I don't know what to say about this exchange. What do
you think of the professor's "rationale"?
Not To Exceed (NTE) on Cost Plus Fixed Fee Contracts
Posted to Pre-Award Procurement and Contracting on 1/30/2003 by
Clyde Reid
The Scenario:
I'm in the middle of a dispute between contractor and the Buying
Command. The PCO has placed "Not To Exceed (NTE)" limits on
Material/Travel/Repairs in support of various Clins. The
contractor says that the three items in question still need to
be negotiated. The buying commands say no, it doesn't. We need
to determine who's right on this issue and what FAR/DFAR
guidance to quote.
The Question:
Can "Not To Exceed (NTE)" be used on CPFF Contracts? If so,
under what circumstances?
The Answer:
A telephone call was made to find out more about the background
of this question and it was discovered that one or more of the
contractor’s accountants of a Fortune 500 Company (meaning a
large business) were apparently unfamiliar with CPFF type
contracts and much more used to dealing with Firm Fixed Price
contracts. The accountants viewed the CPFF contract as an
undefinitized contract since they were not certain what the
final price on the contract was going to be. They raised the
question and the Contract Administrator had limited exposure to
CPFF contracts also. That was where this question came from. It
was explained in the telephone call that the Contracting Officer
that made the award of the CPFF contract had reasons to add in
the additional not to exceed limits on material, travel and
repairs due to previous experience on other contracts with this
contractor.
Answer: Yes it can and under whatever circumstances that the
Contracting Officer feels it is justified to protect the
Government’s best interests.
Rationale: There is no exact FAR or DFARS reference for this. It
is simply one more tool in the Contracting Officer’s Contracting
tool bag to be utilized when it is felt appropriate by the
Contracting Officer to help limit the liability of the
Government.
-------------------------------------------
Do any of the people managing cost-reimbursement contracts for
our government have a clue about what they are doing?
By
Tricia on Friday, February 21, 2003
- 11:06 am:
Apparently not in your opinion.
By
formerfed on Friday, February 21,
2003 - 11:26 am:
Good title for this thread. I can see how a contractor
doesn't understand, although it's hard to figure out how they
won the award especially if this is a significant one. But
there's no excuse for an answer like this from the "professor."
Government people look to the professor for expert guidance. I
wonder how many people walk away from this and similar responses
with the wrong impression?
By
Anonymous on Friday, February 21,
2003 - 11:42 am:
Vern,
Are you saying that the contracting officer can't put an NTE on
a CPFF line item.
Why not?
By
Vern Edwards on Friday, February
21, 2003 - 11:53 am:
Here's the answer that the professor should have
given:
Yes, the parties to a cost-reimbursement contract can agree on a
"not to exceed" or "ceiling" amount for some particular element
of cost. See FAR § 31.109, which discusses advance agreements on
cost. Perhaps the most common such agreements are "caps" on
indirect cost rates.
But the professor should have pointed out that in this case the
question is: What is the contractual implication of the "not to
exceed" agreement? What does it mean? Does "not to exceed" mean
that the contractor is not obligated to spend more than that
amount, or does it mean that the contractor must spend whatever
is necessary but that the government will not reimburse it for
more than that amount? What did the parties intend by "not to
exceed"? Is the "not to exceed" agreement a limitation on the
contractor's obligation or is it an agreement to share costs?
Only the parties know for sure. Or maybe they don't know.
By
Anonymous on Friday, February 21,
2003 - 12:10 pm:
Vern,
Can you cite an instance where there was a “Not to Exceed” and
the contractor was contractually bound to spend more.
By
Vern Edwards on Friday, February
21, 2003 - 01:13 pm:
Anonymous:
Yes, I can provide an example.
My favorite example is a contract between General Dynamics and
the Federal Aviation Administration for radar sets. The parties
had negotiated a fixed-price-incentive (firm target) contract
that went badly. They negotiated a conversion to a
cost-reimbursement contract with a "ceiling price." Things
continued to go badly and the FAA terminated the contract for
default before the ceiling price was reached. The FAA refused to
reimburse the contractor for its costs and the contractor
appealed to the Department of Transportation Contract Appeals
Board. The Board held for the contractor. See: General
Dynamics Corporation, DOTCAB No. 76-9A, 78-2 BCA ¶ 13,281
(April 7, 1978). The FAA refused to comply with the Board's
order to pay up and the contractor appealed to the U.S. Claims
Court, which upheld the Board's decision. See: General
Dynamics Corp. v. U.S., 229 Ct.Cl. 399 (Feb. 10, 1982). The
court held that if the contractor had reached the ceiling it
would have had to complete the work at no additional cost to the
government and pay the government damages in the event of
default. In other words, at the ceiling the contract effectively
would have converted from cost-reimbursement to fixed-price.
