4 CFR 21.0
(a): Prejudice |
Comptroller
General - Key Excerpts |
New
Unequal Treatment
The protester also alleges that the agency applied more
stringent standards in its evaluation of DRS’ IMS than
Lockheed’s. Specifically, DRS alleges that the agency
permitted Lockheed to exceed the 10-page IMS limit. While
we agree with the protester that the agency improperly
failed to enforce the solicitation’s 10‑page IMS limit, we
find that the protester cannot demonstrate that it was
prejudiced by the agency’s waiver of the requirement.
It is a fundamental principle of government procurement
that competition must be based on an equal basis; that is,
offerors must be treated equally and be provided with a
common basis for the preparation of their proposals.
Lockheed Martin Corp., B-411365.2, Aug. 26, 2015, 2015 CPD
¶ 294 at 14. However, an agency may waive compliance with
a material solicitation requirement in awarding a contract
only if the award will meet the agency’s actual needs
without prejudice to other offerors. ExecuTech Strategic
Consulting, LLC; TRI-COR Indus., Inc., B‑410893 et al.,
Mar. 9, 2015, 2015 CPD ¶ 103 at 12.
The solicitation provided that the “IMS is expected to be
presented in the form of a Gantt chart,” which the RFP
required “to be no more than ten (10) pages in length.”
RFP at 109. Both offerors submitted an IMS section in
their technical acceptability volume, which included an
introductory narrative and a 10-page Gantt chart. See AR,
Tab 18, DRS Initial Vol. II, Technical Proposal, at 42-53;
AR, Tab 24, Lockheed Initial Vol. II, Technical Proposal,
at 73-81. DRS’s initial proposal contained a narrative
with additional IMS information that was about 1-page
long, while Lockheed’s narrative, which also contained
additional IMS information, was about a page and a half.
Id. In its response to the agency’s second FPR notice, DRS
did not change its 1‑page narrative, and submitted only an
updated 10-page Gantt chart. AR, Tab 22, DRS FPR2 Vol. II,
IMS Slip Pages, at 1-10. Lockheed, in its revised FPR,
submitted an updated narrative, which included its
response to an evaluation notice as well as its original
narrative, and an updated 10-page Gantt chart. AR, Tab 28,
Lockheed FPR2 Vol. II, 77-85. DRS alleges that the
evaluation was unequal because the agency considered
information in Lockheed’s IMS that was outside of the
solicitation’s 10‑page limit.
Based on our review of the record, we conclude that the
agency failed to enforce the IMS page limit and
effectively waived the requirement. We find, however, that
this wavier does not provide a basis to sustain the
protest. Competitive prejudice is an essential element of
a viable protest; and where the protester fails to
demonstrate that, but for the agency’s actions, it would
have had a substantial chance of receiving the award,
there is no basis for finding prejudice, and our Office
will not sustain the protest. Lockheed Martin Corp., supra
at 14. In this regard, even where an agency waives a
material solicitation requirement, our Office will not
sustain the protest unless the protester can demonstrate
that it was prejudiced by the waiver, i.e., where the
protester would have altered its proposal to its
competitive advantage had it been given the opportunity to
respond to the altered requirements. See Vocus Inc.,
B-402391, Mar. 25, 2010, 2010 CPD ¶ 80 at 6.
Here, both offerors included narratives and Gantt charts
in their IMS section that, when added together, exceeded
the 10-page limit. The agency effectively waived the page
limit when the evaluators chose not to remove pages in
excess of the 10‑page requirement in its evaluation of the
offerors’ IMS. Thus, the protester cannot demonstrate that
it was prejudiced by the agency’s waiver of the page limit
because the agency treated both offerors equally in this
regard. Moreover, even if the agency did not consider
information in DRS’s narrative, as it had for Lockheed, we
find no prejudice because the protester cannot demonstrate
that it would have submitted an acceptable offer if it was
given an opportunity to increase its IMS page limit.
In cases where the protester argues that an agency waived
a certain requirement, prejudice does not mean that, had
the agency failed to waive the requirement, the awardee
would have been unsuccessful. See LASEOD Group, LLC,
B-405888, Jan. 10, 2012, 2012 CPD ¶ 45 at 5. Rather, the
pertinent question is whether the protester would have
submitted a different offer that would have had a
reasonable possibility of being selected for award had it
known that the requirement would be waived. Id. While the
protester is correct that additional pages would have
permitted it to submit an IMS that answered the agency’s
concerns regarding the length or duration of certain tasks
(deficiencies 3, 4, 5 and 7) and provided a more detailed
training schedule (deficiency 8), an increase in pages
would not have enabled the protester to resolve its IMS
deficiencies for delivery of spares prior to written
authorization (deficiency 1), delivery of spares prior to
the end of interim contractor support options (deficiency
2), and that builds six and seven do not occur on the same
date (deficiency 6). We therefore deny this aspect of DRS’
protest. (DRS Network &
Imaging Systems, LLC B-413409, B-413409.2: Oct 25,
2016)
In
any event, even if the evaluation of the offerors’ prices was
flawed, Odyssey’s arguments demonstrate that the alleged errors
could not have prejudiced the protester. In this regard, our
Office will not sustain a protest unless the protester
demonstrates a reasonable possibility that it was prejudiced by
the agency’s actions; that is, unless the protester demonstrates
that, but for the agency’s actions, it would have had a
substantial chance of receiving the award. Armed Forces
Hospitality, LLC, B‑298978.2, B-298978.3, Oct. 1, 2009, 2009 CPD
¶ 192 at 9-10; McDonald-Bradley, B-270126, Feb. 8, 1996, 96-1
CPD ¶ 54 at 3.
Here, Odyssey contends that the differences between Odyssey’s
proposed staffing and the non-incumbent offerors’ proposed
staffing resulted in an “approximately” $1.2 million price
difference, which was “nearly the entire difference” between
Odyssey’s and Offeror 3’s evaluated prices. Protester’s Comments
(Mar. 21, 2016) at 33. As the record shows, however, the
difference between Odyssey’s and Choctaw’s evaluated prices was
$2.8 million, and the difference between Odyssey’s and Offeror
3’s evaluated prices was $1.4 million. AR, Tab 85, SSDD, at 8.
Thus, even if the protester’s arguments concerning the agency’s
price evaluation had merit, the protester’s own calculations
show that its evaluated price would still be more than $200
thousand higher than Offeror 3’s evaluated price. See id.
Because the solicitation provided for award to the offeror that
submitted the LPTA proposal, Offeror 3, and not Odyssey would be
in line for award. We therefore conclude that the protester’s
arguments concerning the evaluation of price fail to demonstrate
any possibility of prejudice, and find no basis to sustain the
protest. See Chandler Solutions, LLC, B‑409655.2, Aug. 13, 2014,
2014 CPD ¶ 239 at 4. (Odyssey
Marketing Group, Inc. B-412695,B-412695.2: Apr 21, 2016)
(pdf)
Adherence to
the RFP’s Evaluation Scoring Scheme
edCount alleges that the agency failed to follow the evaluation
scoring scheme outlined in the RFP when it assigned point scores
to the proposals. According to the protester, the agency did not
use the point score system detailed in the solicitation. edCount
contends that there is no way to determine the basis for, or
underlying reasonableness of, the point score assigned to its
proposal.
We agree with this aspect of edCount’s protest. Agencies may not
properly announce one basis for evaluating proposals and making
a source selection decision and then evaluate proposals and make
award on a different basis. Johnson Controls Security Systems,
LLC, B-296490.3 et al, Mar. 23, 2007, 2007 CPD ¶ 100 at 7. For
example, an agency may not properly specify the relative weight
of evaluation considerations in a solicitation and then apply a
different weighting scheme when evaluating proposals and making
a source selection decision. Id. While an agency’s use of point
scores can serve to guide intelligent decisionmaking, the
assignment of the underlying point scores must be on an
intelligible, reasonable, equal and consistent basis for all
proposals. Nexant, Inc., B-407708, B-407708.2, Jan. 30, 2013,
2013 CPD ¶ 59 at 7.
Here, the record shows that the evaluators did not assign point
scores to the proposals in a manner that was consistent with the
evaluation criteria outlined in the RFP. Specifically, the
record shows that the evaluators assigned only overall point
scores for each technical evaluation factor without scoring the
proposals using the more detailed scoring scheme outlined under
the subfactors included under each factor. The agency concedes
as much, stating:
As an initial matter, and for purposes of clarification, ED’s
[the Department of Education’s] Technical Evaluation Panel (“TEP”)
. . . specifically chose not to follow the instructions in
evaluating offerors’ proposals set forth in the Technical
Evaluation Plan and Instructions. [Citations to the record
omitted]. Rather, the record shows that ED’s technical
evaluators analyzed each offeror’s technical proposal in
accordance with the narrative evaluation [subfactors] set
forth under each technical evaluation subfactor [factor] (i.e.
Organizational Capability and Experience; Technological
Experience; Soundness of Technical Work Plan; and Management
Plan). Instead, the TEP employed a more holistic approach to
evaluating proposals under each technical [factor].
Agency Legal Memorandum, July 15, 2013, at 2 (emphasis in
original).
As an initial matter, the agency appears to take the position
that it was not required to assign point scores in a manner
consistent with the point values assigned to the evaluation
subfactors because the express instruction to so score proposals
was only articulated in the agency’s source selection plan, and
nothing in the RFP specifically stated that the agency would
assign point scores on a subfactor-by-subfactor basis. We
disagree. The agency’s position ignores that these subfactors
and their corresponding point scores also were identified in the
RFP. RFP at 16-18. This solicitation language, which identified
23 separate subfactors (with specific point score values for
each) obligated the agency to assign point scores in a manner
consistent with the scheme articulated in the RFP.
There is nothing in the record to show that the agency scored
proposals in a manner consistent with the terms of the RFP, and,
as noted, the agency concedes this issue. On the contrary, the
record includes numerous examples where the agency’s scoring of
the protester’s proposal clearly was not compliant with the
subfactor weighting scheme announced in the solicitation. These
defects permeate both the individual evaluators’ scoring, as
well as the consensus scoring.
For example, with respect to the individual scores assigned by
the evaluators, the record shows that evaluator no. 3 assigned
edCount’s proposal the lowest score of 12 points (out of a
possible 25 points) under the technological experience factor.
That individual’s score sheet does not show either the
subfactors under which the evaluator assigned points, or the
number of points deducted for each perceived weakness. Agency
Report (AR), exh. 6, evaluator 3 worksheet, at 13-14. It also
cannot be ascertained from the record whether this individual’s
assignment of points was attributable to more important, or less
important, subfactors.
In addition, the record shows that, in arriving at their
consensus point score, the individual evaluators simply averaged
their total point scores, even though there were wide variations
in those scores, and even though a number of the weaknesses
forming the bases for the individual evaluator point scores were
not carried forward to the consensus evaluation report. AR, exh.
20, Technical Evaluation Consensus Report, at 8. The record is
devoid of any explanation of how the evaluators resolved the
wide variation in the scores assigned by the individual
evaluators, or why they concluded that a simple average of the
individual scores assigned to the higher-level factors
accurately reflected the collective judgment of the evaluators.
While the use of a mathematic average to develop a consensus
score is not per se improper, see, Smart Innovative Solutions,
B-400323.3, 2008 CPD ¶ 220, at 3-4, we cannot conclude that it
was reasonable here.
In sum, the record shows that, because the evaluators elected to
ignore the solicitation’s detailed evaluation scheme--and more
specifically, the relative weight of the evaluation subfactors
established by the terms of the RFP--the evaluation results
included pervasive mathematical anomalies in the scores assigned
to the edCount proposal. We conclude that the cumulative effect
of these errors renders the agency’s point scores essentially
meaningless.
Prejudicial Effect of the Agency’s Point Scoring Error
Despite the agency’s failure to adhere to the RFP’s subfactor
evaluation scheme in assigning a point score to the edCount
proposal, we nonetheless conclude that the agency’s error was
not prejudicial to edCount. Prejudice is an essential element of
every viable protest, and where none is shown or otherwise
evident, we will not sustain a protest, even where a protester
may have shown that an agency’s actions arguably were improper.
ITT Corp.-Electronic Sys. , B-402808, Aug. 6, 2010, 2010 CPD ¶
178 at 7.
The record shows that, although the overall consensus point
score assigned to edCount’s proposal essentially was meaningless
for the reasons discussed above, the agency did identify 14
specific weaknesses in the proposal across every technical
evaluation factor. In making her competitive range
determination, the contracting officer described these
weaknesses in detail. She found that several proposals,
including edCount’s, were “so significantly weaker” than other
proposals that there was no reasonable expectation that they
could be improved without significant revisions; as a
consequence, she eliminated edCount’s and the other proposals
from the competitive range. AR, exh.21, Competitive Range
Determination, at 22.
Thus, although the point score assigned to the edCount proposal
could not have formed a rational basis for eliminating the
proposal from the competitive range, the agency’s underlying
detailed analysis of the edCount proposal does provide a
reasonable basis for its elimination from the competitive range.
Smart Innovative Solutions supra at 4. (edCount,
LLC--Protest and Costs, B-407556.3, B-407556.4, B-407556.5,
B-407556.6, Aug 15, 2013) (pdf)
We deny the
protest because the record shows that BCPeabody was not
prejudiced by the Corps’ unequal evaluation of proposals.
Although an offeror has the burden of submitting an adequately
written proposal, and an agency may downgrade a proposal for the
lack of requested information, an agency may not ignore prior
performance information of which it is aware. Consolidated Eng’g
Servs., Inc., B-279565.2, B-279565.3, June 26, 1998, 99-1 CPD ¶
75 at 6. Where multiple proposals propose the same
subcontractor, once the agency becomes aware of that
subcontractor’s experience, including from another firm’s
proposal, it cannot reasonably assign one proposal a higher
score than another based on that experience. Id. Here, the
proposals of both Edens and BCPeabody included BFC as their
respective cut-off wall construction subcontractor, and it was
not reasonable for the Corps to find BFC’s experience acceptable
for Edens but unacceptable for BCPeabody.
However, our Office will not sustain a protest unless the
protester demonstrates a reasonable possibility that it was
prejudiced by the agency’s actions; that is, unless the
protester demonstrates that, but for the agency’s actions, it
would have had a substantial chance of receiving the award.
McDonald-Bradley, B-270126, Feb. 8, 1996, 96-1 CPD ¶ 54 at 3;
see Statistica, Inc. v. Christopher, 102 F.3d 1577, 1581 (Fed.
Cir. 1996).
We agree with the Corps that BCPeabody was not prejudiced by the
agency’s error. BCPeabody candidly stated in its initial protest
that it intended to submit a project experience narrative for
Bauer Foundations Canada. Although the parties agree that the
firms are affiliated, Bauer Foundations Canada is a distinct
legal entity from BFC. Thus, under the terms of the RFP, the
Corps would have “noted as a deficiency” the lack of a letter of
commitment from Bauer Foundations Canada. Accordingly, we have
no basis to disagree with the Corps’s assertion that such a
deficiency would have resulted in the rejection of BCPeabody’s
proposal as unacceptable for a reason independent of the
evaluation of experience and past performance. (BC
Peabody Construction Services, Inc., B-408023, May 10, 2013)
(pdf)
Smith initially
complained that, among other things, the agency had unequally
shared information relating to the agency’s estimated cost and
budget. Specifically, Smith argued that some offerors had been
improperly informed at an industry conference that the agency’s
budget for this procurement was $2.3 million, and not $9
million, as Smith had believed. Smith contends that, had it
known of the lower budget, it “would have prepared a
significantly lower [proposal] that was much closer, if not less
expensive than [FN’s proposal].” Protest at 8.
In response to the protest, the agency stated that the
protester’s understanding of the agency’s budget was incorrect
because the agency’s budget was, in fact, approximately $9.9
million. See Legal Memorandum at 16. The protester withdrew this
ground of protest in its comments.
In a supplemental protest, Smith argues that the agency
improperly relaxed the delivery requirement without giving the
protester an opportunity to compete for the agency’s actual
requirements. Smith contends that its price would have been
significantly lower if it had not had to provide the phase two
product samples within 90 days. Specifically, Smith argues that
its proposed price would have been less than FN’s awarded price.
In support of this, Smith provided a declaration from its
procurement manager that describes the protester’s proposed
pricing under each of the first three procurement phases. The
declaration explains how Smith, to account for the relaxed
delivery schedule, would have reduced its proposed $1.81 million
price for the three phases by more than $1.12 million. See
Protester’s Supp. Protest and Comments, exhib. A, Decl. of Smith
Procurement Manager, at 2-8.
Where an agency’s requirements materially change after a
solicitation has been issued, it is generally required to issue
an amendment to notify offerors of the changed requirements and
afford them an opportunity to respond. Federal Acquisition
Regulation (FAR) § 15.206(a); Murray-Benjamin Elec. Co., L.P.,
B-400255, Aug. 7, 2008, 2008 CPD ¶ 155 at 3-4. Amending the
solicitation provides offerors an opportunity to submit revised
proposals on a common basis that reflects the agency’s actual
needs. Multimax, Inc., et al., B-298249.6 et al., Oct. 24, 2006,
2006 CPD ¶ 165 at 6.
Here, the basis for the agency’s exclusion of Smith’s proposal
from the competitive range was the proposal’s significantly
higher price. The record shows that Smith was the only offeror
that proposed to satisfy the RFP’s delivery schedule for the
phase two product samples. After exclusion of Smith’s proposal
from the competitive range, the agency amended the RFP to relax
the delivery schedule. We think that it should have been
reasonably apparent to the Navy that the relaxation of the
delivery schedule could affect the firms’ proposed prices and
that the Navy should have allowed Smith an opportunity to
provide a revised proposal that met the relaxed delivery
schedule.
Nevertheless, we do not find that the protester was prejudiced
by the agency’s actions. Competitive prejudice is an essential
element of a viable protest; where no prejudice is shown or
otherwise evident, our Office will not sustain a protest, even
if a deficiency in the procurement is evident. Moon Eng’g Co.,
Inc., B-256079, May 5, 1994, 94-1 CPD ¶ 296 at 4. In its initial
protest, Smith stated that its higher proposed price was based
upon the protester’s understanding of the amount of available
government funding, and not the solicitation’s delivery
schedule. See Protest at 6-8. After being informed that the
protester’s understanding of the available government funding
was not mistaken, Smith withdrew this protest allegation without
explanation. Smith now asserts that its much higher price is
based upon the solicitation’s delivery schedule. Smith, however,
does not reconcile this new claim with its earlier assertion
that its higher price was based upon its understanding of the
amount of funding available.
Smith provides a declaration from its procurement manager to
support its claim that Smith would have reduced its overall
price by nearly 62 percent had Smith known of the agency’s
actual delivery requirements for the phase two product samples.
See Protester’s Supp. Protest and Comments, exhib. A, Decl. of
Smith Procurement Manager. This statement purports to explain
how the protester’s research and development and production
costs for all three development phases would be significantly
reduced to reflect the relaxed schedule for the four product
samples. In this regard, the procurement manager identifies
reduced cost elements (such as, for example, engineering and
production labor costs, and material costs) for each development
phase. This statement, however, is not supported by any
documentation or detail (such as, labor hours or labor mix
underlying the bottom line labor or production costs)
demonstrating how Smith’s proposed price was derived or why it
would change.
