertent
omission. She checks with her lawyer, who confirms that the
clause should be in the document and that a board or court would
probably insert it pursuant to the Christian Doctrine.
The KO notifies the contractor that the clause is missing and
that it applies despite the fact that it is not in the document.
However, the contractor has never been to school and has never
heard of termination for convenience or the Christian Doctrine,
so he tells the KO that he doesn't agree to let the Government
terminate the contract for its convenience and that the KO can't
just insert a clause that he never heard of and to which he did
not assent. Nothing the KO says or does convinces him, not even
providing copies of court decisions.
What does the KO do? She doesn't want to terminate the contract
at this time, but she knows that a termination may be coming.
Does she send the contractor a certified letter stating that the
clause is, in fact, included in their contract and let it go at
that, or does she issue a contract modification to insert the
clause in the contract document?
If the KO decides to issue a modification, does she do so
unilaterally? If yes, what does she put in block 13 of Standard
Form 30?
Does she check block 13A? If yes, what does she cite as her
authority? She can't cite the Changes clause, because the
changes clause for fixed-price supply contracts, FAR 52.243-1,
doesn't include "inserting a clause" among the things listed in
paragraph (a) that the KO can change.
Does she check block 13B? If yes, would inserting the clause be
an administrative change pursuant to FAR 43.301(b)? After all,
she doesn't think she's changing the legal agreement, she's just
changing the contract document to reflect what the legal
agreement really is, right?
(She doesn't check block 13C, because that would require her to
obtain the contractor's signature.)
Does she check block 13D? If yes, what type of modification is
it, unilateral or bilateral, and what does she cite as her
authority?
Or does she just ingore block 13?
By joel hoffman on Wednesday,
February 23, 2000 - 08:30 am:
Vern, thanks for the
clarification. After thinking about it some more, adding a new
clause and its effect on the Contractor retroactively is
probably outside the scope of the contract, thus the changes
clause isn't applicable. An out of scope supplemental agreement
is appropriate.
However, I don't necessarily agree that the KO must or should
obtain the Contractor's bilateral agreement to add a clause
which is already a contract requirement but was omitted from the
contract documents at award (i.e., when the Christian Doctrine
specifically applies to the situation). It is not a change.
Years ago, our headquarters Counsel advised to add such clauses,
using an Admin Mod - they are already a contract requirement.
I see no real value in "negotiating" and obtaining agreement on
a contract term which is already applicable. I don't mind
meeting with the Contractor and explaining the situation and
mutually discussing its effect on the Contractor or the
contract. But I don't need his official "agreement", which is
what a bilateral mod represents.
I already deal with several of the DOD's mega-contractors (cost
plus corporate mentality) who love to dictate to us their own,
"new" and "novel" (read "twisted") interpretations of existing,
traditional FFP contract terms. I wondered where they learned
such practices, until I realized they are all run by ex-brass
and KO's far removed from practice.
I don't need or want to negotiate their agreement whether or not
existing contract terms apply. Happy Sails! Joel
By
Vern Edwards
on Tuesday, February 22, 2000 - 07:33 pm:
Joel:
I know that you know this, but I want to clarify it for others
who do not know: A contracting officer cannot use the "changes
clause" (any of the FAR 52.243 clauses) to add a clause (as
defined in FAR 52.101) to a contract. The changes clauses
enumerate what they allow contracting officers to do, and none
of them allow contracting officers to add clauses. Nor do I know
of any other FAR Part 52 clause that authorizes the unilateral
addition of clauses to a contract. In order to add a clause to a
contract the parties would have to negotiate a supplemental
agreement (bilateral modification), as defined in FAR 43.101 and
discussed in FAR 43.103.
If the parties agree that a clause should have been included in
their contract and that it already applies to the contract by
operation of law even though the contract document makes no
mention of it, then they still should sign a supplemental
agreement in order to acknowledge and document their agreement
in that regard.
And a note to all:
Several of you have advised Linda Koone to check with her
lawyer. That's well-intentioned and helpful, but I know Linda
personally (and saw her recently) and you all should know that
she is a knowledgeable and experienced Navy contracting
official. She knows to check with her agency's lawyer before
deciding that the Christian Doctrine entitles the Government to
read a clause into a contract. She also knows that it is better
to reach an agreement with the contractor rather than to force
the clause down its throat. I'm sure that she asked her question
about the Christian Doctrine just to get our thoughts and to
stimulate some discussion. Since I know her I thought that I
would share some information about her.
By joel hoffman on Tuesday,
February 22, 2000 - 05:15 pm:
Again, I suggest you check with
counsel. The "Christian Doctrine" is not applicable when the
Government attempts to retroactively apply a new statutory
requirement to an existing contract. If the contract in question
precedes the statute, I believe the "changes clause" is
appropriate, at the least. If there will be additional cost to
the Contractor to implement, in such case, you must negotiate.
