4
CFR 21.8 (d): Payment of Protester's Costs |
Comptroller General - Key Excerpts |
New
The protester requests reimbursement of its proposal
preparation costs, all of its protest-related legal fees,
and the fees incurred in filing this claim for costs with
GAO. The agency has agreed to reimburse the protester
reasonable proposal preparation costs and the fees
associated with the one meritorious challenge to the
agency’s technical evaluation on which the protest was
sustained, but disputes the request to reimburse the
protester for the legal fees associated with pursuing this
claim for reimbursement. We consider each of these
elements of the claim, in turn, below.
Proposal Preparation Costs
The protester seeks to recover $48,851.68 as the
reasonable costs of preparing its proposal. Claim at 2.
Where our Office sustains a protest, we may recommend that
the protester be reimbursed its costs of filing and
pursuing a protest and preparing a proposal. 4 C.F.R. §
21.8(d). Although we normally do not recommend
reimbursement of proposal preparation costs where a
protester has a further opportunity for award, we may
recommend reimbursement where, for instance, changed
circumstances render no longer relevant a proposal that
was previously submitted. See COBRO Corp., B‑287578.2,
Oct. 15, 2001, 2001 CPD ¶ 181 at 8-9. Here, because the
awarded lease contains no termination clause, there is no
relief available to the protester except reimbursement of
its costs. In these circumstances, we recommend the
reimbursement of the reasonable costs of preparing the
protester’s proposal. The agency has offered to reimburse
the protester $47,242.00, the amount requested by the
protester, less reimbursement for certain disputed travel
expenditures. Agency Reply at 14.
Specifically, GSA contends that the attendance of the wife
of Federal Builders’ principal at the market survey--the
initial meeting at the current leased facility between the
agency and the protester--was unnecessary, and the agency
thus requests that we not grant the protester’s request
that we recommend reimbursement of Federal Builders for
her expenses. Agency Reply at 3-4. The agency notes in
this regard that the wife is not an employee of Federal
Builders and that the protester claims no reimbursement
for her time. See Claim, Exh. 5, Letter from Agency to
Federal Builders, Feb. 2, 2015 at 2. The protester asserts
that the disputed amount of reimbursement, $1,609.48, is
reasonable, given that the protester is not asking for the
reimbursement for the expenses incurred by the attendance
of other Federal Builders employees at the market survey
meeting, and that the principal’s wife performed valuable
services of notetaking. Protester’s Comments, Sept. 18 at
8.
We agree with the agency that the protester has not shown
that the wife’s expenses are reimbursable. The manager’s
wife was not an employee of the firm, and the protester
has sought no reimbursement for her time spent as a note
taker, thus calling into question whether her presence at
the meeting was a reasonable business expense. Further,
the fact that the protester has not requested
reimbursement of the expenses incurred by other
individuals at the meeting in no way alters the fact that
the protester has not shown that the wife’s expenses were
reimbursable. We therefore recommend that the agency
reimburse the protester proposal preparation costs of
$47,242.00, that is the level of reimbursement agreed to
by the agency, and the amount requested by the protester
less reimbursement for expenses related to the manager’s
wife’s attendance at the market survey meeting.
Attorneys’ Fees Associated with Pursuing the Protest at
GAO
The protester also requests reimbursement of all of its
attorneys’ fees in this matter, totaling $231,796.64. The
agency responds that the protester should be reimbursed
only for the costs of pursuing the one issue on which we
sustained the protest, the agency’s unreasonable
conclusion that the awardee had committed to meeting the
solicitation requirement that it pay Davis-Bacon wage
rates for expansion of its proposed facility. Agency Reply
at 4-14.
We recommend that the protester be reimbursed the cost of
filing its comments on the agency report and supplemental
protest, as well as all subsequent attorneys’ fees
incurred. The allegation that the agency unreasonably
concluded that the awardee had committed to paying
Davis-Bacon wage rates--the issue on which the protest was
sustained--was contained in the combined comments and
supplemental protest; rather than take timely corrective
action, the agency continued to defend its evaluation,
causing the protester to incur unnecessary attorneys’
fees.
According to protest counsel’s invoices to Federal
Builders, the protester incurred legal fees of $177,252.50
after the filing of the agency report. See Claim, Exh. 2.