We accept on its face Smith’s assertions in its supplemental
protest that the relaxed schedule would have allowed it to
reduce its overall costs by [DELETED]. In other words, we accept
that Smith’s overall price could be lower based upon the relaxed
schedule. Nevertheless, the record does not show any reasonable
possibility that the relaxation of the delivery schedule for the
four product samples would result in a nearly 62 percent
reduction in Smith’s total price. In light of Smith’s earlier
statement that its proposed price was based upon the amount of
government funding the firm believed was available, we are not
persuaded by the unsupported declaration of Smith’s procurement
manager, and we will not sustain the protest on this basis.
(Smith Enterprise, Inc., B-407529,
B-407529.2, B-407529.3, Dec 28, 2012) (pdf)
Calnet challenges
the evaluation of McNeil's past performance, claiming that the
agency unreasonably failed to consider one of the three PPQs
received for McNeil. According to the protester, had the agency
considered the third PPQ, McNeil's past performance rating would
have been lower, and a different source selection decision might
have resulted.
Prejudice is an essential element of every viable protest; we
will not sustain a protest unless the protester demonstrates a
reasonable possibility that it was prejudiced by the agency's
actions; in effect, a protester must show that, but for the
agency's actions, it would have had a substantial chance of
receiving the award. Armorworks Enter's., LLC, B-400394.3, Mar.
31, 2009, 2009 CPD para. 79 at 3. Here, we find that, even if
Calnet is correct that the agency improperly failed to consider
the third PPQ, Calnet was not prejudiced.
The record shows that the agency rated past performance using
the same numeric scores (ranging from 1 to 4) assigned under the
various elements of the PPQs. See, AR, exh. 18. The agency
calculated an arithmetic average of the scores, and then
assigned adjectival ratings in accordance with the thresholds
established in the RFP. Based on this approach, Calnet's
proposal received an average numeric score of 3.3 under each of
the evaluated areas (and thus an overall past performance score
of 3.3) and, correspondingly, a low risk rating. AR, exh. 67, at
2-4. In the case of McNeil, the record shows that the agency
received three PPQs for the firm, but decided that one of the
three should not be considered in the scoring. As calculated,
McNeil's average scores were 4 points each in the areas of
program management, quality management/performance and cost
performance, and 3.7 in resource management, resulting in its
very low risk rating. AR, exh. 67, at 6-8. Including the scores
from the third PPQ in the calculation would have reduced
McNeil's average scores to 3.45 for program management, 3.57 for
resource management, 3.5 for quality management/performance, 2.8
for cost performance, and its overall score to 3.3 points. AR,
exhs. 59, 67. Since this is the same overall score received by
Calnet, McNeil would have remained in line for award ahead of
Calnet due to its lower price. It follows that Calnet was not
competitively prejudiced by the alleged evaluation error, and
that there thus is no basis for sustaining Calnet's protest on
this ground.
Calnet asserts that the agency unreasonably failed to make
qualitative adjustments to McNeil's past performance scores
based on negative comments included in the third PPQ. However,
since the negative comments were written by the reference in
explanation of the ratings assigned, the agency reasonably could
assume that the essence of the comments already was reflected in
the numeric ratings. Moreover, the commentary underlying the
ratings assigned for all three of the PPQs was specifically
noted in the agency's past performance evaluation, and the
source selection authority thus was fully aware of the negative
comments in making the award decision. AR, exh. 67, at 6-8.
In its initial protest, Calnet asserted that the agency
improperly failed to consider three cure notices that allegedly
were issued to McNeil under three different contracts. The
agency responded in its report that it had not found information
concerning the three contracts during its evaluation when it
searched the past performance information retrieval system (PPIRS)
using McNeil's name and its contractor and government entity
(CAGE) code, and that there was no other evidence of cure
notices in connection with the three contracts. In its comments,
Calnet did not rebut the agency's response. Accordingly, we
consider this aspect of Calnet's protest abandoned. See
Washington-Harris Group, B-401794, B-401794.2, Nov. 16, 2009,
2009 CPD para. 230 at 5 n.3.
While preparing its report responding to Calnet's cure notice
argument, the agency performed an additional search of the PPIRS
using the contract numbers supplied by Calnet in its protest,
and found several past performance reviews of McNeil in
connection with one of the three contracts. AR, exhs. 61, 62 and
63. Calnet argues that this information should be factored into
McNeil's past performance evaluation. However, the RFP did not
require the agency to consider information beyond that included
in the PPQs; it advised only that the agency could use
information obtained from other sources. RFP at 55. Thus, the
agency's failure to discover or consider the information during
the evaluation does not constitute an evaluation impropriety
and, since this information did not come to light until well
after award, there is no basis for considering it now. (Calnet,
Inc., B-402558.2; B-402558.5; B-402558.7, June 3, 2010)
(pdf)
The protester challenges the agency's evaluation of NanoScale's
past performance. Truetech argues that because none of
NanoScale's prior contracts involved the production or delivery
of A200 sorbent powder or M295 decontamination kits, these
contracts are not relevant. Protest at 12, 14; Comments at
11-12. Therefore, the protester contends that NanoScale should
have been assigned a past performance rating of high risk or
unknown risk. Protest at 12. The protester further contends that
the SSA's alternative assessment based on a neutral rating
should be given no weight because it is merely an attempt at
"'preemptive deployment' of post hoc rationales." Comments at
15.
As a preliminary matter, we need not resolve Truetech's
challenge to NanoScale's past performance rating of very low
risk. As explained above, the SSA's alternative assessment
establishes that she would have selected the proposal submitted
by NanoScale, even assuming that all of NanoScale's past
performance references were considered to be not relevant. In
short, the record establishes that Truetech was not prejudiced
even were we to find that the Army unreasonably concluded that
NanoScale's past performance references were relevant. Our
Office will not sustain a protest unless the protester
demonstrates a reasonable possibility that it was prejudiced by
the agency's actions, that is, unless the protester demonstrates
that, but for the agency's actions, it would have had a
substantial chance of receiving the award. See McDonald-Bradley,
B-270126, Feb. 8, 1996, 96-1 CPD para. 54 at 3; Statistica, Inc.
v. Christopher, 102 F.3d 1577, 1581 (Fed. Cir. 1996). (Truetech,
Inc., B-402536.2, June 2, 2010) (pdf)
Next, Alsalam argues that the Army failed to reasonably evaluate
DynCorp's cost proposal, either as part of the agency's initial
evaluation, or its reevaluation. We agree with the protester
that the record here does not sufficiently establish that the
agency reasonably evaluated DynCorp's proposed costs. However,
as discussed below, we again think, on this record, that there
was no prejudice to Alsalam, because we see no reasonable
possibility that correcting the alleged errors would make
Alsalam the low-cost offeror.
When an agency evaluates a proposal for the award of a
cost-reimbursement contract, an offeror's proposed estimated
costs are not dispositive because, regardless of the costs
proposed, the government is bound to pay the contractor its
actual and allowable costs. FAR sections 15.305(a)(1);
15.404-1(d); Palmetto GBA, LLC, B-298962, B-298962.2, Jan. 16,
2007, 2007 CPD para. 25 at 7. Consequently, the agency must
perform a cost realism analysis to determine the extent to which
an offeror's proposed costs are realistic for the work to be
performed. FAR sect. 15.404-1(d)(1). We review an agency's
judgment in this area only to see that the agency's cost realism
evaluation was reasonably based and not arbitrary. Hanford Envtl.
Health Found., B-292858.2, B-292858.5, Apr. 7, 2004, 2004 CPD
para. 164 at 9.
Alsalam primarily argues that, despite the agency's
reevaluation, the record does not show whether the agency
reasonably evaluated DynCorp's proposed costs for DMA salaries
under CLIN X004AA.[9] Specifically, the protester contends that
the awardee's proposal does not show whether the costs for CLIN
X004AA included certain fringe benefit cost elements required by
the solicitation, such as the Saudi insurance known as General
Organization for Social Insurance, Defense Base Act insurance,
and hardship and housing allowances. See RFP attach. 2, at 4-6.
The protester argues that since these costs are not identified
in the awardee's proposal, they may not have been included in
its costs for this CLIN. Alsalam notes that DCAA report on its
cost proposal concluded that, for Alsalam, these costs
represented approximately $[deleted]--indicating the potential
cost effect on DynCorp's costs. AR, Tab 5.1, DCAA Alsalam
Evaluation, at 11.
As part of its reevaluation, the Army prepared a new cost
evaluation document. This document primarily reiterates the
agency's position that the initial evaluation reasonably found
that the awardee's proposed costs for CLIN X004AA contained all
of the required cost elements. See AR, Tab 25.2/25.3, Addendum
to Final Cost/Price Analysis, at 1. The Army contends that the
DCAA reports cited in the initial evaluations also confirm that
DynCorp's costs for this CLIN contained the cost elements at
issue, and that the Army cost evaluation also verified that the
cost elements were included. Price Analyst Response to GAO
Questions, Dec. 14, 2009, at 1. The agency argues that the
difference between the offerors' costs for this CLIN is due to
differences between their profit and general and administrative
(G&A) rates. AR, Tab 25.2/25.3, Addendum to Final Cost/Price
Analysis, at 1. As discussed above, offerors were required to
propose fixed and cost reimbursement CLINS. For CLIN X004AA, the
base DMA salaries were established by the solicitation. RFP at
17; attach. 2 at 4-6. Thus, proposed costs should have primarily
reflected differences between offerors' profit, indirect rates,
and fringe benefit costs.
While it appears possible that the majority of the cost
difference between the offerors for this CLIN is explained by
the differences between the offerors' profit and G&A rates, the
record does not clearly show how or whether the agency reached
this conclusion. In this regard, the agency's reevaluation
document provides only summary and conclusory remarks regarding
whether DynCorp's proposed cost for CLIN X004AA included all of
the required cost elements. Although the reevaluation again
states that the DCAA report concluded that the cost elements
were included in DynCorp's proposal for this CLIN, the DCAA
report does not mention the disputed cost elements. Compare
Price Analyst Response to GAO Questions, Dec. 14, 2009, at 1,
with AR, Tab 5.2, DCAA Report for DynCorp, Jan. 15, 2009.
Moreover, despite requests by our Office for specific citations
to the record, the Army has not shown that DynCorp's proposal
included the disputed cost elements or that the agency evaluated
those costs.
Notwithstanding these concerns, we think that, based on the
record, there is no possibility of prejudice to Alsalam here
because even if DynCorp failed to include the fringe benefit
costs, a cost realism adjustment would not overcome the
awardee's $11.4 million advantage over the protester's overall
price. Specifically, the protester's estimate of the required
cost realism adjustments--$[deleted] for CLIN X004AA and
$[deleted] under CLINs X004AB and X006AA--would not make Alsalam
the lower-priced offeror. Because DynCorp's proposal would
remain higher-rated technically, and lower priced, we think that
there is no reasonably possibility of prejudice to Alsalam.
The protest is denied. (Alsalam
Aircraft Company, B-401298.4, January 8, 2010) (pdf)
Under the
corporate experience subfactor, offerors were evaluated for
demonstrated experience in providing engineering and technical
services related to the statement of work. RFP at 59. Among
other things, offerors were specifically required to supply
three work examples related to surface ship corrosion control
post shakedown availabilities, and two examples related to
monitoring surface ship shipboard work during an availability
period while in a building yard or shipyard. RFP Amend. 4, at 5.
The agency found ATS’s proposal unclear as to which of the
listed experience information was to be evaluated for the work
examples requested. During discussions, the agency advised ATS
that “ATS provides corporate experience information . . ., but
does not specify which information is to be used for the work
examples requested.” Discussion Question 9. In its final
proposal revision (FPR), ATS provided an explanation of how the
information in its proposal related to the work examples
requested. Thereafter, in evaluating ATS’s FPR, the agency found
that the listed experience was not highly relevant. ATS asserts
that the discussions in this area were not meaningful because
the record shows that, during the initial evaluation, one of the
evaluators made comments that were not communicated to ATS.
This argument is without merit. The statements of the individual
evaluator to which ATS refers were not carried forward into the
consensus evaluation, which formed the basis for ATS’s score
under the corporate experience subfactor, and upon which the
discussion questions were based. Accordingly, the evaluator’s
comments do not provide a basis for questioning the adequacy of
discussions with ATS. See generally Lakeside Escrow & Title
Agency, Inc., B-310331.3, Jan. 7, 2008, 2008 CPD para. __
(where individual evaluator comments are not included in
consensus evaluation report, objections to statements of
evaluator are irrelevant). In any case, ATS’s proposal received
75 total technical points, while the awardees’ proposals
received 95.7 and 85.8 technical points. Under the corporate
experience subfactor, ATS’s FPR received 19 of the 25 available
points. Final Evaluation, Subfactor B-1. This being the case,
even if ATS’s proposal received a perfect score of 25 points for
corporate experience, its total evaluated score would only
increase to 81 points. Since, even under this scenario, ATS’s
proposal would be rated lower technically than the two awardees’
proposals, and its price would remain higher than both awardees’
prices, ATS would not be in line for award even if it prevailed
on this aspect of its protest. Under these circumstances ATS was
not prejudiced by any failure by the agency to provide
meaningful discussions. G&N, L.L.C., B-285118 et al., July 19,
2000, 2000 CPD para. 3 at 11. (Alliance
Technical Services, Inc., B-311329; B-311329.2, May 30,
2008) (pdf)
In September
2006, the Navy announced its intention to conduct a
public-private competition pursuant to OMB Circular A-76 for
performance of non-guard security support services at government
installations nationwide; these services are currently being
performed by approximately 460 civilian and 1480 military
personnel. Solicitation No. N69450-07-R-0054 was issued in
connection with this pending competition, and Mr. Myatt was
designated as the ATO responsible for developing and submitting
an agency tender pursuant to the solicitation requirements.
On February 8, 2008, prior to the solicitation’s initial closing
date, the ATO submitted a protest to this Office, challenging
certain provisions of the solicitation which mandated a
particular method for calculating the costs of performance by
the government’s most efficient organization (MEO). The ATO
maintained that the solicitation’s cost calculation provisions
were illogical and unfair. Following submission of that protest,
this Office conducted various telephone conference calls with
the ATO, the ATO’s counsel, agency counsel, and the contracting
officer. During these calls, agency counsel advised our Office
that the agency had extended the solicitation’s closing date to
March 20, and was further considering whether it would amend the
solicitation provisions regarding calculation of MEO costs.
Accordingly, we dismissed the ATO’s February 8 protest. Clark E.
Myatt, B-311234, Mar. 6, 2008. On March 19, the ATO submitted
this protest, again challenging, among other things, the
solicitation’s cost methodology for comparing the MEO’s costs
with private offerors’ costs, and noting that the agency had
neither addressed the ATO’s previously identified concerns, nor
further extended the solicitation’s March 20 closing date.
By letter to our Office dated April 3, the agency states that it
did not receive any acceptable private sector offers in response
to the solicitation. Accordingly, the agency maintains that “the
MEO cannot suffer any competitive prejudice” from the contested
terms of the solicitation under which the competition was to be
conducted. We agree. In situations where no acceptable private
sector offers are submitted, OMB Circular A-76 directs that the
agency must do one of two things: revise and reissue the
solicitation, or implement the agency tender. OMB Circular A-76,
attach. B, sect. D.4.d (May 29, 2003). Under either alternative,
there is no prejudice to the ATO resulting from the terms of the
previously issued solicitation.[3] Since competitive prejudice
is a necessary element of any viable protest, we have no basis
to further review the ATO’s allegations. See, e.g., OK Produce;
Coast Citrus Distrib., B-299058, B‑299058.2, Feb. 2, 2007, 2007
para. CPD 31 at 6; CRAssociates, Inc., B‑282075.2, B‑282075.3,
Mar. 15, 2000, 2000 CPD para. 63 at 10. (Clark
E. Myatt, Agency Tender Official, B-311234.2, April 15,
2008) (pdf)
Prejudice is an essential element of every viable protest
and, where it is not demonstrated or otherwise evident, we will not sustain a
protest allegation, even where the record shows that the agency’s actions were
arguably improper. GC Servs. Ltd.
P’ship, B-298102, B-298102.3, June 14, 2006, 2006 CPD para. 96 at 7-8; Statistica,
Inc. v. Christopher, 102 F.3d 1577, 1681 (Fed. Cir. 1996). PM was not prejudiced by the
alleged evaluation improprieties. While
PM asserts that its proposal should have received a total technical score of
94.9 points, it does not challenge Four Seasons’s proposal’s score of 98 points,
or the agency’s substantive evaluation findings supporting its conclusion that
Four Seasons’s proposal was technically superior. Under these circumstances, even
if we agreed with PM regarding the agency’s evaluation of its proposal, there
would be no basis for questioning the award, since Four Seasons’s proposal still
would be technically superior to PM’s (or, at worst, technically equivalent),
and lower cost. These assertions thus do
not provide a basis for sustaining the protest.
(Sections deleted)
In any case, as noted, PM’s evaluated cost
was $71,351,906, while the awardee’s was $68,122,022.65, for a
difference of $3,229,883.35, or approximately 4.4 percent. The
record also shows that, in preparing its proposal, PM applied a
[deleted] percent escalation rate for its SCA labor costs, AR
exh. F, at 3, while Four Seasons applied a [deleted] percent
escalation rate. Agency Supplemental Submission, Jan. 25, 2008,
at 6. Given the approximately 4.4 percent difference between the
firms’ prices, the record shows that the slight variance between
their escalation rates ([deleted] percent) could not have
affected the relative standing of their cost proposals.
Accordingly, PM was not prejudiced by the escalation provision.
GC Servs. Ltd. P’ship, supra. (PM
Services Company, B-310762, February 4, 2008) (pdf)
ACC raises a
number of objections to the evaluation of its proposal under
each evaluation factor. According to the protester, its proposal
was evaluated “in a manner that evidences a poorly structured,
subjective, and ill-designed evaluation process, which did not
offer a predefined variable measurement matrix with technically
sound measurement constructs having a uniform evaluative
process.” Protest at 1-2.The agency provided a detailed report
in response to the protest that specifically addressed each of
ACC’s numerous arguments. In its comments responding to the
report, ACC simply states that the agency’s report “further
substantiates the claim which was originally submitted by the
protester” but provides no specific rebuttal to any of the
agency’s explanation. Protester’s Comments. We have reviewed the
agency’s substantive response to the protester’s initial
allegations and, in the absence of any evidence or arguments to
the contrary from the protester, we have no basis to conclude
that the agency’s evaluation was unreasonable. Industrial Prop.
Mgmt., B-291336.2, Oct. 17, 2003, 2003 CPD para. 205 at 5.
Moreover, we think the record shows that there was no prejudice
to ACC arising from any alleged evaluation errors. In this
regard, even if we assume that ACC’s proposal should have been
assigned the highest possible rating under each non-price
factor, based on the record, we see no reasonable possibility
that the contracting officer would have concluded that ACC’s
proposal was worth paying more than twice the price of Svanaco’s
proposal, or the proposal of the second-lowest-priced,
similarly-rated offeror. Prejudice is an essential element of
every viable protest, and where none is shown or is otherwise
evident, we will not sustain a protest. Joint Mgmt. & Tech.
