New
In requesting reconsideration, SCB argues that, in
dismissing its protest as academic, we failed to consider
the consequences of the VA’s termination and that the VA’s
decision to take corrective action enabled the agency to
avoid resolution of the protest. In this regard, SCB
contends, citing to Saltwater, Inc.-Recon. & Costs,
B-294121.3, B-294121.4, Feb. 8, 2005, 2005 CPD ¶ 33, that
the protest is not academic where, as here, the corrective
action provides no meaningful remedy. Recon. Request at 3.
SCB further contends that, by terminating XTec’s contract
for the convenience of the government after XTec produced
all of the PIV cards, FAR § 12.403(d) permits the VA to
receive the PIV cards and pay XTec 100 percent of the
contract price, thus circumventing GAO’s protest process.
Id. at 2.
Under our Bid Protest Regulations, to obtain
reconsideration the requesting party must set out the
factual and legal grounds upon which reversal or
modification of the decision is deemed warranted,
specifying any errors of law made or information not
previously considered. 4 C.F.R. § 21.14(a). We have held
that information not previously considered means
information that was not available during the earlier
protest. Norfolk Dredging Co.,--Recon., B-236259.2, Oct.
31, 1989, 89-2 CPD ¶ 405 at 2. SCB’s request meets this
standard for reconsideration.
Subsequent to the filing of SCB’s request for
reconsideration, we learned that on September 23--the same
day we notified the VA of SCB’s protest--the VA modified
XTec’s contract to require one bulk delivery of the
400,000 PIV cards. We also learned that the VA did not
direct XTec to stay performance until two days after
receiving notice of the protest. VA E-mail to GAO, Jan.
20, 2015; VA Response to Recon. Request at 2. We further
learned that the VA had no need to resolicit the
requirement after terminating the contract for the
convenience of the government because it had sufficient
stock of the cards after accepting delivery of, and paying
XTec for, the full quantity of 400,000 cards. VA E-mail to
GAO, Jan. 22, 2015.
In light of this new information, together with
reconsideration of the conclusions reached by our Office,
we agree with SCB that, as in Saltwater, Inc.--Recon. &
Costs, supra, the VA’s corrective action did not remedy
the concern raised in the protest. The VA’s decision to
terminate the contract after modifying the contract to
accelerate delivery, and after the awardee substantially
performed (and where the agency had no intention of
resoliciting for its requirements) is not the
commonly-understood meaning of an agency’s representation
that it is terminating the underlying contract. As a
result, we grant SCB’s request that we reconsider our
decision to dismiss its protest as academic.
We now turn to the merits of SCB’s protest. SCB contended,
in its earlier protest, that the VA erred in determining
that SCB’s PIV cards did not meet the requirements of the
RFQ. SCB argued that the VA’s evaluation methodology was
faulty because the solicitation did not contain the
information needed for the cards to pass the testing
process described in the agency’s report. Comments at 4.
As a general rule, a procuring agency must provide
sufficient information in a solicitation so that offerors
can compete intelligently and on a relatively equal basis.
IBM Global Business Servs., B-404498, B-404498.2, Feb. 23,
2011, 2012 CPD ¶ 36 at 8; Meridian Mgmt. Corp., B‑285127,
July 19, 2000, 2000 CPD ¶ 121 at 6. Based on the record
before our Office, we find that the RFQ did not reasonably
provide offerors adequate information to compete
intelligently. Specifically, the VA acknowledges that the
RFQ “did not set forth what is required in order for a
smart card to perform in the current VA PIV System.” VA
E-mail, Jan. 22, 2015. Further, this solicitation
deficiency was latent--that is, the deficiency was not
apparent until the VA submitted its agency report showing
that the evaluation methodology required offerors to rely
on information that the agency never provided. Finally, we
find that this latent solicitation deficiency resulted in
competitive prejudice to SCB because it resulted in the
elimination of SCB’s quote, which was otherwise in line
for award, from the competition. Accordingly, we sustain
SCB’s protest.