See, too, Cost-Reimbursement Contracting, 2d ed., by
Cibinic and Nash, pp. 24 - 27. The authors point out, first:
"One major problem [with cost ceilings] is determining whether
the ceiling operates to deny the contractor's right to stop work
when the ceiling is reached." The authors, say: "A precisely
drafted ceiling will operate both to deprive the contractor or
additional funding and require the contractor to complete
performance within the stipulated amount." But they point out:
"The Court of Claims has stated that overall cost ceilings will
be strictly construed against the Government in the event of
ambiguities, [citation omitted]. It is thus incumbent upon the
Government to exercise careful draftsmanship in preparing such
provisions."
By
Anonymous on Friday, February 21,
2003 - 01:24 pm:
Vern,
You are equating “Not to Exceed” with “Ceiling.” I would assume
that “Not to Exceed” means “exceed at your own risk” while
“ceiling” means “you may have to spend more, but this is all you
are going to recover.” Again, can you cite an instance where
there was a “Not to Exceed” and the contractor was contractually
bound to spend more.
By
Vern Edwards on Friday, February
21, 2003 - 01:38 pm:
Anonymous:
Yes, I am equating "not to exceed" with "ceiling." On what do
you base your assumption as to the differences that you ascribe
to the meanings of the two terms? Are you reading from some
official definitions? From some court-imposed definitions?
By
Anonymous on Friday, February 21,
2003 - 02:03 pm:
Vern,
The FAR “LIMITATION OF GOVERNMENT LIABILITY” clause for a letter
clause reads as follows,” the contractor is not authorized to
make expenditures or incur obligations exceeding ….”
Unless, you have an authoritative usage for "NTE" which is
different from this, I would say the Professor wins this round.
By
dave on Friday, February 21, 2003 -
02:06 pm:
Years ago when acquiring R&D on a CPFF basis, we quite
commonly used ceilings on indirect costs, I don't see why we
can't put a ceiling on travel, etc. Of course these ceilings
were always negotiated with the offeror to reach preaward
agreement.
By
formerfed on Friday, February 21,
2003 - 02:24 pm:
Another thing about the professor's reply is that it
didn't address the contractor's misunderstanding. It states
"...the contractor’s accountants of a Fortune 500 Company
(meaning a large business) were apparently unfamiliar with CPFF
type contracts and much more used to dealing with Firm Fixed
Price contracts. The accountants viewed the CPFF contract as an
undefinitized contract since they were not certain what the
final price on the contract was going to be...." So with this
understanding, the contractor viewed the NTE as a ceiling on an
non-definitized letter contract. If he led in with some
explantion as well as Vern's suggestion, things are clear.
By
Eric Ottinger on Friday, February
21, 2003 - 02:34 pm:
Eric
Iniitally, I thought the Professor was talking about an "NTE" on
a separate ODC (Other Direct Cost) CLIN, which makes perfect
sense to me.
Treating travel, repairs, etc. as cost elements under a larger
CLIN and then asking the contractor to segregate these costs to
keep them under some NTE or ceiling strikes me a as a
nonstandard and rather painful approach to the problem.
Eric
By
Eric Ottinger on Friday, February
21, 2003 - 02:44 pm:
The above should have been addressed to Formerfed, not
Eric.
By
Charlie Dan on Friday, February 21,
2003 - 03:30 pm:
In response to the post of 2/21 by Anonymous:
The Limitation of Government Liability clause from FAR 52.216-24
doesn't exactly define the term "not to exceed." Further, the
guidance for letter contracts in FAR 16.603 includes a
requirement to "include an overall price ceiling in the letter
contract." Seems to use the terms "not-to-exceed" and "ceiling"
interchangeably. In my experience, these terms are synonymous in
everyday use.
I probably wouldn't be as blunt as Vern, but it concerns me that
the contractor and the federal agency on this contract seem to
be inexperienced with cost reimbursement contracting.