Servs., B-294229, B-294229.2, Sept. 22, 2004, 2004 CPD para. 208
at 7. (American Cybernetic
Corporation, B-310551.2, February 1, 2008) (pdf)
We find that SERAPH was not prejudiced by the alleged improper
evaluation of its two key personnel since, even if we agreed
with SERAPH, it would not be in line for award. More
specifically, the contemporaneous evaluation record shows that
SERAPH’s proposal was not selected for award due to the agency’s
evaluation conclusion that the proposal represented a moderate
risk under the understanding of work evaluation factor, and not
because the agency determined that SERAPH’s proposed personnel
had inadequate experience. In this regard, the agency
specifically stated in the competitive award memorandum that
SERAPH’s proposed staff has the experience and training
necessary to perform the contract. AR, Tab 9, at 15. While the
memorandum includes the comments (stated above) concerning the
two proposed personnel, the agency nevertheless concluded that
“the noted risks are not significant to warrant an overall
elevated risk rating.” Id. In other words, SERAPH’s green/low
risk rating under the relevant past experience/proposed
personnel factor was unaffected by the agency’s observations
regarding the two personnel. (SERAPH
Inc., B-297452, January 12, 2006) (pdf)
We will deny a protest where, notwithstanding that a
solicitation overstated an agency’s requirements, the protester
has not shown competitive prejudice; that is, unless the
protester demonstrates that, but for the agency’s actions, it
would have had a substantial chance of receiving the award (or,
in these circumstances, submitting an acceptable quotation).
McDonald‑Bradley, B‑270126, Feb. 8, 1996, 96‑1 CPD para. 54 at
3; see Statistica, Inc. v. Christopher, 102 F.3d 1577, 1581
(Fed. Cir. 1996). Here, the Navy has only supported a
requirement for a single sample report, not the multiple sample
reports specified in the RFQ. Nevertheless, and even after our
Office identified the issue, IVI has made no attempt to show
that it could have met the agency’s requirement for a single
report, regardless of the time provided. As such, IVI has not
been competitively prejudiced by the requirement for multiple
reports in the RFQ. (Information
Ventures, Inc., B-297225, December 1, 2005) (pdf)
While, as noted above, the contemporaneous documentation and
hearing record evidence that the unacceptability of Cogent’s
proposal under the design subfactor was based upon a number of
evaluated weaknesses, the record also shows that the PEB
considered some weaknesses to be more material than others. That
is, the hearing testimony evidenced that the PEB, in its
contemporaneous deliberations, considered weaknesses
assessed--in Cogent’s design--with respect to its proposed
scanner and its peak loading factor to be more significant than
other identified weaknesses, even though the PEB did not
specifically rank weaknesses.[10] See, e.g., TR at 47-50.
Moreover, the Army admitted in its report that some of the
weaknesses identified in the final consensus evaluation report
actually concerned Cogent’s earlier proposals and not the firm’s
final revised proposal. See AR at 29-34. The record shows that
removing Cogent’s proposed scanner from the list of evaluated
weaknesses under the design subfactor would require the agency
to reconsider whether Cogent’s proposal remained unacceptable in
light of the other evaluated weaknesses. Accordingly, we find
from this record that there is a reasonable possibility, under a
fair evaluation of Cogent’s final proposal under this subfactor,
that Cogent’s proposal could be found acceptable. If Cogent’s
proposal were found acceptable, the agency then would be
required to perform a price/technical tradeoff to determine
whether Cogent’s lower proposed price reflected the best value
to the government. (Cogent
Systems, Inc., B-295990.4; B-295990.5, October 6, 2005) (pdf)
Med Optical also asserts that the agency’s evaluation of
its proposal, in the areas of personnel qualifications and
demonstrated capability, was unreasonable. We need not address
these issues since the record shows that the protester was not
prejudiced by any alleged errors in these areas. Our Office will
not sustain a protest unless the protester demonstrates a
reasonable possibility that it was prejudiced by the agency’s
actions, that is, unless the protester demonstrates that, but
for the agency’s actions, it would have had a substantial chance
of receiving the award. McDonald-Bradley, B-290126, Feb. 8,
1996, 96-1 CPD 54 at 3; see Statistica, Inc. v. Christopher, 102
F.3d 1577, 1581 (Fed. Cir. 1996). Here, even if Med Optical had
received perfect scores in both areas where it challenges the
agency’s evaluation, its proposal would still be lower rated
technically and substantially higher priced than the awardee’s.
Accordingly, Med Optical would not be in line for award even if
it prevailed in its challenge to the evaluation of its proposal.
Marwais Steel Co., B‑254242.2; B-254242.3, May 3, 1994, 94-1 CPD
291 at 7. (Med Optical,
B-296231.2; B-296231.3, September 7, 2005) (pdf)
Here, we agree with DOE that the record establishes that
even if RCS were correct in its assertions, there was no
possible prejudice to the protester. We first note that RCS has
not protested the evaluation of LATA/Parallax's proposal or the
evaluation of its own proposal under the key personnel
evaluation criterion, and has abandoned its protest concerning
the evaluation under the experience and past performance
evaluation criteria. With regard to the remainder of RCS's
protest, the record reflects that the agency downgraded the
protester's proposal under the technical approach, integration
and schedule, and project and risk management criteria because
of the agency's determination that the protester's proposed
approach posed certain risks. However, even if RCS had received
the maximum score under each of these criteria, its overall
score would have increased to only 835 points, which is still
lower then the awardee's proposal's technical score of 860
points. [4] Given this, the fact that the protester's evaluated
cost was47 million higher than the awardee's, and that the
protester has made no claim that it would have been able to
reduce its proposed costs, we fail to see how the protester was
prejudiced by the alleged errors in the agency's evaluation, or
how the protester would have a reasonable possibility for award
if the solicitation had been amended and the protester given an
opportunity to submit a proposal with a different technical
approach "that would have complied" with what the protester
argues was "the specified design." See EBA Ernest Bland Assoc. ,
B-270496, Mar. 13, 1996, 96-1 CPD 148 at 6. (Restoration
and Closure Services, LLC, B-295663.6; B-295663.12, April
18, 2005) (pdf)
In essence, UVC was already competing with an understanding that
a schedule as long as the 360-day schedule that UVC proposed
would be acceptable; therefore, UVC was not competitively
prejudiced by the agency's acceptance of LS's lower-priced
proposal and a delivery schedule of 279 days, which was still
shorter than UVC's proposed schedule. Our Office will not
sustain a protest unless the protester demonstrates a reasonable
possibility that it was prejudiced by the agency's actions; that
is, unless the protester demonstrates that, but for the agency's
actions, it would have had a substantial chance of receiving the
award. McDonald Bradley , B-270126, Feb. 8, 1996, 96-1 CPD 54 at
3; see Statistica, Inc. v. Christopher , 102 F.3d 1577, 1581
(Fed. Cir. 1996). Although UVC argues that allowing LS to have a
longer schedule amounts to unequal treatment, UVC has failed to
demonstrate competitive prejudice with respect to this ground of
protest. (United Valve Company,
B-295879, April 25, 2005) (pdf)
It is not improper for an agency to accept an expired offer
without reopening negotiations where acceptance is not
prejudicial to the competitive system. Krug Life Scis., Inc. ,
B-258669.2, Feb. 22, 1995, 95-1 CPD 111 at 4; The Fletcher
Constr. Co., Ltd. , B-248977, Oct. 15, 1992, 92-2 CPD 246 at 6.
Even where, as here, the acceptance period has expired on all
offers, an agency may allow the successful offeror to waive the
expiration of its proposal acceptance period without reopening
negotiations and make award on the basis of the offer as
submitted. The Fletcher Constr. Co., Ltd. , supra . Here,
although the acceptance of Gentex's expired offer permitted
Gentex to waive the expiration of the offer, because no changes
were made to Gentex's proposal, this waiver did not prejudice
the competitive system or provide Gentex with an unfair
competitive advantage. Although Scot asserts that it can now
provide a lower price to the agency, the agency was not required
to reopen the competition when proposals expired to allow the
offerors to revise their proposals. See BioGenesis Pac., Inc. ,
B-283738, Dec. 14, 1999, 99-2 CPD 109 at 6 (agency not required
to consider protester's revised proposal submitted after
proposals expired but could make award based on unchanged
expired proposals). (Scot, Inc.,
B-295569; B-295569.2, March 10, 2005) (pdf)
In short, we agree with SBA that it erred in considering UEA for
a Certificate of Competency (COC) because the COC process is not
applicable to noncompetitive 8(a) acquisitions. SBA Report at 2;
SBA Supplemental Report at 1-2. Although SBA failed to follow
applicable regulations once CNCS determined that UEA was not
responsible and referred the matter to SBA, we fail to see, and
UEA has not explained, how it was prejudiced by this error. That
is, the matter of UEA's responsibility was considered by SBA as
part of its COC process, with SBA determining not to issue a COC
to UEA. As such, it is clear from the record that SBA ultimately
agreed with CNCS's determination regarding UEA's responsibility,
with the end result remaining the same--CNCS does not contract
with SBA for performance of the services by UEA. In short,
whether the matter of UEA's responsibility was considered by SBA
through the process provided for by the regulations that
contemplates a determination as to whether SBA agrees with the
procuring agency's nonresponsibility determination, or whether
the matter of UEA's responsibility was considered by SBA through
the COC process, nothing in the record indicates that the
process or result would have differed in a manner that would
have favored UEA--SBA considered the matter, and concluded that
it did not disagree with CNCS's nonresponsibility determination.
Thus, it is apparent that SBA would not have appealed the CNCS
determination not to contract with UEA under the 8(a) program,
which was the only appropriate action under applicable
regulations that could be taken to contest the procuring
agency's determination here. (United
Enterprise & Associates, B-295742, April 4, 2005) (pdf)
In addressing organizational conflicts of interest, our Office
has held that, where the record establishes that a conflict
exists, we will presume that the protester was prejudiced,
unless the record establishes the absence of prejudice. See The
Jones/Hill Joint Venture , B-286194.4 et al. , Dec. 5, 2001,
2001 CPD 194; TDF Corp. , B-288392, B288392.2, Oct. 23, 2001,
2001 CPD 178. Similarly, where, as here, the record establishes
that a procurement official was biased in favor of one offeror,
and was a significant participant in agency activities that
culminated in the decisions forming the basis for protest, we
believe that the need to maintain the integrity of the
procurement process requires that we sustain the protest unless
there is compelling evidence that the protester was not
prejudiced. See Department of the Air Force--Request for Recon.
, B-234060, B234060.2, Sept. 12, 1989, 89-2 CPD 228. As
discussed below, the agency has failed to provide compelling
evidence that Druyun's bias in favor of Boeing did not influence
the various decisions leading to the award of the SDD contract
to Boeing. (Lockheed Martin
Corporation, B-295402, February 18, 2005) (pdf)
We will not sustain a protest absent a showing of competitive
prejudice, that is, unless the protester demonstrates that, but
for the agency's actions, it would have a substantial chance of
receiving award. McDonald-Bradley , B-270126, Feb. 8, 1996, 96-1
CPD 54 at 3; see Statistica, Inc. v. Christopher , 102 F.3d
1577, 1581 (Fed. Cir. 1996). Here, CourtSmart has not stated or
shown that it could or would have modified its quotation had it
known of the agency's interpretation of the "fieldtested"
requirement. Although CourtSmart argues that it was prejudiced
because it was not given an opportunity to submit a revised
quotation, [7] it does not state that the revisions it sought to
make addressed the "field-tested" requirement. To establish
prejudice in circumstances such as here, the protester must show
that it would have submitted a different quotation that would
have had a reasonable possibility for award had it known of the
agency's interpretation of this provision. See Geo-Seis
Helicopters, Inc. , B-294543, Nov. 22, 2004, 2004 CPD ___ at
3-4; Brown & Root, Inc. and Perini Corp., a joint venture ,
B270505.2, B270505.3, Sept. 12, 1996, 962 CPD 143 at 10-11. (CourtSmart
Digital Systems, Inc., B-292995.8, December 9, 2004) (pdf)
With
regard to AVCARDs protest of the evaluation and source selection
decision, our Office will not sustain a protest unless the
protester demonstrates a reasonable possibility of prejudice,
that is, unless the protester demonstrates that, but for the
agencys actions, it would have had a substantial chance of
receiving the award. McDonald-Bradley , B-270126, Feb. 8, 1996,
96-1 CPD 54 at 3. Here, the agency rated AVCARDs proposal lower
than MSCs under all of the non-price evaluation factors. Given
that AVCARDs proposal was significantly higher priced than MSCs,
in order to prevail in its protest, AVCARD would have to
demonstrate that the agency should have rated AVCARDs proposal
higher than MSCs proposal in at least one of the non-price
evaluation areas. Based on our review of the record, AVCARD
cannot demonstrate this, and therefore cannot establish the
requisite prejudice. (AVCARD,
B-293775.2, December 30, 2004) (pdf)
SWR asserts that the agency improperly failed to take into
account the relative weights of the evaluation factors in
scoring the proposals. The agency concedes that it arrived at
total evaluation scores for the proposals by averaging the
factor and subfactor scores without taking into account the
weights of the factors and subfactors. However, there is no
basis for finding that correctly weighted scoring would have had
any significant impact on the award decision. For example, the
agency demonstrates in its report that under one reasonable
weighting scheme the protester's total score would have
increased from 77 to 78.2 points, while the awardee's total
score would have increased from 94 to 94.6. AR, Tab 23, at 1-2.
SWR questions the weighting scheme the agency uses, but does not
identify any other scheme that would significantly change the
scoring to SWR's advantage. Indeed, since Demosthenes's proposal
was scored significantly higher than SWR's under every
individual evaluation factor and subfactor, it is reasonable to
conclude that its rating would remain significantly higher than
the protester's under any rational scheme. We conclude that SWR
has failed to show that it was competitively prejudiced by the
agency's error; our Office will not sustain a protest absent a
showing of such prejudice. See McDonald-Bradley , B270126, Feb.
8, 1996, 96-1 CPD 54 at 3; see Statistica, Inc. v. Christopher ,
102 F.3d 1577, 1581 (Fed. Cir. 1996). (SWR,
Inc., B-294835; B-294835.2, December 20, 2004) (pdf)
Although we recognize that it is the agency's obligation to
ensure that prospective contractors are registered in the CCR
database before award, see FAR 4.1102(a), Kloppenburg has failed
to establish that it was prejudiced by the award to Alutiiq
before the firm's Chesapeake office was registered. Competitive
prejudice is necessary before we will sustain a protest; where
the record does not demonstrate that the protester would have
had a reasonable chance of receiving award but for the agency's
actions, we will not sustain a protest, even if deficiencies in
the procurement process are found. McDonald-Bradley , B-270126,
Feb. 8, 1996, 96-1 CPD 54 at 3; see Statistica, Inc. v.
Christopher , 102 F.3d 1577, 1581 (Fed. Cir. 1996). Here, DoDEA
made award to Alutiiq only after confirming that Alutiiq's
Chesapeake office would promptly register in the CCR database,
and Alutiiq did so. Although the agency should have awaited the
registration of Alutiiq's Chesapeake office in the CCR database
before making award, Kloppenburg has failed to establish that it
was prejudiced by this error. See Graves Constr., Inc. ,
B-294032, June 29, 2004, 2004 CPD 135 at 3. (Kloppenburg
Enterprises, Inc., B-294709, December 10, 2004) (pdf)
Cross Match asserts that incorporating the noncompeted items at
the quoted prices into Identix's BPA was inconsistent with the
RFQ requirement that the prices for these items be equal to or
lower than the prices for the evaluated items. We agree. DHS
concedes that Identix's quoted pricing for some of the
noncompeted items from Identix's GSA schedule exceeded the
pricing for the evaluated items, but asserts that this was not a
violation because the noncompeted item pricing did not need to
meet the "equal or less" requirement until after the negotiation
of pricing, which had not yet occurred, and because no orders
had been issued. DHS Comments, June 8, 2004, at1819; DHS
Comments, June 15, 2004, at 2. However, Identix's quotation was
noncompliant with that pricing restriction when the BPA was
awarded to Identix on September 30. While DHS may have intended
subsequently to modify the BPA to remove the improper pricing,
this does not alter the fact that the BPA as awarded included
noncompliant pricing. As a result, the issuance of the BPA was
inconsistent with the basis upon which quotations were issued
and thus improper. It is generally improper for an agency to
solicit quotations on one basis and then make award on a
materially different basis. See Cellular One , B-250854, Feb.
23, 1993, 93-1 CPD 169 at 4; Ann Riley & Assocs., Ltd. ,
B241309.2, Feb. 8, 1991, 91-1 CPD 142 at4. This is the general
rule, and it is a fundamental one in our federal procurement
system, but it may be waived if competitors are not prejudiced
thereby. See Cellular One , supra ; Ann Riley & Assocs., Ltd. ,
supra . Similarly, our Office will not sustain a protest unless
there is a reasonable possibility of prejudice, that is, unless
the protester demonstrates that, but for the agency's improper
actions, it would have had a substantial chance of receiving
award. McDonald-Bradley , B-270126, Feb. 8, 1996, 96-1 CPD 54 at
3; see Statistica, Inc. v. Christopher , 102 F. 3d 1577, 1581
(Fed. Cir. 1996). Cross Match argues that it was prejudiced
because, by quoting pricing for the noncompeted items from
Identix's GSA schedule that was higher than permitted by
section2.1, Identix was in a position to gain an improper
advantage by shifting its costs to the unevaluated pricing and
reducing its evaluated pricing. (Cross
Match Technologies, Inc., B-293024.3; B-293024.4, June 25,
2004) (pdf)
The parties agree that, during discussions, the protester
suggested the possibility of savings through the use of smaller
concrete blocks. The agency considered this suggestion and
determined that it could be acceptable. It then held subsequent
discussions in which the agency concedes that the "CO
[contracting officer] apparently raised the block size issue
with the other offerors as part of the discussions seeking cost
savings in the precast concrete portion of the Project."
Memorandum of Law at 302. The protester contends that the use of
the smaller sized block was one of unique innovation that should
not have been disclosed to other offerors during discussions.
The agency contends that use of the small block size involved a
change in the specifications that the agency was required to
communicate to the other competitors in order to uphold fair
competition. It is not necessary to resolve this dispute,
however; if the protester is correct, it has nonetheless failed
to demonstrate competitive prejudice. Even assuming that the
disclosure were improper, the agency argues that the protester
suffered no prejudice because both the protester's initial and
final proposals are based on using the concrete block sizes
described in the RFP, not the smaller block sizes that the
protester mentioned during discussions. Memorandum of Law at
305-06. The agency also submits that the awardee, similarly, did
not propose the use of smaller concrete blocks in either its
original or revised proposals. Id. at 305. Thus the agency's
actions in disclosing to other competitors the possibility of
cost savings through the use of smaller concrete blocks had no
effect on the protester's chance of receiving the award; had no
disclosure occurred, the protester still would not have received
the award. (DuRette Construction
Company, Inc., B-294379, September 15, 2004) (pdf)
Cross Match asserts that incorporating the noncompeted items at
the quoted prices into Identix's BPA was inconsistent with the
RFQ requirement that the prices for these items be equal to or
lower than the prices for the evaluated items. We agree. DHS
concedes that Identix's quoted pricing for some of the
noncompeted items from Identix's GSA schedule exceeded the
pricing for the evaluated items, but asserts that this was not a
violation because the noncompeted item pricing did not need to
meet the "equal or less" requirement until after the negotiation
of pricing, which had not yet occurred, and because no orders
had been issued. DHS Comments, June 8, 2004, at1819; DHS
Comments, June 15, 2004, at 2. However, Identix's quotation was
noncompliant with that pricing restriction when the BPA was
awarded to Identix on September 30. While DHS may have intended
subsequently to modify the BPA to remove the improper pricing,
this does not alter the fact that the BPA as awarded included
noncompliant pricing. As a result, the issuance of the BPA was
inconsistent with the basis upon which quotations were issued
and thus improper. It is generally improper for an agency to
solicit quotations on one basis and then make award on a
materially different basis. See Cellular One , B-250854, Feb.
