By
Vern Edwards on Tuesday, October
15, 2002 - 08:18 am:
Here is a Q&A from DOD's Ask A Professor:
"What is Award Amount on SF1442 when have unawarded options?
Posted to Pre-Award Procurement and Contracting on 9/26/2002 by
A. Ross
The Scenario
We have a construction IFB with a base bid item and an option.
We are not exercising the option. We will be awarding on the
SF1442. The FAR does not provide any instructions on how the
Award part of the form is to be completed. One theory is that
the SF 1442 should include the unexercised option price in the
award amount with a notation in an attachment sheet that its
funding is not obligated. Another view is that only the amount
of the base bid which is actually being awarded should be the
amount.
The Question
In completing the SF 1442, should Block 22, Amount, include the
base bid and the option which is not being exercised or only the
base bid price.
The Answer
The answer to your question lies within the SF 1442. Note that
Block 21 requires the entry for the Items Accepted, which
according to your background information is for the base bid
only. For future reference you may want to review FAR 36.213-4
and DFARS 236.213-70,which address awards as well as additive
and deductive items."
Do any Wifconers have any thoughts on the professor's answer to
the question? Are options and additive bid items one and the
same? Is an option "accepted" even when it has not been
exercised? What answer would you have given the questioner? What
is the proper award amount?
By
Linda Koone on Tuesday, October 15,
2002 - 10:29 am:
Vern:
I've never used an SF 1442 or awarded a construction contract,
so that certainly limits my understanding of the issue. I would
have to say that the "Professor" appears to be confusing issues
here. From a quick reading of additive and deductive items,
these do not appear to be the same as options so I don't know
why the answer even mentions them. The question is asking
strictly about options. Perhaps the questioner and the Professor
had some exchanges outside of the posted question and answer
that would explain why the answer addresses this issue.
Who knows?
I believe the answer to the direct question as to the amount
that should be entered into Block 22 is correct. You certainly
wouldn't include the amount for the unexercised option. But I do
think you should include the option CLIN in Block 21 when you
list the items accepted.
By
formerfed on Tuesday, October 15,
2002 - 10:40 am:
I agree with Linda. The Professor seems to confuse the
two issues.
As a side point, many automated systems pick up the award
obligation amount from blocks on the actual award. I know the
basic system behind SPS for example, would post an obligation of
funds for more than intended if the option was included in block
22.
By
anonymous1 on Tuesday, October 15,
2002 - 06:38 pm:
I believe that the Professor was partly correct. The
Block 21 would not address an option, not accepted at contract
award. An option is not "accepted" until the Government properly
exercises a valid option to accept it (I assume that the
contract in question provides for some continuing period to
accept the option).
The Professor included a reference to additive and deductive bid
items, which are distinct from "options". I didn't read any
information germaine to the question concerning options or
whether or not to describe an unawarded option in the SF 1442 in
the DFARS 236.213-70 reference.
I also didn't understand the applicability of the reference to
FAR 36.213-4, "Notice of Award", to the question.
Sorry, but I need to remain anonymous, here.
By
Vern Edwards on Tuesday, October
15, 2002 - 07:28 pm:
anonymous1:
You say the option is not "accepted" until the government
exercises it. Thus, for you, accepting is the same as
exercising. But the bid includes the offer of an option. If you
don't include the option item in block 21, doesn't that mean
that you haven't accepted the offer of the option? And how can
you exercise the option if you have not accepted the offer of
the option?
By
anonymous 2 on Tuesday, October 15,
2002 - 08:32 pm:
In my organization, the mechanism for the Government
to unilaterally "exercise its option" to award the option within
the acceptance period is a term of the contract. Our
construction contracts clearly describe this unilateral right in
the description of the option in the CLIN schedule. Why would
one need to separately acknowledge that right on the SF 1442, in
such a case?
Perhaps other organizations don't make this a contract term?
By
anonymous1 on Tuesday, October 15,
2002 - 08:37 pm:
Vern, the SF 1442 should clearly state which of the
RFP documents are part of the contract. OOPS, the above message
is from me (Anonymous1) Did I answer all your questions?
By
Vern Edwards on Wednesday, October
16, 2002 - 09:40 am:
anonymous1:
I'm confused. Are you also anonymous 2?
