By
joel hoffman
on Thursday, March 01, 2001 - 09:11 pm:
QUESTION: Posted to "ASK A PROFESSOR" Pre-Award Procurement
and Contracting on 2/20/01 by Jackie J
"The Scenario
Several line items on a Delivery Order have a variance between
estimated quantities and actual quantities. Some variances are
greater than 15% of the estimated quantities and some are less
than 15%. Our interpretation of the Variation in Est Qty clause
is when there is a variance of greater than 15%, the unit price
can be renegotiated upon request by either party. The clause
does not clearly state how to address simply the unit quantity
issue (without addressing the unit price) when it is less than
15%.
QUESTION:
A DO line item has an est qty of 30 cubic yards. Ktr removed 32
cubic yards. Do we pay the ktr for removing 30 cubic yards (at
the original unit price bid) or do we pay the ktr for 32 cubic
yards (at unit price bid)? "
ANSWER: In specific answer to the question, you pay for the
actual quantity at the contract unit price.
BACKGROUND: The Variation in Estimated Quantity Clause (FAR
52.211-18) addresses the right of either party to demand an
equitable adjustment in the unit price, if the actual quantity
of a unit priced item exceeds or underruns the estimated
contract quantity by more than 15%. (The Clause also allows the
Contractor to request a time extension, if such an overrun
caused an increase in the contract performance period).
The clause is not intended to address how payment for actual
quantities is measured or paid. This is usually addressed in a
technical provision describing measurement and payment. If the
contract uses a Government guide specification for exacavation,
the technical spec will describe how to measure and pay.
Hope this helps you. Happy Sails!
By
Anonymous
on Monday, March 05, 2001 - 02:02 pm:
SCENARIO: Contract specifications require contractor to fill
hole with rock. The schedule of items has estimated quantity of
rock to fill hole at 2 tons. The construction VEQ clause is in
the contract. The actual quantity of rock required to fill the
hole is approximately 15 tons. The contractor doesn't notify
Government and orders addtional 13 tons of rock and fills hole
IAW contract specifications.
QUESTIONS: (1) Does VEQ apply? (2) Does a contractor have duty
to inform Government of gross over/underrun quantities in
situations such as above?
By
joel hoffman on Monday, March 05, 2001 - 02:50 pm:
Normally not (assuming this is a unit-priced contract line
item), unless somewhere else in the contract requires such
notification. One key point was your statement that the Kontr
filled it IAW contract specifications - it was within the scope
of work.
Yes, the VEQ is applicable. However, there is no need for a unit
price adjustment unless the cost per unit varied to fill a 15
ton hole versus a two ton hole. Sounds like one truck load of
rock. I'd just pay for the 15 tons at the unit price - takes an
admin mod to adjust the quantity and funding. I may not have all
the facts. Happy Sails! Joel
By
bob antonio on Monday, March 05, 2001 - 03:20 pm:
Joel:
My initial impression is that this does not fall within the
intent of the VEQ clause because of the substantial change in
quantity. I would look to either the changes clause or the
differing site conditions clause. Under these clauses, the
contractor is to provide notification.
I would have to do a bit more research on this.
By
joel hoffman on Monday, March 05, 2001 - 06:39 pm:
Bob, if we were speaking of a substantial quantity, the
discrepancy might possibly be worthwhile looking into, as a
"cardinal change" or something else. However, 15 tons of rock is
no more than one large dump truck load, vs. a small dump truck
load for 2 tons. I don't think its worth the effort and expense
to make a big deal out of it. Anon, are we talking about a
substantial cost here? Is the unit price high? I doubt if the
Government can negotiate much of a VEQ savings. Current case law
supports the concept of only making a unit price adjustment if
there is a substantial difference in the contractor's cost per
unit for the first 2 to 3 tons and the next 9-10 tons. The bid
unit price is not a factor. The Contractor's unit cost is
probably not much different for 15 than for 2. The cost to both
parties to process a mod is more than the savings or additional
unit cost difference.
Now, if the contractor's unit price is outrageous, shame on
whomever determined that the original price was fair and
reasonable. Unit price bid items can be time bombs if there are
overruns, and no - you don't "reprice" the overrun quantities at
actual cost plus mark-up.
Happy Sails!