23, 1993, 93-1 CPD 169 at 4; Ann Riley & Assocs., Ltd. ,
B241309.2, Feb. 8, 1991, 91-1 CPD 142 at4. This is the general
rule, and it is a fundamental one in our federal procurement
system, but it may be waived if competitors are not prejudiced
thereby. See Cellular One , supra ; Ann Riley & Assocs., Ltd. ,
supra . Similarly, our Office will not sustain a protest unless
there is a reasonable possibility of prejudice, that is, unless
the protester demonstrates that, but for the agency's improper
actions, it would have had a substantial chance of receiving
award. McDonald-Bradley , B-270126, Feb. 8, 1996, 96-1 CPD 54 at
3; see Statistica, Inc. v. Christopher , 102 F. 3d 1577, 1581
(Fed. Cir. 1996). Cross Match argues that it was prejudiced
because, by quoting pricing for the noncompeted items from
Identix's GSA schedule that was higher than permitted by
section2.1, Identix was in a position to gain an improper
advantage by shifting its costs to the unevaluated pricing and
reducing its evaluated pricing. We find no reasonable
possibility of prejudice to Cross Match. (Cross
Match Technologies, Inc., B-293024.3; B-293024.4, June 25,
2004) (pdf)
Where a proposal deviates from a specification by a negligible
amount, the agency may waive the requirement, so long as it did
not prejudice other vendors. Gulf Copper Ship Repair, Inc.,
B-292431, Aug. 27, 2003, 2003 CPD ¶ 155 at 4 (deviation of 1
inch water depth specification properly waived by agency);
Magnaflux Corp., B-211914, Dec. 20, 1983, 84-1 CPD ¶ 4 at 3-4
(agency permitted to waive deviation from specification which
was minor and did not result in prejudice); Champion Road Mach.
Int’l Corp., B-200678, July 13, 1981, 81-2 CPD ¶ 27 at 4
(deviation of two horsepower is minor and should have been
waived by agency where price, quantity, quality, and delivery
were not affected). In our view, since the approximately
one-half mile deviation from the 25-mile requirement appears
minor on its face and, according to SSA, did not diminish the
purpose of the restriction, it could reasonably be viewed by SSA
as negligible. The deviation therefore was waivable, so long as
First Federal, the only other vendor in the competition, was not
prejudiced. There is no evidence of competitive prejudice. In
this regard, while First Federal asserts that the waiver gave
ISC an “unfair competitive advantage,” (Protest at 9), it does
not show how it would have altered its proposal to improve its
competitive standing had it been given an opportunity to respond
to the relaxed requirement. See Copper Ship Repair, Inc., supra.
For example, it does not assert that knowledge of the relaxation
would have affected its price or the location of its proposed
facility. Given the absence of any evidence of prejudice to
First Federal, we conclude that the agency had a defensible
legal position and, thus, that the protest was not clearly
meritorious. It follows that there is no basis to recommend
reimbursement of protest costs in this case. (First
Federal Corporation--Costs, B-293373.2, April 21, 2004) (pdf)
Contracting agencies have broad discretion to take corrective
action where they determine that such action is necessary to
ensure fair and impartial competition. RS Info. Sys., Inc.,
B-287185.2, B-287185.3, May 16, 2001, 2001 CPD ¶ 98 at 4. Where
the corrective action taken by an agency is otherwise
unobjectionable, a request for revised price proposals is not
improper merely because the awardee’s price has been exposed.
Strand Hunt Constr., Inc., B-292415, Sept. 9, 2003, 2003 CPD ¶
167 at 6. We have recognized a limited exception to that rule
where the record establishes that there was no impropriety in
the original evaluation and award, or that an actual impropriety
did not result in any prejudice to offerors, reopening the
competition after prices have been disclosed does not provide
any benefit to the procurement
system that would justify compromising the offerors’ competitive
positions. Hawaii Int’l Movers, Inc., B‑248131, Aug. 3, 1992,
92-2 CPD ¶ 67 at 6, recon. denied, Gunn Van Lines; Dept. of the
Navy--Recon., B‑248131.2, B‑248131.4, Nov. 10, 1992, 92-2 CPD ¶
336. Here, while the agency correctly determined that there was
a deficiency in the RFP, there is nothing in the record to
establish, and the agency has not shown, a reasonable
possibility that any offeror was prejudiced by the deficiency.
In short, the record does not establish that the defective
solicitation resulted in the reasonable possibility of prejudice
to any of the offerors. Thus, given that SCG’s competitive
position has been compromised by disclosure of its price, there
is no benefit to the procurement system that would justify
reopening the competition. Hawaii Int’l Movers, Inc., supra.
Accordingly, we sustain the protest. By letter of today to the
Secretary of Homeland Security, we are recommending that SCG’s
award be reinstated. We also recommend that the agency reimburse
SCG its costs of filing and pursuing the protest, including
reasonable attorneys’ fees. 4 C.F.R. § 21.8(d)(1) (2003). SCG’s
certified claim for costs, detailing the time spent and the
costs incurred, must be submitted to the agency within 60 days
of receiving of our decision. 4 C.F.R. § 21.8(f)(1). (Security
Consultants Group, Inc., B-293344.2, March 19, 2004) (pdf)
Nowhere in its protest submissions does Frasca allege that the
“bundled” requirements precluded it from having a reasonable
chance for award. To the contrary, it identified in its response
to the “sources sought” notice and in its past performance
proposal two firms that it affirmatively stated it would be
teaming with to provide the training portion of the work, and
provided past performance information concerning one of these
firms, never suggesting to the Navy that the teaming
arrangements had not been finalized or that bundling was
impeding its ability to compete. Although Frasca now asserts
that the teaming arrangements with these firms “did not come to
final fruition,” Frasca does not contend that the discussions
failed due to the bundling restrictions. Protester's Comments at
6. Rather, it complains only that it did not have sufficient
time to submit a proposal when it was provided another
opportunity to compete under the amended RFP, because Frasca had
discontinued discussions with its potential teaming partners
when its past performance proposal was rejected in October as
untimely, and the Navy had established a short deadline for
proposal submissions. Thus, the record shows that to the extent
Frasca was unable to compete, it was due to the breakdown of
teaming discussions caused by Frasca's untimely proposal
submission, not by bundling. (Frasca
International, Inc., B-293299, February 6, 2004) (pdf)
In this instance, while the protester argues that the
bundling would adversely affect small business firms, many of
whom are currently performing work included in the bundled
procurement, the protester has failed to demonstrate that the
consolidation significantly inhibits or precludes its ability to
compete. In fact, FSI claimed that it can perform the entirety
of the bundled requirements. In this regard, FSI stated that it
responded to the “sources sought” notice “with full confidence
that we could perform all aspects of the contract and more” and
that “FSI is very qualified for this BPA,” and the record shows
that FSI, through SBA, attempted to noncompetitively obtain this
work under the 8(a) program. Protest at 8; Protester's Comments
at 8. We conclude, therefore, that the protester has not made a
showing of competitive prejudice as a result of the bundling of
the agency's office supply requirements. (Future
Solutions, Inc., B-293194, February 11, 2004) (pdf)
D.N. also complains that the evaluation of contractor
expertise was unequal. Here, D.N. argues that neither offeror
had all of the required certifications, which were necessary for
a blue rating, and thus Daston should only have received a
purple rating like D.N.[8] Although we agree with D.N. in this
regard, we see no prejudice to D.N. from this error. Daston was
still rated superior to D.N. in the two more important technical
factors, and was lower in price, so even if the contractor
expertise ratings were made equal, there is no reasonable basis
to conclude that D.N.’s proposal would have had a reasonable
probability of being selected for award. See J.A. Jones/Bell, A
Joint Venture, B-286458, B-286458.2, Dec. 27, 2000, 2001 CPD ¶
17 at 4 n.1.
D.N. also contends that the Army failed to raise during
discussions that the size of past projects was a concern in the
evaluation of past performance, or that its subcontractor’s past
performance under military contracts was limited to hardware
support. Although these issues were not specifically raised
during discussions, D.N. has not shown that it was prejudiced.
It does not argue that it would have, or could have, identified
contracts of a larger size, or that its subcontractor’s
references would have included other than contracts for hardware
support had these issues been raised, or that as a result of
discussions its proposal would have been found sufficiently
superior to Daston’s lower priced proposal to be selected for
award. Continental Serv. Co., B‑271754, B‑271754.2, July 30,
1996, 96-2 CPD ¶ 65 at 6. (D.N.
American, Inc., B-292557, September 25, 2003) (pdf)
Nevertheless, even if SPAWAR should not have accepted
Dell’s quotation as submitted and later permitted the firm to
“correct” it via modification of the BPA, there is no basis for
concluding that the agency’s actions prejudiced GTSI. In this
regard, our Office will not sustain a protest unless the
protester demonstrates a reasonable possibility of prejudice,
that is, unless the protester demonstrates that, but for the
agency’s actions, it would have had a substantial chance of
receiving the award. Parmatic Filter Corp., B-285288.3,
B-285288.4, Mar. 30, 2001, 2001 CPD ¶ 71 at 11; see Statistica,
Inc. v. Christopher, 102 F.3d 1577, 1581 (Fed. Cir. 1996). GTSI
has not shown, nor does the record otherwise indicate, that it
was prejudiced with respect to the monitor issue. The evaluated
price of GTSI’s quotation ($[DELETED]) already included the
price for the compliant monitors. Adjusting Dell’s price upward
(to $[DELETED]) to reflect the higher price (an additional
$[DELETED]) for the compliant Dell M992 19-inch and the Sony
GDM-FW900 24-inch monitors as indicated in Dell’s February 17
response, still leaves the award price lowest by a substantial
margin ($[DELETED]). Agency Memorandum to File, May 6, 2003, at
3. Further, even if SPAWAR had noted the ambiguity in Dell’s
quotation before award and had reopened discussions to resolve
it--which necessarily would have given GTSI the opportunity to
revise its price--there is no basis for concluding that it would
have lowered its price sufficiently to displace Dell as the
low-priced vendor. Given Dell’s advantage under the non-price
factors, we are unable to find that GTSI was prejudiced. (GTSI
Corp., B-292298; B-292298.2; B-292298.3, August 14, 2003) (pdf)
That said, where an agency determines that an item other
than the one specified in an RFQ will meet its needs, it
generally should amend the RFQ and reopen the competition.
U.S. Technology Corp., B-224372, Oct. 2, 1986, 86-2 CPD ¶
383 at 3. We will sustain a protest objecting to an
agency’s failure to amend an RFQ to clarify that products
other than a specified one will be considered only if the
protester establishes a reasonable possibility that it was
prejudiced by the agency’s failure to amend, however; that
is, where the protester offers some evidence that had it
known of the potential for competition, it would have
altered its quotation to its competitive advantage. See
Datastream Sys., Inc., B-291653, Jan. 24, 2003, 2003 CPD ¶
30 at 6. We have recognized the possibility of prejudice
where a protester that was the only vendor offering the
product specified in an RFQ alleges that it would have
lowered its price had it been aware of the potential for
competition, and where the vendor offering the specified
product alleges that it could have offered a different,
lower-priced, acceptable product had it been on notice
that the agency would consider equivalent items. U.S.
Technology Corp., supra, at 3. (Zarc
International, Inc., B-292708, October 3, 2003)
(pdf)
The protester has made a prima facie showing of
similarity between the work performed under the combat
arms range project and the project to be performed here,
which the Air Force has neither taken issue with nor
attempted to rebut. Even assuming that the agency
should have regarded the combat arms range project as
relevant and considered it in evaluating the protester's
past performance, however, we see no basis to conclude
that consideration of this contract would have resulted in
an increase in Wadsworth's past performance rating. In
this regard, prejudice is an essential element of a viable
protest, and we will sustain a protest only where a
reasonable possibility of prejudice is evident from the
record. Lithos Restoration, Ltd., B-247003.2, Apr. 22,
1992, 92-1 CPD ¶ 379 at 5-6. Here, Wadsworth's performance
on the missile alert facility project, which was over six
times greater in dollar value than the combat arms range
project, was rated as “at best” satisfactory. In addition,
only about a quarter of the value of the combat arms
contract was for work similar to the work to be
accomplished here, meaning that while the contract was
relevant, its relevance was limited. In light of these
factors, we see no reasonable possibility that the
contracting officer would have raised the protester's
overall past performance rating to very good based on its
performance on the latter project. (Wadsworth
Builders, Inc., B-291633, January 24, 2003) (txt
version)
The record here, which consists of, among other things,
the individual evaluator score sheets for the oral
presentations, does not contain any evidence that the
agency's evaluation of Innovative Management's oral
presentation was affected by Innovative Management's use
of copied transparencies rather than originals. For
example, while the record provides numerous statements
regarding the strengths and weaknesses of Innovative
Management's proposal and oral presentation, there is no
mention or any other indication that any of these
statements resulted from, or were somehow affected by,
Innovative Management's use of copied transparencies.
Accordingly, we fail to see how Innovative Management was
prejudiced by the agency's alleged error in not having
Innovative Management's original transparencies available
for use during its oral presentation. (Innovative
Management, Inc., B-291375, November 20, 2002) (txt
version)
We recognize that it could be argued that the failure to
exclude a firm with an alleged conflict of interest from
a competition is a defect in a solicitation that should
be challenged prior to the submission of proposals or
quotations. See 4 C.F.R. § 21.2(a)(1)
(2002). Solicitation provisions, however, are not
generally the vehicle for excluding firms with a
conflict of interest from competing for award; rather,
conflicts are generally handled on a case-by-case basis
without public notice through the solicitation.
Moreover, treating protests such as this one as
premature may avoid unnecessary litigation, since the
allegedly conflicted firm may not be the eventual
awardee, either because it loses the competition or
because the agency ultimately concludes that the firm
has an impermissible conflict of interest. See
Saturn Indus.--Recon., B-261954.4, July 19,
1996, 96-2 CPD ¶ 25 at 5. Unless the firm with
the alleged conflict of interest is actually selected
for award, the protester has not suffered any
competitive prejudice; we will not sustain a protest
absent a showing of such prejudice. McDonald-Bradley,
B-270126, Feb. 8, 1996, 96-1 CPD ¶ 54 at 3; see Statistica,
Inc. v. Christopher, 102 F.3 d 1577, 1581 (Fed. Cir.
1996). (REEP,
Inc., B-290688, September 20, 2002)
Competitive prejudice is a prerequisite to
sustaining a protest. Where the record does not demonstrate that, but for
the agency's actions, the protester would have had a reasonable chance of
receiving the award, our Office will not sustain a protest, even if a deficiency
in the procurement is found. McDonald-Bradley, B-270126, Feb. 8,
1996, 96-1 CPD ¶ 54 at 3; see Statistica, Inc. v. Christopher,
102 F.3d 1577, 1581 (Fed. Cir. 1996). Based on our review of the record,
we find that the denial of the Blue Team's request to use a decommissioned DD
963 destroyer as an at-sea test platform did not result in competitive prejudice
to the protester so as to warrant sustaining its protest in this regard. (Bath Iron Works Corporation, B-290470; B-290470.2, August 19, 2002)
The record shows, as discussed below, that the agency’s actual needs were for three separate contractors to perform the three solicited sales. If the RFP did not sufficiently indicate that three awards to three separate contractors was contemplated, it would be defective, in that multiple awards to the same contractor under the RFP would not satisfy the agency’s actual need to limit each awardee to a single task order. However, under an amended RFP with this defect eliminated, METEC could not receive any additional task orders beyond the one that it already has. Accordingly, the protested awards under this RFP did not prejudice METEC. See Plum Run, B-256869, July 21, 1994, 94-2 CPD ¶ 38 at 6-7 (protester was not prejudiced by an award under a defective solicitation where the award would remain the same if the agency amended the solicitation and the protester revised its proposal); see also Recon Optical, Inc.; Lockheed-Martin Corp., Fairchild Sys., B-272239, B-272239.2, July 17, 1996, 96-2 CPD ¶ 21 at 3-4
(protesters do not have the direct economic interest necessary to protest awards to each other where the
solicitation provides for multiple awards, the protesters received the fullest awards
possible, and it would not be able to obtain an additional stake in the procurement,
even if their protests were sustained). (The
METEC Group, B-290073; B-290073.2, May 20, 2002 (pdf))
SOS is
correct that, where the relative weights of subfactors
are not disclosed in the RFP, the subfactors are
understood to be of equal importance to each other. North-East
Imaging, Inc., B-256281, June 1, 1994, 94-1 CPD
¶ 332 at 2. However, competitive prejudice is an
essential element of every viable protest. Geonex
Corp., B-274390.2, June 13, 1997, 97-1 CPD ¶ 225 at
4. Our Office will not sustain a protest unless the
protester demonstrates a reasonable possibility that it
was prejudiced by the agency's actions, that is, unless
the protester demonstrates that, but for the agency's
actions, it would have had a substantial chance of
receiving the award. McDonald-Bradley, B-270126,
Feb. 8, 1996, 96-1 CPD ¶ 54 at 3; see Statistica,
Inc. v. Christopher, 102 F.3d. 1577, 1581 (Fed. Cir.
1996). (SOS
Interpreting, Ltd., B-287477.2, May 16, 2001)
Protester, a small
disadvantaged business (SDB), was not prejudiced by
agency's failure to apply 10-percent SDB evaluation
preference provided for in solicitation, where (1)
awardee was SDB, against which the preference would not
apply in any case, and (2) there is no basis to conclude
that protester inflated its bid price in reliance on
application of preference. (Si-Nor,
Inc., B-286910, January 5, 2001)
We dismiss the protest
as to this allegation because there is no showing that
MCS was prejudiced by the consolidation of the
requirements. Competitive prejudice is an essential
element of every viable protest. Lithos Restoration
Ltd., B-247003.2, 92-1 CPD para. 379 at 5. Where the
record does not demonstrate that, but for the agency's
actions, the protester would have had a reasonable
chance of receiving the award, our Office will not
sustain a protest, even if a deficiency in the
procurement is found. McDonald-Bradley, B-270126, Feb.
8, 1996, 96-1 CPD para. 54 at 3; see Statistica, Inc. v.
Christopher, 102 F.3d 1577, 1581 (Fed. Cir. 1996). Here,
although MCS strenuously argues that the claimed
benefits of the agency's consolidated procurement
approach are illusory and/or do not warrant
consolidation, the protester has failed to demonstrate
that the consolidation significantly inhibits or
precludes its ability to compete. On the contrary, MCS
vigorously argues that the requirements do not differ
significantly in character from its current food service
contracts, and it maintains that it can perform the
consolidated requirement. (MCS
Management, Inc., B-285813; B-285882, October 11, 2000)
Turning to the
protester's specific argument, while solicitation
amendments generally must be issued in writing in order
to afford firms an opportunity to respond to changed
requirements, we will sustain a protest based on an
agency's failure to issue a written amendment only where
the failure prejudiced the protester. First St. Invs.
