At the end of 1976, I met the
Director of the Procurement Control and Clearance Division of
the Naval Material Command in Arlington, Virginia. The Director was a legend
of the
contracting community and any significant Navy contract had to
be approved by his office prior to award. I was there because
of a controversy involving a contract to acquire a
new class of
nuclear cruisers.
The attendees at the meeting surrounded a conference table and waited for the
Director to make his appearance. After several minutes, the Director entered the room and placed a chart on the
table. "What do you see?" "What do you see?" He
demanded. The fellow
next to me said, "It says fixed-price incentive." "No, no, look at it,"
the Director said. It was a chart that depicted a
fixed-price incentive (firm target) contract (FPIF). "Look how flat it is," the
Director said. I tried to look at the chart but I was more
interested in seeing the Director. Out of the corner of my eye,
I saw him dressed in a dark suit, vest, watch chain connected
to the middle button of his vest and dangling perfectly from
one side to the other. He had a paunch and
tufts of white hair on his head and he looked like
Winston Churchill—the World War II Prime Minister of the United
Kingdom. He was Gordon Wade Rule—the highest-ranking
civilian in Navy contracting. Years later, I met a
colleague of Gordon Rule and told him about my first impressions.
The colleague looked at me and laughed, "Gordon not only
looked like Churchill, he thought he was Churchill." Since
this first meeting with Gordon Rule, I have been interested in
the FPIF contract type and how it can be used on government contracts.
The Rule Contract
Table 1 is the pricing structure
that Gordon Rule was talking about during our meeting. For
the purpose of discussion in this article, it will be referred to as the "Rule
Contract."
Table 1: FPIF Structure on the Navy Contract Provided by Gordon
Rule.
Structure |
Description |
Target Cost |
$76,000,000 |
Target Profit |
$9,700,000 |
Target Price |
$85,700,000 |
Ceiling Price |
133 percent of Target Cost at
$101,000,000 |
Share Ratio |
95/5 between $64,600,000 and
$87,400,000
90/10 below $64,600,000 and from $87,400,000 to Point of
Total Assumption |
Point of Total Assumption |
$92,366,660 |
Someone familiar with an FPIF contract will notice
what Gordon Rule was talking about. For those who are not, the following discussion explains the
mechanics of an FPIF contract pricing structure.
Mechanics of the
FPIF Contract
The FPIF contract includes cost and price points, a ratio, and a
formula. They include
- Target Cost (TC): The
initially negotiated figure for estimated contract costs and
the point at which profit pivots.
- Target Profit (TP): The
initially negotiated profit at the target cost.
- Target Price: Target
cost plus the target profit.
- Ceiling Price (CP):
Stated as a percent of the target cost, this is the maximum
price the government expects to pay. Once this amount is
reached, the contractor pays all remaining costs for the
original work.
- Share Ratio (SR): The
government/contractor sharing ratio for cost savings or cost
overruns that will increase or decrease the actual profit. The
government percentage is listed first and the terms used are
"government share" and "contractor share."
For example, on an 80/20 share ratio, the government's share
is 80 percent and the contractor's share is 20 percent.
- Point of Total Assumption
(PTA): The point where cost increases that exceed the
target cost are no longer shared by the government according
to the share ratio. At this point, the contractor’s profit is
reduced one dollar for every additional dollar of cost. The
PTA is
calculated with the following formula.
PTA = (Ceiling
Price - Target Price)/Government Share + Target Cost
All of these points and shares
have an effect on costs, profit, and price. However, two tools in
the structure—the ceiling price and the share
ratio—dramatically affect the potential costs, profits, and
prices.
For the examples in tables 3, 4,
and 5, I use the target cost, target profit, profit rate at
target cost, and target price identified in Table 2. The ceiling
price and share ratio will vary according to example.
Table 2: FPIF Structure Used
for Examples in Tables 3, 4, and 5.
