Anonymous
Posted on
Thursday, July 10, 2003 - 11:22 am
Here's an interesting issue I can't find addressed in the
FAR, CAS, or DCAA CAM. Assume a salaried manager working for
a contractor routinely works in excess of 40 hours per week.
The manager's salary is charged to G&A and allocated to
final cost objectives as required.
Now assume the manager spends 4 hours per day one week -- a
total of 20 hours -- working on a project whose costs are
unallowable. How is this unallowable labor "removed" from
the G&A pool for purposes of determining indirect cost
rates? The manager, like other G&A employees at the
contractor, does not keep track of his total hours worked
per week or month (there is no requirement that "indirect"
employees do so to the best of my knowledge). Removing
one-half of the manager's weekly salary (20 out of 40 hours)
from the G&A pool is unfair to the contractor because the
manager worked well over 40 hours during the particular
week.
Is there a way to remove the unallowable cost from the G&A
pool with precision without knowing how many total hours
(including uncompensated overtime) the manager actually
worked during the particular week? I can't think of any way.
What do contractors usually do in this situation? Try to
reach some type of compromise solution with their ACO or
DCAA, perhaps by having the manager estimate, after the
fact, how many hours he worked during the pay period at
issue and then removing an appropriate percentage of the
salary?
The FAR and CAM rules on uncompensated overtime address
direct-charge employees but I'm not aware of any guidance on
uncompensated overtime for indirect-charge employees who do
not keep track of the total hours they actually work each
week/month.
AnonYmus Posted on
Thursday, July 10, 2003 - 04:44 pm:
First of all, both 31.201-6 and CAS 405 recognize that
unallowable costs, particularly "directly associated"
unallowable costs, only need to be excluded from indirect
cost pools (e.g., G&A) if material in amount. You first need
to determine if you are talking about a material amount of
unallowable labor costs.
Secondly, an exact precision is not required with respect to
indirect costs. Many contractors would conduct a survey of
their executives and determine an overall percentage of such
unallowable time and decrement their otherwise allowable
salary and fringe expenses by that overall percentage.
Example calculation: 20 hours out of 60 is 30% times annual
salary and fringe costs times the number of executives as a
percentage of the total G&A cost pool.
In my experience (20+ years) nobody from DCAA or DCMA or IG
would question the above methodology, especially given that
the executives in question don't fill out timesheets. It's a
very good faith attempt to comply and I would confidently
expect it to pass.
Also, you need to be aware that in the late 1970's, DOD
developed the "30 percent rule" with respect to such
costs--after extensive correspondence between the DOD CAS
Working Group and the CAS Board. I wasn't involved in that
correspondence (I was in high school) and, honestly, I've
never seen anything in writing on such a rule -- but all the
"old timers" know about it and agree that otherwise
unallowable salary costs less than 30% of the executives'
time can qualify as "immaterial" and, hence, there is no
need to track those salary costs as being unallowable.
Finally, Dick Johnson wrote a piece on this topic in one of
last years' quarterly ABA Section of Public Contract Law
Journals. If you have access to a library, you should
definitely check it out. If anyone has the title/volume of
publication, perhaps they could post it for you ...
Hope this helps.
joel
hoffman Posted on
Thursday, July 10, 2003 - 04:55 pm:
That's an interesting question. One must be careful when
categorizing labor as "direct" or "indirect." Can you please
clarify what you mean when you say the manager's salary is
allocated to final cost objectives as required"?
You are confusing me when you say that the manager is
spending 4 hours a day on ONE [unallowable] project. Should
the manager's costs be considered as G&A if they are putting
that much effort into one specific job? Is it a long term
effort? It would seem that allocating his/her costs to
generally to all projects is inappropriate in the first
place. happy sails! joel hoffman
Anonymous Posted on
Thursday, July 10, 2003 - 05:42 pm:
AnonYmus - thanks. I've never heard of the 30% rule and
will try to get a copy of that PCLJ.
Joel - I'm using the terms "direct" and "indirect" to refer
to whether the person's time is direct-charged or
indirect-charged. Assume the manager in the hypo is the
contractor's Manager of Contracts. His salary is collected
in an indirect cost pool (which pool will depend on the
contractor's accounting practices) and allocated, perhaps
through intermediate indirect cost pools, to final cost
objectives, i.e., to individual contracts, using an
equitable methodology (e.g., based on direct labor hours).
