SEC. 823. EXEMPTION FROM DESIGN-BUILD
SELECTION PROCEDURES. Subsection (d) of section 2305a of title 10, United States Code, is amended by striking the second and third sentences and inserting the following: ““If the contract value exceeds $4,000,000, the maximum number specified in the solicitation shall not exceed 5 unless—
|
Exemption from design-build selection procedures (sec. 823)
The House bill contained a provision (sec. 861) that would amend section 2305a of title 10, United States Code, to exempt solicitations issued pursuant to an indefinite delivery/indefinite quantity contract from the statutory limitation on the number of offerors that may proceed to step two of the procurement selection process. The Senate amendment contained no similar provision. The Senate recedes. |