Structure Elements
|
Structure Amounts |
Target Cost |
$10,000,000 |
Target Profit |
$1,000,000 |
Profit Rate at
Target Cost |
10% |
Target Price |
$11,000,000 |
Ceiling Price
At the ceiling price, the
government's liability for cost within the terms of the original
contract ends and the contractor pays for
all costs above the ceiling price. The setting of the ceiling price
significantly affects the relationship between the government
and the contractor once the target cost has been reached. The example
in Table 3 includes 4 different ceiling prices
and the same 70/30 share ratio. Remember, the ceiling
price is stated as a percentage of the target cost.
Table 3: FPIF Target Costs and Profit with Different Ceiling Prices and
Constant 70/30 share ratio.
Dollar
Costs |
Ceiling Prices
(Percent of Target Cost) |
115 |
120 |
125 |
130 |
$8,000,000 |
$1,600,000 |
$1,600,000 |
$1,600,000 |
$1,600,000 |
9,000,000 |
1,300,000 |
1,300,000 |
1,300,000 |
1,300,000 |
10,000,000 |
1,000,000 |
1,000,000 |
1,000,000 |
1,000,000 |
10,500,000 |
850,000 |
850,000 |
850,000 |
850,000 |
11,000,000 |
500,000 |
700,000 |
700,000 |
700,000 |
11,500,000 |
0 |
500,000 |
550,000 |
550,000 |
12,000,000 |
500,000 |
0 |
400,000 |
400,000 |
12,500,000 |
1,000,000 |
500,000 |
0 |
250,000 |
13,000,000 |
1,500,000 |
1,000,000 |
500,000 |
0 |
PTA |
$10,714,286 |
$11,428,571 |
$12,142,857 |
$12,857,143 |
As can be seen, there is no difference in
profit for any of the examples where costs are less than the target cost. This is because the ceiling price affects the cost
and profit structure somewhere after the target cost is exceeded. Since the ceiling price is used to determine the PTA, it also
results in different PTAs. Notice the PTAs for each ceiling
price. Prior to the PTA, but after the target cost is reached,
the 70/30 share ratio is in effect and the government shares 70
percent of all overruns and the contractor shares 30 percent of
all overruns. Once the PTA is reached, the contractor’s
profit will
be reduced on a dollar-for-dollar basis up to the ceiling price. Remember when
Gordon Rule said "Look how flat it is?" He was referring to the
incentive curve. The incentive curve reflects the amount
of potential profit for each cost level throughout the FPIF
structure.
The smaller
the profit increment as costs increase, the flatter the
incentive curve becomes.
The flatter the curve becomes, the closer
it approaches a cost plus fixed-fee (CPFF) contract since the
fixed-fee on a CPFF remains constant for all levels of costs. By increasing
the ceiling price on an FPIF contract, the government's share in cost overruns and
the contractor's opportunity to recover costs is placed at a
higher dollar level. The higher
the ceiling price, the flatter the FPIF incentive curve is because it
is being stretched in length.
Share Ratios
To compare the
effect of share ratios on an FPIF structure, Table 4 includes 5
different share ratios ranging from 50/50 to 90/10. As mentioned earlier,
the government's share of savings or overruns is the first
number in the share ratio. In Table 4, a
simple share ratio structure is used—one with the same share ratio
throughout the structure— to analyze the effect of different
share ratios. Share ratios can be complex and can include more
than one share ratio. However, to explain the effects of
different share ratios, a simple structure is adequate.
Table 4: FPIF Target Costs and Profits with Different Share
Ratios.