On the other hand, if the contract in question is later than the
statutory or regulatory language mandating an EFT implementation
date, the Christian Doctrine may be applicable. You might be
able to add the requirements by "Administrative Modification",
because they were already a mandatory contract condition.
A significant question arises from the fact that several
exculpatory reasons were explained in the implementing
directions to forego the "mandatory" EFT requirements, in such
cases. If any of those conditions exist, the Contractor might
rightfully complain if the Government unilaterally adds the
clauses to the contract, after award. Happy Sails! Joel
By
Eric Ottinger on
Tuesday, February 22, 2000 - 12:46 pm:
Linda,
Here is the section on waivers out of the Treasury Department
Regulation.
http://frwebgate1.access.gpo.gov/cgi-bin/waisgate.cgi?WAISdocID=403894750+0+0+0&WAISaction=retrieve
It may be easier to make the "one time payment" or determine
that the cost of EFT is more than the cost of a check, than to
fight with your contractor. As someone else recommended, it
might be a good idea to talk to your legal counsel.
Eric
Sec. 208.4 Waivers.
Payment by electronic funds transfer is not required in the
following cases:
(a) Where an individual determines, in his or her sole
discretion, that payment by electronic funds transfer would
impose a hardship due to a physical or mental disability or a
geographic, language, or literacy barrier, or would impose a
financial hardship. In addition, the requirement to receive
payment by electronic funds transfer is automatically waived for
all individuals who do not have an account with a financial
institution and who are eligible to open an ETASM
under Sec. 208.5, until such date as the Secretary determines
that the ETASM is available; (b) Where the political,
financial, or communications infrastructure in a foreign country
does not support payment by electronic funds transfer; (c)
Where the payment is to a recipient within an area designated by
the President or an authorized agency administrator as a
disaster area. This waiver is limited to payments made within
120 days after the disaster is declared; (d) Where either: (1)
A military operation is designated by the Secretary of Defense
in which uniformed services undertake military actions against
an enemy, or (2) A call or order to, or retention on, active
duty of members of the uniformed services is made during a war
or national emergency declared by the President or Congress;
(e) Where a threat may be posed to national security, the life
or physical safety of any individual may be endangered, or a law
enforcement action may be compromised; (f) Where the agency does
not expect to make more than one payment to the same recipient
within a one-year period, i.e., the payment is non-recurring,
and the cost of making the payment via electronic funds
transfer exceeds the cost of making the payment by check; and
(g) Where an agency's need for goods and services is of such
unusual and compelling urgency that the Government would be
seriously injured unless payment is made by a method other than
electronic funds transfer; or, where there is only one source
for goods or services and the Government would be seriously
injured unless payment is made by a method other than electronic
funds transfer.
By
Vern Edwards
on Tuesday, February 22, 2000 - 10:52 am:
John, et al.,
FACs 90-29 (June 3, 1995) through 90-46 (March 17, 1997) are
available in the Federal Register edition at the Federal
Acquisition Regulation site, http://www.arnet.gov/far/. Just
click on the link at the top of this page.
Vern
By
John Ford on Tuesday,
February 22, 2000 - 09:59 am:
Vern, based on the information
you have provided, this certainly is a clause that promotes a
substantial government interest. Thanks for the information. Now
that I have learned something for today, my day is a success and
I can go home while I am ahead of the game. We do not have
access to FACs before the 97 series so your research was most
helpful.
By
Vern Edwards
on Friday, February 18, 2000 - 10:28 am:
John:
The electronic funds transfer clauses mentioned by Linda in her
original inquiry are, I believe, FAR 52.212-4(i), 52.232-33, and
52.232-34. These were added to FAR by FAC 90-42 on August 29,
1996, 61 Fed. Reg. 45770, an interim rule. The FAC also added
FAR Subpart 32.11, Electronic Funds Transfer.
According to the Supplementary Information that accompanied the
FAC in the Federal Register, the clauses are mandated by Public
Law 104-134, the Omnibus Consolidated Rescissions and
Appropriations Act of 1996, part of which was the Debt
Collection Improvements Act of 1996, which the FAC quotes in
part as follows:
"(e)(1) Notwithstanding subsections (a) through (d) of this
section, sections 5120(a) and (d) of Title 38, and any other
provision of law, all Federal payments to a recipient who
becomes eligible for that type of payment after 90 days after
the date of the enactment of the Debt Collection Improvement Act
of 1996 shall be made by electronic funds transfer."
According to the FAC, this requirement is codified in 31 U.S.C.
§ 3332. The FAC states that the statute defines "Federal
payments" to include "vendor payments and expense
reimbursements." According to the FAC, the statute made EFT
payments mandatory for all contractors after January 1, 1999,
except where the Government is unable to make such payments. The
power to waive this requirement is delegated to the Secretary of
the Treasury. The FAC says that payments by credit card are
considered to be EFT payments.
