By
Anonymous
on Tuesday, September 12, 2000 - 01:28 am:
What's the best way to incorporate a proposal in a contract?
The rfp is in the uniform contract format.
By
Ramon Jackson on Tuesday, September 12, 2000 - 11:04 pm:
Rita Sampson had cautionary words in the old Water Cooler
that are worth reading again.
Ron Vogt (Is this you as Anonymous?) opens the issue in this
forum and passes the ball to this thread.
Ron, what you remember is probably in the old
Water Cooler. It is archived, but difficult to deal with
since all formats. other than "by date," go back to a blank Open
Forum. In fact, if you don't have a good idea of the exact
thread and approximate time of a post it is nearly useless in
itself. The search engines do have it indexed and posts may pop
out of carefully structured searches.
Maybe it would help if the question above were redefined.
Perhaps to "when might it be appropriate" to incorporate a
proposal. From purely secondary contact with the issue, reading
and consideration I'm interested in the following issues:
- Incorporation seems worth considering for certain
straightforward solicitations calling for a highly structured
and limited response (sealed bit onward to some point on the
spectrum). Is there good discussion of issues in finding the
break point?
- Incorporation of complex proposals responding to complex
solicitations, seems to fall more into the category of removing
rattlesnakes by hand - with expertise, a plan, and more than a
little caution. I have an impression too many cases of
incorporation fall into this area and fail to respect the
potential for biting back -- the kind of thing Rita Sampson
seemed to have in mind. Are the people stating they will
incorporate proposals actually doing the planning and
structuring of instructions that would drive and a proposal
structured for incorporation? Are some so bad that they will
incorporate those beloved "approaches" so that when the learning
curve dictates approach modification a formal change is
required?
We've been around on the theory, do we have cases and examples?
By
Anonymous
on Tuesday, September 12, 2000 - 11:32 pm:
I didnt ask when it's appropriate to incorporate a proposal
in a contract. I asked what's the best way to do it. What are
the mechanics?
By
Ramon Jackson on Tuesday, September 12, 2000 - 11:52 pm:
There are mechanics for picking up diamondbacks. Go ahead.
Follow those mechanics when you are drunk on a dark night.
If you are only interested in the mechanics without judgment or
interest in when to apply them I suspect similar results will be
in store.
By
Anonymous
on Wednesday, September 13, 2000 - 09:42 am:
I'm simply asking for advice in solving a practical problem.
What makes you think we didn't use judgment?
By
joel hoffman
on Wednesday, September 13, 2000 - 10:04 am:
Anon, I have seen several methods to incorporate a proposal
into the contract. Also depends upon the type and format of the
contract. For service contracts, using the uniform contract
format, I believe I would describe what part of the proposal I
would incorporate into the contract in a narrative within the
Section "C", the Statement of Work. If SF26 is used, block 18 is
checked and the appropriate volumes of the proposal can be
listed.
For construction and design-build RFP's we don't use the UCF
format. We use a format similar to the Construction
Specifications Institute (CSI) format. Section 0800 are the
Special Contract Requirements (SCR's - equivalent to UCF,
Section "H"). We use an SCR which USACE is presently working on
incorporating as an EFAR Clause, which states that the contract
includes the accepted proposal and provides an order of
precedence, in case of descrepancies between the RFP and the
proposal.
Note that the FAR Clause "Order of Precedence" is not used with
CSI format, as the FAR clause refers to the Statement of Work
(Section C) as the "specifications." The FAR Clause places the
proposal above the minimum RFP requirements.
The USACE SCR places any "betterment" (both meets and exceeds
the RFP minimums) first, then the RFP minimums, then other
aspects of the proposal, in case of conflict. This clause
requires the Government to carefully review the proposals,
discover and reject any deviations from the minimum RFP
requirements. A condition of award is that the proposa does not
deviate from the minimum RFP requirements.
The SF1442 contains (block 20?) to check that the proposal is
part of the contract and you can identify it in an attachment.
