Matter of: | L. W. Matteson, Inc. |
File: | B-290224 |
Date: | May 28, 2002 |
|
Richard W. Miller, Esq., for the protester.
Edward T. Goldstein, and Robert M. Anderson, Esq., U.S. Army Corps of Engineers, for the agency.
David A. Ashen, Esq., and John M. Melody, Esq., Office of the General Counsel, GAO, participated in the preparation of the decision.
DIGEST
Under invitation for bids for dredging, agency reasonably rejected bid as
unbalanced where bidder failed to include cost of preparing a site for disposal
of dredged sediment in its unit price for dredging sediment, for which payment
would be made over the term of the project, and instead included disposal site
costs in its lump sum price for grubbing and clearing, a minor work item, such
that the disposal site costs comprised 99 percent of the price for grubbing and
clearing; rejection of the bid was proper based on the agency's reasonable
determination that the unbalancing posed an unreasonable risk that bidder would
receive substantial up-front payment upon completing the grubbing and clearing
work, whether or not it had completed the site preparation work.
DECISION
L. W. Matteson, Inc. (LWM) protests the rejection of its bid as unbalanced under
invitation for bids (IFB) No. DACW37-01-B-0012, issued by the U.S. Army Corps of
Engineers for dredging work and placement of rockfill at backwater lakes in Pool
10 of the Upper Mississippi River, near Prairie du Chien, Wisconsin. LWM
disputes the agency's determination that its bid was unbalanced.
We deny the protest.
The IFB sought fixed-price bids for dredging
approximately 180,000 cubic meters of sediment from the lakes and safely
transporting and disposing of the dredged material; clearing (felling, trimming
and cutting of trees, as well as disposal of trees and other vegetation);
grubbing (removal of stumps and large roots); stripping (removal of surface
humus and material); and placing a geotextile underlayer and 310 metric
tons of rockfill. The requirements were divided among eight contract line
items (CLIN), including CLINs 0001 and 0008, requesting fixed, per-cubic-meter
unit prices for dredging sediment, and lump sum CLIN 0003, for clearing and
grubbing the rockfill site. The Corps received two bids: LWM's was
low at $1,511,020, and J. F. Brennan's was second low at $1,544,270. Both
bids were in excess of the (revised) government estimate ($1,247,307).
The contracting officer's review of bids revealed that LWM's price for CLIN
0003, for clearing and grubbing, was unusually high in comparison to the
government estimate and the other bid; while the government estimate for CLIN
0003 was $1,720, and J.F. Brennan's price was $1,000, LWM's price for the item
was $298,500. In response to the contracting officer's notification that
its price for CLIN 0003 was considered to be “extremely high,” and his
request for bid verification, Letter from Corps to LWM, Oct. 2, 2001, at 2,
LWM explained that its CLIN 0003 price largely reflected the cost for preparing
a site at which the dredged sediment could be deposited. Specifically,
according to LWM:
Our intentions on bid day were to develop the Kapinus site as our primary
disposal site. Use of this site will require considerable earth moving
(over 120,000 yards by our estimate) and, two road crossings. It is the
development of that disposal site, which will come long before any dredging will
take place, that makes up 99% of our bid for the clearing and grubbing bid item.
When I was putting the bid together, I was confused as to which bid item would
pay for the disposal site development. [Specification] Section 02327--Disposal
of Dredge Material has no payment clause. That being the case, I looked
for a lump sum bid item that had something to do with disposal site development
and could come early in the project. . . . Section 02325 “Dredging”
does not mention paying for site development either. Letter from LWM to
Corps, Oct. 10, 2001, at 1.
The contracting officer interpreted the IFB as providing that disposal of the
dredged material was not to be separately priced, but instead was to be included
in the unit prices for dredging under CLIN 0001 (and under the very limited
CLIN 0008 option item). The contracting officer determined that
LWM's bid thus was materially unbalanced in that the CLIN 0003 price was
excessive, bearing no relation to the actual cost of the clearing and grubbing
work, and might constitute an advance payment. Upon learning of the
resulting rejection of its bid, LWM filed an agency-level protest. The
agency denied that protest, finding that LWM's price for CLIN 0003 was so
unreasonably high that it constituted an advance payment and posed an
unreasonable risk to the government. LWM thereupon filed this protest with
our Office. LWM asserts that including the site preparation costs for the
disposal site in its CLIN 0003 bid price was not inconsistent with the
terms of the solicitation, and did not warrant rejecting its bid as unbalanced.