Dollar Costs |
Share Ratios
(Government/Contractor) |
50/50 |
60/40 |
70/30 |
80/20 |
90/10 |
Contractor's
Profit Based on Share Ratios Above and Costs In Left Column |
$8,000,000 |
$2,000,000 |
$1,800,000 |
$1,600,000 |
$1,400,000 |
$1,200,000 |
8,500,000 |
1,750,000 |
1,600,000 |
1,450,000 |
1,300,000 |
1,150,000 |
9,000,000 |
1,500,000 |
1,400,000 |
1,300,000 |
1,200,000 |
1,100,000 |
9,500,000 |
1,250,000 |
1,200,000 |
1,150,000 |
1,100,000 |
1,050,000 |
10,000,000 |
1,000,000 |
1,000,000 |
1,000,000 |
1,000,000 |
1,000,000 |
10,500,000 |
750,000 |
800,000 |
850,000 |
900,000 |
950,000 |
10,600,000 |
700,000 |
760,000 |
820,000 |
880,000 |
900,000 |
10,700,000 |
650,000 |
720,000 |
790,000 |
800,000 |
800,000 |
10,800,000 |
600,000 |
680,000 |
700,000 |
700,000 |
700,000 |
10,900,000 |
550,000 |
600,000 |
600,000 |
600,000 |
600,000 |
11,000,000 |
500,000 |
500,000 |
500,000 |
500,000 |
500,000 |
11,500,000 |
0 |
0 |
0 |
0 |
0 |
PTA |
$11,000,000 |
$10,833,333 |
$10,714,286 |
$10,625,000 |
$10,555,556 |
Prior to the target
cost, the different share ratios provide profits based on
the contractor’s share of saved costs alone. Under the 50/50
share ratio, a contractor can increase its profit by $1 million
when costs are $2 million less than the target cost because its
share is 50 percent of any savings. On the
other hand, with the 90/10 share ratio, a contractor can increase
its profit by only $200,000 when costs are $2 million less
than the target cost because its share is only 10 percent of any
savings. The message is clear—there is less
incentive to reduce costs as the government share
increases.
Once the target cost is exceeded, a contractor with a 50/50
share ratio has its profit reduced quickly below the PTA because
it is sharing in half of the cost overruns above the target cost. On the other hand, the reduction in profit is
less dramatic for the 90/10 ratio. In effect, the
incentive curve is being flattened below the PTA. Take another
look at the overrun structure for the 50/50 and 90/10 share
ratios.
Ceiling Prices and Share
Ratios Working Together
Now that
you have seen the basics for different ceiling prices and
different share ratios, it is time to see how they can work
together. Table 5 illustrates the effect of different share
ratios coupled with different ceiling prices. Compare
a 50/50 share ratio with a 115 percent ceiling price structure
to that of a 90/10 share ratio with a 135 percent ceiling
price structure. Quite a difference!
Table
5: FPIF Target Costs and Profits with
Different Ceiling Prices and Share Ratios.
Dollar Costs |
Share Ratios
Combined with Ceiling Prices |
50/50
115 |
60/40
120 |
70/30
125 |
80/20
130 |
90/10
135 |
$8,000,000 |
$2,000,000 |
$1,800,000 |
$1,600,000 |
$1,400,000 |
$1,200,000 |
8,500,000 |
1,750,000 |
1,600,000 |
1,450,000 |
1,300,000 |
1,150,000 |
9,000,000 |
1,500,000 |
1,400,000 |
1,300,000 |
1,200,000 |
1,100,000 |
9,500,000 |
1,250,000 |
1,200,000 |
1,150,000 |
1,100,000 |
1,050,000 |
10,000,000 |
1,000,000 |
1,000,000 |
1,000,000 |
1,000,000 |
1,000,000 |
10,500,000 |
750,000 |
800,000 |
850,000 |
900,000 |
950,000 |
11,000,000 |
500,000 |
600,000 |
700,000 |
800,000 |
900,000 |
11,500,000 |
0 |
400,000 |
550,000 |
700,000 |
850,000 |
12,000,000 |
(500,000) |
0 |
400,000 |
600,000 |
800,000 |
12,500,000 |
(1,000,000) |
(500,000) |
0 |
500,000 |
750,000 |
13,000,000 |
(1,500,000) |
(1,000,000) |
(500,000) |
0 |
500,000 |
13,500,000 |
(2,000,000) |
(1,500,000) |
(1,000,000) |
(500,000) |
0 |
PTA |
$11,000,000 |
$11,666,667 |
$12,142,857 |
$12,500,000 |
$12,777,778 |
The 50/50 share
ratio and 115 percent ceiling price structure is referred to
as a “tight structure” because it places a good deal of cost
control incentive on the contractor. On the other hand, the
90/10 share ratio and 135 percent ceiling price structure is
referred to as a “loose structure” because there is less cost
control incentive placed on the contractor. With the
combination of a high ceiling price and a high government share,
we have flattened the incentive curve significantly.
