By
joel hoffman
on Tuesday, May 30, 2000 - 08:15 pm:
Ralph, I'm out of the office,
this week, so don't have access to my files and don't have time
to research the Internet. I have a full file on this subject
with Case citations back in the office.
However, I will guarantee that the "Victory Principle" has been
re-affirmed in Court, after 1992. The Eng BCA "Bean Dredging"
Decision, circa 1989, briefly overturned the Victory Principle.
The ENG Board decided that overruns beyond 115% of the estimated
quantity should be re-priced , based on actual costs of the
overrun quantity. This amounted to cost plus percentage of cost
contracting! It was ludicrous. This decision only applied to
Civil Works funded work.
Soon after, in another case, the name escapes me, The ASBCA
refused to follow Bean for Military Construction. At this point,
we had two diametrically opposed rulings which applied to Civil
or Military funded work.
The Claims Court,circa 1994, re-affirmed the ASBCA and "Victory"
Principle, deciding that the Bean Decision was WRONG. Current
Corps of Engineers policy, which I was involved in formulating
after Bean was finally dumped, is that price adjustments are
only based on difference in unit cost to the contractor between
the first 115% and the overrun beyond 115% - irrespective of the
contract unit price. If you can wait until next week, I will
cite you the Cases. Happy Sails!
By
Ralph Broome on
Tuesday, May 30, 2000 - 05:19 pm:
Joel
I believe that what your saying in your 3rd paragraph is that
you don't reprice the entire work, but only the increase or
decrease to the cost of the work caused by the quantity
variation. Am I correct? Also, do you have a reference for the
ASBCA and Claims Court case(s) that re-affirms the "Victory"
decision. I have been told that Burnett Constr. Co. v. U.S. (26
Ct. Cl. 296, "1992") overturned the "Victory" case. Would you
have anything on this?
By
joel hoffman
on Saturday, May 27, 2000 - 10:39 pm:
The VEQ clause is intended to
enable a unit price adjustment for actual payable quantities of
unit priced work outside a range of 85-115% of the estimated
quantity, under certain circumstances.
The VEQ Clause is not intended to "control" overruns. The
technical specifications, in combination with the drawings,
generally describe what work is payable. The drawings should
indicate a "pay line" for rock, so that the Contractor can't
just pile it on and expect payment. If the contractor is
performing work within the paylines established in the specs
and/or drawings, you will have to pay for the extra quantity.
If the work beyond 115 % of the estimated quantity costs the
contractor less per unit or costs the contractor more per unit
than the cost to the contractor per unit for the first 115%,
either party can request an adjustment to the unit price on the
overrun work. The adjustment is only based on difference in unit
cost to the contractor. The contract unit price, itself, has
little bearing on the adjustment or whether to make an
adjustment. In other words, we do not "reprice" the overrun work
to determine what to pay for the it. This method of adjustment
is called the "Victory Principle," based on an old Court
case,recently re-affirmed by ASBCA and by the Claims Court.
In an overrun, assuming no difference in method required to
place the overrun rock, there may be a savings per unit (ton or
cubic yard?),because the contractor has recouped its
mobilization costs. Absent a bid item for "mobilization and
demobilization", the contract unit price is assumed to include
an allowance for this. There might also be some savings per unit
due to economy of scale (e.g., discounts from the quarry for
more rock purchased?) caused by the overrun. The unit price
should include a share of the site overhead costs, which mostly
are "fixed", daily costs. If no time extension is involved, you
might be able to obtain a reduction for those savings. On the
other hand, the extra work may cause extra time on the job. Then
the contract unit price may or may not include its proportional
share of site overhead.
At any rate, don't allow the contractor to simply reprice the
overrun at actual cost. Happy Sails!
By
Vern Edwards
on Friday, May 26, 2000 - 10:58 am:
Christine:
You are quite right that the contractor cannot charge the
government for quantities in excess of what is actually needed
based on the drawings and specifications.
Any request for an equitable adjustment under the variation in
quantity clause must be based on:
(1) entitlement (actual quantities exceeded estimated quantities
by more than +/- 15 percent);
(2) damages and causation (the contractor must have suffered an
increase in the cost or time required to perform that was caused
by the variation in excess of +/- 15 percent), and
(3) quantum (the amount requested must be based on the damages
suffered and must be reasonable).
The dollar amount of the request must pass the test of
reasonableness in accordance with FAR 31.201-3.
So you are right to say that the government is not "wide open"
to unreasonable claims.
The point in response to Ralph Broome's original inquiry is that
the variation in quantity clause does not impose on the
contractor a duty to warn the government of an impending
quantity overrun. Some other clause may impose such a duty, and
a wise contractor would notify the government in advance if it
could, but the government cannot cite the variation in quantity
clause as ground for refusing to compensate the contractor if it
fails to give the government a heads up.