By
Anonymous on Friday, February 21,
2003 - 03:54 pm:
Charlie,
It is apparent that that Letter contracts or other UCAs were the
context the company accountants had in mind.
Are you sure that you are looking at the same FAR 16.603 that I
am. I don't see the word "ceiling."
By
Vern Edwards on Friday, February
21, 2003 - 07:15 pm:
Anonymous of 2:03 p.m.:
What do you mean, "the Professor wins this round"?
You better go back and read again, the professor's comments and
mine. The only thing the professor said was that it is okay to
use a not to exceed in a cost-reimbursement contract. I agreed
with the professor's answer.
My complaint about the professor is not that his answer was
wrong, but that he didn't do what a good professor does --
explain and clear up the questioner's confusion. All he did
was clarify the scenario and then give a half-baked answer.
The professor should have referred the questioner to FAR §
31.109, as I did, and explain that not-to-exceeds are used in
cost-reimbursement contracts all the time, as I did. (I did a
Westlaw search for court and BCA decisions in which the terms
"cost-reimbursement" and "not to exceed" occur and got 185
hits.) He should have explained that the term has no generally
accepted meaning, as I did. Then, as I did, he should have
referred the questioner to the Cibinic and Nash discussion of
ceilings, pointing out some of the pitfalls of such agreements.
But the professor did none of those things.
Your point appears to be that there is a distinction between the
terms "not to exceed" and "ceiling." Is that right? As you said:
"I would assume that 'Not to Exceed' means 'exceed at your own
risk' while 'ceiling' means 'you may have to spend more, but
this is all you are going to recover.'"
How about this sentence from McDonnell Douglas Corp. v. U.S.,
39 Fed. Cl. 665 (Dec. 5, 1997): "The [Incentive Price Revision}
clause was designed to establish the total final contract price
not to exceed the contract ceiling price."
Or this one, from CACI, Inc. v. General Services
Administration, GSBCA No. 15,588, Dec. 13, 2002: "Appellant
was to be paid an hourly rate not to exceed a ceiling
contained in a repair order for services rendered."
Or this one, from Vehicle Research Corp., ASBCA No.
26,581, July 19, 1983: "The contract contained the standard
Armed Services Procurement Regulation (ASPR) clauses including
Allowable Costs, Fixed Fee and Payment (1968 Sep) and Limitation
of Cost (1966 Oct). The contract also provided that appellant
would be paid an overhead rate not to exceed a ceiling
of 100% of direct costs. The final overhead rate for the
contract was to be determined by Government audit subject to the
100% ceiling."
My point is that there is no clear distinction between a
"not-to-exceed" amount and a "ceiling" such that we can discern
the contractual implications from the terms alone. To the extent
that you believe that there is such a distinction, I disagree.
By
Anon2U on Friday, February 21, 2003
- 09:25 pm:
I have worked at my civilian agency for 5 years and I
have never seen a cost plus fixed fee contract, let alone any
fancier type. The only place I have discussed them is in the
school house. Therefore, I may be a GS-14 soon and have zero
experience with CP contracts. In discussion with several of the
supervisors, they have almost no experience either. The
exception is probably in our construction division. Main reason:
Cost plus contracts are administratively burdensome and we no
longer have the manpower to monitor them. Our usual contracts
are IDIQ labor hour and delivery orders against GSA FSS.
So yes, the government has lost most of its experience and skill
in the various contracts.
That is why I read this column, the court/protest decisions, and
go to every class they will let me attend. I am trying to learn
but nothing replaces real experience that few COs have anymore.
I think we may have to specialize more just like doctors do.
By
Eric Ottinger on Saturday, February
22, 2003 - 09:18 am
Vern,
You fault the professor for not discussing advance agreements,
but there is no evidence that the contractor is aware of this
hypothetical Part 31 agreement. Clearly the contractor is
confused, but there is nothing in the scenario to suggest that
the contractor is totally oblivious.
In any case, advance agreements should be clearly spelled out in
an “H” clause or attached to the contract. That leaves very
little room for the confusion that we see in the professor’s
scenario, unless we posit that both the contract administrator
and the contractor’s accountants are both incapable of reading
the contract. More likely, there is nothing but “NTE” or “Not to
Exceed” in Section B and both are trying to intuit what this
means.