Now, with what we
have seen so far, let's go back to the contract that Gordon
Rule was complaining about in 1976. To do this, we will compare a moderate FPIF structure with a 70/30 share ratio and 125 percent
ceiling price to the Rule contract.
Table 6:
Moderate FPIF Structure Compared to the Rule Contract.
Dollar Costs |
Profit
Dollars |
Profit
Rate |
70/30
125 |
Rule Contract |
70/30
125 |
Rule Contract |
$60,000,000 |
$14,500,000 |
$10,730,000 |
24,17% |
17.88% |
65,000,000 |
13,000,000 |
10,250,000 |
20.00% |
15.77% |
70,000,000 |
11,500,000 |
10,000,000 |
16.43% |
14.29% |
75,000,000 |
10,000,000 |
9,750,000 |
13.33% |
13.00% |
76,000,000 |
9,700,000 |
9,700,000 |
12.76% |
12.76% |
80,000,000 |
8,500,000 |
9,500,000 |
10.63% |
11.88% |
85,000,000 |
7,000,000 |
9,250,000 |
8.24% |
10.88% |
90,000,000 |
5,000,000 |
8,870,000 |
5.56% |
9.86% |
95,000,000 |
0 |
6,000,000 |
0% |
6.32% |
100,000,000 |
5,000,000 |
1,000,000 |
Loss |
1.00% |
101,000,000 |
6,000,000 |
0 |
Loss |
0% |
As Table 6 shows, there is quite a
difference between our moderate FPIF structure and the Rule
contract. Look at the $95 million dollar
cost level. Here the moderate FPIF results in no profit while the Rule
Contract provides a 6.32 percent
profit rate and a dollar profit of $6 million. This difference is caused by the higher ceiling
price and the higher government share of overruns on the Rule
Contract. Take a look at the profit rate on costs before the
target cost is reached. It increases more slowly on the Rule
contract as costs are reduced below the target cost of $76
million. Here, the flattening effect of the higher government share
on
any cost savings is evident.
What Was Gordon Rule Saying?
With the basic mechanics of an FPIF contract under your belt, we can
go back to that day in 1976 when Gordon Rule said "What
do you see?" "What do you see?” "Look how flat it
is." Well, a CPFF is a flat
curve. For example, on a CPFF contract, the share ratio is
100/0 because the government shares all of the cost
savings and overruns within the original contract terms. Additionally, the
ceiling price could be infinite if the government wishes. So,
a CPFF contract has a 100/0 share ratio and whatever ceiling
price the government is willing to accept. Gordon Rule was
claiming that the FPIF example in the "Rule Contract" was, in
fact, a CPFF contract. Was he right? In Table 7, a CPFF
contract structure is compared to the structure of the Rule
Contract.
Table 7: CPFF Contract
Structure Compared with the Rule Contract Structure
Dollar Costs |
Profit
Comparison (Dollars) |
Profit
Comparison (Profit Rate) |
CPFF |
Rule Contract |
CPFF |
Rule Contract |
$60,000,000 |
$9,700,000 |
$10,730,000 |
16.17% |
17.88% |
65,000,000 |
9,700,000 |
10,250,000 |
14.92% |
15.77% |
70,000,000 |
9,700,000 |
10,000,000 |
13.86% |
14.29% |
75,000,000 |
9,700,000 |
9,750,000 |
12.93% |
13.00% |
76,000,000 |
9,700,000 |
9,700,000 |
12.76% |
12.76% |
80,000,000 |
9,700,000 |
9,500,000 |
12.13% |
11.88% |
85,000,000 |
9,700,000 |
9,250,000 |
11.41% |
10.88% |
90,000,000 |
9,700,000 |
8,870,000 |
10.78% |
9.86% |
95,000,000 |
9,700,000 |
6,000,000 |
10.21% |
6.32% |
100,000,000 |
9,700,000 |
1,000,000 |
9.70% |
1.00% |
101,000,000 |
9,700,000 |
0 |
9.60% |
0% |
For the CPFF
contract in Table 7, the fixed-fee is set at the same rate as
the target profit on the Rule contract—$9.7 million at a cost
of $76 million. Remember that between $64,600,000 and
$87,400,000, the share ratio on the Rule contract was 95/5. So, the CPFF share ratio
of 100/0 is quite close to that of the Rule contract at 95/5
between $64.6 million and $87.4 million. After $87.4 million,
the Rule contract converts to a 90/10 share ratio until the PTA
which is between $92 and $93 million. Notice how the percent of
fee on costs closely parallels the percent of profit on the Rule
contract. As Gordon Rule emphasized, it is flat—it is nearly a CPFF
contract.