Ltd. Partnership, B-270894.2, B-270894.3, Aug. 15, 1996,
96-2 CPD para. 69 at 7-8. There was no prejudice here.
(Aqua-Flo,
Inc., B-283944, December 30, 1999)
Although contracting
agency may have improperly performed a price/technical
tradeoff between proposals in violation of the
solicitation's evaluation scheme, the protester was not
prejudiced by the improper tradeoff decision where the
record shows that agency reasonably concluded that
protester's proposal was technically unacceptable.
(SBC
Federal Systems, B-283693; B-283693.2, December 27,
1999)
Here, we need not
determine whether the exchanges with MTI constituted
discussions--and thus whether the agency should have
established a competitive range and conducted
discussions with other offerors in it--because it is
clear from the record that CMCI was not prejudiced by
the agency's failure to hold discussions with it. In
this regard, competitive prejudice is an essential
element of every viable protest, Lithos Restoration,
Ltd., B-247003.2, Apr. 22, 1992, 92-1 CPD para. 379 at
5, and we will not sustain a protest for failure to hold
discussions where it is apparent from the record that
the protester could not have improved its proposal
enough through discussions to be in contention for
award. Schleicher Community Corrections Center, Inc.,
B-270499.3 et al., Apr. 18, 1996, 96-1 CPD para. 192 at
6, recon. denied, B-270499.6, Aug. 15, 1996, 96-2 CPD
para. 68; Strategic Analysis, Inc., supra, at 5;
Northrop Worldwide Aircraft Servs., Inc., B-262181, Oct.
27, 1995, 95-2 CPD para. 196 at 8-9, recon. denied,
B-262181.3, June 4, 1996, 96-1 CPD para. 263. Such is
the case here. (Charleston
Marine Containers, Inc., B-283393, November 8, 1999)
The determination that
the scoring of prices here was not rational does not end
our inquiry. Our Office will not sustain a protest
unless there is a reasonable possibility of prejudice,
that is, unless the protester demonstrates that, but for
the agency's actions, it would have had a substantial
chance of receiving the award. McDonald-Bradley,
B-270126, Feb. 8, 1996, 96-1 CPD para. 54 at 3; see
Statistica, Inc. v. Christopher, 102 F.3d 1577, 1581
(Fed. Cir. 1996). Because our decision here turns on
prejudice, we set forth below a lengthy analysis of how
prices should have been scored to accurately reflect the
relative cost of these proposals to the government, as
called for in the RFP. Based on our review, we conclude
that MDI was not prejudiced by the agency's improper
scoring of the price proposals. (Medical
Development International, B-281484.2, March 29,
1999)
|
|
Comptroller
General - Listing of Decisions |
For
the Government |
For
the Protester |
New
DRS Network & Imaging Systems,
LLC B-413409, B-413409.2: Oct 25, 2016 |
Cogent Systems, Inc., B-295990.4;
B-295990.5, October 6, 2005 (pdf) |
Odyssey
Marketing Group, Inc. B-412695,B-412695.2: Apr 21, 2016
(pdf) |
Lockheed Martin Corporation,
B-295402, February 18, 2005 (pdf) |
edCount, LLC--Protest and Costs,
B-407556.3, B-407556.4, B-407556.5, B-407556.6, Aug 15, 2013
(pdf) |
Security Consultants Group, Inc.,
B-293344.2, March 19, 2004 (pdf) |
BC Peabody Construction Services, Inc.,
B-408023, May 10, 2013 (pdf) |
Wilson Beret Company, B-289685, April 9, 2002 (pdf) |
Smith Enterprise, Inc., B-407529,
B-407529.2, B-407529.3, Dec 28, 2012 (pdf) |
|
Calnet, Inc., B-402558.2;
B-402558.5; B-402558.7, June 3, 2010 (pdf) |
|
Truetech, Inc., B-402536.2, June
2, 2010 (pdf) |
|
Alsalam Aircraft Company,
B-401298.4, January 8, 2010 (pdf) |
|
Alliance Technical Services, Inc.,
B-311329; B-311329.2, May 30, 2008 (pdf) |
|
Clark E. Myatt, Agency Tender
Official, B-311234.2, April 15, 2008 (pdf) |
|
PM Services Company, B-310762,
February 4, 2008 (pdf) |
|
American Cybernetic Corporation,
B-310551.2, February 1, 2008 (pdf) |
|
Language Services Associates, Inc.,
B-297392, January 17, 2006 (pdf) |
|
SERAPH Inc., B-297452, January 12,
2006 (pdf) |
|
Information Ventures, Inc.,
B-297225, December 1, 2005 (pdf) |
|
Med Optical, B-296231.2;
B-296231.3, September 7, 2005 (pdf) |
|
Restoration and Closure
Services, LLC, B-295663.6; B-295663.12, April 18, 2005 (pdf) |
|
United Valve Company, B-295879,
April 25, 2005 (pdf) |
|
Scot, Inc., B-295569; B-295569.2,
March 10, 2005 (pdf) |
|
United Enterprise & Associates,
B-295742, April 4, 2005 (pdf) |
|
CourtSmart Digital Systems, Inc.,
B-292995.8, December 9, 2004 (pdf) |
|
AVCARD, B-293775.2, December 30,
2004 (pdf) |
|
SWR, Inc., B-294835; B-294835.2,
December 20, 2004 (pdf) |
|
Kloppenburg Enterprises, Inc.,
B-294709, December 10, 2004 (pdf) |
|
Cross Match Technologies, Inc.,
B-293024.3; B-293024.4, June 25, 2004 (pdf) |
|
DuRette Construction
Company, Inc., B-294379, September 15, 2004 (pdf) |
|
Cross Match Technologies, Inc.,
B-293024.3; B-293024.4, June 25, 2004 |
|
First Federal Corporation--Costs,
B-293373.2, April 21, 2004 (pdf) |
|
Frasca International, Inc.,
B-293299, February 6, 2004 (pdf) |
|
Future Solutions, Inc.,
B-293194, February 11, 2004) (pdf) |
|
Aerotek Scientific LLC, B-293089,
January 23, 2004 (pdf) |
|
D.N. American, Inc.,
B-292557, September 25, 2003 (pdf) |
|
GTSI Corp., B-292298;
B-292298.2; B-292298.3, August 14, 2003) (pdf) |
|
Zarc
International, Inc., B-292708, October 3, 2003 (pdf) |
|
Enola-Caddell JV, B-292387.2;
B-292387.4, September 12, 2003 (pdf) |
|
M.K. Taylor, Jr.
Contractors, Inc., B-291730.2, April 23, 2003 (pdf) |
|
Wadsworth
Builders, Inc., B-291633, January 24, 2003 (txt
version) |
|
Datastream Systems, Inc., B-291653, January 24, 2003 (txt
version) |
|
Sabreliner Corporation, B-290515.4, November 20, 2002
(txt
version) |
|
Innovative Management, Inc., B-291375, November 20, 2002 (pdf)
(txt
version) |
|
Knightsbridge
Construction Corporation, B-291475.2, January 10, 2003 (pdf)
(txt
Version) |
|
REEP,
Inc., B-290688, September 20, 2002 |
|
Bath Iron Works Corporation, B-290470; B-290470.2, August 19, 2002 |
|
The
METEC Group, B-290073; B-290073.2, May 20, 2002 (pdf) |
|
4-D
Neuroimaging, B-286155.2; B-286155.3, October 10, 2001
(PDF
Version) |
|
McRae
Industries, Inc., B-287609.2, July 20, 2001 (PDF
Version) |
|
SOS
Interpreting, Ltd., B-287477.2, May 16, 2001 |
|
Myers
Investigative and Security Services, Inc., B-286971.2;
B-286971.3, April 2, 2001 (PDF
Version) |
|
The
Community Partnership LLC, B-286844, February 13, 2001
(PDF
Version) |
|
Si-Nor,
Inc., B-286910, January 5, 2001 (PDF
Version) |
|
Norvar
Health Services--Protest and Reconsideration, B-286253.2;
B-286253.3; B-286253.4, December 8, 2000 (PDF
Version) |
|
NMS
Management, Inc., B-286335, November 24, 2000 (PDF
Version) |
|
MCS
Management, Inc., B-285813; B-285882, October 11, 2000
(PDF
Version) |
|
Instrument
Control Service, Inc., B-285776, September 6, 2000 (PDF
Version) |
|
Johnson
Controls World Services, Inc., B-285144, July 6, 2000
(PDF
Version) |
|
NV
Services, B-284119.2, February 25, 2000 (PDF
Version) |
|
Aqua-Flo,
Inc., B-283944, December 30, 1999 (PDF
Version) |
|
SBC
Federal Systems, B-283693; B-283693.2, December 27,
1999 (PDF
Version) |
|
Bristol-Myers
Squibb Company, B-281681.12; B-281681.13, December 16, 1999
(PDF
Version) |
|
Charleston
Marine Containers, Inc., B-283393, November 8, 1999 (PDF
Version) |
|
West
Coast Unlimited, B-281070.2, August 18, 1999 (PDF
Version) |
|
Spectrofuge
Corporation of North Carolina, Inc.--Recon, B- 281030.3,
April 9, 1999 (PDF
Version) |
|
Medical
Development International, B-281484.2, March 29, 1999
(PDF
Version) |
|
U.
S. Court of Federal Claims - Key Excerpts |
Prejudice to [protester] MJLM
Before turning to the substance of MJLM’s challenges to the agency’s cost realism
analysis, the Court addresses whether—even assuming their merit—MJLM would be entitled to
relief. Thus, it is well-established that “[a] protester must show not simply a significant error in
the procurement process, but also that the error was prejudicial, if it is to prevail in a bid protest.”
Statistica, Inc. v. Christopher, 102 F.3d 1577, 1581 (Fed. Cir. 1996) (citing Data Gen. Corp. v.
Johnson, 78 F.3d 1556, 1562 (Fed. Cir. 1996)). In that regard, “[a] party has been prejudiced
when it can show that but for the error, it would have had a substantial chance of securing the
contract.” Labatt Food Serv., Inc. v. United States, 577 F.3d 1375, 1378 (Fed. Cir. 2009) (citing
Bannum, Inc., 404 F.3d at 1358); Galen Med. Assocs., 369 F.3d at 1331; Info. Tech., 316 F.3d at
1319.
Here—even assuming that MJLM was correct that the CO’s cost analysis was flawed—it
cannot meet its burden of showing prejudice. Thus, according to MJLM, if the CO had accepted
the cost evaluator’s analysis in its entirety, the result would have been to require an upward
adjustment in API’s price of some $1.6 million and in MJLM’s by $262,000. See Pl.’s Mot. at
44–45. In that case, MJLM’s proposed costs over a five-year period would have been $629,000
less than API’s (rather than $756,495 greater as the CO determined). Id.11 But the value of the contract over the five-year period was close to $50 million, and price was the least important
consideration in choosing the awardee under the RFP. AR Tab 6 at 178. The RFP, in fact,
provides that the adjectival ratings for the technical evaluation criteria, when combined, are to be
considered “significantly more important” than cost. Id.
Further, the CO’s award determination memorandum makes it clear that a small price
advantage in MJLM’s favor would not have changed the result because the agency had
determined that API’s proposal was “significantly stronger than MJLM’s.” Id. Tab 60 at 6710.
As CO Matz explained:
[T]he differences in Cost between the two offerors did not serve as a significant
discriminator in my decision. Both offerors proposed costs that were determined to
be fair, reasonable, and realistic. Even though API’s proposed cost was 1.5% lower
than the overall cost proposed by MJLM and 1% below the IGCE, I did not view
that as a significant factor in the evaluation here since this is a cost reimbursement
contract, so I viewed the two proposed costs as roughly equivalent, with API having
just a slight edge for this factor.
Id. at 6716. Indeed, CO Matz stated that even “if API’s costs had been adjusted to be higher than
MJLM’s probable cost, that would not have altered my best value determination.” Id. at 6715.
In short, even assuming that the agency erred by not adjusting API’s costs upward by as
much as $1.6 million, as MJLM urges it should have done, MJLM has not demonstrated that it
suffered prejudice. For that reason alone, MJLM’s arguments based on the agency’s cost realism
analysis are unavailing. (McConnell Jones
Lanier & Murphy, LLP v. U. S., No. 15-1351C, September 23,
2016)
GAO disagreed with the agency’s conclusion that the contracting
officer did not abuse her discretion. It found that “[a]lthough
an offeror has the burden of submitting an adequately written
proposal, and an agency may downgrade a proposal for the lack of
requested information, an agency may not ignore prior
performance information of which it is aware.” AR 24-1456; 2013
WL 1944164, at *4 (citing Consolidated Eng’g Servs., Inc.,
B-279565.2, .3, 99-1 CPD ¶ 75, 1998 WL 1045204, at *4 (Comp.
Gen. June 26, 1998)). Because the Corps’s contracting officer
was aware of Bauer’s experience from other proposals, including
especially that by Edens, she could not reasonably find Bauer’s
experience acceptable for Edens but unacceptable for BCPeabody.
Id. (“Here, the proposals of both Edens and BCPeabody included
[Bauer] as their respective cut-off wall construction
subcontractor, and it was not reasonable for the Corps to find
[Bauer’s] experience acceptable for Edens but unacceptable for
BCPeabody.”).
GAO nonetheless denied
BCPeabody’s protest, finding that it was not prejudiced by the
contracting officer’s error. AR 24-1457; 2013 WL 1944164, at *4.
BCPeabody had included with its briefing to GAO a project
information sheet completed by Bauer Foundations Canada, a
separate legal entity from Bauer. That affiliated entity was not
covered by Bauer’s letter of commitment to BCPeabody, and
therefore the protest was denied. AR 24-1457; 2013 WL 1944164,
at *5.
(pages deleted)
II. Prejudice
To succeed on the merits, a
bid protestor must show not only that there was an error in the
procurement process but also that it was prejudiced by the
error. See Data Gen. Corp. v. Johnson, 78 F.3d 1556, 1562 (Fed.
Cir. 1996). In this respect, a protestor must demonstrate that
there was a “substantial chance it would have received [the]
contract award, but for the alleged error in the procurement
process.” McAfee, Inc. v. United States, 111 Fed. Cl. 696, 712
(2013) (quoting Gentex Corp. v. United States, 58 Fed. Cl. 634,
653 (2003) (in turn citing Information Tech. & Applications, 316
F.3d at 1319)); see also Alfa Laval Separation, Inc. v. United
States, 175 F.3d 1365, 1367 (Fed. Cir. 1999). This inquiry into
“prejudice” is distinct from the inquiry into standing. While
both use the “substantial chance” doctrine, prejudice at the
jurisdictional threshold can be satisfied on the basis of the
plaintiff’s allegations, whereas prejudice on the merits can
only be satisfied by the effect of an agency decision adjudged
to be unlawful. See Linc Gov’t Servs., LLC v. United States, 96
Fed. Cl. 672, 696 (2010).
BCPeabody has demonstrated
that it was prejudiced by the contracting officer’s abuse of
discretion. If the contracting officer had acted reasonably in
light of the facts and circumstances at hand, BCPeabody would
have had a “substantial chance” of receiving the contract.
BCPeabody would have been a technically acceptable bidder
offering the lowest price by more than $1,000,000.
(sections deleted)
CONCLUSION
For the reasons stated,
BCPeabody’s motion for judgment on the administrative record is
GRANTED, as is BCPeabody’s Motion for Permanent Injunction, ECF
No. 47. The government’s and Edens’s motions for judgment on the
administrative record are accordingly DENIED.
The Corps’s award of the
contract to Edens is set aside, and the Corps is required to
restore BCPeabody to the competition and to reevaluate the
proposals that were submitted. The clerk is directed to
issue a final judgment in accord with this disposition.
Costs are awarded to plaintiff. (BCPeabody
Construction Services, Inc. v. U. S. and Edens Construction Co.,
Inc., No. 13-378C, September 25, 2013) (pdf)
II. Digitalis Was Not
Prejudiced by Any Errors in the Procurement.
Even assuming arguendo that Digitalis had standing to challenge
the
merits of the procurement, it would still be required to show
that any
procurement errors caused prejudice. Bannum, 404 F.3d at 1351.
Here,
Digitalis cannot show that any such errors were prejudicial.
Accordingly, we
cannot sustain its protest.
As a general matter, an agency procuring products or services is
obliged
to “obtain full and open competition through the use of
competitive procedures
in accord with the requirements of this chapter and the Federal
Acquisition
Regulation.” 10 U.S.C. § 2304(a)(1)(A). There are, however,
exceptions to
this requirement, such as when the goods or services are
available from only
one source and no other item will satisfy the agency’s needs.
Id. § 2304(c)(1).
Such procurements may be set aside if they lack a rational basis
or involved a
violation of a statute, regulation, or procedure. See Weeks, 575
F.3d at 1358;
Galen Med. Assocs., Inc. v. United States, 369 F.3d 1324, 1329
(Fed. Cir.
2004). Here, Digitalis challenges both the rational basis of
this procurement
and its compliance with various limitations placed on such
non-competitive
acquisitions.
Our review of the administrative record lends credence to a
number of
Digitalis’ allegations of hasty and shoddy contracting. As
previously noted,
however, even if a protestor proves there were procurement
errors, the protest
will be sustained only if the errors “significantly prejudiced”
the protestor. Bannum, 404 F.3d at 1353. This is a factual determination. Id. A
protestor
must show there was a “substantial chance” it would have
received the
contract but for the agency’s errors. Id. (citing Info. Tech.,
316 F.3d at 1319;
Alfa Laval Separation, Inc. v. United States, 175 F.3d 1365,
1367 (Fed. Cir.
1999)).
Plaintiff disputes the applicability of the prejudice
requirement, arguing
that a protestor is required to show prejudice only when
alleging a violation of
statute or regulation and not when challenging the rational
basis of the
procurement. Pl.’s Reply at 8 (citing Impresa Constuzioni Geom.
Domenico
Garufi v. United States, 238 F.3d 1324, 1332 (Fed. Cir. 2001)).
Digitalis’
reliance on Impresa, however, is misplaced. For one, Impresa
does not
explicitly support Digitalis’ interpretation but merely mentions
prejudice only
in the context of an alleged violation of statute. Without a
more explicit
statement, we will not take this as an implicit change in our
standard of review.
Second, Digitalis’ argument is rebutted by subsequent cases,
such as Bannum,
that affirm the requirement of prejudice regardless of whether
the error
involved the rational basis or a violation of statute or
regulation. See Bannum, 404 F.3d at 1351; Dyonyx, L.P. v. United
States, 83 Fed. Cl. 460, 466 (citing
Bannum, 404 F.3d at 1351) (“[I]f the government action lacked a
rational
basis, a factual inquiry must be conducted to determine whether
the protester
was prejudiced by the conduct.”). Finally, the Administrative
Procedures Act,
upon which our entire bid protest standard of review is founded,
mandates that
“due account shall be taken of the rule of prejudicial error.” 5
U.S.C. § 706.