Happy Sails!` Joel
By
Anonymous
on Wednesday, September 13, 2000 - 10:49 am:
Mr. Hoffman:
If we incorporate the proposal into Section C, do we have to
rewrite the SOW to incorporate the proposal language, or do we
just append the proposal to the SOW?
By
Peggy Richter
on Wednesday, September 13, 2000 - 11:25 am:
We often incorporate a proposal into a contract here as we
are usually buying RDT&E where the contractor's stated approach
/ method of analysis is what earned them the award (i.e. there
is more than one way to do the work and the technical proposal
was a critical factor). In such cases, you need to have your
govt. engineers check the proposal carefully -conflicts can be
well hidden from a casual overview. IF your sow is well written,
you shouldn't have any conflicts and if you do, you will want to
have the SOW have precedence. Note that in the case of a
conflict, you may be negotiating the contractor's technical
approach or have problems later on. IF your sow is less than
ideal (as happens on occasion), you may find the CONTRACTOR's
proposal has conflicts where the proposed approach/method/ etc
is better than what you have in the SOW. Again, you may be in
negotiations on that (and have some issues if you competed the
procurement). The end result, however, is the same - there
should be no conflicts between the SOW and the technical
approach proposed by the contractor so that incorporation makes
it one unified whole at time of award.
By
Anonymous
on Wednesday, September 13, 2000 - 11:53 am:
Ms Richter:
So you would attach the technical proposal to the SOW in Section
C after making sure that there were no conflicts. Then the two
would be read together, with the tech proposal describing the
method that would be used to perform the tasks specified in the
SOW. If there were conflicts, then you would negotiate them out
before making the award.
If there are conflicts between the tech proposal and the SOW and
you have to negotiate them out, would you conduct another round
of discussions with all the offerors?
By
Ramon Jackson on Wednesday, September 13, 2000 - 12:41
pm:
Well "Anonymous" who can tell whether you, or your agency
uses good judgment? We haven't a clue. Some do, many don't.
There is a method. From observing results it is often used
without sound judgment, just habit. Results sometimes make those
paying attention want to weep. Looking at the apparent
application of some intending to incorporate makes weeping a
high probability. They know how, not the rest.
You don't tell us whether this if for buying vehicles,
janitorial services, an antimissile defense system, or studies
into the cure for AIDS. Not a word on contract type. What is the
method for striking a match? It can definitely depend on who,
where and for what.
Rita made some good observations. Peggy actually adds to that
with her caution about due diligence by the engineers. There are
other issues. I have to wonder whether Peggy's people (who last
I knew weren't amateurs) don't get into occasional unnecessary
difficulties by incorporating too much into the "RD" part of the
RDT&E contract.
T&E is usually pretty standardized and much more straightforward
than R&D on the path to the product to test. Let's take AIDS.
The test protocols are well developed in medicine and we
probably actually want independent T&E. We also generally want
the contractor to test internally along the same lines. I have
no real problem with incorporating a contractor's proposed test
plan, probably nearly a copy of industry standards, into the
contract if that is desired. I question the need since a
contractual pointer to acceptable testing is probably
sufficient.
The contractor proposes a particular research and development
approach that catches our eye, as Peggy mentions, and we
incorporate it. Six months or a year into the program we find
several aspects of the shiny "approach" that seemed so
innovative needs modification in light of experience. Parts are
indeed promising, others definitely need changing, but in R&D
the approach modification itself may be a sort of R&D. Are we
going to "enjoy" constantly evaluating requests for changed
approach and executing new and binding contract language as this
develops?
The issue applies to every R&D effort I can think of at the
moment. When the program office and contractor survey the
progress and decide learning has driven a need to change course
I'd want to be able to make the correction within the
contract's bounds and not have to go for a mod. This
particularly applies if my contracting office hasn't learned to
do these things in parallel and fast. An R&D program office
wanting to incorporate may be issuing itself a straight jacket.