Abuses of the FPIF
The Federal Acquisition Regulation (FAR) at 16.403-1 (b)
explains that an FPIF contract is appropriate when a fair and
reasonable incentive and a ceiling can be negotiated that
provides the contractor with an appropriate share of the risk
and the target profit should reflect this assumption of
responsibility. The FAR further points out that an FPIF is
to be used only when there is adequate cost or pricing
information for establishing reasonable firm targets at the time
of initial contract negotiation. Further, FAR 16.401
explains that incentives are designed to motivate contractors to
meet government goals and objectives.
The guidance in the
FAR, although general, appears sound. However, what happens when
people and the survival of their programs or their organizations are involved? Unfortunately, the FPIF can be manipulated and abused by government and/or industry.
It can be used to submit below anticipated cost offers, to hide huge
anticipated overruns, or to deceive the uninitiated who only
recognize the phrase "fixed-price."
One Industry’s Experience with the FPIF
In the 1970s, 1980s, and into the
1990s, a series of General Accounting Office (GAO) reports
discussed cost overruns on shipbuilding contracts. For the most
part, these reports discussed FPIF contracts. Table 8 provides a
summary of the anticipated cost overruns on most shipbuilding
contracts during this period.
Table 8: Anticipated
Cost Overruns and Savings Reported on Shipbuilding FPIF
Contracts.
Report Date |
Number of FPIF Contracts |
Expected Costs Above Target
Costs |
Expected Savings Below Target
Costs |
Number of Contracts Expected to
Finish at Target |
Number |
Dollars |
Number |
Dollars |
1987a |
22 |
19 |
$1,413,000,0000 |
3 |
$25,900,000 |
N/A |
1989b |
46 |
25 |
3,297,000,000 |
6 |
315,000,000 |
15 |
1990c |
44 |
24 |
3,784,100,000 |
6 |
230,800,000 |
14 |
1992d |
45 |
32 |
4,400,000,000 |
3 |
102,000,000 |
10 |
a Navy Contracting: Cost Overruns and Claims
Potential on Navy Shipbuilding Contracts, GAO/NSIAD-88-15,
October 16, 1987, p. 7
b Navy Contracting: Status of Cost Growth and
Claims on Shipbuilding Contracts, GAO/NSIAD-89-189, August
4, 1989, p. 2
c Navy Contracting: Ship Construction Contracts
Could Cost Billions Over Initial Target Costs,
GAO/NSIAD-91-18, October 5, 1990, p. 12
d Navy Contracting: Cost Growth Continues on Ship
Construction Contracts, GAO/NSIAD-92-218, August 31, 1992,
p. 11 |
As we can see from the
table, the majority of the contracts had cost estimates for
completion that exceeded the original target costs. Additionally, the amount of estimated cost overruns dwarfed the
amount of estimated savings in each GAO report. These numbers defy the law of
averages. If we simply look at these results without asking
questions, we would declare the FPIF contract type as
ineffective. However, there is more to it than that.
During the 1970s and 1980s, the commercial shipbuilding market
was shrinking for U. S. shipbuilders and the U. S. Navy
became the “sole-customer” for their work. At the same time, the Navy
emphasized competition on its contracts and placed more emphasis
on price in making decisions for contract awards. Price
became more important because of tight budgets. The
industry, recognizing that its commercial market had dried-up,
placed survival above profit and cut prices in a frenzy of
low-ball offers. Since the government was the sole customer, it
had pricing power over its contractors. According to the GAO
One shipbuilder said
the Navy has sent a message that ship contracts will be awarded
based on price and the response has been to bid aggressively. 1
How aggressive was
the bidding? Here is one example.