Here, Digitalis makes multiple allegations of error, some of
which
appear to be well-founded. As already discussed, however, none
of these
errors, if rectified, would have put Digitalis in a position to
receive the
contract. Stated differently, we cannot say that but for these
errors, Digitalis
had a substantial chance at the contract. For example, Digitalis
argues that the
synopsis misidentified the object sought. The fact remains,
however, that
when Digitalis did eventually see the synopsis, it was
immediately spurred to
action. There was no confusion as to the thrust of the
procurement. Digitalis
also argues that the comment period was not reasonable, as
required by FAR
Part 5.203(b). We are sympathetic to the argument that five
days—two of
which were weekend days—and an eleventh-hour modification strain
the
bounds of reasonableness. The fact remains, however, that
Digitalis did not
notice the synopsis until more than three weeks later. Even if
the comment
period had been 20 days, it would not have changed the outcome
of the
procurement. The same is true for Digitalis’ allegations that
the agency
commenced negotiations prematurely in violation of FAR Part
6.303-1(a) and
that the agency violated 10 U.S.C. § 2304(f)(4)(A) by making a
sole-source
acquisition on the basis of a failure to plan ahead or the
expiration of funds.
In neither case were these errors prejudicial and thus are no
basis on which to
sustain Digitalis’ protest. (Digitalis
Education Solutions, Inc. fv. U. S. and Morris & Lee d/b/a
Science First, No. 10-855, February 11, 2011) (pdf)
2. Two Types of Prejudice
Analysis
Because it is central to a
plaintiff’s demonstration that it is an interested party under §
1491(b)(1), this threshold showing of “prejudice (or injury) is
a necessary element of standing.” Myers, 275 F.3d at 1370. As
such, prejudice is a threshold jurisdictional issue that the
Federal Circuit has stressed must be reached before addressing
the merits in a bid protest. ITAC, 316 F.3d at 1319; Myers, 275
F.3d at 1369–70; see Media Techs. Licensing, LLC v. Upper Deck
Co., 334 F.3d 1366, 1370 (Fed. Cir. 2003) (“Because standing is
jurisdictional, lack of standing precludes a ruling on the
merits.”). The lawfulness of the contested agency decisions is
thus wholly immaterial to this initial showing of prejudice. See
Whitmore v. Arkansas, 495 U.S. 149, 155 (1990) (“The threshold
inquiry into standing in no way depends on the merits of [a
plaintiff’s] contention that particular conduct is illegal.”);
Night Vision Corp. v. United States, 68 Fed. Cl. 368, 392 (2005)
(noting that this initial examination of prejudice “does not
include weighing facts and making substantive determinations on
the merits”). Rather, this showing turns entirely on the impact
that the alleged procurement errors had on a plaintiff’s
prospects for award, taking the allegations as true. See
USFalcon, Inc. v. United States, 92 Fed. Cl. 436, 450 (2010)
(explaining that “for purposes of standing” the court “must
accept the well-pled allegations of agency error to be true”).
Given this focus on a plaintiff’s allegations of agency error,
the court terms this standing prejudice, “allegational
prejudice.”
In order to prevail in a bid
protest, however, a plaintiff must satisfy a second type of
prejudice requirement, one that has caused a good deal of
confusion because it is often mistaken for its standing
doctrinal fraternal twin. See USFalcon, 92 Fed. Cl. at 450
(explaining why two examinations of prejudice are needed); Serco,
Inc. v. United States, 81 Fed. Cl. 463, 482 n.25 (2008) (noting
that “prejudice analysis” comes in “two varieties”); see also
L-3 Global Commc’ns Solutions, Inc. v. United States, 82 Fed. Cl.
604, 608 n.4 (2008); DynCorp Int’l LLC v. United States, 76 Fed.
Cl. 528, 536 (2007); Systems Plus, Inc. v. United States, 69
Fed. Cl. 757, 769 (2006); Textron, Inc. v. United States, 74
Fed. Cl. 277, 285 (2006). The need for this second showing of
prejudice is captured in section 10(e) of the Administrative
Procedure Act (“APA”), 5 U.S.C. § 706, which is incorporated in
28 U.S.C. § 1491(b) as the standard of review to establish
entitlement to relief in bid protest cases. See Textron, 74 Fed.
Cl. at 284–85; Metro. Van and Storage, Inc., 92 Fed. Cl. at 248.
The court thus terms this second showing of prejudice, “APA
prejudice.”
In particular, the APA
instructs that “due account shall be taken of the rule of
prejudicial error” when determining whether to set aside any
unlawful agency decision. 5 U.S.C. § 706; see supra note 30.
Concordantly, the Federal Circuit has held that the court must
conduct a second prejudice inquiry—one to which the court’s
determination on the merits is a prerequisite—in order to
“assess[] whether an adjudged violation of law warrants setting
aside a contract award.” Bannum, Inc. v. United States, 404 F.3d
1346, 1357 (Fed. Cir. 2005). To satisfy this second prejudice
inquiry, a plaintiff “must show that there was a ‘substantial
chance’ it would have received the contract award but for the
errors” that the court determines the agency made. Id. at 1353.
To summarize, Federal
Circuit precedent has used the doctrine of prejudice in two
distinct ways, the first relating to the pre-decisional standing
inquiry of “allegational prejudice,” the second corresponding to
“APA prejudice.” Compare ITAC, 316 F.3d 1319 (explaining that
“the prejudice issue must be reached before addressing the
merits” (emphasis added)) with Bannum, 404 F.3d at 1351
(explaining that a “bid protest proceeds in two steps,” whereby
the court first decides the merits, then determines if the
plaintiff was prejudiced by any adjudged violations of law). It
is interesting to note that both categories of prejudice apply
the “substantial chance” test. Compare ITAC, 316 F.3d at 1319
with Bannum, 404 F.3d at 1353; see USfalcon, 92 Fed. Cl. at 450.
But that is not the end of
our “prejudice” inquiry. Partly to clarify the distinction
between the two prejudice inquiries, bid protest jurisprudence
writ large can be seen as evolving into a three-step analysis.
First, in order to demonstrate allegational prejudice, a
plaintiff must show that it would have had a substantial chance
of being awarded the contract but for the combined impact of all
agency decisions alleged to be unlawful. See ITAC, 316 F.3d at
1319; USFalcon, 92 Fed. Cl. at 450; Serco, 81 Fed. Cl. at 482
n.25; Textron, 74 Fed. Cl. at 285. Second, and only if the
plaintiff makes this threshold showing of prejudice, the court
determines whether the challenged agency decisions were contrary
to law. See id. And third, in order to demonstrate APA
prejudice, the plaintiff must show that it would have had a
substantial chance of being awarded the contract but for the
combined impact of any agency decisions adjudged to be unlawful.
See Bannum, 404 F.3d at 1353; USFalcon, 92 Fed. Cl. at 450;
Serco, 81 Fed. Cl. at 501; Textron, 74 Fed. Cl. at 285.
To be sure, the second
prejudice inquiry (the third step in the above analysis) is not
always required. If all alleged procurement errors ultimately
withstand the court’s scrutiny—i.e., if the court upholds as
lawful every agency decision challenged by a plaintiff—the need
for a second prejudice inquiry will be obviated. See Bannum, 404
F.3d at 1357; Info. Tech. and Applications Corp., 51 Fed. Cl. at
357. By the same token, if none of the challenged agency
decisions survives judicial review—i.e., if all decisions
alleged to be unlawful are adjudged to be so—a second prejudice
inquiry would simply duplicate the first and would thus be
redundant. USFalcon, 92 Fed. Cl. at 450. However, where a
plaintiff succeeds on the merits of some but not all of its
allegations, a second examination of prejudice becomes
necessary. This is because the plaintiff’s success in
demonstrating allegational prejudice in such cases does not
guarantee its success in demonstrating APA prejudice. See id.
Specifically, the plaintiff in such cases may be able to satisfy
the substantial chance test based upon the combined impact of
all allegedly unlawful agency decisions, but may fail to do so
based upon the cumulatively lesser impact of those decisions
that the court ultimately determines to be unlawful. Id.
C. Does Plaintiff Have
Standing To Sue?
With the above framework in
place, the court turns to defendant and intervenor’s central
argument in support of their RCFC 12(b)(1) motions to dismiss.
To reiterate briefly, the movants argue that plaintiff’s
challenges to the Army’s price evaluation, under Counts 1 and 2,
are untimely challenges to the terms of the Solicitation. E.g.,
Def.’s Mot. to Dismiss at 10–11; Intervenor’s Mot. to Dismiss at
18–20 (same). Accordingly, the movants argue that plaintiff has
waived its right to bring either challenge and that this waiver
erects a jurisdictional bar that mandates dismissal of Counts 1
and 2. E.g., Def.’s Mot. to Dismiss at 10–11 (citing Blue &
Gold, 492 F.3d at 1313); Intervenor’s Mot. to Dismiss at 25–27
(same). With plaintiff’s challenges to the Army’s price
evaluation dismissed, the movants conclude that plaintiff cannot
demonstrate prejudice because it would not have a substantial
chance of award even if successful in its remaining challenges.
E.g., Def.’s Mot. to Dismiss at 13; Intervenor’s Mot. to Dismiss
at 27.
1. The Waiver Rule Is Not
a Jurisdictional Bar
Contrary to the movants’
contention, however, the waiver rule of Blue & Gold does not
erect a jurisdictional bar to plaintiff’s claims. See Def.’s
Mot. for J. at 11 n.1; Intervenor’s Mot. to Dismiss at 25–27.
Rather, the Federal Circuit’s express ground for recognizing a
waiver rule is the Tucker Act’s non-jurisdictional mandate for
“expeditious resolution” of bid protest actions. Blue & Gold,
492 F.3d at 1313 (citing 28 U.S.C. § 1491(b)(3)).
In Blue & Gold, the Federal
Circuit began its discussion with the patent ambiguity doctrine,
under which an offeror’s failure to seek clarification of a
patent ambiguity in a government solicitation precludes
acceptance of the offeror’s interpretation in any subsequent
court action. Id. (citing Stratos Mobile Networks USA, LLC v.
United States, 213 F.3d 1375, 1381 (Fed. Cir. 2000)). Blue &
Gold explained that recognition of a waiver rule—with respect to
challenges to patent ambiguities or patent errors in a
government solicitation—vindicates the equitable principle that
“[v]endors cannot sit on their rights to challenge what they
believe is an unfair solicitation, roll the dice and see if they
receive award [sic] and then, if unsuccessful, claim the
solicitation was infirm.” Id. at 1314 (quoting Argencord Mach. &
Equip., Inc. v. United States, 68 Fed. Cl. 167, 175 n.14
(2005)).
Blue & Gold further
analogized the waiver rule to the doctrines of laches and
equitable estoppel. Id. at 1314–15 (citing, inter alia, Wit
Assocs., Inc. v. United States, 62 Fed. Cl. 657, 662 n.5
(2004)). Of course, these equitable doctrines do not impose
jurisdictional requirements, but rather create affirmative
defenses that a defendant must invoke. See, e.g., PlanetSpace,
Inc. v. United States, 92 Fed. Cl. 520, 530 (2010) (citing Poett
v. Merit Sys. Prot. Bd., 360 F.3d 1377, 1384 (Fed. Cir. 2004)).
The Federal Circuit
concluded its analysis in Blue & Gold by recognizing that “the
jurisdictional grant of 28 U.S.C. § 1491(b)(1) contains no time
limit requiring a solicitation to be challenged before the close
of bidding.” Blue & Gold, 492 F.3d at 1315. In other words, Blue
& Gold repudiated the possibility of tethering the waiver rule
to the Tucker Act’s jurisdictional requirements. Rather, the
Federal Circuit explained that it is the statutory mandate of §
1491(b)(3) for “expeditious resolution”—a non-jurisdictional
requirement—along with “the rationale underlying the patent
ambiguity doctrine”—a rationale founded upon equitable
considerations—that “favor recognition of a waiver rule.”
Concordantly, the Court of
Federal Claims has consistently applied the waiver rule of Blue
& Gold as part of the court’s determination on the merits in a
bid protest. E.g., Moore’s Cafeteria Servs. v. United States, 77
Fed. Cl. 180, 185 (2007); Masai Techs. Corp. v. United States,
79 Fed. Cl. 433, 444 (2007); Benchmade Knife Co. v. United
States, 79 Fed. Cl. 731, 737 (2007). In some instances, the
court has dismissed an untimely challenge to the terms of a
solicitation on the ground that the challenge failed to state a
claim upon which relief may be granted. E.g., Unisys Corp. v.
United States, 89 Fed. Cl. 126, 136–37 (2009); Int’l Mgmt. Srvcs.,
Inc. v. United States, 80 Fed. Cl. 1, 9 (2007). Of course,
dismissal for failure to state a claim is itself a decision on
the merits. See, e.g., Federated Dept. Stores, Inc. v. Moitie,
452 U.S. 394, 399 n.3 (1981).
Finally, defendant’s attempt
to analogize the waiver rule to the Tucker Act’s statute of
limitations is misguided. See Hr’g Tr. at 13. Id. The
Tucker Act’s statute of limitations, 28 U.S.C. § 2501, is
jurisdictional because it is a condition on the United States’
waiver of sovereign immunity. John R. Sand & Gravel Co. v.
United States, 457 F.3d 1345, 1354 (Fed. Cir. 2006), aff’d, 552
U.S. 130 (2008); Martinez v. United States, 333 F.3d 1295, 1316
(Fed. Cir. 2003) (en banc). In that regard, § 2501 is
exceptional among statutes of limitations. Like other timeliness
rules, most statutes of limitations are treated as affirmative
defenses that are themselves subject to waiver if not raised in
a timely manner. John R. Sand & Gravel Co. v. United States, 552
U.S. 130, 133 (2008). To be sure, failure to bring a claim
within any limitations period invariably bars relief, as a
practical matter. As a matter of jurisprudence, however, this
does not deprive the court of jurisdiction over the untimely
claim.
In short, the waiver rule of
Blue & Gold creates an equitable, rather than jurisdictional,
bar to a disappointed offeror’s untimely challenge to the terms
of a government solicitation. Thus, although the court agrees
that plaintiff’s challenges to the Army’s price evaluation,
under Counts 1 and 2, are untimely, see infra p. 40, this does
not deprive the court of jurisdiction over those claims. Equally
important, because it is a determination on the merits,
applicability of the Blue & Gold waiver rule has no place in the
court’s inquiry into allegational prejudice, the inquiry
pertinent to the threshold question of plaintiff’s standing. See
ITAC, 316 F.3d at 1319; Myers, 275 F.3d at 1369; Media Techs.
Licensing, 334 F.3d at 1370. By grounding their motions to
dismiss upon operation of the waiver rule, defendant and
intervenor seek to inject a merits determination into an inquiry
that abides none. See id.
2. Plaintiff Can
Demonstrate Allegational Prejudice
Furthermore, beyond the
issue of the applicability of the waiver rule of Blue & Gold to
jurisdiction, the court concludes that plaintiff has readily
demonstrated allegational prejudice and thus standing to sue.
This is because plaintiff would have had a substantial chance of
receiving the AAA contract but for the combined impact of the
alleged errors in the Army’s procurement. See USFalcon, 92 Fed.
Cl. at 450 (explaining that a plaintiff can “cumulatively
establish prejudice” through the impact of “multiple errors”);
Serco, 81 Fed. Cl. at 501 (holding “that the combined impact of
the errors encountered here clearly prejudiced each of the
protesters”). As explained below, but for the challenged aspects
of the Army’s evaluation of price and past performance,
plaintiff would have rated favorably under both of these
evaluation factors and would have been well positioned to
prevail in a trade-off analysis.
Under Counts 1 and 2,
plaintiff posits various grounds for its allegation that the
Army’s price evaluation was unlawful. Am. Compl. ¶¶ 65–81; Pl.’s
Mot. for J. at 33–42. Plaintiff alleges that the law required
the Army to calculate Total Evaluated Price (the basis for
award) as the Total Amount for all CLINs rather than as the sum
of unit prices. E.g., Pl.’s Mot. for J. at 34–35. Taking that
allegation as true as this court must, see supra p. 19, had the
Army hypothetically calculated Total Evaluated Price as
plaintiff proposes, plaintiff’s ranking in price would have
leapt from a distant seventh to a fairly close second,
immediately below intervenor (the awardee). See AR 600. And
defendant misses the mark when it argues that plaintiff’s “high
price is not the result of the evaluation method used by the
Army, but rather a business decision on the part of [plaintiff]
to include an extraordinarily high unit price” for CLIN 0011.
Def.’s Mot. to Dismiss at 9. Plaintiff’s proposed unit prices
for CLIN 0011—which totaled $[number redacted] for all four
contract periods—represented a vastly disproportionate [number
redacted]% of plaintiff’s sum of unit prices. See AR 321, 600.
By contrast, CLIN 0011 contributed a relatively negligible
[number redacted]% of plaintiff’s Total Amount for all CLINs,
which was approximately $[number redacted] million. Id.
Therefore, it appears to the court that plaintiff’s poor ranking
in price thus resulted, not from any business decision on
plaintiff’s part, but from the Army’s decision to use the sum of
unit prices as the basis for award.
In addition, under Count 4,
plaintiff alleges that the SSA’s past performance evaluation
unlawfully excluded from consideration a wide range of relevant
past performance information. See, e.g., Am. Compl. ¶¶ 115–19;
Pl.’s Mot. for J. at 24–29. Had the SSA expanded the scope of
the past performance evaluation as plaintiff alleges the law
required—so as to encompass purportedly negative past
performance information for other offerors and positive
information for plaintiff—plaintiff’s ranking in past
performance would have changed dramatically. See, e.g., Pl.’s
Mot. for J. at 24–29. Intervenor’s past performance rating, in
particular, would have been further reduced had the SSA included
the negatively rated GLS PPQ in her evaluation, as plaintiff
alleges the law required. See, e.g., Pl.’s Mot. for J. at 24;
Intervenor’s Resp. to Pl.’s Mot. for J. (“Intervenor’s Resp.”)
at 21–22. Indeed, had the SSA conducted the more expansive
evaluation that plaintiff urges, plaintiff might well have
ranked first in past performance with a rating of “Very Low
Risk,” while all other offerors would have been assigned a
rating of “Moderate Risk” or worse. See Pl.’s Mot. for J. at 27,
31.
If plaintiff were thus
ranked second in price and first in past performance, the SSA
would have been required to include plaintiff in the trade-off
analysis. See AR 54. As noted above, the RFP required the SSA to
“conduct a trade off based on a comparative assessment of the [p]ast
[p]erformance and [p]rice factors,” with the proviso that the
“[p]ast [p]erformance factor is significantly more important
than price.” Id. Thus, even a modest improvement in plaintiff’s
ranking in past performance, along with a second-place ranking
in price, would have afforded plaintiff a substantial chance of
prevailing in a trade-off analysis and thus being selected for
award. Accordingly, plaintiff has demonstrated allegational
prejudice and has standing to sue.
Before turning to the
merits, however, the court must address the movants’ second
argument. As noted above, defendant argues that plaintiff lacks
standing because, as the seventh-ranked offeror in price and
past performance, “it never had a ‘substantial chance’ of
receiving award” and “was outside the zone of consideration.”
Def.’s Mot. to Dismiss at 8, 9 (emphases added). In a slight
variation on this logic, intervenor attempts to limit plaintiff
to demonstrating allegational prejudice based upon the
incremental impact of one alleged error at a time. See
Intervenor’s Mot. to Dismiss at 17. In a sense, this argument
conflates allegational prejudice with APA prejudice. By
insisting that plaintiff’s poor ranking precludes it from being
an interested party, the movants essentially would have
plaintiff prove the merits of its allegations—i.e., prove that
the contested procurement decisions are unlawful—before it may
rely upon the impact of those decisions in demonstrating
prejudice.