We therefore recommend that Federal Builders be reimbursed
$177,252.50--the cost of filing the supplemental protest
containing the allegation on which the protest was
sustained, as well as all of the fees incurred as a result
of the agency’s decision to continue the litigation rather
than take corrective action. In addition, the agency has
agreed that the protester is entitled to reimbursement for
fees related to compliance with and admission to the
protective order, and with filing a successful opposition
to the agency’s request for dismissal of the protest. See
Agency Comments, Sept. 24 at 5, 7. The agency calculates
the fees related to the protective order at $709.60 and
the protester does not dispute that calculation. See id.
at 7-8. A review of invoices for June and July indicates
that protest counsel billed the protester $4,960 in fees
to respond to the agency’s unsuccessful motion for partial
dismissal. In these circumstances, we recommend that
Federal Builders be reimbursed a total of $182,922.10 in
attorneys’ fees for filing and pursuing its protest at
this Office.
Costs Associated with Pursuing the Claim
Pursuant to our Bid Protest Regulations, we may recommend
that a contracting agency pay a protester the costs of
pursuing its claim for reimbursement with our Office. 4
C.F.R. § 21.8(f)(2). This provision is intended to
encourage the agency’s expeditious and reasonable
consideration of a protester’s claim for costs. JAFIT
Enters., Inc.--Claim for Costs, B-266326.2, B-266327.2,
Mar. 31, 1997, 97-1 CPD ¶ 125 at 4. However, we will
recommend payment of such costs only if it is shown that
the agency failed to consider, or unreasonably delayed
consideration of, the protester’s claim. Blue Rock
Structures, Inc.--Costs, B‑293134.2, Oct. 26, 2005, 2005
CPD ¶ 190 at 6.
Here, the protester submitted its claim for costs to the
agency on November 6, 2014; that claim included, in part,
the following: line item entries for all time spent and
expenses incurred by Federal Builders and its consultants
in preparing and pursuing its protest; detailed monthly
invoices for outside counsel, Jones Day, that identified
by attorney the time spent working on the protest; support
for the reasonableness of Jones Day’s hourly rates;[2] and
line item entries for all time spent by Federal Builders
in pursuit of the protest. Claim, Nov. 6, 2014, Exh. 2.
On the principal issue of the reasonable amount of
attorneys’ fees to reimburse, the agency had all of the
information necessary to make an offer of settlement to
Federal Builders at the time the protester first submitted
its certified claim to the agency, but the agency instead
waited 10 months before making its offer. This delay is
attributable to the agency. Further, the agency’s initial
offer of settlement of the legal fees portion of the claim
that immediately preceded the protester’s submission of
its claim to this office was only $4,000. Claim, Nov. 6,
2014, Exh. 14, Letter from Agency to Federal Builders,
July 24, 2015 at 7. That offer was less than two percent
of the amount that the protester had requested, and was
considerably less than the amount ($39,104.53) to which
the agency itself agreed in the course of the subsequent
negotiations to settle this claim. See Agency Comments,
Sept. 24, 2015, at 10 (agreeing to reimburse protester
$39,104.53 for attorneys’ fees for filing and pursing the
protest and supplemental protest).
In our view, the lengthy delay in the agency’s initial
offer of settlement of the legal fees and the disparity
between the offer and what the agency later agreed should
be reimbursed support the reasonableness of the
protester’s request for reimbursement of the attorneys’
fees required to pursue the claim with this Office. We
therefore recommend that the agency reimburse Federal
Builders $21,577.50 for the costs of pursuing its claim
with GAO. See Email from Federal Builders to GAO, Oct. 26,
2015 (containing invoices for August and September); Email
from Federal Builders to GAO, Nov. 9, 2015 (containing
October invoice).