Navy analyses
indicate that both contracts were awarded at a substantial cost
risk to the government based on comparisons of the proposed
prices with the Navy's estimates. In both of these awards, the
Navy believes that there is a strong possibility that the
contractors will exceed ceiling prices. 2
Yes, under these two
contracts target cost was not the issue. The Navy concluded
that the contractors offered to work at a loss
somewhere beyond the ceiling price.
Beware of the Hidden Target Cost
If an industry or a contractor is trying to survive in a competitive environment, how might it approach the FPIF. As we have seen, contractors will
bid below cost when they believe it is in their interest. Does the FPIF provide an
opportunity for a contractor to offer a very low price, expect a
very large overrun, and hope for a small profit? Yes, it does. Table 9 provides a theoretical example that includes an FPIF with a 95/5 share ratio and a 135 percent ceiling price. Included in
the table is a "proposed target cost" which is the official
offer amount that the contractor submits to the government. In
the second column, there are a range of the contractor's real
goals for its target cost.
Table 9: Example of a Potential Contractor's View of a FPIF.
Contractor's Proposed Target Cost |
Contractor's
Actual Goals |
Target Cost |
Cost Overrun |
Overrun Rate |
Dollar Profit |
Profit Rate |
$100,000,000 |
$100,000,000 |
$0 |
0.00% |
$10,000,000 |
10.00% |
100,000,000 |
105,000,000 |
5,000,000 |
5.00% |
9,750,000 |
9.29% |
100,000,000 |
110,000,000 |
10,000,000 |
10.00% |
9,500,000 |
8.64% |
100,000,000 |
115,000,000 |
15,000,000 |
15.00% |
9,250,000 |
8.04% |
100,000,000 |
120,000,000 |
20,000,000 |
20.00% |
9,000,000 |
7.50% |
100,000,000 |
125,000,000 |
25,000,000 |
25.00% |
8,750,000 |
7.00% |
100,000,000 |
126,315,789 |
26,315,789 |
26.32% |
8,684,211 |
6.88% |
100,000,000 |
129,807,000 |
29,807,000 |
29.81% |
5,193,000 |
4.00% |
100,000,000 |
130,000,000 |
30,000,000 |
30.00% |
5,000,000 |
3.85% |
100,000,000 |
135,000,000 |
35,000,000 |
35.00% |
0 |
0 |
100,000,000 |
140,000,000 |
40,000,000 |
40.00% |
5,000,000 |
Loss |
Assume that the
contractor sets a goal of a 4 percent profit on costs.
From past experience, the contractor expects that the government
will be willing to negotiate a 95/5 share ratio, a 135 percent
ceiling price, and a 10 percent profit rate at target cost.
The contractor proposes a target cost of $100,000,000 but is
really focusing on the 4 percent profit amount. At that
profit rate, the contractor's actual target cost goal is
$129,807,000. The government determines that the offer is
fair and reasonable and negotiations are completed. At the
time of agreement on the pricing structure, $100,000,000 is the
contractual target cost and the contractor's actual goal is
$129,807,000 for a target cost. In effect, the contract is
negotiated with nearly a 30 percent cost overrun and a 4 percent
profit.
A Government Incentive to Underestimate Costs
Does a government organization ever have an interest in understating the cost of
an item? The President's Blue Ribbon Commission on Defense
Procurement, popularly known as the Packard Commission, gave us
the following answer.
Once military
requirements are defined, the next step is to assemble a small
team whose job is to define a weapon system to meet these
requirements, and "market" the system within the government, in
order to get funding authorized for its development. Such
marketing takes place in a highly competitive environment, which
is desirable because we want only the best ideas to survive and
be funded. It is quite clear, however, that this competitive
environment for program approval does not encourage realistic
estimates of cost and schedule. So, all too often, when a
program finally receives budget approval, it embodies not only
overstated requirements but also understated costs. 3
If the government
has an interest in underestimating the cost of a system, it
can use an FPIF to its advantage by simply loosening the pricing structure of the FPIF contract. Let's look
at an actual example—the original contract for the Trident
submarine awarded in 1974.
