TITLE VIII--ACQUISITION POLICY, ACQUISITION MANAGEMENT, AND RELATED MATTERS

Subtitle B — Amendments to General Contracting Authorities, Procedures, and Limitations

P. L. 115-

House Conference Report. 115-404

SEC. 823. EXEMPTION FROM DESIGN-BUILD SELECTION PROCEDURES.

Subsection (d) of section 2305a of title 10, United States Code, is amended by striking the second and third sentences and inserting the following:

““If the contract value exceeds $4,000,000, the maximum number specified in the solicitation shall not exceed 5 unless—

“(1) the solicitation is issued pursuant to a indefinite delivery-indefinite quantity contract for design-build construction; or

“(2) (A) the head of the contracting activity, delegable to a level no lower than the senior contracting official within the contracting activity, approves the contracting officer's justification with respect to an individual solicitation that a maximum number greater than 5 is in the interest of the Federal Government; and

“(B) the contracting officer provides written documentation of how a maximum number greater than 5 is consistent with the purposes and objectives of the two-phase selection procedures.”.

Exemption from design-build selection procedures (sec. 823)

The House bill contained a provision (sec. 861) that would amend section 2305a of title 10, United States Code, to exempt solicitations issued pursuant to an indefinite delivery/indefinite quantity contract from the statutory limitation on the number of offerors that may proceed to step two of the procurement selection process.

The Senate amendment contained no similar provision.

The Senate recedes.