Conclusion
In sum, we recommend that the agency reimburse Federal
Builders a total of $259,488.52, including proposal
preparation costs of $47,242.00, $182,922.10 in attorneys’
fees for filing and pursuing the protest, $7,746.92 for
the time spent by Federal Builders’ manager in assisting
counsel in preparing and pursuing the protest, and
$21,577.50 for the costs of pursuing its claim for
reimbursement. (Federal
Builders, LLC-The James R. Belk Trust--Costs
B-409952.3: May 6, 2016) (pdf)
In our view, Debcon raised a clearly meritorious challenge
to the evaluation. Notwithstanding the Corps’s position in
the agency report and supplemental agency report, it was
contrary to regulation for the agency to rate Debcon, as a
small business, merely acceptable under the small business
participation plan factor where higher ratings were
available. Nevertheless, the Corps argues that any
misevaluation under the small business participation plan
factor was not prejudicial to Debcon either because
Atherton was also a small business, or because the small
business participation plan evaluation “did not figure in
the overall decision to award to Atherton.” Corps
Opposition to Costs at 3. Our review of the record leads
us to disagree. The RFP provided that the non-price
factors, when combined, would be significantly more
important than price in making the source selection
decision, RFP amend. 1 at 4, and as noted above, Debcon’s
proposal offered a lower price than Atherton’s. Although
we cannot say whether the Corps would still have
determined that Atherton’s proposal justified the payment
of its higher price if Debcon had been evaluated properly
under the small business performance plan factor, in such
circumstances, we resolve doubts regarding prejudice in
favor of a protester. Raytheon Co., B-409651, B-409651.2,
July 9, 2014, 2014, CPD ¶ 207 at 17.
As to Debcon’s other evaluation challenges, however, the
Corps presented a defensible legal position based on the
factual record, so we cannot regard those issues as
clearly meritorious. For example, Debcon argued that the
Corps improperly imposed an unstated evaluation criterion
and unreasonably evaluated the past performance factor by
requiring offerors to have at least two very relevant past
performance references in order to be eligible for the
highest past performance rating. Our Office has held that
such a requirement is reasonable, however, and need not be
disclosed in the solicitation. See A&D Gen. Contracting,
Inc., B‑409296, Feb. 24, 2014, 2014 CPD ¶ 71 at 5 (protest
denied where evaluation required a minimum of four
relevant projects to be eligible for highest past
performance rating, even though requirement was not
disclosed in solicitation). Since Debcon had only one very
relevant project as its past performance, the Corps
considered Debcon to be ineligible to receive the best
past performance rating (substantial confidence). Thus,
the Corps was not required to consider the project’s
greater complexity or Debcon’s positive ratings for that
work. Similarly, Debcon’s argument that the past
performance evaluation showed unequal treatment when
compared to Atherton was also not clearly meritorious. The
Corps presented a defensible legal position that the
evaluation of Debcon and Atherton differed because
Atherton submitted multiple past performance examples,
making irrelevant Debcon’s effort to compare its past
performance with Atherton’s on the basis of relevance and
quality.
Ultimately, Debcon presented one clearly meritorious
evaluation challenge, while its other grounds of protest
were either not clearly meritorious or the corrective
action was prompt. Accordingly, we must consider whether
the reimbursement of only a portion of the protester’s
costs is proper. As a general rule a successful protester
should be reimbursed the costs incurred with respect to
all the issues pursued, not merely those upon which it has
prevailed. Salvation Army Cmty. Corr. Program--Costs,
B‑298866.3, Aug. 29, 2007, 2007 CPD ¶ 165 at 7
(recommending reimbursement of costs including those
raised after receipt of agency report). In determining
whether to limit the reimbursement of costs, our Office
considers, among other things, whether the successful and
unsuccessful arguments share a common core set of facts,
are based on related legal theories, or are otherwise not
readily severable. Burns & Roe Servs. Corp.--Costs,
B-310828.2, Apr. 28, 2008, 2008 CPD ¶ 81 at 2-3.
In applying these principles, we have severed costs
arising from allegations of misevaluation under separate
evaluation factors on the basis that they are not clearly
intertwined. For example, challenges to a past performance
evaluation were not clearly intertwined with clearly
meritorious challenges to the technical factor evaluation
and the resulting tradeoff. Genesis Bus. Sys.--Costs,
B-411264.11, Dec. 10, 2015, 2015 CPD ¶ 389 at 4; see also
Carney, Inc.--Costs, B-408176.13, Feb. 14, 2014, 2014 CPD
¶ 82 at 5 (severing costs for alleged misevaluation of
price from clearly meritorious challenge to technical
capability factor evaluation); Loyal Source Gov’t Servs.,
LLC--Costs, B-407791.4, Feb. 14, 2014, 2014 CPD ¶ 139 at 4
(severing costs for evaluation challenges from clearly
meritorious challenge to adequacy of best value tradeoff
rationale). In a similar fashion, we severed the costs for
challenges to the evaluation of the awardee and to the
agency’s alleged failure to amend a solicitation because
those issues were not clearly intertwined with a clearly
meritorious allegation of unequal discussions. VSE Corp.;
Univ. of Hawaii--Costs, B‑407164.11, B‑407164.12, June 23,
2014, 2014 CPD ¶ 202 at 8.