Time is money and all are burned while we jump through
unnecessary programmatic hoops.
We hope the contractor's proposed approach includes scope for
these necessary course corrections. In the press to present the
bright and shiny object to the evaluators, in response to
instructions, or foolishness the contractors often paint
everyone into a corner if "how" becomes contractual. That is why
I believe up front planning in the early stages of a
solicitation, covering all instructions, and being quite aware
of these issues is the only safe way of handling the issue. To
put it bluntly, if the SOW and proposal contain anything but
very minor conflict, when incorporation is the objective, I have
to suspect lapse in planning and execution.
It seems much better to segregate those aspects that must be
contractual in nature from the part that is used only to
convince the evaluators that the offeror has a real
understanding of and has done the preliminary planning to
accomplish the job. In Vern's view the latter is the test that
passes the contractor into the contract, not the contract.
Particularly in the R&D end of the spectrum locking down only
the necessities makes sense. I believe one of the necessities is
the framework for working the other issues within the
contract, not by constant modification. As one approaches the
straight buy and less complex tasking the application of
incorporation improves. Eventually we reach a sealed bid that
is, I believe, a straight and relatively simple incorporation of
a bare bones "proposal."
I think the issues and examination of practical results of
incorporation a potentially interesting discussion. If you don't
want "your" thread used we can start another.
By
joel hoffman
on Wednesday, September 13, 2000 - 01:12 pm:
Anon, Sorry - I wasn't clear enough. Meant to say that I
would write some narrative in the original RFP Section C,
stating that the successful Offeror's XXXXXXXXX (describe which
volume) of the accepted proposal would become part of the
contract. I would also add that the proposal could not deviate
from the minimum RFP requirements but could offer "betterments"
which both meet and exceed the minimum RFP requirements.
No, don't rewrite Section C. The portion of the accepted
proposal is simply listed on the contract award SF28 or whatever
form you use for your contract award. The incorporated portion
of the proposal becomes an attachment under Section J (for UCF
contracts).
Note that the proposal then has the same status as other UCF
format attachments under the FAR clause "Order of Precedence",
so you better ensure that there are no conflicts between the
proposal and other documents of equal hierarchy.
Section "L" or "M" should state whether or not I would entertain
deviations (deviations allowed in the initial proposal ONLY if I
announced an intention to conduct discussions). I would further
explain that in order to be eligible for award, there could be
no deviations from the solicitation requirements in the final
revised proposal. I would explain that if the Government were to
accept deviations in the initial offer, it would be done by
amendment for all offerors to share and compete on an equal
basis during subsequent negotiations.
This does not preclude the Government from entertaining
"alternate proposals", when allowed in the RFP. In that case,
the alternate proposal must still be technically acceptable. The
proposal is incorporated the same way as before. The difference
is, we don't share the allowed alternate approaches with all
other offerors by amending the solictiation.
Hope this helps. Happy Sails! Joel
By
joel hoffman
on Wednesday, September 13, 2000 - 01:33 pm:
This is the Order of Precedence Clause used for COE
design-build contracts, in lieu of the FAR Clause "Order of
Precedence." Construction RFP's use a very similar SCR. Note,
that the Corps of Engineers doesn't use the UCF format for
construction contracts (at least we aren't supposed to - there
are a couple of lone wolf districts out there, still using UCF
for everything, including construction).
Happy Sails! Joel
"SCR___. DESIGN-BUILD CONTRACT - ORDER OF PRECEDENCE
(a) The contract includes the standard contract clauses and
schedules current at the time of contract award. It entails (1)
the solicitation in its entirety, including all drawings, cuts,
and illustrations, and any amendments, and (2) the successful
offeror's accepted proposal. The contract constitutes and
defines the entire agreement between the Contractor and the
Government. No documentation shall be omitted which in any way
bears upon the terms of that agreement.