It would not be unheard of for the Manager of Contracts to
be given a special project, for example, working on the
company's response to a government investigation. Per FAR
31.205-47, such costs might turn out to be unallowable. The
fact that he will spend a certain number of hours per week
on this particular task doesn't mean that the rest of his
time needs to be charged as a direct cost. At least that's
my understanding.
joel hoffman Posted on
Thursday, July 10, 2003 - 06:50 pm:
Okay, but allocating "overhead" or "general and
administrative" costs to individual contracts "based on
direct labor hours" is inconsistent with the concept of
indirect costing or with the concept of "G&A". In my
experience, for most smaller firms, G&A is usually allocated
to each contract as a percentage of the total contract cost.
The percentage is usually derived by dividing the allowable
and allocable G&A pool by some base, which is normally all
company contract direct costs.
In that case, the easiest way to adjust for the unallowable
hours is to estimate the percentage of his/her time spent on
the unallowable effort, prorate his/her costs in the G&A
pool, then re-calculate the allowable G&A rate. Unless this
is a pretty small firm, the disallowed costs probably won't
affect the G&A rate much.
If you are into CAS, this isn't a small contract action, the
firm will have a method to adjust the overhead pool, and it
probably won't make a dent in the G&A rate. happy sails!
joel
Anonymous Posted on
Thursday, July 10, 2003 - 08:29 pm:
Joel -
Thanks for your input. In my experience, certain types of
overhead are frequently allocated based on direct labor
hours (or dollars). G&A is more commonly allocated based on
a broader base, such as total cost input or value-added cost
input. But frankly I don't think it matters for the purpose
of the real issue here. Regardless of the allocation base,
you're faced with the question of whether to calculate the
adjustment based on a 40-hour work week (which hurts the
contractor because the person works more than 40 hours per
week) or on some other basis (which could be difficult to
support because these types of employees don't keep track of
all hours worked).
AnonYmus indicated the contractor may not have to remove ANY
unallowable hours if the total unallowables don't exceed 30%
of the person's total time. This sounds more generous (to
the contractor) than most govt accounting rules, but I will
definitely check it out. In your view (if I'm following
you), DCAA may accept good faith estimates of the percentage
of the employee's total time that was spent on the
unallowable activity. This isn't quite as favorable as the
30% rule, but it's still better than having to make the
adjustment based on a 40-hour work week.
AnonYmus Posted on
Friday, July 11, 2003 - 08:43 am:
Joel --
Anonymous is using terms correctly and, based on that, I
reckon s/he knows what's s/he is talking about. Contractors
are permitted to allocate overhead pools on almost any
appropriate base, and many choose Direct Labor Hours or
Direct Labor Dollars as their allocation base. Perfectly in
compliance with all FAR and CAS regulations.
A fully CAS-covered contractor generally has to allocate G&A
expenses on one of three allocation bases, of which Total
Cost Input (TCI) is one acceptable choice. A contractor not
subject to CAS 410 has much broader latitude to chose an
appropriate G&A allocation base ... could even use Cost of
Sales or Revenue in theory. Nothing in FAR Part 31 would
prohibit it.
Anonymous has correctly framed the question -- if an
employee who is classified as "indirect" charges a
more-than-insignificant amount of labor to an expressly
unallowable activity (e.g., due diligence for a merger or
acquisition)-- AND the company is using "total time
accounting" -- AND the indirect employees don't fill out
timesheets because they only get paid salary regardless of
how many hours are worked -- then how is the value of the
unallowable salary (and associated fringe benefits)
calculated for purposes of complying with 31.201-6 and CAS
405?
Hopefully, I've shown Anonymous some options for dealing
with the situation. The determination of materiality will
definitely drive the correct answer. I'm told there is a "30
percent rule" by "oldtimers" who spent years in Pentagon
policy-making positions (OUSD, AT&L). I've never seen it but
I believe them.
Finally, I'm back in the office today and will get down
to the library to find the Dick Johnson article I mentioned.
I'll post the pertinent publication info and, if there's
anything interesting, I'll post that too.
joel hoffman Posted on
Friday, July 11, 2003 - 09:35 am:
Your right and I understand that overhead can be based on
direct labor in lieu of total direct costs.
But it isn't generally "allocated" to each contract based on
direct hours expended on each contract. That would then be a
direct cost. It's a matter of semantics. I use the term
"allocate" to indicate how overhead is "charged" to a
contract, not how the rate is "calculated". I was looking
for a clarification on how it is "allocated" or "charged" to
each contract. happy sails! joel
AnonYmus Posted on
Friday, July 11, 2003 - 01:02 pm:
Joel,
Perhaps it is semantics, but let's take another run at it.
(I apologize in advance if I'm patronizing you...)
The contractor's overhead rate (percentage) is calculated as
the ratio of the cost pool to the allocation base. The sum
of allowable costs in the overhead pool is the numerator and
the sum of allowable + unallowable "things" in the base is
the denominator. (I say "things" because an allocation base
doesn't have to be dollars ... could be computer usage hours
or labor hours or pages of reproduction, etc.)