Advance agreements are bilateral. However, the scenario clearly
indicates a unilateral action on the part of the PCO, “The PCO
HAS PLACED "Not To Exceed (NTE)" limits on
Material/Travel/Repairs in support of various Clins.”
Travel, repairs and sometimes materials are typically
categorized as ODCs (Other Direct Costs). It isn’t uncommon for
the government to put controls on such expenditures,
particularly travel. Note that the scenario states that the PCO
has done this because of experience that he has had with the
contractor in the past. I would infer that the contractor sent
twenty people to a meeting when no more than five were needed.
It is conceivable that the contractor has previously allocated
too much of the total budget to “Material/Travel/Repairs.” If
the PCO doesn’t want to spend any more than $50,000 for repairs,
the sensible thing to do is to establish a separate cost/no fee
ODC CLIN for repairs with an estimated cost of $50,000. This is
simple. Negotiating an advance agreement on the repairs cost
element in a larger CLIN is the hard way to do it. In any case,
I have a hard time imagining the government setting absolute
limits for cost elements like material and repairs. This would
be the worst kind of micro-management.
All and all, this looks more like technical direction than a
Part 31 advance agreement. The contractor seems to understand
that this is a temporary limit. Specifically, it appears that
the contractor thinks that this is the usual 50% limit, which
would not be raised until the contract is fully negotiated.
More likely, this is technical direction to the effect that the
contractor should not expend more than the NTE amount on these
ODC costs at this stage in the contract. When more funding is
available, these NTE limits will be adjusted upward.
The professor does not get an “A” for clarity or detail. On the
other hand, there is no need to read in an approach which is
inconsistent with the scenario, cumbersome and administratively
costly.
If either the PCO or the professor advised imposing an advance
agreement on an element of cost (i.e. materials) for a
commercially oriented firm, with accountants who find government
contracting confusing, that would merit some comment. That would
be really dumb.
Eric
By
Vern Edwards on Saturday, February
22, 2003 - 10:51 am:
Eric:
I think you read too much into "the CO has placed." What can
that mean?
Are you aware of any standard FAR clause that gives a CO
authority to unilaterally add a CLIN or place limits on costs
incurred after a contract has been formed? I can't think
of any off hand and I don't think it can be done under the
Changes clause. If I'm correct, then I think that the proper
interpretation of "the CO has placed" is that the parties
negotiated a contract that includes an NTE provision that the
contracting officer wanted to establish. This was nothing more
than an advance agreement on costs as contemplated by FAR §
31.109.
FAR does not prescribe any format for advance agreements on
cost. An advance agreement can be included in a Section H
clause, in a CLIN, or in an attachment to the contract. I
negotiated many, many NTE advance agreements, and many of them
were written into the CLIN description:
"Nothwithstanding any other provision of this contract,
including the Allowable Cost and Payment clause, the Contractor
shall not be entitled to reimbursement for more than a total of
$50,000.00 for material cost, as defined in FAR § 31.205-26(a),
regardless of the Contractor's incurred allowable cost for the
materials required to complete the performance of this contract.
All material cost incurred in excess of $50,000.00 shall be
expressly unallowable under this contract."
Maybe that should have appeared in Section H, but what
difference does it make? If incorporated into the contract at
the time of formation that language satisfies every requirement
of FAR § 31.109. Two sentences. What is so cumbersome and
administratively costly about that?
As I recall, you are in the weapons acquisition business. I
negotiated several complex advance agreements on cost with
General Electric, Lockheed, Rockwell and other weapons
contractors that dealt with complex allowability issues and that
were several pages long. However, not all advance agreements are
like that.
There would be no problem had the contracting officer drafted
the agreement in the contract more carefully. The professor
could and should have explained all that to the questioner.
Vern
By
Vern Edwards on Saturday, February
22, 2003 - 12:41 pm:
Eric:
I need to say something. I know why you wrote in today -- you
think that my criticisms of AAP are harsh and you are seeking
justice for the professor. I understand that.
What I want you to understand is that I want DAU to be the best
institution of its type anywhere in the world. I like the very
idea of DAU and I want to be proud of it. But I cannot be proud
of it now, because the quality of its output at AAP is
consistently poor.