(b) In the event of conflict or inconsistency between any of the
provisions of this contract, precedence shall be given in the
following order:
(1) Betterments: Any portions of the accepted proposal which
both conform to and exceed the provisions of the solicitation.
(2) The provisions of the solicitation. (See also Contract
Clause: SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION.)
(3) All other provisions of the accepted proposal.
(4) Any design products including, but not limited to, plans,
specifications, engineering studies and analyses, shop drawings,
equipment installation drawings, etc.. These are "deliverables"
under the contract and are not part of the contract itself.
Design products must conform with all provisions of the
contract, in the order of precedence herein.
(End of Clause)"
By
Ron Vogt on
Wednesday, September 13, 2000 - 01:50 pm:
The mechanics of incorporating is only the beginning of the
problem. What both the government and the contractor should be
concerned with is the enforcability of the proposal as a
contract requirement. As the Omni case (from the "Dam" messages)
demonstrates, everything stated in a proposal does not
necessarily become a contractual requirement, despite a clause
in the contract stating that the proposal was incorporated and
became additional contract requirements.
I don't have access to the Nash & Cibinic article, so I'm doing
this without the benefit of their analysis. Nevertheless, here's
my take on the problem:
Let's say the government is looking for a contractor to manage
its spare parts inventory, and issues an RFP with several
performance requirements. RFP also says that technical proposals
will be incorporated into the contract. Contractor responds with
a technical proposal that says it will use a whiz-bang software
system that will do everything the RFP requires, plus more. As
this is a best value procurement, the government awards it the
contract, despite its higher price.
Two months later, the contractor concludes that its whiz-bang
software won't work, and falls back on using older software that
accomplishes the minimum RFP requirements. Government says that
the contract requires the extra features on the new software,
and threatens default, deductions, etc.
What's the answer?
According to Omni, the government may well be right. The
contractor promised service capabilities that exceed the RFP
requirements, and these capabilities were incorporated into the
contract. The court in Omni stated: "If a successful bidder
presented a level of service exceeding solicitation
requirements, the court agrees those proposed capabilities would
become contract requirements." What saved the contractor in Omni
was that it proposed staffing levels, not service capabilities.
In short, the mechanics of incorporating a proposal are not the
main problem. It's the interplay between the contractual
requirements and the technical proposal.
By
Peggy Richter
on Wednesday, September 13, 2000 - 01:52 pm:
Joel put it pretty well in terms of how you want to do this
-- your section C should have a "fill in the blank" for you to
put in the proposal date and # pages.
Anon asked: If there are conflicts between the tech proposal and
the SOW and you have to negotiate them out, would you conduct
another round of discussions with all the offerors?
== If they are anything that could possibly be considered other
than clarification issues, you will need to do it prior to award
or you can expect to have to do it after award at a much larger
$ impact. If you don't include the other offerors, you can
pretty much expect someone to protest. You want to avoid
technical leveling (by this I mean divulging a contractor's
approach to it's competitors).
If there are no conflicts and you included in your RFP a
statement of intent to incorporate the proposal (as Joel
indicates), then you don't need to further negotiate as you have
already included the other offerors in the initial RFP.
In RDT&E, yes, sometimes the contract gets moded as you go along
because the R&D leads to avenues that no one expected. Hopefully
it is not because of an error in the SOW or in an undetected
"straight jacketing". Incorporating a tech proposal into a
contract is risky because anything that is ambiguous suddenly
becomes the Govt.'s responsibility, so it is not something you
want to do without a good reason. It's one thing to do this with
something like "come up with the next version of a Sidewinder"
and another to use this for "do vacuming of the Government
buildings".
By
Anonymous
on Wednesday, September 13, 2000 - 03:12 pm:
Mr. Jackson:
The contract is for base civil engineering services. The
contract type is fixed-price-award-fee. The SOW describes what
must be done and the contractor's proposal describes how he will
plan, organize, staff, direct and control the processes he will
use to perform those tasks. The technical narrative in the
proposal is about 250 pages long. Thats the part I'm talking
about.