By
joel hoffman on Monday, March 05, 2001 - 06:43 pm:
Anon, before assuming too much, here, please advise:
1)Is the rock priced as lump sum or unit price bid item?
2) If unit priced, what is the bid unit price?
Thanks, Happy Sails! Joel
By
Anonymous
on Tuesday, March 13, 2001 - 12:05 pm:
The scenario provided was hypothetical. I would outline a
connection to actual projects but keep getting error messages.
From the limited discussions above, I can see that the same
questions come up when faced with this type of situtation, i.e.,
which clause(s) are applicable.
By
bob antonio on Tuesday, March 13, 2001 - 12:14 pm:
Anonymous:
Are you trying to link to some documents?
By
joel hoffman
on Tuesday, March 13, 2001 - 09:23 pm:
Anon, perhaps reviweing the information, starting at page
7-15.5 found at
http://www.hnd.usace.army.mil/chemde/cap/s15.pdf
will answere some of your questions. I wrote this guidance ,
about sometime around 1994, after the Foley vs. US Court of
Claims Case, on the same subject. The guidance is still legally
current. Happy Sails! Joel Hoffman
By
joel hoffman on Tuesday, March 13, 2001 - 09:46 pm:
For those of you who wonder what the above link discusses: It
is a PDF file; there are two applicable subjects:
1) how and when do you adjust the unit price for an item due to
an overrun or underrun of the estimated quantities?
2) how do you pay for overruns and underruns from the estimated
quantities?
Happy Sails! Joel
By
Anonymous
on Wednesday, March 14, 2001 - 09:42 am:
Maybe it's just the length of what I was trying to send (4-5
paragraphs)? Shorter messages seem to work so... The actual
problem we run into on our contracts is substantial quantity
variations (such as the example provided) due to unknown
conditions. We build rock riprap structures in marsh conditions
and the rock settles or sinks during construction (and yes we do
extensive geotechnical investigations of project sites prior to
going to design). Our problem really isn't use of the VEQ
clause, but what clause(s) apply when there is a substantial
over or underrun. We have contemplated or actually used the VEQ,
Changes, Differing Site Conditions, and Termination for
Convenience clauses in the past. Our contracts for this work are
FFP. The rock is unit priced on a per ton basis. Any suggestions
to our contracting methods or when to use the above clauses are
welcome.
By
joel hoffman
on Wednesday, March 14, 2001 - 04:55 pm:
Anonymous, it looks like you are uncomfortable with unit
priced (FFP) contracts or bid items. The reason unit prices are
used is because there will be variations. Yes, sometimes the
variations will be large. Before you award the contract, you
must ensure that the apparent succesful bidder's unit prices
aren't so far out of whack that an overrun will be devastating.
The following is not personally addresed to you, Anon. If you
have a competitively negotiated or sole source negotiated
contract, there is no excuse for not being pro-active about
this. Yes, bid contracts also require an analysis for
reasonableness. The FAR requires it. I used to routinely do it
in City work and private consulting for cities and developers,
before starting work for the Govermment. I never understood why
everyone in the Federal Government seems to look the other way
about ridiculous unit prices, until there is an overrun. Then,
"Oh, my! The unit price is too high!" This is precisely why
Government contracting personnel must use a business approach -
they must understand the contract they are awarding before they
award it. Happy Sails! Joel Hoffman
By
joel hoffman on Wednesday, March 14, 2001 - 05:30 pm:
Anon, it really is quite simple. If you award a unit priced
contract item, you pay for the actual work performed at the unit
price, unless their was a change which either added or deleted
SCOPE OF WORK. Any work added or deleted by a change or
differing site condition is to be separately priced from the
originally described scope of work (the scope - not the
"quantity of work" described).
The exception to the above rule is when there is no change or
differing site condition, but there was an overrun or underrun,
and there is a difference in the unit cost to the contractor to
perform actual quantites outside of a band of 85-155% of the
estimated quantity.
In the case of an underrun, the Contractor may well request an
adjustment, if it didn't recover sunk costs (fixed, daily costs,
mobilization costs, etc.). You then must compare the actual cost
to perform less than 85% of the estimated quantity with what it
would cost per unit had the Contractor performed 85% of the
estimated quantity. Thus, the Contractor is guaranteed only 85%
of its fixed or one-time costs, if there is an underrun.