I would like DAU to improve the AAP site so I can brag about
that institution and refer it to others. I have written to DAU
about the site, but to no avail, so I am using Wifcon. I must
admit that it doesn't seem to be working -- no matter how much I
and others here criticize AAP, DAU doesn't take corrective
measures. In fact, I'm not sure that anybody in DAU is keeping
track of the site or checking the quality of the answers
provided there. Maybe they don't have the staff. It I was
running DAU I would rather drop AAP than manage it poorly.
Quality is not just a matter of accuracy, although that is
essential. Quality is also a matter of pedagogical
effectiveness. It is, after all, called "Ask A Professor," i.e.,
Ask A Teacher. I'm a teacher. I like to answer questions and
explain things to people, and it drives me crazy to see so many
inaccurate and incomplete answers coming from the "professors"
at AAP.
It seems to me that the response to a question should be
somewhat like: "Boy, I'm glad you asked that! Here, sit down,
grab a cup of coffee and let me tell you all about it." The
professor should recognize any underlying confusion on the part
of the questioner and go beyond a bare-bones response. A
professor should be driven by the need to teach, to pass
useful knowledge on to others.
I guess I'm becoming bitter. I want excellence in all things in
acquisition, and it seems clearer to me every day that I have
little hope of getting any satisfaction in that regard. Many of
my teaching collegues feel the same way. Perhaps I should stop
taking potshots at AAP and even drop out of Wifcon Chat. I've
thought about it a lot, lately. Goodness knows, I've got other
things to do. I've signed up to take a class in elephant
management at a wildlife sanctuary this summer. I'm very
excited. I've always wanted to be Toomai of the Elephants. I
won't think about contracting once.
Vern
By
cherokee21 on Saturday, February
22, 2003 - 06:48 pm
Vern:
Hope you don't go away to raise those "pink elephants". I get
cranky too. Suspect that I have been involved in contracting
almost as long as you but have not had the time to study it the
way you do. Do respect your opinion highly, so maybe you can
help out in the next thread I intend to post "The dreaded
CPIF/CPAF combo" which really worries me with my client.
By
longtimer on Saturday, February 22,
2003 - 09:45 pm:
Vern, I've sometimes disagreed with your opinions. By
opinions I mean only certain conclusions extending beyond FAR
and case law discussions. Those I've always found to be truly
excellent. In trying to argue with you I've found I've been
driven to learn and research in detail--usually to conclude
myself you are correct in those points. You did much the same on
the old Water Cooler.
I'm afraid if you go away the board will degenerate into pretty
half baked chat. You tend to force rigor. In the matter of
explicit advice and reference I don't think anyone compares.
The elephants sound great and I wish I could join. Have a great
time and stay with this herd too.
By
cherokee21 on Saturday, February
22, 2003 - 11:48 pm:
I'm not sure what "long timer" is trying to say, but
guess he/she thinks highly of you. As I do. I will post that
"DREADED CPAF/CPIF contract tomorrow. Really need an opinion-.
Thanks 05B
By
Eric Ottinger on Sunday, February
23, 2003 - 09:40 am:
Vern,
I am not concerned about the Professor’s honor. Nobody is going
to be challenging me or the professor to a duel. I’ve already
stated that his response lacks clarity and detail. If he put
that answer in the bluebook, he wouldn’t pass the final exam.
I have no problem with Section B. If the PCO had put a paragraph
in like you suggested, what is the probability that both the
contract administrator and the contractor’s accountants would
neglect to read such plain language. An advance agreement is, by
the FAR definition, something clearly spelled out in writing.
Since this is evidently not the case, I doubt there is an
advance agreement.
I think there is nothing but a “Not to Exceed” or “NTE.” The
commercially oriented “Fortune 500” company accountants, based
on their limited experience with government contracts, have
jumped to the conclusion that this is the kind of expenditure
limit that is required for a CLIN which has not yet been fully
negotiated.
It doesn’t make sense for the PCO to negotiate one amount and
then set a permanent ceiling at 50% of the negotiated amount.
Hence, I conclude that the PCO merely wants to limit
expenditures for travel, materials and repairs for a period of
time until more funding is available and the ceiling will be
raised to the negotiated amount.
I would characterize this as “technical direction.” I could, and
have, sent the same kind of direction in a letter. That doesn’t
rule out the possibility that there was a bit of negotiation, if
the contractor wasn’t comfortable with the ceiling. Program
managers give this kind of direction all of the time, often will
a lot less formality.