Federal Acquisition Regulation (FAR) § 14.404-2(g) provides that a “bid may
be rejected if the prices for any line items or subline items are materially
unbalanced (see [FAR §] 15.404-1(g)(1)).” Unbalanced pricing exists
when, despite an acceptable total evaluated price, the price of one or more
contract line items is significantly overstated or understated, as indicated by
the application of cost or price analysis techniques. FAR §
15.404-1(g)(1). While unbalanced pricing may increase risk to the
government, agencies are not required to reject an offer solely because it is
unbalanced. Id. Rather, where the contracting officer
receives an unbalanced offer, the contracting officer is required to consider
the risks to the government associated with the unbalanced pricing in making the
award decision, and whether a contract will result in unreasonably high prices
for contract performance. FAR § 15.404‑1(g)(2). An offer
properly may be rejected if the contracting officer determines that the lack of
balance poses an unacceptable risk to the government. Id.; see
HSG Philipp Holzmann Technischer Service GmbH, B‑289607, Mar. 22,
2002, 2002 CPD ¶ __ at 5.[1]
Our analysis in this case begins with consideration of whether the disposal site
preparation costs included in LWM's CLIN 0003 price instead should have been
included under CLIN 0001, as the agency argues; if it was improper to
include these disposal costs under CLIN 0003, then, given that these costs
represented 99 percent of LWM's CLIN 0003 price, LWM's bid included a
significantly overstated contract line item price and thus satisfied the FAR
definition of an unbalanced bid. We agree with the Corps that CLIN 0003
clearly was not to include the disposal site preparation costs. The CLIN
0003 clearing and grubbing work was defined in the IFB as follows:
Clearing shall consist of the felling, trimming, and cutting of trees into
sections and the satisfactory disposal of the trees and other vegetation
designated for removal, including down timber, snags, brush, and rubbish
occurring in the areas to be cleared.
Grubbing shall consist of the removal and disposal of stumps, roots larger than
75 millimeters in diameter, and matted roots from the designated grubbing areas.
Specification 02230, §§ 1.1.1, 1.1.2. Not
only does clearing and grubbing appear to differ substantially in character from
the extensive earth moving and road crossings contemplated by LWM as part of
disposal site preparation, but the clearing and grubbing was to be undertaken
within the limits of the rockfill area, that is, in a different location than
the contemplated disposal site. Amend. 0001, § 7.
It is equally clear from our review of the solicitation that disposal site
preparation costs were to be included under CLIN 0001. In this regard,
Specification 02325, Dredging, § 1.14, in discussing payment for dredging,
provided that:
Payment under this [dredging] item shall include all costs for dredging work and
satisfactory disposal (placement) of dredged material in the Contractor selected
disposal (placement) area(s). No separate payment will be made for:
. . . disposal (placement) area sitework . . . . We conclude that there
was no reasonable basis for LWM's including its costs for disposal site
preparation in CLIN 0003 rather than CLIN 0001. Id. It
follows that the agency properly determined that LWM's price was unbalanced. [2]
By including its disposal site preparation costs in its CLIN 0003 price rather
than under CLIN 0001, LWM's pricing approach created the potential that LWM
could recover a disproportionate share of the overall contract price early in
the performance period. Although LWM has expressed its intention to incur
the disposal site preparation costs at the beginning of the project (asserting
that development of the disposal site is a necessary prerequisite to beginning
dredging), neither the IFB nor its bid obligated it to do so. As a result,
the agency concluded, in the event of early termination of LWM's contract, the
agency would have expended a substantial sum for CLIN 0003 work that had not
been performed. Indus. Builders, Inc., supra, at 7-8.
We think the agency reasonably found that this was an unacceptable risk to the
government; this risk warranted rejecting LWM's bid as unbalanced.[3]
The protest is denied.
Anthony H. Gamboa
General Counsel