RECOMMENDATION
Because this delivery order has been fully performed and
the agency does not plan to resolicit for its
requirements, we recommend that SCB be reimbursed the
costs of preparing its quotation, as well as the
reasonable costs of filing and pursuing its protest and
its request for reconsideration. 4 C.F.R. §§ 21.8(b), (d).
SCB should submit its certified claim for costs, detailing
the time expended and costs incurred, directly to the
agency within 60 days of receiving this decision. 4 C.F.R.
§ 21.8(f)(1).
The request for reconsideration is granted; the protest is
sustained. (SCB
Solutions, Inc.--Reconsideration B-410450.2: Aug 12,
2015) (pdf)
In its request for reconsideration, the Army argues that
we erred in citing to our decision in Laidlaw Envtl. Servs.
(GS), Inc.; International Tech. Corp.--Claim for Costs,
B-249452, B-250377.2, Nov. 23, 1992, 92-2 CPD para. 366 at
4, to support our conclusion that the exercise of an
unevaluated contract extension amounted to a sole-source
extension beyond the scope of the contract, and in
determining that the option to extend DAV's contract had
not been evaluated as part of the initial competition.
To prevail on a request for reconsideration, the
requesting party must either show that our decision
contains errors of fact or law, or present information not
previously considered that warrants the decision's
reversal or modification. 4 C.F.R. sect. 21.14(a) (2009);
Department of Housing and Urban Dev.--Recon., B-279575.2,
Nov. 4, 1998, 98-2 CPD para. 105 at 2; Department of the
Army--Recon., B-271492.2, Nov. 27, 1996, 96-2 CPD para.
203 at 5. A request for reconsideration that reiterates
arguments made previously and merely expresses
disagreement with the prior decision does not meet the
standard for granting reconsideration. Gordon R.A.
Fishman--Recon., B-257634.4, Sept. 9, 1996, 96‑2 CPD para.
110 at 2-3. Here, the Army does not show that our decision
contains material errors of law or fact that warrant
modification or reversal or our prior decision.
The Army argues that we erred in citing to the Laidlaw
decision, because that case is factually distinguishable
from the facts presented in MCS's protest. Specifically,
in Laidlaw the option to extend the contract was added to
the contract at time of award, whereas in this case the
option to extend the contract clause was included in the
solicitation under which the offerors competed for the
initial award.
We agree that Laidlaw is factually distinguishable from
this case. That factual distinction, however, does not
demonstrate error, given that our decision was based upon
the FAR requirements for exercising options. As explained
in our prior decision, FAR sect. 17.207(f) requires that a
contracting officer, before exercising an option, make a
written determination that the exercise of the option is
in accordance with the terms of the option and the
requirements of FAR sect. 17.207 and FAR Part 6. FAR
sect. 17.207(f) further states that to meet the
requirements of FAR Part 6 regarding full and open
competition, the option must (1) have been evaluated as
part of the initial competition, and (2) be exercisable at
an amount specified in or reasonably determinable from the
terms of the basic contract. Both in Laidlaw and under the
facts presented here, the agency exercised an option that
had not been evaluated as part of the initial competition.
We found that the Army had not evaluated the option to
extend the contract as part of the initial competition,
and concluded that, in accordance with FAR sect.
17.207(f), the agency was required to (but did not)
reasonably justify the extension of the contract in
accordance with FAR sect. 6.303.
The Army does not contend that it evaluated the option to
extend the contract as part of the initial competition, but instead argues that it "basically conducted the
equivalent of such an evaluation, to the extent
practicable, when the Army evaluated the base year and
option year prices, which are the predicates upon which
the price of an extension period would be based, depending
upon when the extension was exercised." Recon. Request at
7. The Army also contends that the option to extend the
contract "essentially is self-executing because, when the
contracting officer decides to exercise the extension, the
clause causes the limits and rates specified in the
contract to be the applicable limits and rates, with no
upward or downward adjustment in rates permitted" except
as a result of revisions to prevailing labor rates. Id.