If I intend to have a cost element segregated, I would set up a
separate CLIN. I assume that is what this PCO did, although that
is not quite the scenario presented to the professor.
We are both making inferences. I find mine more credible.
All,
I don’t think it is a good thing to be throwing rocks at other
sites.
On the other hand, AAP is a rich source of discussion topics. It
would be silly not to use this resource. Vern is doing something
which I have been intending to do. So I commend him for it.
In my experience, some professors are excellent and some
professors don’t know any more than what they have just read,
preparing the lesson plan the night before. None of this is new.
I think there is a disconnect between the faith that the higher
levels place in education and the quality education that is
actually available. This is a point where Vern and I are
probably in agreement. In the academic world, anything which is
slack and poorly thought out will be attacked. Academics don’t
waste a lot of energy on being polite. This isn’t very pretty,
but it keeps everyone on their toes.
In the world of government procurement, a lot of slack, poorly
informed stuff gets published. Until we have the kind of
vigorous peer review process that you see in the academic world,
I doubt we will have a body of knowledge worth teaching in
school.
If you look at the archives, you will see that Vern, Joel,
Formerfed, Ron and numerous others are creating a body of useful
knowledge that the average working 1102 isn’t going to find
anywhere else. It is not “excellent.” (I doubt any of us have
time for that) but is unique and useful.
I try not to be rude to people who are obviously inexperienced.
Also, I would think it bad form to attack someone who is not in
a position to respond.
If I were counseling a young person I would say that if you want
to express yourself in your professional life, like some people
do on radio talk shows, that’s how people will categorize you.
It is best to vent in private and among friends. I don’t waste
my time giving such advice to people who are my age or older.
In any case, if you really want to zing an obnoxious contractor
or whoever, polite understatement works much, much better.
All and all, I don’t think terms like “clueless” and “witless”
are appropriate.
You will note that I am trying to stick to the middle and avoid
being a hypocrite. If in fact the PCO asked this commercially
oriented firm to segregate an element of cost in a way that the
firm doesn’t normally segregate costs, I have characterized that
choice as “dumb.” It also goes against policy that has been
expressed many times at high levels. We shouldn’t be imposing
government unique requirements on commercial firms unless there
is a very good reason to do so.
Eric
By
longtimer on Sunday, February 23,
2003 - 05:00 pm:
Cherokee21, I do have great respect for Vern. I differ
at times with some of his rare opinions where they extend into
what might be called "political" or into views of what
influences rule making. In matters of what the FAR says, what
court decisions apply and wise contractual action I give great
weight to what Vern says as he does the research, has the
experience and the exposure to real thinkers in the field. There
have been occasions where I did question him in those areas.
Usually upon investing time in the question I found he'd been
there and done that.
Eric brings up a very good point in connection with DAU and AAP.
In academic publications there is a brutal process of peer
review. A real concern with AAP is that it is an authority by
association, yet apparently no peer review process is in effect.
I think it would be much more effective to require peer review
there. It is a process that drives out the weak conclusion or
simple mistake. To some degree this board has peer review in the
manner in which what some characterize as "attacks" force
defending one's argument. What is missing here is a final
summation of the result. Threads tend to just taper off,
sometimes without any conclusion seemingly reached. One often
has to read and even study the full thread and then try to sift
out the conclusion--if any. That is the nature of discussion
boards. AAP should be different.
It is evident to me is that DAU and particularly AAP are
operating without the kind of rigor a "university" should
exhibit (This is an example of the sort of thing Vern and I
may differ about.). My impression, when attending, was that
there was a great deal of rotation and too little funding for
what is needed. Again, Eric's post makes a point in saying
"there is a disconnect between the faith that the higher levels
place in education and the quality education that is actually
available." It is not only DAU, it is our entire "educational"
system that is producing credentialed people that are indeed
clueless.
Unlike Eric, I am perfectly willing to use such words. I
do where I'm face to face with people. One reason I am anonymous
here is that I'm personally better able to stay more objective
and even "walk away" before getting into an endless argument
with someone I consider clueless. I have better things to do
after 30+ years in government. I am both concerned with and
fully understand Vern's last paragraph on February 22, 2003 at
12:41 pm:
I guess I'm becoming bitter. I want excellence in all
things in acquisition, and it seems clearer to me every day
that I have little hope of getting any satisfaction in that
regard. Many of my teaching collegues feel the same way.