You did not answer my questions. Suppose that the solicitation
included two bid/contract items: Item No. 1, the base bid item,
and Item No. 2, the option. Question 1: If you don't enter Item
No. 2 in SF1442, block 21, Items Accepted, then how can you say
that you accepted the bidder's offer with regard to the option?
Question 2: If you have not accepted the offer with regard to
the option, then how can you exercise the option later?
Here's another question: Suppose that the base bid item price is
$100 and the option price is $50 and that you have accepted the
option, but do not intend to exercise it at the time of award.
What amount should you enter in SF1442, block 22?
By
Anonymous on Wednesday, October 16,
2002 - 04:33 pm:
I always looked at options as a mechanism for
extending the validity of an offer. The option (offer) is not
accepted until it is exercised. Before exercising an option,
doesn't a PCO have to prepare a sole source justification? If
the option was accepted at the time the initial contract was
let, why would this be necessary?
By
Vern Edwards on Wednesday, October
16, 2002 - 06:49 pm:
If an option is merely an offer, then it could be
withdrawn at any time prior to acceptance. But we know that's
not the case. An option is binding on the option giver. So, an
option must be some kind of contract. Right?
By
anonymous1 on Wednesday, October
16, 2002 - 08:23 pm:
Vern, Yes, it is a term of the contract, as I stated.
Anonymous, there are different types of options. In a
construction contract, an option is usually for additional work.
Generally, the contract states that the Government may exercise
the option within X days of contract award or within X days of
NTP. That type option does not require any additional
justification.
Service contracts often use options to extend the period of
services. That's a different animal.
By
Vern Edwards on Wednesday, October
16, 2002 - 08:57 pm:
Anonymous and anonymous1:
A contracting officer does not have to prepare a sole source
justification in order to exercise an option if: (1) the option
is priced and (2) the price was evaluated during the competition
that led to the award of the contract. See FAR § 17.207,
especially paragraph (f). Options in supply, construction and
services contracts are no different in that regard.
By
anonymous1 on Wednesday, October
16, 2002 - 09:56 pm:
Vern, I agree with your statement(but remember that
FAR 17.207 restrictions are not applicable to construction
contracts).
By
anonconorig on Wednesday, October
16, 2002 - 10:21 pm:
Vern: in answer to your question "an option must be
some sort of a contract, right?" I don't think so. I think it's
part of an element of forming a contract, but to my way of
thinking-an option is no more than a lingering offer, the
acceptance might not occur. There are several elements that
might preclude the Feds from exercising an acceptance, i.e.,
unavailable funds, late in giving a preliminary notice, changing
market conditions (material). I have seen contracts whereby
there has been separate CLINS within the base that are additive.
Different animal, I think, than an option. By the Feds not
exercising an option they are not in breach. Not following
through on CLINS within the base, might, I think. For those
reasons, I think the form should only reflect the base-not the
options.
By
joel hoffman on Thursday, October
17, 2002 - 05:55 am:
Vern, I believe that there is no need to separately
describe an optional bid item (not exercised at contract award)
in the construction contract SF 1442, anymore than something
like a contingency bid item for say, rock excavation.
Here, I'm comparing an option CLIN in a construction contract to
a unit-priced CLIN for rock excavation. As a line item in the
bid schedule, the parties have agreed to a unit price for rock
excavation, should rock be encountered during excavation. The
price is pre-agreed, but is only applicable in the event that
rock is encountered. Municipal, state, private and federal
underground utility construction contracts typically contain
such bid items. Building construction contracts in areas where
rock may be encountered often contain similar provisions.
Similarly, with an option, the bidder/offeror proposes a price
for an optional CLIN. Upon contract formation, the parties
agree, within the terms of the contract, that the price is
applicable if the owner properly exercises the option. The
Government has contracted for the right to exercise the option.
I think it is simple. happy sails! joel hoffman
By
Vern Edwards on Thursday, October
17, 2002 - 10:10 am:
anonconorig:
If the government awards a contract that includes an option, and
the contractor repudiates the option before the government
exercises it, is the contractor's repudiation a breach of
contract? If so, then an option is contractual in nature and not
just an offer. If not, then an option has no contractual value
prior to its exercise. Do you think I'm wrong about that? Can a
contractor send a CO a letter withdrawing an option prior to its
exercise?
Joel:
SF1442 does not come with any instructions, so I frankly don't
know what you're supposed to put in block 21 at the time
of award. I'm trying to arrive at an answer through reasoning.