We find no merit to the Army's arguments, which would
render meaningless the specific language of FAR sect.
17.207(f) that requires that an option be evaluated as
part of the initial competition. The Army's interpretation
of this clause would either ignore the first requirement
under FAR sect. 17.207(f) or deem it to be satisfied when
the second requirement is met--that is, render one of the
two parts of the clause meaningless. Such an
interpretation would be inconsistent with the fundamental
principle that statutes and regulations must be read and
interpreted as a whole, thereby giving effect to all
provisions. See Sea Box, Inc., B‑291056, Oct. 31, 2002,
2002 CPD para. 181 at 3. In this regard, the agency cites
to no legal authority or any other authority that would
support its argument that an "equivalent" evaluation
satisfies this unambiguous regulatory requirement.
The purpose of the contract clause at FAR sect. 52.217‑8
is merely to reserve for the agency a right to seek from
the contractor--without further negotiation--an additional
period of performance beyond the end of a contract period
where exigent circumstances create the need for continued
performance. See FAR sect. 37.111; Akal Security, Inc.,
B‑244386, Oct. 16, 1991, 91-2 CPD para. 336 at 5. With
respect to the agency's argument that the option to extend
the contract clause was "self-executing," the fact that
the clause reserves this right for the procuring agency
does not mean that it relieves the agency of its
obligation to comply with the requirements in the FAR. The
Army's contention that, as a practical matter, an option
to extend under FAR 52.217‑8 would never be evaluated as
part of the initial competition does not create an
exception to the requirements of FAR sect. 17.207(f).
Rather, it simply means that where, as here, the agency
exercises an option to extend the contract that does not
satisfy the FAR sect. 17.207(f) requirements, the agency
should have a reasonable justification for its extension
in accordance with FAR Part 6.
The request for reconsideration is denied. (Department
of the Army--Reconsideration, B-401472.2,
December 7, 2009) (pdf) (For original case, see
Major Contracting Services,
Inc., B-401472, September 14, 2009)
EPA’S REQUEST FOR RECONSIDERATION
In its request for reconsideration, the agency asks that
we rescind or modify our June 4, 2007 decision sustaining
IBM’s protest, based on events that took place after we
issued our decision and based on information not
previously considered by our Office. In making its
request, EPA relies on an “Interim Agreement,” dated April
3, 2008, between it and IBM, pursuant to which IBM, on
April 4, 2008, withdrew its proposal from further
consideration for award during the agency’s implementation
of our recommendation for corrective action and agreed to
reimburse the agency for the costs paid by the agency to
the firm in accordance with the above-described
recommendation for corrective action.
Under our Bid Protest Regulations, to obtain
reconsideration, the requesting party must set out the
factual and legal grounds upon which reversal or
modification of the decision is deemed warranted,
specifying any errors of law made or information not
previously considered. 4 C.F.R. sect. 21.14(a) (2008).
Here, we conclude that the standard for reconsideration
has not been satisfied.
As stated above, in requesting reconsideration, the agency
relies on events that took place after we issued our June
4, 2007 decision sustaining IBM’s protest. In this regard,
on March 27, 2008, the agency suspended IBM from receiving
federal contracts based on information developed during
the course of a federal investigation into activities
related to IBM’s proposal and negotiations in this
procurement. According to the record, as documented in the
requests for reconsideration (not in the record as
developed during our review of IBM’s original protest),
the agency’s debarring official determined that there was
adequate evidence to support allegations that IBM
employees obtained protected source selection information
relevant to this procurement from an EPA
employee--information which IBM officials knew was
improperly acquired--and that IBM used this information
during its negotiations to improve its chance of winning a
contract, in violation of federal procurement procedures
and the procurement integrity provisions of the Office of
Federal Procurement Policy Act. Interim Agreement, Apr. 3,
2008. The agency’s suspension of IBM was issued as a
temporary action pending completion of the investigation
and other possible proceedings, including debarment
action. Suspension Notice, Mar. 27, 2008.