The functional area people who evaluated the technical proposal
liked what the contractor said and want to make sure that he
does what he said he is going to do. We frankly didn't think
about whether the proposal would be part of the contract or not
when we issued the RFP. We assumed that it would be, but now we
aren't so sure that's true unless we say so in the contract
document. We think that we have to incorporate the proposal in
the contract in order to protect ourselves.
Our lawyer says he doesn't have any heartburn about what we want
to do "in principle," but wants us to figure out how we're going
to do it before we come to him for his review. That's why we
thought we'd ask the question at this site.
By
Vern Edwards
on Wednesday, September 13, 2000 - 05:02 pm:
Anonymous:
I don't have an answer to your question about how to incorporate
an offeror's proposal into a contract. Sorry. Maybe one of the
other folks will come through for you yet. But I wonder if you
would allow me to offer you some food for thought.
You indicated that you prepared your RFP in the uniform contract
format. I therefore presume that you used Standard Form 33,
Solicitation, Offer, and Award. According to FAR 15.504(c), you
may award the contract on SF 33, SF 26, Award/Contract, or
Optional Form 307, Contract Award.
Look at the Award portion of SF 33, blocks 19 through 28. The
first block in that portion of the form, block 19, says,
"Accepted as to items numbered... ." (I presume that the "items"
are the contract line items.) Acceptance is what makes the
contract. SF 33 provides for unilateral action; there is no
place for the contractor's signature. What do you accept? You
accept the offeror's offer. FAR 2.101 says that "proposal" is a
synonym for offer. Thus, if you award the contract using SF 33
you have accepted the offeror's proposal (offer) and it is a
part of the contract whether you like it or not. If the terms of
the proposal (offer) differ from the terms of the RFP, then the
proposal (offer) will govern, since it is well-established law
that you can only accept a proposal (offer) based on its terms.
In effect, you will agreed to terms that were different from
those in your RFP, whether you meant to or not. An RFP is merely
a wish list of terms; it is the offer that was accepted that
determine what is in the contract.
(One problem with SF 33 is that it does not say which part of
the uniform contract format the proposal becomes a part of, and
that is important because of the order of precedence clause. I
suspect that it would be considered an attachment, and
attachments trump Section C. But even it it were incorporated
into Section C, the proposal would govern since that is what you
accepted. You can't save yourself by unilaterally putting it
where the order of precedence clause would serve your interests
instead of the offeror's.)
Better go to SF 26. That form gives you two choices for award:
(1) block 17 or (2) block 18. Block 17 says that the contract
includes "this award/contract" (I suppose that means the SF 26
itself), the solicitation, and terms incorporated by reference.
It requires that you get the offeror's signature. Thus, you can
write the contract any way you want, and if you get the offeror
to sign it you're home free. SF 26,. block 17, allows you to
incorporate the proposal intelligently, by attachment, page
substitution, pen and ink change, or cutting and pasting into
the appropriate section(s) of the uniform contract format. You
and the offeror will be bound by whatever you sign.
SF 26, block 18, says that the contract consists of the
government's solicitation, the offer, and the "award/contract"
(SF 26?). It, like SF 33, provides for unilateral action. There
is no place for offeror signature. We have case law that says
that the offer trumps the solicitation when SF 26, block 18 is
used; see F&F Laboratories, Inc., ASBCA No. 33007, 89-1
BCA ¶ 21207. (A very funny case.)
So award on SF26, block 18, is similar to award on SF 33. You
have accepted the proposal (offer) and will be bound by it.
OF 307 is similar to SF 26.
So whatever you do, think about which form you will use to award
the contract. The choice can have important legal consequences.
My advice is that you use SF 26, block 17, and make sure that
the document that you send to the winning offeror for signature
reflects the terms that you want in the contract. If those terms
differ from the offeror's final proposal revision, then you are
continuing discussions by making a counteroffer.