As a contract incurs the "things" in the allocation base, it
"absorbs" overhead in proportion to the ratio. We say
overhead is allocated to the contract but the contract is
absorbing the overhead based on the allocation ratio.
A contract can absorb overhead at a pre-planned (i.e.,
fixed) rate that then is trued-up at year-end, or a contract
can absorb overhead at the current Year-to-Date actual
overhead ratio as calculated from actual costs. Contractor's
choice. (See CAS 418 for more on this if necessary. Note
that CAS 406 prohibits contract overhead absorption at an
individual actual overhead rate for each month unless there
are exceptional circumstances.)
Technically speaking, ALL costs are allocated to contracts.
Direct costs are directly allocated and indirect costs are
indirectly allocated. We use the term "charged" but it's not
really the correct term of art.
So how's that for semantics? Are we on the same page?
Regards
joel hoffman Posted on
Friday, July 11, 2003 - 04:53 pm:
AnonYmus, Yep, I agree with you. happy sails! joel
AnonYmus Posted on
Monday, July 14, 2003 - 04:57 pm:
More on the "30 percent letter" --
On 30 November 1976 the Assistant SECDEF (Installation &
Logistics), Dale Babione issued guidance to DOD regarding
interpreting the CAS 405 provisions regarding "directly
associated" costs.
Following are selection quotes taken from the letter ...
"This policy establishes the basis for determining whether
cost is significant and should be identified to the
unallowable activity or cost objective as a directly
associated cost and subsequently disallowed. For these
purposes, the amount, if any, to be identified to the
unallowable activity or cost objective shall be determined
on the basis of an official's or employee's time (actual or
estimated workhours) directly attributable to the
unallowable cost activity or cost objective."
"There shall be a conclusive presumption that a portion of
an official's or employee's salary is a directly associated
cost and significant and thus unallowable if such official
or employee devotes 30% or more of his time to the
unallowable cost activity or objective. That amount shall
then be identified to the unallowable cost activity or cost
objective and disallowed therewith."
"With respect to time of officials or employees attributable
to unallowable cost activities or cost objectives, which
time constitutes less than 30% of the total time associated
with that official's or employee's total work time, the
following criteria will be normally utilized for the purpose
of determining whether such time devoted to the unallowable
cost activity or cost objective is significant:
a. The absolute dollar amount involved. The larger the
amount, the more likely it is to be significant. If the
amount of individual salary associated with the unallowable
cost activity or cost objective is less than $5,000, then
such amount will not be considered to have met this
criterion. However, if the aggregate amount of salary
associated with the unallowable cost activity or objective
for two or more employees in the same expense or cost pool,
is $20,000 or more, then such aggregate amount shall be
considered to have met this criterion. If the questioned
salary costs fall below the applicable criterion above, such
costs should not be questioned and b. and c. below do not
apply.
b. The relationship of total costs to questioned costs. As
applicable, compare the total salary cost pool with the
questioned aggregate amount, or the total individual salary
cost with the questioned amount of individual salary. The
smaller the amount of questioned salary in relation to the
total salary cost, the less likely it is to be significant.
c. The relationship between the activity represented by the
questioned salary cost and the expressly or mutually agreed
to be unallowable cost activity or cost objective. The
further removed from the unallowable cost activity or cost
objective, the less likely it is to be significant.
NOTE: The above criteria will be normally utilized for the
purpose of determining whether associated costs other than
salary are significant."
So materiality is not only driven by percentage, but also by
dollar amount.
Hope this helps.
PWG Posted on
Wednesday, July 16, 2003 - 07:14 am:
AnonYmous:
I was impressed with your ability to explain the Cost
Accounting concepts. Later this week or early next week I
plan to post a question about the appropriate cost treatment
of contractor training costs. I hope you will look for it
and respond. I want to give some thought to the situation
first rather than hastily posting the question. I have found
that if I take the time to clearly and concisely draft my
question, the forum responses are more on target and
responsive to my issues.
thanks in advance
AnonYmus Posted on
Wednesday, July 16, 2003 - 03:30 pm:
PWG -- Looking forward to it. As you can tell by past
threads, there are others here who have strong cost
accounting/CAS skills. My talent (such as it is) is to be
surrounded by the world's leading experts in this sort of
thing. I ask, they answer or point me toward the right
answer, I confirm/do some further research, and I post.
The problem is that this stuff isn't to be found in many
books. Trueger is out of print, Rosen's book is out of
print, Rishe's book is out of print, and Karen Manos's book
doesn't go to the printer until 12/31. I predict that her
book, when published, will become the definitive guide to
the FAR Part 31 cost principles and related issues.
Regards