The FAC was issued in response to an interim regulation issued
by the Treasury Department to implement the statute. According
to the FAC, the statute says that until January 1, 1999, payment
could be made by other means to those who certified that they
did not have an account with a financial institution or an
authorized payment agent. The FAC says, "Note that the
certification is an explicit statutory requirement of 31 U.S.C.
3332(e)(2)."
Thus, according to the FAC, the requirement to pay by EFT is
statutory. Do you think that this would qualify as a
"significant" policy that would warrant application of the
Christian Doctrine to incorporate the clause?
By joel hoffman on Friday,
February 18, 2000 - 01:04 am:
Linda, I suggest seeking advice
from Counsel.
When the Prompt Payment Act Amendments of 1988 were finally
implemented and mandated for all contracts awarded on or after
(April 1, 1994 -I think), we had a pile of contracts awarded
just after that date without the PPA clause and revised payments
clause because we didn't receive the FAR notice until later.
We issued Administrative Modifications to add the clauses to all
those contracts,including wording to the effect that the clauses
were already applicable by law but were omitted from the clauses
included in the contract (IFB or RFP)documents. Thus, no change
affecting either parties rights - admin mod.
Contractors raised Hell because they didn't know about the new
clauses either but all complied.
Happy Sails! Joel
By
Vern Edwards
on Friday, February 18, 2000 - 12:17 am:
John:
When you get a chance, take a look at General Engineering &
Machine Works v. Sean C. O'Keefe, Acting Secretary of the Navy,
a decision of the U.S. Court of Appeals for the Federal Circuit,
No. 92-1440, April 16, 1993, 991 F.2d 775. This case was based
upon a contract awarded in 1982, under the old DAR.
What happened was that the Navy inadvertently incorporated the
wrong DAR payment clause into a T&M contract. The proper clause
would have required the contractor to account for materials in a
separate overhead pool. The Navy and DCAA decided that as a
result of having left the proper clause out of the contract, the
Government had overpaid the contractor $86,775, and demanded
repayment, since the DAR had required the inclusion of the
proper clause. The contractor filed a claim and lost before the
ASBCA, which incorporated the proper clause based on the
Christian Doctrine. The contractor appealed the ASBCA's decision
to the Federal Circuit, which upheld the board's decision.
I quote now from the Federal Circuit's decision:
"[T]he Christian Doctrine applies to mandatory contract clauses
which express a significant or deeply ingrained strand of public
procurement policy... ." [Note the disjunctive "or" between
"significant" and "deeply ingrained."]
The Court then cited a long list of cases in support of this
statement.
The Court concluded that a clause requiring accounting for
materials in a separate overhead pool was "sufficiently
ingrained in public procurement policy to properly trigger use
of the Christian Doctrine."
Then the Court said:
"However, the Christian Doctrine has also been employed to
incorporate less fundamental or significant mandatory
procurement contract clauses if not written to benefit or
protect the party seeking incorporation... ."
This, too, was followed by a long list of cases.
You've persuaded me that a court or board might not apply the
Christian Doctrine to a clause requiring payment by EFT. But, is
it possible that a court of board would say that such a clause,
if required by statute and not just regulation, does, on
the basis of that very fact, reflect a "significant" public
procurement policy (though not "deeply ingrained")? Keep in mind
that in the original Christian case the termination for
convenience clause was not required by statute, just by
regulation. Is it possible that a court or board might conclude
that a clause specifically required by statute is, by
definition, a "significant" public policy?
I'd like to know what you think after you read the case, if you
get a chance to do so.
By
Eric Ottinger on
Thursday, February 17, 2000 - 11:54 am:
All,
Leaning somewhat to John Ford’s point of view, I have a hard
time imagining that the Christian Doctrine is going to be
applied for something that comes down to an issue of
administrative convenience.
I am not sure that Linda has asked the right question. And I am
not sure that we are helping her very much.
I think she is asking us how to convince a contractor to go the
EFT route after the contract has been awarded without the
appropriate clause.
From the point of view of negotiation strategy, the Christian
doctrine is way down my list. If the contractor is going to be
doing business with the Government in the future, the contractor
is going to have to make the change to EFT.
If this is somehow a strictly "one each" contract, with a
contractor who has no interest in future government contracts, I
don’t think it is worth the fight. I would find some way to
accommodate him.
If we are dealing with a hard-headed contractor who doesn’t
really like to be doing business with the Government, I suspect
that a phrase like “Christian Doctrine” isn’t going to impress
him very much. He will be likely to dig in his heels just to
call your bluff.
Whether, this clause is a “significant government interest” or
not, we won’t know whether the Christian doctrine applies to
this specific clause until the issue is litigated. But I can’t
imagine that anyone with good sense would wish to litigate this.