Perhaps I should stop taking potshots at AAP and even drop out
of Wifcon Chat. I've thought about it a lot, lately. Goodness
knows, I've got other things to do.
Within my family and reasonably close acquaintances I have
five cases of university professors who have abandoned teaching
explicitly because the students have increasingly been both
unprepared and opinionated. They have seen people who have not
put in the disciplined effort they have challenging their
teaching. We have, as a society, somehow placed uninformed
opinion on a par with years of specific study. People have
confused a theoretical "I'm as good as you" with demonstrable
difference in knowledge. They have endowed themselves with the
gain without any pain of study or experience.
We are not going to see excellence anywhere and may indeed reach
third world status unless we stop allowing such idiocy. Maybe it
is hopeless. If everyone who knows different through hard work
abandons the field the shammers will win. Vern is a professional
who devotes time here to force us all to do work if we want to
stay on his playing field. It improves the discussion. I choose
to use my name and face in other areas (What are we coming to
when a significant number of people cannot identify the Pacific
Ocean on a map!). Vern provides his identified expertise to us
here. It is needed.
By
cherokee21 on Sunday, February 23,
2003 - 06:53 pm:
Well said, "longtimer"!
By
Eric Ottinger on Sunday, February
23, 2003 - 07:22 pm:
Longtimer,
Nicely said.
I don't advocate peer review for AAP because, in my opinion,
that would probably just kill it. This whole enterprise of
discussing procurement topics on the Internet is pretty tenuous.
You singled out DAU. I will note that wasn't my intention.
Otherwise, total agreement.
Eric
By
longtimer on Monday, February 24,
2003 - 06:02 pm:
Eric, I probably left an impression I was not
impressed with DAU. On the contrary. I not only got benefit from
some of their offerings, I enjoyed the time and association.
Within their means I think they do very good things.
What does bother me is that their means and their influence does
not seem commensurate with the need for research and education
in the field. Neither does their funding appear right.
Considering the number of dollars passed from taxpayer through
contracting and the amounts wasted through poor contracting the
entire system is underfunded. At least DoD has put this
institution in place. Considering the DoD contract dollar flow I
think DAU should be funded at a higher level and chartered to do
true university level RD&E (for Research, Development and
Education) in the field.
We seem to keep talking about effective contracting, educating
the contracting work force and improvement without putting
either the money or effort behind the talk. Again, considering
the scale of the budget passed through contracting, something
seems to be wrong here.
I'd like to see the system beefed up. For one thing a funded AAP
staff that does peer review of answers. The last time I looked
into the thing it was not much more formal than this chat.
Someone posted a question and someone, when time and inclination
allowed, got around to posting an answer. It was sort of an
informal and ad-hoc system.
Improvement would take formal organization and some funding.
Perhaps even specific staffing is needed just to do initial
reference and research work, farm out the questions to the
"professors" and coordinate review of answers. I strongly
suspect the present format was part of the Internet/interactive
craze. It does serve a purpose, but you do get what you pay for.
I think AAP could use more formal resources and funding.
By
joel hoffman on Monday, February
24, 2003 - 10:15 pm:
Other than the in-house "professors" , DAU doesn't pay
for the other respondents' time. They answer questions as time
allows. I believe the folks administering the site are
contractor personnel.
happy sails! joel hoffman
By
formerfed on Tuesday, February 25,
2003 - 08:59 am:
Longtimer,
Your comments reminded me of a article I read. I just searched
for it but can't locate it. Much of what you said was reflected
in that article, albeit at a higher level.
The article said there is a need for systematic training
throughout the government for everyone involved in the
acquisition process. It recognized that the prescribed 1102
training is good, but that's only a starter. For example,
there's a huge push on for use of performance-based contracting.
While many 1102's received training in that, their
program/technical counterparts do not. So how is an 1102 going
to get program requirements stated in terms sufficient for a
performance-based award?
The author recommended a complete assessment of all training
needed throughout. Next sufficient money is provided. Then
everyone is required to take it most likely through some FAI
and/or DAU initiative. Finally there's a periodic assessment and
re-evaluation of needs. The overall theme expressed is that so
much is at stake in making and administering good contracts but
a formal and funded government wide training program is needed.