By
Mary Thompson on Thursday, March 22, 2001 - 12:14 pm:
Can someone tell me what clause governs payment provisions to
small companies? We are a small disadvantage 8(a) company; the
prime states that we can't receive payment until the government
reimburses them (prime) first. If there is a clause please site.
If the clause is not in the subcontract agreement outside of
negotiating this provision into the contract what other choices
do I have. And finally, if there is a clause, is this clause
considered mandatory flow-down.
thanks
By
C Mercy on Thursday, March 22, 2001 - 03:31 pm:
There are several clauses-it wopuld help to know3 what kind
of contract the prime holds--is it FP,CR and is it for
supplies,services,R&D ? But at first glance I can preety much
tell you that it is not what it says in the primes contract that
governs but rather what it says in your contract with him that
governs.
By
C Mercy on Thursday, March 22, 2001 - 03:32 pm:
Sorry for the typos-pushed the wrong button
By
anon02 on Thursday, March 22, 2001 - 03:53 pm:
The clauses that are applicable to the prime contract should
also be applicable to your subcontract, unless other provisions
are cited in your subcontract. If you are providing
non-commercial items, and are not receiving payment, FAR
32.112-1 and 32.112-2 provide some direction.
By
AnonX on Thursday, March 22, 2001 - 04:13 pm:
Mary:
There is no government (FAR) clause that says the prime can't
pay the sub until the government pays the prime. You cut a deal
with the prime. What does it say about payment? Maybe you agreed
to a horrible clause of your prime's own invention. Or maybe
your prime doesn't have the money to pay you and doesn't want to
borrow it, or is just a slow-payer.
Anon2:
The clauses that apply to a prime contract do not necessarily
apply to a subcontract. The key is this: What does the
subcontract actually say?
By
Ron Vogt on
Thursday, March 22, 2001 - 05:36 pm:
Mary -
I can't tell from your post whether you are negotiating a
contract or whether you are having payment problems under an
existing contract. Nevertheless, some general rules apply:
First, it is what is in your contract that counts. If you are
negotiating, then get in a payment clause that calls for you to
be paid within X days after invoice, usually 30 days. If under
an existing contract, look for your payment clause and demand
that the prime comply. In either case, whether a clause is a
mandatory flowdown or not, only your subcontract matters. There
is no Christian Doctrine for subcontracts.
Second, your prime's claim that it can't pay you until the
government pays it is questionable. There is no such FAR
requirement. If your prime means that it doesn't have the funds
to pay you until it gets paid, then you're going to have an
ongoing problem with this prime.
Bottom line: look to your contract and use whatever means you
have in the contract to enforce payment.
You should also consider informing the contracting officer. FAR
32.112 details actions the CO can take if the prime is
delinquent to the sub. However, this only applies to contracts
for non-commercial items in which the prime is receiving some
sort of contract financing, such as progress payments. Even for
other contracts, it may not hurt to notify the CO, but you have
to evaluate the risk to your relationship with the prime.
By
Kennedy How on
Friday, March 23, 2001 - 12:51 pm:
I don't really know where the sub contacting the PCO will do
much good, since the Government does not normally have privity
of contract with the subcontractors. Other than what is included
in FAR 32.112, there isn't much more guidance.
In my experience, this was mainly one of those cash flow
problems inherent in a lot of contracts that don't have progress
payments, but have a long period of performance (from the
standpoint of the delivery of hardware). The subcontractor that
had to be paid early on tended to be on shaky ground if the
prime didn't have the cash flow available to pay him. Here, cash
flow is defined as what the prime internally has in his bank
account or other sources, not from progress payments. I know one
time a prime requested progress payments, but the PCO declined,
saying the prime could get a short-term loan (the prime told me,
not at those rates and not at the risk of mortgaging my
business).
Kennedy
By
joel hoffman on Friday, March 23, 2001 - 04:55 pm:
Ron is correct.
If this is a construction contract, you have certain rights
under the Miller Act, but you have to take actions within
certain timeframes. If the prime is not paying within the terms
of your subcontract, you can take action with respect to the
prime's payment bond. The Contracting Office is supposed to know
enough about this to advise you of your rights. However, the
Government can't advise you how to take action under the Miller
Act. My server is getting ready to shut down, so can't provide
you a link at the moment. If this is a construction contract,
please advise and I will get back to you. Happy Sails! Joel
By
joel hoffman on Saturday, March 24, 2001 - 04:14 pm:
If this is a Federal, fixed-price construction contract, the
following link may be of interest to subcontractors. It is
advice for Resident offices to furnish primes, in the event of a
subcontractor complaint of non-payment, and a "Miller Act
Information Statement" to furnish subs and suppliers having
trouble getting paid by their prime contractor. It is a pdf file
from one of our contract admin SOP's.
Note that there is no contract provision which restricts a prime
from paying its subs or suppliers before receiving payment from
the Government. The Prompt Payment provisions in the contract DO
REQUIRE a prime to pay subs and suppliers NO LATER THAN seven
days after receiving progress payments, which include progress
due subs or suppliers. This provision does not restrict the
prime from earlier payment, if that is what the subcontract
terms include. Some people confuse the Prompt Pay provisions,
with "pay before paid" subcontract terms. See pages 5-11 at this
link:
http://www.hnd.usace.army.mil/chemde/cap/Chapter%208/c8ex9-12.pdf
Happy Sails! Joel Hoffman
By
Mary Thompson on Thursday, March 29, 2001 - 05:49 pm:
Thanks to all!!!!
By
Eric Ottinger
on Tuesday, April 10, 2001 - 07:45 pm:
Mary,
This recent memo regarding the "Paid Cost Rule" should be of
interest. DoD expects our large business prime contractors to
pay subcontractors in a timely manner.
http://www.acq.osd.mil/dp/paidcost.pdf
Eric
By
joel hoffman on Wednesday, April 11, 2001 - 06:13 pm:
Eric, I'll also emphasize, in addition to the other points of
discussion in the attachment to memo which you cited, the Prompt
Payment Act (at least for construction contracts) mandates that
primes will pay their subs and suppliers within the number of
days enumerated in the contract clause (7 days) after payment by
the Government.
In addition, primes are not entitled to hold funds due subs or
suppliers, after being paid by the Government. The Government
must hold any funds the prime requests to be withheld from subs
or suppliers, for work accomplished or costs incurred, not the
prime.
|