Eric
By
John Ford on
Thursday, February 17, 2000 - 10:27 am:
Vern, I stand by my statement
that the Christian Doctrine has only been applied to mandatory
clauses that are designed to protect significant government
interests. In the cases cited from Nash and Cibinic, all the
clauses fit this description, as you seem to agree for the most
part. What the quote says is that the boards did not do an
analysis of the appliction of the Christian Doctrine to the
clause at issue in certain cases. Instead, they merely applied
the Doctrine without a full explanation of why it controled the
case. This demonstrates a problem with the way many board, and
some court, decisions are written. Often what they do not say
causes more confusion than what they do say. Another good
example of this is the discussion of the Eichleay formula in
various cases. Some cases make the explicit statement that the
formula applies only to fixed indirect costs while others do not
make this distinction. This imprecision in language makes it
difficult to know what the rules of the game are and provides
ammunition to both sides in a dispute. Additonally, it inhibits
early resolution of many matters that result in strained
relations between the government and its contractors. Writing in
the Forum impresses me with the difficulty of writing clearly,
but it is something I think the boards can do better.
By
Lisa Billman
on Thursday, February 17, 2000 - 09:39 am:
Regardless of whether
enforceable when absent, what have you heard about enforcement
when present? I have been told by RM types that the statute does
not allow for withholding of payment for failure to submit EFT
information. If so, what good is a clause that requires the
submission of EFT information?
I realize that contractors are required to be registered in CCR
prior to award of DoD contracts; however, I understand that our
paying office cannot get EFT information or choose not to rely
on EFT information from CCR (don't know the exact reaon).
Therefore, submission of EFT information by the contractor is
still required.
By
Vern Edwards
on Wednesday, February 16, 2000 - 05:29 pm:
John:
You might want to check your assertion about the Christian
Doctrine applying only to clauses intended to protect
significant government interests. The following is from Cibinic
and Nash, Formation of Government Contracts, 3rd ed., p.
77:
"In the early application of [the Christian Doctrine], it was
held to apply only to clauses that contained significant
procurement policies, Chamberlain Mfg. Co., ASBCA 18103, 74-1
BCA ¶ 10,368 (Government Property clause). Subsequently, cases
appeared to apply the rule to all mandatory clauses without
analyzing whether they contained significant policies. See, for
example, Balimoy Mfg. Co., ASBCA 43768, 93-1 BCA ¶ 25,437 (First
Article Approval caluse); Rogers Constr., Inc., IBCA 2777, 92-1
BCA ¶ 24,503 (Assignment of Claims clause); M.E. McGeary Co.,
ASBCA 36788, 90-1 BCA ¶ 22,512 (Disputes Concerning labor
Standards clause); and Fireman's Fund Ins. Co., ASBCA 38284,
91-1 BCA ¶ 23,439 (Disputes clause). Some later cases did,
however, analyze whether the mandatory clause contained
significant policies. See, for example, Miller's Moving Co.,
ASBCA 42114, 92-1 BCA ¶ 24,707 ( the board incorporated the
Services Contract Act provisions in a contract because the Act
was an 'obligatory congressional enactment'); and H&R Machinists
Co., ASBCA 38440, 91-1 BCA ¶ 23,373 (the board incorporated the
Default clause in the contract because it implemented
'fundamental procurement policy')."
I admit that I don't quite know what to make of this quote. Some
of the clauses that the Professors seem to suggest did not
represent significant procurement policies seem significant to
me. It looks, however, like a board or court may apply the
Christian Doctrine to any "statutorily mandated" clause.
By
John Ford on
Wednesday, February 16, 2000 - 04:46 pm:
To date, the Christian Doctrine
has only been applied to mandatory clauses that are intended to
protect significant government interests. Not every clause
mandated by statute fits that description. Thus, it is arguable
that not every statutorily mandated clause is covered. However,
in regard to EFT, I cannot find a statute that mandates
contractor payments be made in this way. The closest I come is
Section 30 of the OFFP Act which encourages agencies to use
electronic commerce procedures whenever and to the extent
practicable. Thus, whether it is mandated by statute may not be
a factor. In that case, we fall back on general Christian
Doctrine principles. Based on this, I do not believe EFT clauses
are covered by the Christian Doctrine. As in all cases of this
nature, I suggest you consult with your legal advisor.
By
Vern Edwards
on Monday, February 14, 2000 - 04:01 pm:
Linda:
I would say that if the clause is required by a statute then the
Christian Doctrine applies.
Vern
By
Linda Koone
on Monday, February 14, 2000 - 10:13 am:
Electronic Funds Transfers (EFT)
Clauses. . . mandatory based on statute and thus applicable even
in absence of the FAR Clause (by virtue of the Christian
Doctrine); or enforceable only if specifically referenced in a
contract?
Any opinions? |