Following IBM’s receipt of the suspension notice, IBM
acknowledged the apparent violations by its employees and
agreed to withdraw its proposal from further consideration
for award in this procurement; IBM also agreed to refund
to the agency all costs paid to IBM in connection with the
underlying protest and to take other steps, such as
conducting a full examination of the firm’s federal
compliance program and cooperating with EPA investigators
and other federal officials, to promptly and appropriately
conclude the matter. In return, the agency agreed to
immediately terminate the temporary suspension and to
remove IBM’s name from the Excluded Parties List, subject
to specific terms and conditions. Interim Agreement,
supra. IBM formally withdrew its proposal on April 4,
2008.
In requesting rescission or modification of our decision
sustaining IBM’s protest, the agency states that it
“recognize[s] the public interest in providing the federal
acquisition community and other interested parties with
the results of [our Office’s] thorough analysis in this
matter,” but maintains that “there are countervailing
considerations when an offeror’s efforts to secure a
federal contract have been tainted by improper conduct,”
and it asks that we “recognize these circumstances in
[our] final disposition of the protests.” EPA Request for
Reconsideration at 2. However, we conclude that the agency
has failed to provide any basis warranting our rescission
or modification of the underlying decision sustaining
IBM’s protest.
In this regard, the agency has cited no legal authority to
support its request and it has not, for example,
demonstrated any error or injury that results from the
decision as written; moreover, the agency has neither
alleged nor shown any nexus between the alleged improper
use of proprietary information by IBM employees and our
finding with respect to the agency’s improper adjustment
of fixed-price elements in IBM’s proposal. In short, the
agency has not pointed out any procedural or substantive
flaw in the underlying decision resulting from subsequent
events and from information that was not previously
disclosed during the development of the protest record or
at the time the decision was issued which would
necessitate some sort of correction of that decision in
light of the newly-disclosed information.
While we are not aware of any instance in which our Office
has been asked to rescind a published protest decision,
the United States Civilian Board of Contract Appeals
recently addressed a request that the Board vacate one of
its decisions. See Hedlund Constr., Inc. v. Dep’t of
Agriculture, CBCA 105-R, Civilian B.C.A., June 5, 2008
(citing U.S. Bancorp Mortgage Co. v. Bonner Mall P’ship,
513 U.S. 18, 29 (1994), in which the Supreme Court
explained its view that settlement of a dispute by the
parties after the issuance of a decision does not justify
vacatur of an issued decision). See also ROI Invs. v. GSA,
GSBCA 14402-R, 99-1 BCA para. 30,353 (absent some
extraordinary circumstance, the public interest would not
be served by rescinding a published decision).
In our view, published decisions provide valuable
information to the procurement community in terms of, for
example, analyzing violations of procurement statutes and
regulations and explaining why such violations provide a
basis for sustaining a protest. To the extent that EPA
asks that we “recognize [the] circumstances” regarding the
subsequently disclosed investigation and the agreement
between it and IBM, the discussion in this decision
denying the agency’s request for reconsideration
effectively does so. In this connection, we note that our
recommendation for corrective action was valid under the
facts as they existed during our Office’s review of IBM’s
original protest, and we expect no further action with
regard to that recommendation based on subsequent events.
CGI’S REQUEST FOR RECONSIDERATION
CGI requests that we vacate the underlying decision
sustaining IBM’s protest on two grounds--first, that IBM
was not an interested party and, therefore, lacked
standing for purposes of filing a protest in light of its
acknowledged procurement integrity violations resulting in
its suspension from receiving federal contracts and,
second, that “profound factual uncertainties undercut the
factual conclusions on which the GAO decision was
premised.” CGI Request for Reconsideration at 1.