Block 21 is entitled, "Items Accepted." I assume that means,
"Items of the Offeror's Offer That Are Accepted." Do you think
it means something different? If so, what?
Now, if the solicitation has two line items, one for the base
bid and one for the option, and if the CO doesn't accept the
offer of the option, then how can the CO claim the right to
exercise the option? Don't refer to an option clause, because an
option clause pertains only to an option item that has been
accepted.
Some of the people responding to my questions think that an
option is merely an offer that is accepted at the time the
option is exercised. Thus, they think there is no need to enter
the option item number in block 21, because the option is not
accepted until it is exercised. But it is clear that a
contractor is contractually bound to an option and cannot
repudiate it before it is exercised. (I could cite all kinds of
case law about this, but at this point I'd rather just work the
question through reasoning.) Thus, an option must have
originated with an offer of its terms that are binding because
they were accepted by a CO. Do you think I'm wrong about this?
It seems to me that SF 1442 block 2b2 should include only
the price of the base bid item, since I think the purpose of
block 22 is to record the funds obligated by the award and no
funds are obligated for the option until the option is
exercised. However, maybe the purpose of block 22 is just to
express the overall "dollar value" of the contract, as that term
is used in FAR § 1.108(c). If so, then I guess it should include
both the base bid item price and the option price. As I said,
SF1442 does not come with any instructions. What do you think?
By
Anonymous Researcher on Thursday,
October 17, 2002 - 10:45 am:
Uniq Computer Corp. for Benefit of U.S. Leasing
Corp. v. United States, 20 Cl.Ct. 222 (1990):
"[A] noted text writer explains that an option contract is an
agreement to keep an offer open for a prescribed period of time
during which that offer is irrevocable. 1 S. Williston, A
Treatise on the Law of Contracts § 61A (3d ed. 1957). An
option is 'a unilateral contract whereby the optionor for
valuable consideration grants the optionee a right to make a
contract of purchase but does not bind the optionee to do so;
the optionor is bound during the life of the option, but the
optionee is not.' Id. The power conferred on the option holder
is called the power of acceptance, who therefore has the legal
authority to consummate the contemplated transaction by merely
exercising that contractual right. The option giver, on the
other hand, is bound to execute the exchange for the duration of
the agreement. 1A A. Corbin, Corbin on Contracts, A
Comprehensive Treatise on the Working Rules of Contract Law
§ 259 (1963)."
Kelley v. United States, 19 Cl.Ct. 155 (1989):
"An 'option to purchase,' is a contract by which the owner of
property agrees with another person that the latter shall have
the right, power, or privilege to buy the former's property at a
fixed price within a certain or specified time, or within a
reasonable time in the future, and on agreed terms and
conditions. 91 C.J.S. Vendor and Purchaser § 2 (1955). See
generally Aerojet General Corp. v. Kirk, 318 F.Supp. 55
(N.D.Fla.1970), aff'd, 453 F.2d 819 (5th Cir.1971), cert.
denied, 409 U.S. 892, 93 S.Ct. 110, 34 L.Ed.2d 149 (1972). Since
an option is a contract, it must contain all the incidents and
essentials of a contract. To be legally enforceable, it must be
clear, certain, specific, and unambiguous, its terms must be
clear and definite and free from all ambiguity; in order that a
valid option exist, it is necessary that all material terms of
the agreement be definitely settled and not left indefinite
subject to future agreement."
By
anonconorig on Thursday, October
17, 2002 - 11:15 am:
Vern:
In answer to your last sentence response to me,in what I term a
"standard" base with options,the answer ,I believe is no.
However, contracting being so diverse, which I sometimes like,
there can be circumstances whereby the contractor can repudiate.
Not receiving preliminary notice in accordance with stated
period of time is one. Another might be an issue of
impracticability to perform. For instance, we recently
negotiated with a Federal agency a base and option year contract
with a clause whereby we could notify the agency, within a
certain period of time, that we would not be able to perform an
option if the instrument that we used to perform the work was
sold, destroyed, or became economically impracticable by our
definition. Might be unusual, granted, but was done.
The ability to unilaterally act is unique in public contracting,
I think, as opposed to commercial contracting (barring a clause
that allows the buyer to unilaterally act)That's what makes this
interesting. I still believe that the option is not accepted
until if and when it is accepted. Another thought, could we tie
the value in the block to the Anti-Deficiency Act?