More importantly, the
movants misapprehend the nature of the inquiry into allegational
prejudice, an inquiry aimed at assessing the plaintiff’s likely
prospects for the contract award, see ITAC, 316 F.3d at 1319,
but for the combined impact of all alleged errors in the
procurement, see USFalcon, 92 Fed. Cl. at 450. That is,
plaintiff need not demonstrate that it had a substantial chance
of award despite the alleged errors, but rather that it would
have had a substantial chance of award but for the alleged
errors. See ITAC, 316 F.3d at 1319; see also Heritage of Am.,
LLC v. United States, 77 Fed. Cl. 66, 77–78 (2007); Night Vision
Corp., 68 Fed. Cl. at 392.
Indeed, to accept either
defendant’s or intervenor’s logic would be to permit the Army,
indeed any procuring agency, to insulate from judicial review
much of its decision-making in a competitive acquisition. See
Allied Tech. Grp., Inc. v. United States, 94 Fed. Cl. 16, 37
(2010) (rejecting a similar argument due to its “illogical
result of potentially insulating from review an agency’s
decision to declare one proposal acceptable and another
unacceptable”). Under intervenor’s view of the allegational
prejudice inquiry, a procuring agency could evade judicial
oversight by making a series of unfavorable determinations, each
with a negligible impact on the rating of an offeror’s proposal,
but with the cumulative effect of excluding that offeror from
the competitive range. And under defendant’s view, a procuring
agency could accomplish the same goal by rating a losing offeror
so unfavorably on a single evaluation factor as to fling it
irretrievably far from the zone of consideration. The court has
previously rejected, as a “transparent and misleading attempt[]
to change binding law,” defendant’s similar contention that an
agency’s decision to exclude an offeror from the competitive
range precludes the offeror from establishing standing. Dyonyx,
L.P. v. United States, 83 Fed. Cl. 460, 469 (2008). Quite
simply, the law cannot abide the result that either defendant or
intervenor seeks.
As explained above,
plaintiff can readily make the required showing of allegational
prejudice because it would have had a substantial chance of
being awarded the AAA contract but for the alleged errors in the
Army’s procurement. See ITAC, 316 F.3d at 1319. Plaintiff is
thus an “interested party” under § 1491(b)(1) and has standing
to bring the instant protest. See id.; AFGE, 258 F.3d at 1302.
(Linc Government Services, LLC, v. U.
S. and McNeil Technologies, Inc., No. 10-375C, November 5,
2010) (pdf)
1. Allied Cannot Show
Prejudice From DOJ’s Technical Evaluation.
The Court agrees with
Allied’s assertion that there were errors in DOJ’s technical
evaluation process. As previously discussed, TEP members used
score sheets to evaluate
offerors’ technical proposals on a point system with adjectival
ratings. For example, factor one, Technical Merit, provided for
ratings of 52-60 (excellent), 43-51 (good), 34-42
(satisfactory), 25-33 (poor), and 0-24 (unacceptable), while
sub-factor one, Understanding of
the Requirements, provided for ratings of 22-25 (excellent),
18-21 (good), 14-17
(satisfactory), 10-13 (poor), and 0-9 (unacceptable). See, e.g.,
AR 834-35. The score sheets
identified how the point system relates to the adjectival
ratings, but the score sheets failed to
indicate how scores should be tabulated. Indeed, the score
sheets do not instruct TEP
members how to assign points, how the number or extent of the
significant strengths should
correspond to total points, or what constituted a “perfect”
score. Id. More importantly, DOJ
left the adjectival ratings for the Technical Merit sub-factors
undefined. Id. Lacking a
defined scoring system, the TEP’s ratings varied significantly
by individual. For example,
four of the six evaluators found Allied’s technical quotation to
be superior, while two
evaluators found Monster’s quotation to be superior by a large
margin. See AR 834-999.
In addition to the disparate scoring, the Court found a number
of inconsistencies in the
written portion of the TEP’s technical evaluation. For example,
TEP members assigned
significant weaknesses to Allied for failing to discuss certain
factors, which Allied actually
included in its offer. See, e.g., AR 854, 610, 734. Some
evaluators also marked both
“significant strength” and “significant weakness” for the same
proposal feature in the same
sub-factor. One evaluator identified Avue’s Concierge Service as
a “significant strength,” AR
850, but then assigned Allied a “significant weakness” for the
same feature, AR 851. Also,
it appears that evaluators credited Monster with “significant
strengths” for ARS system
features for which Allied was not similarly credited. In
sub-factor three, one evaluator gave
Monster a “significant strength” for “undergoing a series of
upgrades throughout the course
of a year,” AR 841-42, without giving Allied the same credit,
despite having the same feature
in its quotation.
The Court also found questionable the CO’s communications with TEP members
following receipt of their initial evaluations. AR 827-32,
896-900, 949-50, 985. The CO
asked four TEP members to provide more detail explaining why
they assigned Monster a low
score. See, e.g., AR 985. In response to the CO’s inquiries, two
TEP members altered their
scores to give Monster higher, or even perfect scores, for three
different sub-factors. See AR
838, 841, 931. Allied also received less than perfect scores in
certain factors, but the
administrative record lacks any evidence that the CO questioned
TEP members about their
evaluations of Allied. See, e.g., 909-11, 943-44.
Despite the errors in DOJ’s technical evaluation, Allied fails
to meet its burden of
demonstrating that DOJ’s actions prejudiced it. To prevail in a
bid protest, a plaintiff must
do more than merely demonstrate an error on the part of the
Government. See Labatt Food
Serv., Inc., 577 F.3d at 1380; Galen Med. Assoc., Inc., 369 F.3d
at 1330 (“‘[T]o prevail in a
protest the protester must show not only a significant error in
the procurement process, but
also that the error prejudiced it.’” (quoting Data Gen. Corp.,
78 F.3d at 1562)). Rather, Allied also must show that “there was
a substantial chance it would have received the contract award
but for [the CO’s] error.” Alfa Laval Separation, Inc., 175 F.3d
at 1367 (quoting Statistica,
Inc. v. Christopher, 102 F.3d 1577, 1582 (Fed. Cir. 1996)).
Thus, a procurement official’s
decision must be sufficiently serious to cause prejudice to a
protestor in the procurement. See
E.W. Bliss Co., 77 F.3d at 448-49.
In this case, given the
substantial difference between Allied’s and Monster’s price
quotations, Allied cannot reasonably show that it would have
received the award in the
absence of DOJ’s errors. For evaluation purposes, the CO used
CLIN 003 for 10,0001 to
15,000 ARS users to compare Monster’s and Allied’s pricing,
using the prepayment discount
Allied proposed in its quotation. AR 1038. At that CLIN level,
Monster’s price for the full
five-year term of the contract, including transition costs as a
non-incumbent contractor, was
$3,204,351. Id. Allied’s price at the same CLIN level, without
transition costs, was
$7,000,486. Id. Allied’s price was 218 percent higher than
Monster’s evaluated price.
Applying the premium Allied imposes for monthly invoicing as
required by the RFQ, Allied’s
price balloons to $11,698,107 for CLIN 003 under the contract’s
five-year term, while
Monster’s price remains the same. AR 1026. This amount is more
than $8 million or 365
percent higher than Monster’s price. AR 1026-28. In the
Acquisition Summary and in the
Notification and Basis of Award, the CO noted that if DOJ used
the BPA at its maximum
CLIN 0023 level of 115,000 employees, Monster’s total price
would be $13 million. AR
1045, 1047. In contrast, Allied’s total price would be
approximately $78 million if DOJ
prepaid Allied’s price annually. AR 592. Allied’s total price
would increase to more than
$112 million if DOJ invoiced monthly at the maximum CLIN level.
AR 1026. Thus, under
CLIN 0023, the difference between Monster’s and Allied’s prices
is slightly less than $100
million. Such a drastic price difference precludes a finding of
any prejudice to Allied. See
Analytical & Research Tech., Inc. v. United States, 39 Fed. Cl.
34, 54 n.19 (1997) (finding
no prejudice where the protestor’s price was 35 percent higher
than the awardee’s despite a
violation of procurement laws); Data Gen. Corp., 78. F.3d at
1563-64 (holding that the
technical advantages of the protestor’s proposal did not offset
the difference in price).
The Court acknowledges that
Allied’s margin of technical superiority may have
increased if the TEP had performed its duties properly. (Pl.’s
Mot. 73.) Indeed, Allied’s
technical proposal may have been superior by as many as fourteen
points in a properly
performed evaluation. Id. at 21. However, any changes to the
technical scoring in Allied’s
favor would not diminish the rationality of awarding the BPA to
a qualified vendor whose
price was significantly lower. This Court in Electronic Data
Systems, LLC v. United States
recently addressed the impact of a significant price difference
under circumstances similar to
this case. No. 09-857C (Fed. Cl. filed Apr. 26, 2010). In that
case, the Court held that despite
the Government’s error in failing to amend a solicitation, “a
significant difference in price .
. . can and often does preclude such a finding.” Id. at 24
(citing Data Gen. Corp., 78 F.3d at 1563; Axiom Res. Mgmt., Inc.
v. United States, 78 Fed. Cl. 576, 590 (2007)). The Court
reasoned that even if the disappointed bidder could have revised
its proposal in light of the
Government’s errors, any such differences would have been
inconsequential given the
dramatic price difference “representing nearly a 29 percent
spread.” Id. at 23-24. The price
difference in this case was much greater. Indeed, Allied’s
evaluated price was at least 218
percent higher than Monster’s. Assigning a higher technical
rating to Allied’s proposal would
not have overcome the staggering price difference. As Judge
Allegra colorfully explained in
Electronic Data Systems, the dramatic price difference “is the
proverbial elephant in the parlor
– and, strive as it might, plaintiff cannot squeeze that
pachyderm out of the door.” Id. at 23.
The CO reasonably considered
the offerors’ price difference in the Acquisition
Summary, noting that “the price evaluation overwhelmingly
favor[ed] Monster” and that
“[t]here is no reasonable way to assert that Allied/Avue,
receiving a technical score 5.04%
higher than Monster justifies paying more than twice as much,
resulting in millions of
additional dollars over the five year term of the BPA.” AR 1039.
The record simply does not
suggest that any DOJ errors reasonably could offset the price
difference so as to make DOJ’s
selection improper. See Data Gen. Corp., 78 F.3d at 1563; see
also Axiom Res. Mgmt. Inc.,
78 Fed. Cl. at 590 (concluding that despite the apparent errors
in the plaintiff’s technical
approach and past performance ratings, the awardee’s lower price
still trumped plaintiff’s
price); Candle Corp. v. United States, 40 Fed. Cl. 658, 665
(1998) (holding that even if the
Government had complied with its legal obligations, the
plaintiff’s price still would have been
considerably more expensive than the awardee’s). The Court thus
cannot find any prejudice
to Allied from DOJ’s technical evaluation. (Allied
Technology Group, Inc. v. U. S. and Monster Government
Solutions, LLC, No. 10-120C, July 2, 2010) (pdf)
The “substantial chance” test has been applied
in the context of ordinary postaward
bid protests. Weeks Marine, Inc. v. United States (Weeks
Marine), 79 Fed. Cl. 22, 35 (2007). With respect to pre-award protests, however, there
exists persuasive authority that a protestor may be required to show only “that an
unreasonable agency decision ‘created a non-trivial competitive injury which can be redressed
by judicial relief.’” Id. (quoting WinStar Comm. Inc. v. United States, 41 Fed. Cl. 748,
763 (1998)). The different standards for pre-award and post-award relief are
explained as resulting from the fact that the “substantial chance” test “envisions a review of
the contract award or bid evaluation process to determine what might have occurred if the
government had not erred.” Id. (quoting WinStar, 41 Fed. Cl. at 763 n.9). By
contrast, in a pre-award solicitation-based protest, “the evaluation of offers has not
even begun.” Id. (quoting WinStar, 41 Fed. Cl. at 763 n.9).
In this case, both parties have submitted complete proposals and
plaintiff’s only claimed injury is the possibility that it might, if afforded
more time, have submitted lower prices. AR passim; Pl.’s Mem. passim. Here, where plaintiff is
making a post-award, solicitation-based protest based on a defect in the solicitation
of which the plaintiff was unaware until after the closing date for offers, see infra Part
II.C.1-2, neither the “substantial chance” standard of Bannum, 404 F.3d at 1353,
applicable to post-award protests where the protest challenges the contract award or bid
evaluation occurring after the closing date for offers, nor the “non-trivial competitive
injury” standard of Weeks Marine, 79 Fed. Cl. at 35, appears suitable. The situation in
this case differs from that in Weeks Marine, or in WinStar, cited in Weeks Marine, both
involving cases in which no evaluation of offers had begun. Weeks Marine, 79 Fed. Cl. at 23;
WinStar, 41 Fed. Cl. at 750. Also, in this case, there is no allegation, as there was in
Weeks Marine, that the violation of law would result in a competitive injury that could
be “business threatening.” Weeks Marine, 79 Fed. Cl. at 35. The court chooses to articulate
a standard for the showing of prejudice that lies between Weeks
Marine, 79 Fed. Cl. at 35 (the identification
of “a non-trivial competitive injury capable of being redressed
by judicial relief”) and Bannum, 404 F.3d at 1353 (the “substantial chance” test), and
takes into account the factual development of the case afforded by the completion
(albeit flawed) of the offering process and the actual evaluation of completed proposals.
In
these circumstances, the court will find prejudice if plaintiff demonstrates that, absent
the error, it would have had a chance of receiving the contract award that is more than
merely speculative. Factual findings on prejudice are to be made from the record evidence. Bannum, 404 F.3d at 1356.
(emphasis added)
(Sections deleted)
Plaintiff argues that
“Allied had no ability to reduce or modify its prices based on
the manner in which Amendment 5 was communicated to Allied or
the information in the amendment itself.” Compl. ¶ 11. According to plaintiff’s
argument in briefing, it was in fact prejudiced by the error in the issuance of Amendment 5:
[I]f Allied had known about Amendment 5 extending the bid
closing date to January 11, 2008 it would have had the opportunity to
look at our current back log and run various costing strategies based on the
government’s revised purchase estimates for the base year and
the option years. Also, it would have provided Allied with the opportunity
to resolve the PIHM Hose issue regarding our proposed source. Having this
issue resolved would allow Allied to be confident that it would get
timely receipts of the PIHM Hose for the option years. Also if Allied had
adequate time to factor in both of these issues it would have provided the
Plaintiff an opportunity to not only lower our base year price
but also determine if option year pricing needed to be escalated.
Additionally, Steve Pack, the President of Allied, was absent
from the office, due to the Christmas holiday, during the period when
the revised offer to Amendment 4 was prepared. . . . Mr. Pack typically is
the final pricing authority on all major bids and proposals. . . . Mr.
Pack also frequently cuts pricing on bid estimates based on his subjective
determination of what it will take to be successful in winning
the contract. Finally, there are many purchased components that are required
to produce the Pigtail assembly. It is Allied’s practice to follow
up with vendors for better pricing up to the date bids are submitted.
Allied also diligently looks for alternative vendors for products where we
believe cost savings can be realized. On December 20, 2007 DSCR’s e-mail
directed Allied to respond to Amendment by December 28, 200[7].
Considering most vendors were unavailable on Monday December 24, 2007 and
obviously Tuesday December 25, 2007 that effectively left Allied
with only two days, December 21, 2007 and December 26, 2007, to work on
its pricing and seek better price quotes.
Pl.’s Mem. 10-11 (citations omitted).
(Sections deleted)
Plaintiff argues that
because Steve Pack, Allied’s president, was absent due to the
Christmas holiday, he was unable to use his discretion to cut
prices “based on hisPl.’s Mem. 11. The court agrees with
defendant that the government should not be held
responsible for Steve Pack’s having taken a vacation when he
believed the deadline for
proposals was December 28, 2007. Def.’s Resp. 3 n.1.
Furthermore, plaintiff argues that
due to the Christmas holiday, after Amendment 4 was issued
Allied was left “with only
two days, December 21, 2007 and December 26, 2007, to work on
its pricing and seek
better price quotes.” Pl.’s Mem. 11. However, even if Allied had
been unable to work on
pricing on December 22-25, it still had six working days
“(December 18, 19, 20, 21, 26
and 27) to revise its pricing.” Def.’s Resp.
Also, and importantly, the price factor was considered along
with the non-price
factor of past performance in order to determine which proposal
provided the best value
to the Government. AR 48. The proposals were evaluated by
weighing price and nonprice
factors equally. Id. As defendant-intervenor correctly states,
"Allied fails to demonstrate how an opportunity to reduce its proposed price – or
even an actual reduction in its proposed price – would result in Allied having an
evaluated price that was sufficiently lower than ILC’s price to overcome ILC’s
superiority with respect to ABVS scoring." Def.-Int.’s Mem. 13. Allied has failed to demonstrate
that, absent the error, it would have had a chance of receiving the contract award that is
more than merely speculative. For the foregoing reasons, the court finds that
plaintiff was not prejudiced by defendant’s error. (Allied
Materials & Equipment Co., Inc., v. U. S. ILC Dover, LP, No.
08-151C, May 13, 2008) (pdf)
In sum, the agreed upon facts of
this case demonstrate that plaintiff was
eliminated from the competitive range with regard to the
unrestricted portion of
this solicitation because the prices set forth in its proposal
were not competitive. In
that regard, plaintiff had no right to receive further
solicitation amendments.
Additionally, Ironclad’s assertion that it would have changed
that pricing
information, had it been privy to Amendment 12, is speculative
and unpersuasive,
at best. Ironclad is simply “[a] disappointed offeror that has
made a business
judgment to propose an expensive product,” and under the law of
this circuit,
plaintiff “cannot utilize the protest system to obtain the
proverbial second bite at
the apple.” Candle Corporation, 40 Fed. Cl. at 665-66 (quoting
Alfa Laval
Separation, Inc. v. United States, 40 Fed. Cl. 215, 235 (1998),
rev’d on other
grounds, 175 F.3d 1365 (Fed. Cir. 1999)); see also Data General,
78 F.3d at 1564.
Finally, the government has shown that because no offerors were
permitted to alter
their prices after the issuance of Amendment 12, the amendment
would have had
no impact upon Ironclad’s price.