In the case of an overrun, you compare the cost per unit to
perform the quantity of work exceeding 115% of the estimated
quantity to the unit cost for the first 115%. You pay for the
first 115% at contract unit price. The Contractor is guaranteed
the unit price for the first 115% (if no change in scope or
differing site condition occurred).
You ask for an adjustment to the unit price to reflect any
savings per unit realized by exceeding 115% of the estimated
quanmtity, if any (ie., quantity discounts, mobilization costs,
etc.) If there are no savings due to excess quantities, you pay
for the overrun quantity at the contract unit price. All you
need is an admin mod to increase funding and to adjust the
estimated quantity up. There is no "change", unless new work was
added to the scope.
The VEQ clause does not apply, unless there will be a demand by
either party for a unit price adjustment, due to any difference
in unit cost to perform actual work outside the 85-115% band.
Simple as that. Happy Sails! Joel
By
Anonymous
on Friday, March 16, 2001 - 10:33 am:
Joel, at what point would you consider labeling a substantial
over/underrun a "cardinal change"? Does cost play a factor here?
By
joel hoffman
on Friday, March 16, 2001 - 01:10 pm:
Anon, it's not cut and dry and depends upon each case. A
cardinal change really occurs when the character of the work
expected of the Contractor falls beyond what both parties could
reasonably contemplate at the time of contract formation.
For instance, in a 1989 Engineer BCA Case, Bean Dredging Corp
was awarded a contract for maintenance dredging (Miss. River? I
forget) Between the time the contract was awarded
and the time of performance, a couple of hurricanes hit the
area. As a result, the actual dredging quantities were something
like triple the estimated quantity. There is no way that the
parties contemplated this extra work. A differing site condition
wasn't applicable, because the change in quantities occurred
after award.
Neither party claimed a "cardinal change". The COE tried to hold
Bean to its bid price, pursuant to the VEQ clause and Bean
demanded a renegotiated price for the quantities above 115%,
under the VEQ Clause.
The ENGBCA agreed with Bean that to hold them to the previous
adjustment standard under the VEQ Clause (having to show that it
cost more per unit for the overrun than for the first 115%), was
unconscionable.
However, the ENGBCA didn't hold that there was a cardinal
change. It fundamentally changed the way unit price adjustments
under the VEQ Clause were priced ("repricing" overruns, based on
actual cost). Well, there were a lot of problems with this
ruling. One major problem was that they created a defacto "cost
plus percentage of cost" method of payment for overruns.
To make a long story shorter, both the ASBCA and the Claims
Court disagreed with the Bean Decision concerning proper
adjustments under the VEQ clause.
In 1993's "Foley Vs. US." decision (a COE military contract, not
civil works), the Court re-affirmed the old VEQ method ("the
Victory" Decision). Although a Military contract decision,
Claims Court decisions became applicable to contracts under the
ENGBCA, thus negating the ENGBCA's 1989 methodology.
Nobody addressed whether the "Bean" case should have been
considered a cardinal change. Had I been involved in that case,
I would have argued that we really had a cardinal change in the
scope of work. I suspect, had the case come up after the Foley
Decision, it would have been treated as a cardinal change, not a
VEQ problem.
As a bottom line answer to your question, each case is
considered on its own merit. If the actual scope of work does
not change from what was contemplated, and we're only dealing
with an inaccurate estimated quantity, I would hold that there
probably is no cardinal change. The basic principle is that each
party has to live with the agreed unit price. Therefore, the
importance of reviewing unit prices for bid items, prior to
award, is absolutely crucial.
Hope this makes some sense. I've been dealing with VEQ's for a
long time, and each case seems to be unique, in some respect! In
commercial and local government work, we typically used an
arrangement that the price would be re-negotiated, outside of
90-110%, if either party was dissatisfied with the contract unit
price. That isn't the case in Government contracts.
But strangely enough, nobody still around knows why it evolved
this way, in the Federal Government. The COE most likely
developed this clause, many years ago. Most current construction
clauses evolved from old COE/DOD policy before FAR. Happy Sails!
Joel
By
Anonymous
on Friday, March 16, 2001 - 03:27 pm:
Thanks Joel, you've more than answered my question. |