For those who understand my proposal vs. offer argument, you can
see why it is important to make the distinction clear in your
RFPs.
By
joel hoffman
on Wednesday, September 13, 2000 - 06:44 pm:
Anon,
Based on your stated desires of the Government, the KO could
consider this: Establish a competitive range and conduct
discussions with those offerors.
Explain to them that the Government intends to incorporate "that
part of the successful offeror's proposal describing how it will
plan, organize, staff, direct and control the processes he will
use to perform those tasks." NOTE: I assume that this material
is segregable from unwanted parts of the proposal for
identification purposes - if no,t make it so in the amendment
discussed below.
During discussions you must point out deviations in the existing
proposals. You may bargain with offerors to improve their
technical approaches if you don't like them - just don't
transfuse one offeror's ideas into discussions with others or
you WILL be protested. That is too complex to fully describe
here.
Upon conclusion of discussions (or can be done anytime at or
before requesting final proposals), issue an Amendment to add a
statement in Section C that says that the (part of the
successful offeror's proposal describing how it will plan,
organize, staff, direct and control the processes he will use to
perform those tasks - whatever you called that part of the
proposal submission in theSection "L" proposal submission
requirements). State that the accepted proposal will be
considered an attachment in Section J. That will clarify the
order of precedence after award.
Ask for revised proposals and evaluate - making darned sure that
the successful offeror's proposal doesn't deviate from your
solicitation.
Be aware that the offerors might revise their technical and/or
cost proposals if they know it will become a contract
requirement.
Use the correct block on the contract award document, as Vern
explained.
My suggestion only concerns mechanics not the wisdom of
incorporating a technical approach proposal as a contract
requirement. This could backfire on you, as several others have
warned. If the Contractor proposes a specific technical approach
which doesn't produce the results required by Section C - you
may very well have bought a substandard approach and have to pay
more to obtain satisfactory results - I would suggest you make
it clear during negotiations and in the amendment that if the
proposed approach is later determined by the Government to be
inadequate in meeting the specified minimum results, the
Contractor will have to propose a corrective adjustment its
technical approach at no additional cost to the Government.
See how complicated this can get???????
Happy Sails! Joel
By
joel on Wednesday, September 13, 2000 - 07:01 pm:
Correction to my last post - In one paragraph I left out the
end of an already too long sentence:
"Upon conclusion of discussions (or can be done anytime at or
before requesting final proposals), issue an Amendment to add a
statement in Section C that says that the (part of the
successful offeror's proposal describing how it will plan,
organize, staff, direct and control the processes he will use to
perform those tasks - whatever you called that part of the
proposal submission in the Section "L" proposal submission
requirements) will be incorporated into the contract.
State that the accepted proposal will be considered an
attachment in Section J. That will clarify the order of
precedence after award."
Happy Sails! Joel
(Also state that if the proposed approach is later determined by
the Government to be inadequate in meeting the minimum
requirements in Section C, the Contractor will have to propose a
corrective adjustment its technical approach at no additional
cost to the Government.)
By
Vern Edwards
on Friday, September 15, 2000 - 01:58 pm:
What timing! The September edition of The Nash & Cibinic
Report includes an article by Prof. Nash entitled,
"Performance-Based Contracting: Incorporating the Proposal in
the Contract." He discusses three issues: (1) whether such
incorporation conflicts with the fundamental purpose of
performance-based contracting, (2) whether it is wise to
incorporate the entire proposal into the contract, and (3) what
is the impact on the government if it binds itself to a
contractor's proposed method of performance.
For those of you who do not have access to The Report,
Prof. Nash states four principles of incorporation:
"(1) It is uniformly bad policy to incorporate the entire
technical proposal into the contract by reference.
(2) Before deciding to make methods or techniques in the
proposal binding promises, the agency should carefully consider
the benefits and detriments of such a decision.
(3) If elements of a technical proposal are made part of the
resulting contract, they should be specifically identified in
the final contract document and stated in clear promissory
language.