By
Vern Edwards on Thursday, October
17, 2002 - 11:33 am:
anonconorig:
A couple of thoughts in response to your last comments:
1. If the government fails to provide a required notice of
intent to exercise, or notice of exercise, the contractor is
released from its contractual obligation to perform in
accordance with the terms of the option. In such a case, I would
not call the contractor's refusal to perform the option
"repudiation," since the contractor is no longer obligated to
perform.
2. There are legal excuses for nonperformance of a contract and
such excuses apply to options in the same way that they do to
other contracts.
3. I don't agree that the ability to act unilaterally is unique
to public contracting. Many commercial contracts include changes
clauses, cancellation (termination) clauses, and options.
4. The courts appear to take the position that an option is a
contractual obligation to keep an offer available for some
specified period of time and under specified conditions. The
offer of the option must be accepted by the CO in order for the
option to be binding on the contractor; later exercise of the
option is acceptance of the offer which the option has kept
open.
This brings us back to SF1442, block 21. I believe that a CO
must enter the option item number to show that he or she has
accepted the offer of the option. However, the CO must issue the
required contract modification in order to accept the offer
proferred in the option. Make sense?
By
Anonymous on Thursday, October 17,
2002 - 11:39 am:
If you knew you were not going to exercise the option
you should have amended the solicitation. It would have
guarenteed that you do not make award to the wrong bidder.
By
Vern Edwards on Thursday, October
17, 2002 - 12:07 pm:
Anonymous of 11:39am:
Who are you talking to and what are you talking about?
By
anonconorig on Thursday, October
17, 2002 - 12:50 pm:
Vern:
Repudiation was the wrong word in these circumstances, mea
culpa. Actually the Government loses the right to unilaterally
exercise the option unless the contractor waives.
Number 2, yep that's a way out of the option but is applicable
to other contracts.
Number 3, I meant the act to exercise the option unilaterally is
"particularly unique" to the public arena. In most commercial
contracts, I would certainly suggest to our company, depending
on the circumstances, not to accept a unilateral exercise, if
ever detrimental to the company's position in future years.
Except for the opt outs mentioned above, your action under the
Federal Regs are limited.
Number 4, No argument there which is where I think I was headed.
I still think that the base is the only amount that should be
placed in the block barring any instructions. I will say, Vern,
however, this is based on many of my contracts involving the SF
33 form. Consistently, we have seen the base amount placed in
block 20 but with the accompanying Schedule listing the priced
options. Then, of course, elsewhere in the contract are the
provisions on how the options are exercised.
By
joel hoffman on Thursday, October
17, 2002 - 05:35 pm:
Vern, I'd accept the proposal (or bid), dated XXXX in
block 21. That includes the bid or CLIN schedule, including the
option. I'd identify the work which has been awarded in the
block where it says something to the effect that "the contractor
shall provide or perform the following..." I'm out of town on a
slow connection, without the form in front of me. I'd state the
awarded contract amount in the block 22.
anonconorig, I've often seen options to purchase real estate in
both private and public contracts. For some type consideration,
usually a payment, the owner agrees to allow the prospective
buyer an option for a stated period to purchase the real estate.
That is common. happy sails! joel
By
anonconorig on Thursday, October
17, 2002 - 06:53 pm:
Joel, I know that, in fact I once purchased a house
under that lease option. One I didn't but I had to give up the
$5000.00 deposit. I didn't breach however. The option under the
Federal scenario if you don't follow through (on the contractors
side) can be far reaching and severe, usually.
By
JRL on Friday, October 18, 2002 -
08:03 am:
Both 15.504 and 14.408-1 state "When an award is made
to an offer for less than all of the items that may be awarded
and additional items are being withheld for subsequent award,
each notice shall state that the Government may make subsequent
awards on those additional items within the proposal acceptance
period.
In a construction contract that includes an option you should
clearly identify the acceptance period for each option. Then in
block 21 you should make a statement similar to "Item 1 is
hereby accepted. The government reserves the right to award any
option within the specified acceptance period. Then in block 22
you insert the amount for the item(s) that were accepted.
By
Vern Edwards on Friday, October 18,
2002 - 09:05 am:
It sounds like JLR has hit on an answer, which is
similar to Joel's.
By
joelhoffman on Friday, October 18,
2002 - 02:06 pm:
Good job, JLR!! happy sails! joel