By
Christine on Friday,
May 26, 2000 - 10:25 am:
Vern,
I apologize, I was kind of thinking out loud. In supplies I
consider this a cap on liabilities where there is considerable
less oversight than construction. In my own experience we always
knew when a construction contractor was close to exceeded
estimated quantities no matter what we were buying. Construction
Contracts are paid by progress payments all of which are
accepted by the Government as service or item received, usually
every two weeks. To say the Government is wide open I do not
believe. The contractor cannot use any quantities they want and
the Government has paths to establish need.
By
Vern Edwards
on Friday, May 26, 2000 - 10:05 am:
The variation in quantity clause
for construction contracts, FAR 52.211-18, cannot be interpreted
as a cap on the government's liability for variations in
quantity, except to the extent that it limits the government's
liability to variations that exceed 15 percent. The main effect
of the clause is to prevent either party from seeking a price or
time adjustment for variations of less than +/- 15
percent of the estimates.
The clause says that:
(a) if the quantities in the contract are estimated quantities,
and
(b) any actual quantity varies from the estimate by more than
+/- 15 percent, and
(c) if the variation in excess of +/- 15 percent is the cause of
an increase or decrease in the cost of the contract, then
(d) the affected party is entitled to an adjustment equal to the
increase or decrease in cost that is caused by the variation in
excess of +/- 15 percent.
In addition, if the variation increases the time required for
performance, then the contractor may request a time extension.
The variation in quantity clause does not say anything about
the contractor having to notify the government in advance if
actual quantities are going to exceed estimated quantities.
The only notice requirement imposed by the clause is related to
requests for a time extension. The contractor must request a
time extension in writing and within 10 days of the beginning of
the delay or within such longer time as granted by the
contracting officer. The contractor does not have to notify the
government in advance of the beginning of the delay.
This is not to say that a competent, responsible contractor
should not notify the government when it becomes aware of a
problem. I am merely pointing out that the variation in quantity
clause does not impose such an obligation as a condition
precedent to entitlement and does not relieve the government of
any obligation to compensate a contractor in the absence of
advance notification.
Agencies should have on-site construction managers or inspectors
and require them to prepare daily progress or inspection
reports. Those managers or inspectors should make observations
and report trends that indicate that there will be significant
variations in quantities. If an agency does not have enough
staff of its own for this purpose, then it should hire a
construction management contractor.
Agencies can also write clauses for their contracts that require
contractors to notify the agency if they anticipate significant
variations in quantities. But such clauses will work only to the
extent that a contractor knows or has reason to know of such
variations in advance. Also, see FAR 52.243-5, Changes and
Changed Conditions, which requires the contractor to notify the
government of "subsurface or latent physical conditions
differing materially from those indicated in this contract or
unknown unusual physical condidions at the site... ."
By
Chrsitine on Friday,
May 26, 2000 - 08:43 am:
The way I have always
interpreted the variation in quantity clause as a cap of the
Government’s liability. This enabled the Government to tell the
contractor - you exceeded the estimated quantity we are not
responsible for payment above the 15% (or other specified). Of
course this would open up for a claim and whether or not the
Government received a benefit. Both the contractor and the
Government have a responsibility to know what quantities are
available for their respective protection. In order to protect
themselves the contract should be modified if it goes beyond the
specifed estimates.
By
Charles Phillips
on Friday, May 26, 2000 - 08:27 am:
I think it depends upon the
quantity. If twice as much rock is going to be required to build
the project this should immediately send up a red flag. The
contractor has the responsibility to notify the CO of possibly
faulty specifications.
I believe the order of predence is the schedule, specifications
and drawings. If the contract is going to require twice as much
rock as estimated on the bid schedule then there is a conflict
between schedule and drawings and/or specs.
By
Vern Edwards
on Thursday, May 25, 2000 - 03:07 pm:
I assume that you are talking
about fixed-price construction contracts. If so, agencies
usually require the contractor to report actual quantities when
requesting payment. See paragraph (b)(1) of the clause at FAR
52.232-5, Payments Under Fixed-Price Construction Contracts.
Agencies often supplement the FAR clause with a clause of their
own which requires the contractor to report specific quantity
information.
I know of no standard clause for fixed-price contracts that
requires a contractor to notify the government before doing work
in excess of an estimated quantities. However, FAR does not
preclude an agency from including such a clause in its
contracts.
An agency that is administering a construction contract properly
should be aware of prospective quantity overruns before they
occur.
By
Ralph Broome on
Thursday, May 25, 2000 - 10:34 am:
At what point would a contractor
have a duty to inform the Government of a quantity overrun
occurring on construction contract that includes the Variation
in Estimated Quantity Clause? In my current case, the CLIN's
estimated quantity for rock is approximately half of what is
needed to complete the project IAW the contract specs and
drawings. Unless I am misreading my Government Contract Law
Student Manual (GSA-April 1993), it looks like the Government is
unprotected when such a clause is used and the estimated
quantities of the contract are faulty. The plus or minus 15%
variation included in the clause seems to be the indicator of
when either party may request a modification, not an idicator of
when the contractor should notify the Government of a quantity
overrun.
|