(4) When an agency intends to make elements of the technical
proposal part of the contract, the solicitation should clearly
state the procedure that will be used to identify those elements
and incorporate them into the contract."
Worthwhile reading.
By
Ramon Jackson on Friday, September 15, 2000 - 09:10 pm:
Anonymous,
I believe you now have some constructive suggestions on how to
do this with cautions you might consider presenting to the
functional people driving this for reconsideration or their
request. Technical people (I was one), usually with little
exposure to some of these issues, seem to be the most vocal in
wanting exactly what they think they read in proposals made
contractual. They are often the first to howl when faced with
full consequences. In a 250 page technical proposal I'd expect a
howl or two to lurk.
I'm a bit puzzled at the award fee for what now appears to be a
lower risk, fixed price type, but it does offer an alternate
tool for what your functional people seem to want. On the
surface it seems to make the need to solidify the contractor's
behavior by incorporation less necessary. Without analysis of
the actual effort that is just an itch in my mind and something
to consider.
Vern's observations about forms and blocks are excellent warning
flags, now you have some more in his latest reference. At least
push for incorporating "the proposal intelligently, by
attachment, page substitution, pen and ink change, or cutting
and pasting into the appropriate section(s) of the uniform
contract format." Challenge functional people to separate the
precise things necessary for contractual rigidity from those
that can be considered business as usual in intelligently
meeting the variables that will almost certainly come.
For example, they liked the contractor's proposed approach to
planning, organization, staffing and such. If it turns out the
organization and planning activities aren't working as well as
everyone thought are you going to require a contract
modification with the time and expense that involves? Suppose
the functional people come to you and say "Something is
seriously wrong with this process, despite what we thought when
reading all those proposals, it has to change." Are they going
to howl when you explain the facts of having that process
contractually bound and they can just wait while you work a mod
to a fixed-price-award-fee contract? Wouldn't it be better to
focus now on contractually binding a process for
evaluating performance and working to mutually agreeable
adjustment within the contract?
Lastly, you clearly state you did not intend incorporation from
the start. You were pushed into the idea by the functional
people. We have no clue as to their training in contractual
issues, but you do. My little mental light goes to glowing red
at the idea of an accidental stumble into full proposal
incorporation instead of a planned approach with an RFP crafted
to accomplish that result. Fully harmonizing planned documents
is difficult. Rushed, unplanned efforts to blend documents not
intended to be put together is almost certain to contain perhaps
serious glitches. This seems a bit like "impulse shopping" on a
grand scale by your functional people -- usually dangerous and
certainly not something the government's business advisor should
take without concern. Good luck. Let us know the outcome.
Ramon
By
G. Owen on Wednesday, September 27, 2000 - 11:08 am:
Beautiful timing indeed! This thread may have started out as
"How do I incorporate proposal," but Vern's 15 September
quotation of "...uniformly bad policy..." provides the
definitive statement on whether it is prudent to do so.
This quotation could be used to answer other questions in the
future:
* How do I go about making something a directed subcontract?
* How can I "break out" several major subcomponents as GFP so as
to avoid overhead costs?
* Can I use competition to force contractors to accept more
risk?
Maybe answer to original question is a big rubber stamp that
says "Offeror's proposal dated ___ is hereby incorporated by
reference with the same force and effect as if attached hereto
and made a part hereof."
Gordon
By
stermer on Wednesday, September 27, 2000 - 02:24 pm:
If you are you making a "best value" award, trade-off,
technical merit for price, how do you hold the contractor to
their higher level of performance..than the SOW. Are you not
paying for the higher level?
By
joel hoffman
on Wednesday, September 27, 2000 - 03:14 pm:
Stermer, you may "hold them" (contractually at least) to
their proposal by identifying which part of the proposal you are
incorporating into the contract. This is best done by naming or
designating the different areas of the proposal in the
Solicitiation and describing which part of the winning proposal
will be so incorporated.
