A-76,
Handbook: Part I, Ch. 3, H-3 a. - Technical Performance Plan
requirement |
Comptroller
General - Key Excerpts |
Office of Management and Budget
Circular No. A-76 and the Circular No. A-76 Revised Supplemental
Handbook (March 1996) do not require that the government submit
a "technical performance plan" (TPP) for evaluation
under the first step of a two-step sealed bidding acquisition to
determine the low bid for comparison with the government's
in-house bid. The Supplemental Handbook requires a TPP for
evaluation purposes only where the private sector proposal is
selected for cost comparison on the basis of a negotiated or
best value procurement. (BMAR
& Associates, Inc., B-281664, March 18, 1999) |
|
Comptroller
General - Listing of Decisions |
For
the Government |
For
the Protester |
BMAR
& Associates, Inc., B-281664, March 18, 1999 |
|
|
|