Regarding its first argument, CGI points out that a
“non-responsible bidder” has no interest in the outcome of
a procurement--suggesting that a suspended offeror would
similarly lack the requisite interest for filing a
protest--thereby implying that IBM’s suspension and
subsequent agreement to withdraw its proposal from
consideration for award in this procurement should, in
essence, void the published decision. Id. at 2. We do not
find this argument persuasive.
More specifically, it is clear from the record that when
IBM filed its protest on February 26, 2007, it was not a
suspended contractor. We issued our decision sustaining
IBM’s protest on June 4, 2007. The agency issued its
notice of suspension on March 27, 2008, and the Interim
Agreement between the agency and IBM was signed on April
3, 2008. The agency’s suspension notice stated, “effective
immediately, I [EPA’s debarring official] have suspended
[IBM] from participating in Federal procurement and
nonprocurement activities.” Suspension Notice, supra, at
1. Thus, the suspension notice makes clear that the
suspension was to have an immediate, as opposed to a
retroactive, effect.[3] Therefore, since IBM had not been
suspended from competing for federal contracts at the time
the protest was filed, during the development of the
protest record, and when the decision sustaining the
protest was issued, the firm was eligible to compete under
the RFP and had the status of an interested party to
challenge the agency’s evaluation of proposals and award
decision.
Moreover, Federal Acquisition Regulation (FAR) Subpart
9.4, which the agency cited in its suspension notice as
authority for its actions, makes clear that suspension and
debarment do not have a retroactive effect. For example,
FAR sect. 9.405-1(a) provides that “[n]otwithstanding the
debarment, suspension, or proposed debarment of a
contractor, agencies may continue contracts or
subcontracts in existence at the time the contractor was
debarred, suspended, or proposed for debarment unless the
agency head directs otherwise.” Therefore, contrary to
CGI’s suggestion, we have no basis to conclude that the
suspension and Interim Agreement between the agency and
IBM should retroactively affect the interested party
status or standing to protest that IBM had at the time it
filed its protest since, as stated above, at that time,
IBM was not a suspended contractor. In other words, until
the suspension was imposed and IBM was notified (see FAR
sect. 9.407-3(c) (requires that a contractor be
immediately advised when it is suspended)), IBM was “an
actual . . . offeror whose direct economic interest would
be affected by the award of a contract or by the failure
to award a contract,” satisfying our regulatory definition
of an interested party with standing to file and pursue
its protest. 4 C.F.R. sect. 21.0(a)(1). On this record, we
find no merit in CGI’s argument that IBM’s status as an
interested party should be viewed from the vantage point
of the subsequent events, as set forth above, which would
involve the complete disregard of the facts as they
existed from the point at which the protest was filed
until the decision sustaining IBM’s protest was issued.
Regarding its second argument, we similarly find no merit
to CGI’s allegation that “factual uncertainties,” which
purportedly cannot now be resolved, were the foundation
for our decision, thereby compromising the precedential
value of that decision. As discussed above, no error or
injury has been demonstrated that would result from the
decision as written, nor has any nexus between the alleged
improper use of proprietary information by IBM employees
and our finding with respect to the agency’s improper
adjustment of fixed-price elements in IBM’s proposal been
alleged or shown. The value of the underlying decision
sustaining IBM’s protest derives from the legal
conclusions that were drawn in the context of the existing
and known facts. While a subsequent change in facts could
lead to a different legal conclusion, the facts that
emerged based on subsequent events do nothing under the
circumstances here to alter the validity of the original
decision, which applied the law to the facts as presented
during our Office’s review of IBM’s original protest.
The requests for reconsideration are denied. (Environmental
Protection Agency; CGI Federal, Inc.--Reconsiderations,
B-299504.3; B-299504.4, July 23, 2008) (pdf) |