The actual act of incorporation is denoted in one of the blocks
on the contract offer and acceptance Standard Form (several
different forms used, depending upon the type acquisition). Best
to designate what part of the winning proposal will be
incorporated in the initial RFP but you may designate it by
Amendment during pre-award discussions, prior to final, revised
proposals. Happy Sails!
By
Ramon Jackson on Thursday, September 28, 2000 - 03:54
pm:
Stermer, the question you raise is a common concern among the
people reviewing proposals. I'll use an example from an area I
was familiar with.
One requirement deals with hardware and software
transition-integration into an operating environment with
minimal impact. One proposal shines in its overall demonstration
of understanding the problems and presenting thoughtful,
knowledgeable and innovative solutions. One proposal item deals
with the transition issues. It shows a contractor that has
probably learned valuable lessons from experience who has also
really thought of how to mitigate transition risks in general
and ours in particular.
We too have learned from hard experience. We've seen those
charming words, perhaps written by proposal experts without
contact with the firm's delivery teams, turn to dust as we meet
a clueless contractor team (an aside on that subject later). We,
as the technical evaluators, are determined to avoid that and
someone suggests that we incorporate this wonderful proposal to
"hold them to it" and avoid past pain.
I think that is a bad to disastrous idea for reasons I expressed
here earlier -- particularly in those "approach" issues that are
so often the issues. That proposed transition-integration
scenario may be outstanding -- until it hits the reality of your
actual situation. Why turn adjustment from an initial good idea
(based on your descriptions of the environment and maybe a quick
inspection) into a practical solution to the actual environment
a contract modification? When theory meets reality why raise
risk you turn this into a sudden mod that might raise a few too
many opportunities to bring up issues with your own
descriptions?
Instead, spend your effort in doing what is necessary to insure
the proposal, as it should be, is the delivered mutually agreed
upon baseline from which all will depart and that
processes for working adjustment issues are contractual. You
should have covered these in the SOW, but this is the last
chance to insure there will be teamwork under contractual
mandates to address these approach issues. Then, instead of
having the work and possibly risk of a modification you have a
process within the contract's bounds to make the necessary
course corrections with specific knowledge and experience. They
should also cover worst case development in concert of a
contract modification if that becomes necessary. It will likely
save much trouble and money in the long run.
Incorporation offers a sort of straitjacket from which you
cannot escape normal working issues without drastic action. It
can drive too frequent changes or mindless performance that once
sounded good and now grates. Incorporation may sound good, but
you will probably pay later while a more thoughtful approach
will pay off.
The aside. Long before I thought of contracting people as
other than those fools that too often delivered strangely inept
stuff to us field types I had an applicable maintenance horror
story of "who showed up." We had a state-of-the-art digitizer in
the days when these things were really unusual. We put in
requirements for maintenance after the manufacturer's warranty
period expired. This described the digitizer in detail and
required contractor provide trained maintenance people and all
necessary tools and manuals. Enough for us technical types.
We never knew what "contracts" did with our requirement other
than getting a contractor. One day the digitizer quit giving
accurate readings. We called for maintenance. The contractor was
prompt. A man carrying a large tool box arrived. He was escorted
into the room where the computer and digitizer sat, looked
around vaguely and was then shown the big white "table" that was
the digitizer. "Wat's that?" he asked. "That is what you are
going to fix." He then told us he'd never seen such a thing and
demonstrated that by revealing tools appropriate to repair a car
engine.
Needless to say he was sent packing. He wasn't about to touch
that six figure dollar value digitizing table. Eventually after
much swirling about in legal and contracts the contract was
terminated, but our digitizer was never operational again. By
the time the dust settled and we were "allowed" to seek
maintenance again the thing was obsolete. It did make a really
wonderful table top though. We used it for many years as a place
for large layouts of materials and sometimes lunch.
Such experiences are the reasons some of the technical types
glare at "contracts" with dark red glows in their eyes and want
to do what really are foolish things |