For the foregoing reasons, the court concludes that the Corps
was not
required to provide Ironclad with Amendment 12 and, even if the
Corps erred
when it did not provide Amendment 12 to Ironclad, plaintiff has
not carried its
burden to establish that it was prejudiced by that error. Any
claimed error was
therefore harmless. See Galen Medical Associates, 369 F.3d at
1330. Plaintiff’s
contentions regarding Amendment 12 do not vest Ironclad with
standing to
challenge the unrestricted awards. Defendants’ motions to
dismiss plaintiff’s
challenge to those awards, and any claim of error related to
Amendment 12, are
granted. (Ironclad/EEI, A Joint
Venture, v. U. S. and Campbell Roofing & Construction, Inc.,
MGC/Campbell Roofing & Construction, Inc., Crown Roofing
Services, Inc., and R. L. Campbell Roofing Company, Inc.,
No. 07-280C, Filed September 26, 2007) (pdf)
The FASA protest prohibitions of
41 U.S.C. § 253j(d) and FAR 16.505(a)(9) both provide
that the traditional protest routes of the “issuance or proposed
issuance” of a task order or delivery order are not permitted, save for exceptions in the
statute as developed by case law, which are not applicable to this case. See A & D Fire
Protection, Inc. v. United States, 72 Fed. Cl. at 133-34. Alternatively, therefore, to the extent
that ATI’s actions are in the nature of a protest to future task orders under the terms of its
contract, this court is not the proper forum. For the foregoing reasons, the court concludes that ATI, which
is currently in possession of an ID/IQ computer maintenance contract awarded by
Customs, was not prejudiced by the award of a second computer maintenance
contract to DTI and, therefore, has no standing to bring a protest against the second award. The
clerk’s office shall DISMISS the plaintiff’s complaint, and enter JUDGMENT in favor
of defendant and intervenor. Plaintiff’s motion for injunctive relief, and the
remaining briefing schedule set out in the court’s Order of October 11, 2006, are mooted by this
decision. (Automation
Technologies, Inc., v. U. S. and Digital Technologies, Inc.,
Defendant-Intervenor (No. 06-694C, October 27, 2006) (pdf)
The court finds that there was no
prejudice to Systems Plus’s position in this best-value
procurement. The solicitation did not, and was not required to,
rate the relative importance of the
different evaluation criteria. Accordingly, the Contracting
Officer had broad discretion to
determine how important each of the criteria would be in the
evaluation. In his best-value
determination, the Contracting Officer indicated that there was
no particular “weight” assigned to
the evaluation factors: “As . . . competing offeror proposals in
the Technical areas become more
equal in rating, the more important Price will become.” AR Tab
16 (Determination of Best
Value) at 1. The Contracting Officer stated that “[f]rom a
business point of view, the value of
[NetStar’s] quote response (non-cost factors) supercedes [sic]
any variances for interpreting the
ranking of offerors for price.” Id. at 5 (emphasis added). It
thus appears that the Contracting
Officer determined that NetStar’s proposal was sufficiently
superior to other offerors’ proposals
that NetStar should be selected regardless of which measure of
price was evaluated. The
Contracting Officer was not required to choose the lowest-price
proposal, and therefore his
decision that NetStar offered the best value regardless of the
manner in which price was
measured will not be deemed arbitrary, capricious, or otherwise
not in accordance with law
pursuant to 5 U.S.C. § 706(2)(A). See Impresa Construzioni, 238
F.3d at 1332.
The court thus finds that Systems Plus’s position in the
procurement was not prejudiced
by the Contracting Officer’s error in evaluating the pricing in
the bidders’ proposals. Simply put,
Systems Plus would not have been awarded the BPA even if the
Contracting Officer had used the pricing analysis advocated by
the plaintiff. (Systems Plus, Inc.,
v. U. S., and NetStar-1, Inc., No. 05-1219C, Reissued:
February 28, 2006) (pdf)
In order to sustain a challenge to
an award, the challenger must show a prejudicial
violation of an applicable regulation. Impresa, 238 F.3d at
1333. “To establish prejudice,
plaintiff must show that there was a ‘substantial chance’ it
would have received the award
but for the alleged error in the procurement process.” Info.
Tech. & Applications Corp. v.
United States (ITAC), 316 F.3d 1312, 1319 (Fed. Cir. 2003); see
also Data General Corp.
v. United States, 78 F.3d 1556, 1562 (Fed. Cir. 1996) (“[T]o
establish prejudice, a
protester must show that, had it not been for the alleged error
in the procurement process,
there was a reasonable likelihood that the protester would have
been awarded the
contract.”). Neither Precision nor Hawk complied with the source
approval requirement.
Because Precision failed to meet the source approval
requirement, Precision cannot show
that it would have had a “substantial chance” of receiving the
award if defendant had
required source approval. In fact, if the government had
required compliance with the
source approval requirement, Precision not only would have
lacked a “substantial chance”
of receiving the award; it would have been barred from receiving
the award on account of
that very requirement. Accordingly, because Precision itself
does not qualify as an
approved source, it cannot establish that it would have had a
substantial chance of
receiving the award if the government had required compliance
with the source approval
requirement, nor can it establish that it was prejudiced by
Hawk’s receipt of the award
without Hawk’s first obtaining source approval. Precision has
not shown, and the court 9
is not persuaded, that AMCOM’s failure to comply with the source
approval requirement
in this solicitation was in any way “prejudicial” to Precision.
See Impresa, 238 F.3d at
1333. Accordingly, Precision’s challenge to the award on this
ground must fail. (Precision
Standard, Inc., v. U. S., and Hawk Enterprises, LLC., No.
05-1125C, Filed: February 27, 2006) (pdf)
Because plaintiff cannot show that
it was significantly prejudiced, it cannot prevail
on the merits of its claim. In addition to prevailing on the
merits, in order to obtain permanent injunctive relief, plaintiff must show: (1) that it
will be immediately and irreparably injured; (2) that the public interest would be
better served by the relief sought; and (3) that the balance of the hardships tips in favor of the
plaintiff. Bannum I, 60 Fed. Cl. at 730; see also Amoco Prod. Co. v. Village of Gambell, 480 U.S.
531, 546 n.12 (1987); Zenith Radio Corp. v. United States, 710 F.2d 806, 809 (Fed.
Cir. 1983). While this court again acknowledges that plaintiff has shown the presence of an
immediate and irreparable injury, Bannum I, 60 Fed. Cl. at 730-31, plaintiff cannot obtain
injunctive relief based upon the satisfaction of this single factor. “Intervenor has proved
beyond cavil that a bid protest pressed well into contract performance tips the scale in favor
of the awardee.” Id. at 731; see also Gull Airborne Instruments, Inc. v. Weinberger, 694 F.2d
838, 846 n.9 (D.C. Cir. 1982). Finally, the public interest is served by having the BOP observe
applicable procurement regulations in conducting its reviews, but not, based on the
spread in the scores, when plaintiff cannot demonstrate that a potential change in scoring
would make a difference. See Bannum I, 60 Fed. Cl. at 731; see also United States v. John C.
Grimberg Co., 702 F.2d 1362, 1371 (Fed. Cir. 1983). Accordingly, based on the
foregoing, plaintiff has failed to prove that the violation of the applicable procurement regulation prejudiced it. The Clerk
of the Court shall enter judgment for defendant. (Bannum,
Inc. v. U. S. and Dismas Charities, Inc., No. 03-1751C,
January 18, 2006) (pdf) |
|
U.
S. Court of Federal Claims - Listing of Decisions
|
For
the Government |
For
the Protester |
McConnell Jones Lanier & Murphy, LLP
v. U. S., No. 15-1351C, September 23, 2016 |
BCPeabody
Construction Services, Inc. v. U. S. and Edens Construction Co.,
Inc., No. 13-378C, September 25, 2013 (pdf) |
Digitalis Education Solutions, Inc.
fv. U. S. and Morris & Lee d/b/a Science First, No. 10-855,
February 11, 2011 (pdf) |
Linc Government
Services, LLC, v. U. S. and McNeil Technologies, Inc., No.
10-375C, November 5, 2010 (pdf) |
Allied Technology
Group, Inc. v. U. S. and Monster Government Solutions, LLC,
No. 10-120C, July 2, 2010 (pdf) |
|
Allied Materials &
Equipment Co., Inc., v. U. S. ILC Dover, LP, No. 08-151C,
May 13, 2008 (pdf) |
|
Ironclad/EEI, A Joint Venture, v. U.
S. and Campbell Roofing & Construction, Inc., MGC/Campbell
Roofing & Construction, Inc., Crown Roofing Services, Inc., and
R. L. Campbell Roofing Company, Inc., No. 07-280C, Filed
September 26, 2007 (pdf) |
|
Automation Technologies, Inc., v. U. S. and Digital
Technologies, Inc., Defendant-Intervenor (No. 06-694C,
October 27, 2006 (pdf) |
|
Systems Plus, Inc., v. U. S., and
NetStar-1, Inc., No. 05-1219C, Reissued: February 28, 2006 (pdf) |
|
Precision Standard, Inc., v. U. S.,
and Hawk Enterprises, LLC., No. 05-1125C, Filed: February
27, 2006 (pdf) |
|
Bannum, Inc. v. U. S. and Dismas Charities, Inc., No.
03-1751C, January 18, 2006 (pdf) |
|
U.
S. Court of Appeals for the Federal Circuit - Key Excerpts |
As the Court of Federal Claims recognized, to
prevail the bid protester must first show that it was prejudiced
by a significant error in the procurement process. JWK Int’l
Corp. v. United States, 279 F.3d 985, 988 (Fed. Cir. 2002). A
party has been prejudiced when it can show that but for the
error, it would have had a substantial chance of securing the
contract. Bannum, Inc. v. United States, 404 F.3d 1346, 1358
(Fed. Cir. 2005); Galen Med. Assocs., Inc. v. United States, 369
F.3d 1324, 1331 (Fed. Cir. 2004); Info. Tech. & Applications
Corp. v. United States, 316 F.3d 1312, 1319 (Fed. Cir. 2003);
Statistica, Inc. v. Christopher, 102 F.3d 1577, 1581 (Fed. Cir.
1996). It is basic that “because the question of prejudice goes
directly to the question of standing, the prejudice issue must
be reached before addressing the merits.” Info. Tech., 316 F.3d
at 1319; accord Myers Investigative & Sec. Servs. v. United
States, 275 F.3d 1366, 1369-70 (Fed. Cir. 2002) (“[S]tanding is
a threshold jurisdictional issue. . . . [P]rejudice (or injury)
is a necessary element of standing.”). Whether a party has
standing to sue is a question of law that we review de novo. Rex
Serv. Corp. v. United States, 448 F.3d 1305, 1307 (Fed. Cir.
2006). The underlying question of prejudice requires the trial
court to engage in a factual analysis, which we review for clear
error. Bannum, 404 F.3d at 1354.
Labatt urges, and the trial
court found, that because the three offerors improperly
submitted the first round proposal revisions via e-mail, all
proposals had been effectively withdrawn at that time and
therefore eliminated from competition. Relying on Impresa
Construzioni Geom. Domenico Garufi v. United States, 238 F.3d
1324 (Fed. Cir. 2001) (“Garufi”), the trial court found that
Labatt had standing because all proposals were invalidated long
before Labatt’s late response to amendment 0007, so the
government was obligated to rebid the contract and allow Labatt
to compete for it. Because the court concluded that Labatt would
have a substantial chance of receiving the award in a rebid, it
found that Labatt had standing to sue.
The court’s reliance on
Garufi is misplaced. The aggrieved bidder in that case, Garufi,
claimed that the government made an arbitrary and capricious
responsibility determination regarding the winning bidder’s
record of integrity and business ethics. 238 F.3d at 1334.
Garufi had standing to bring its bid protest because if its
claims were true, the government’s arbitrary responsibility
determination resulted in a contract award to a bidder who was
unfairly advantaged by the government’s error. Id. In such a
scenario, Garufi was denied the opportunity to fairly compete
for the contract. Because “the government would [have been]
obligated to rebid the contract” if the protest was successful,
and the “appellant could compete for the contract once again,”
we found Garufi met the “substantial chance” standard and had
standing. Id. Garufi thus stands for the proposition that an
unsuccessful bidder who alleges harmful error in a government
bid contest in which he has an economic interest has the
requisite standing to sue.
The critical difference
between Garufi and the present case is not the existence of
error on the part of the government, but the allegation of an
error that, taken as true, would be prejudicial to the
complaining party’s attempt to procure the contract. It is true
that a bid protester must have a substantial chance of receiving
an award in order to have an economic interest in it and
therefore standing to file a bid protest. Info. Tech., 316 F.3d
at 1319 (“In order to establish standing, [the protester] must
show that it is an actual or prospective bidder . . . whose
direct economic interest would be affected by the award of the
contract or by failure to award the contract . . . .”) (internal
quotation marks omitted); Myers, 275 F.3d at 1370 (confirming
that standing to bring bid protests under the Tucker Act, 28
U.S.C. § 1491(b), is limited to actual or prospective offerors
whose direct economic interest would be affected by the contract
award); Rex Serv. Corp., 448 F.3d at 1307 (defining an
“interested party” as an actual or prospective bidder or offeror
whose direct economic interest would be affected by the contract
award). But in Garufi, the protesting party also alleged a
critical element of standing that is absent here: harmful error
by the government in the procurement process. The trial court’s
application of Garufi to the case at hand relies on a logically
infirm analogy between (1) an allegedly erroneous responsibility
determination in Garufi that advantaged one offeror to the
detriment of all others, and (2) an improper deviation from the
solicitation in this case that equally permitted all offerors to
submit proposal revisions via e-mail, harming none.
In both cases
unsuccessful offerors alleged error on the part of the
government. Here, however, there is no showing of how the
government’s error caused Labatt to suffer disparate treatment
or particularized harm. Instead, Labatt tautologically argues
that it was harmed by the method of transmission error because
it would have a substantial chance of receiving the contract
award in a rebid. By conflating the standing requirements of
prejudicial error and economic interest, Labatt would create a
rule that, to an unsuccessful but economically interested
offeror in a bid protest, any error is harmful. Under this
radical formulation there would be no such thing as an error
non-prejudicial to an economically interested offeror in a bid
contest. We decline to adopt such a rule. Instead, we reiterate
the established law in this circuit that non-prejudicial errors
in a bid process do not automatically invalidate a procurement.
Data Gen. Corp. v. Johnson, 78 F.3d 1556, 1562 (Fed. Cir. 1996);
Grumman Data Sys. Corp. v. Widnall, 15 F.3d 1044, 1048 (Fed.
Cir. 1994) (holding, inter alia, that de minimis errors by the
procuring agency are not sufficient grounds for overturning a
contract award); Andersen Consulting Co. v. United States, 959
F.2d 929, 932 (Fed. Cir. 1992) (same).
II.
In the same vein, Labatt
equates the two irregularities that occurred in this bid
process, (1) its late proposal submission, and (2) all three
offerors’ submission of proposal revisions by e-mail. Labatt
rushes past standing to the merits of its case, contending that
because Federal Acquisition Regulation 15.208(a) makes offerors
responsible for submitting proposals on time and by an
authorized transmission method, the issues of timeliness and
transmission method are necessarily and always of equal
importance. Indeed, Labatt’s primary argument is that it was
arbitrary and capricious for the government to enforce proposal
submission deadlines but not the solicitation’s instructions for
method of transmission. Essentially, its position is that if the
government makes any mistake in a procurement process related to
method of transmission, no matter how slight or unharmful, then
it must nullify the contest and begin anew.
Labatt’s position is
unavailing. As we said above, “to prevail in a protest the
protester must show not only a significant error in the
procurement process, but also that the error prejudiced it.”
Data Gen. Corp., 78 F.3d at 1562; JWK Int’l Corp., 279 F.3d at
988. To establish prejudice a protester must show that there was
a substantial chance it would have received the contract but for
the government’s error in the bid process. Bannum, 404 F.3d at
1358; Galen Med. Assocs., 369 F.3d at 1331; Info. Tech., 316
F.3d at 1319; Statistica, 102 F.3d at 1581. Labatt has not shown
that the government’s improper acceptance of e-mails throughout
the bid process interfered with its ability to receive the
contract award. To the contrary, the government’s mistaken
acceptance of bid revisions via e-mail neither helped nor
hindered any offeror. Labatt’s proposal would not have been
improved and its chances of securing the contract would not have
been increased if DSC cured the e-mail submission error. Thus,
it can not show that there was a substantial chance it would
have received the contract award but for the unauthorized
acceptance of e-mailed revisions and has therefore failed to
show that it was prejudiced by DSC’s erroneous acceptance of
them. There is no connection between the government’s method of
transmission error and Labatt’s failure to secure the contract.
Without a showing of harm specific to the asserted error, there
is no injury to redress, and no standing to sue.
Lateness, on the other
hand, is a different issue. Labatt was disqualified from further
consideration in the solicitation process because its response
to amendment 0007 was late, not because it was sent by e-mail
rather than overnight mail. Labatt was the only offeror to
submit a late response, and its untimely submission constituted
a separate and independently sufficient ground for rejection.
All errors are not equal.
There are inherent competitive advantages to submitting a
proposal after all other parties are required to do so, such as
access to post-deadline news and market information that could
result in last minute changes to the proposal. See, e.g., Data
Gen. Corp., 78 F.3d at 1561 (“The rule [that an offeror may not
modify its proposal after best and final offers are submitted]
is designed to prevent a bidder from gaining an unfair advantage
over its competitors by making its bid more favorable to the
government in a context where the other bidders have no
opportunity to do so.”). To avoid this potential for abuse,
submission deadlines are strictly enforced across the board.
When the rules and procedures of a bid process are applied
equally to all parties, but one party submits a proposal past
the deadline for doing so, the untimely submission becomes a
stranger to the process, and is disqualified from the
procurement. A late proposal is tantamount to no proposal at
all. Such a party has no “substantial chance” of award, and no
more standing to sue than the proverbial man on the street.
The method of
transmission error complained of by Labatt was not relevant to
Labatt’s removal from the competition, or the ultimate award of
the contract to USF. It was removed from the competition for an
untimely submission. Because the asserted error caused no harm,
there is no injury to redress and Labatt is entitled to no
relief. As such, Labatt failed to establish standing to
challenge DSC’s award to USF, and the Court of Federal Claims
had no jurisdiction to vacate the award. (Labatt
Food Service, Inc., v. U. S., No. 2009-5017, August 24,
2009) (pdf)
The trial court did not clearly err in finding that Bannum was
not significantly prejudiced by the BOP’s violations. To
establish prejudice Bannum was required to show that there was a
“substantial chance” it would have received the contract award
but for the BOP’s errors in the bid process. Info. Tech., 316
F.3d at 1319; Alfa Laval, 175 F.3d at 1367; Statistica, 102 F.3d
at 1582. This test is more lenient than showing actual
causation, that is, showing that but for the errors Bannum would
have won the contract. Alfa Laval, 175 F.3d at 1367; Data Gen.,
78 F.3d at 1562. Bannum necessarily relies on the difference
between the 104 points the BOP docked it based on the CEFs, and
the 74.5 points by which Alston Wilkes won the bid. Had the BOP
deducted fewer than 29.5 points for past performance, Bannum
would have prevailed. But neither Bannum nor the record explains
why Bannum had a substantial chance of scoring at least 74.5
points higher on past performance had the BOP reviewed the CEFs
in accordance with the FAR. The independent review pursuant to
the separate GAO proceeding increased Bannum’s past performance
award by 16 to 312 points, an amount insufficient to alter the
award outcome. There is nothing besides Bannum’s conjecture to
support the contention that another review, comporting with the
FAR, would provide it a substantial chance of prevailing in the
bid. Bannum’s argument rests on mere numerical possibility, not
evidence. In sum, we find no clear error in the trial court’s
determination and will not disturb it. Accordingly, the judgment
of the Court of Federal Claims is affirmed. (Bannum,
Inc. v. U. S., No. 04-5008, April 21, 2005) (pdf) |
|
U.
S. Court of Appeals for the Federal Circuit - Listing of
Decisions
|
For
the Government |
For
the Protester |
Labatt Food
Service, Inc., v. U. S., No. 2009-5017, August 24, 2009
(pdf) |
|
Bannum, Inc. v. U. S., No.
04-5008, April 21, 2005 (pdf) |
|
|
|