Table 10: Fixed-Price Incentive Pricing Structure for the
Trident Submarine.4
Pricing Elements |
Pricing Structure |
Target Cost |
$253,000,000 |
Target Profit |
$32,400,000 (12.8% of Target Cost) |
Target Price |
$285,400,000 |
Ceiling Price |
$384,000,000 (152% of target cost) |
Share Ratio |
95/5 from target cost to $279,600,000
85/15 from $279,600,000 to PTA
70/30 below target cost |
As can be seen, the contract had a 95/5
share ratio and an incredible ceiling price of 152 percent of target cost. Here is what
Gordon Rule had to say about this pricing structure
When the Navy
negotiates a 95/5 share above target cost for the first 26
million of overrun of target, the target cost figure is patently phoney. Moreover, when the Navy negotiates a 95/5 share and then
also a 152% ceiling, the target cost figure is patently
ridiculous. First priority for the future must be the
negotiation of more reasonable target costs for our FPI
shipbuilding contracts and if the budget has to be changed, then
change it. 5
Once a system
receives budget approval with an understated cost, the
government must find a way to contract for it at that underestimated
cost. The FPIF
provides the opportunity in two ways. First, it allows the
government to hide expected overruns at the time the contract is
awarded. Or, in Gordon Rule's words, it allows the government to
include "an obvious overrun of target cost built in." 6
Second, the term "fixed-price" can be used to disguise a
cost-reimbursement contract. For example, in regard to the
Trident contract, the Commander of the Naval Ship Systems
Command, explained 7
People said, "That's
a CPFF [cost-plus-fixed-fee] contract under another name," and I
said, "Right. You want to call it that, do what you like.
Call it what you please." ... I suppose it's a matter for some
slight chagrin that what really ought to have been a CPFF
contract turned out to be something else, or to have a different
label on it, but I don't feel bad about it. 8
Some Final
Thoughts
Does the FPIF contract have a place
in federal contracting? I think it does when it is used as
it is intended. However, it can and has been abused.
In testing an FPIF structure, there are a number of things I ask.
Here are several.
Is the government's share of savings
significantly lower below the target cost than its share of
losses above the target cost. For example, is there a
50/50 share ratio below the target cost while a 95/5 share ratio
exists above target cost. This alerts me to the
possibility that the real target cost exceeds the negotiated
target cost in the contract.
Is the ceiling price above 135
percent of target cost? Although a 135 percent ceiling
price is generous,
anything above it is excessive.
Does the share ratio flatten out
around the target cost for an extended period? For
example, is there a share ratio of 95/5 or 100/0 from 10 percent
below target cost to 10 percent above target cost? This
effectively converts the extended part of the FPIF structure to a
cost plus fixed-fee contract.
If I do identify a suspicious FPIF
structure, I turn to the facts surrounding the negotiation of
the target cost. For example,
Is the government's budget for the
item unrealistically low?
Does the government have pricing
power over the contractor? In short, can the government
dictate the contractor's price because of market conditions?
Is the contractor in survival mode
or is the contractor trying to gain a foothold in a program
area?
If there was a final proposal
revision, did the contractor's price drop substantially?
1
Navy Contracting: Cost Overruns and Claims Potential on Navy
Shipbuilding Contracts, GAO/NSIAD-88-15, October 16, 1987, p. 9
2
Ibid
3
President's Blue Ribbon Commission on Defense Procurement, Final
Report, June 30, 1986, p. 45.
4
J. Ronald Fox and Mary Schumacher, "Trident Contracting (C):
Negotiating the Contract," John F. Kennedy School of Government,
1988, pps 6 and 7.
5
Hearings before the Committee on Armed Services, United States
Senate, 94th Congress, Second Session, Part 8, Shipbuilding Cost
Growth and Escalation, p. 4658.
6
Fox and Schumacher, p. 8.
7
In 1976, the Naval Ship Systems Command was renamed the Naval
Sea Systems Command.
|