On the record here, we regard none of the protester’s
challenges to the evaluation of its own proposal as
intertwined with the clearly meritorious challenge to its
evaluation under the small business performance plan
factor. Accordingly, we do not recommend reimbursement of
the costs of filing and pursuing any other issues.
(Debcon, Inc.--Costs
B-412298.3: Apr 26, 2016) (pdf)
Our Regulations provide for
reimbursement, in appropriate circumstances, of reasonable
proposal preparation and protest pursuit costs. 4 C.F.R. §
21.8(d). A protester seeking to recover its protest costs
must submit evidence sufficient to support its claim that
those costs were incurred and are properly attributable to
filing and pursuing the protest. Stocker & Yale,
Inc.--Claim for Costs, B-242568.3, May 18, 1993, 93-1 CPD
¶ 387 at 4. At a minimum, claims for reimbursement must
identify and support the amounts claimed for each
individual expense (including cost data to support the
calculation of claimed hourly rates), the purpose for
which that expense was incurred, and how the expense
relates to the protest before our Office. International
Program Group, Inc.--Claim for Costs, B‑400278.4,
B‑400308.4, June 22, 2009, 2009 CPD ¶ 128 at 3. The burden
is on the protester to submit sufficient evidence to
support its claim; that burden is not met by general,
inadequately-supported statements that particular costs
have been incurred. Aztec Dev. Co.--Claim for Costs,
B‑270275.2, Feb. 13, 1997, 97-1 CPD ¶ 73 at 2. Failure to
file an adequately-supported claim in a timely manner will
result in the loss of the protester’s right to recover
costs. Wind Gap Knitwear, Inc.--Claim for Costs,
B‑251411.2; B-251413.2, Aug. 30, 1995, 95-2 CPD ¶ 94 at 3
(claim that lacks detail is denied).
Although we do not doubt that the protester spent some
time in preparing the protest, and responding to the
agency report, we find that Slaughter has not provided
adequate documentation to support this claim. In this
respect, the protester states that it will “settle the
claim for any amount,” Slaughter Email to GAO, Oct. 16,
2015, and the only supporting documentation provided is a
calendar with the phrase “8 Hrs” written on each of the
weekdays from February through June of 2015. The protester
has not provided any explanation as to what efforts were
performed during that time, or by whom. The claim also
does not provide any cost data to support the calculation
of the hourly rates for Ryan P. Slaughter. Furthermore,
repeated requests by the agency for the protester to
provide a more detailed accounting of its efforts did not
yield any further information.
Although we recognize that the requirement for
documentation may sometimes entail certain practical
difficulties, we do not consider it unreasonable to
require a protester to document in some detail the amount
and purposes of its claimed efforts, and to establish that
the claimed hourly rates reflect actual rates of
compensation. John Peeples--Claim for Costs, B‑233167.2,
Aug. 5, 1991, 91-2 CPD ¶ 125 at 3. Given the complete lack
of documentation we cannot recommend that the Air Force
reimburse the costs sought by Ryan P. Slaughter because
the claim does not meet the established minimum standards.
Wind Gap Knitwear, Inc.‑-Claim for Costs, supra. (Ryan
P. Slaughter--Costs B-411168.4: Dec 14, 2015) (pdf)
DILIGENT PURSUIT
As an initial matter, the agency requests that we deny S3’s
request because the firm failed to diligently pursue its claim.
In this connection, the agency points out that, despite it
having offered S3 an amount in settlement of its request on
September 15, 2014, S3 did nothing to pursue its claim for over
four months.
We agree with the agency that S3 failed to diligently pursue its
claim. Our Bid Protest Regulations contemplate prompt resolution
of protest matters, including claims for protest costs;
accordingly, we require protesters to diligently pursue such
claims. Holloway & Co., PLLC--Costs, B-311342.5, July 6, 2009,
2009 CPD ¶ 146 at 2-3. Here, the record shows that the agency
made a final settlement offer to S3 on September 15, 2014. That
offer expressly invited S3 to contact the contracting officer
should the firm have any questions concerning the agency’s
settlement offer. Agency Response to Cost Claim, exh. 2,
Contracting Officer’s Final Decision Concerning S3’s Claim, at
4. Notwithstanding the contracting officer’s invitation to
answer any questions that S3 might have concerning the agency’s
settlement offer, the record shows that S3 did nothing--either
to arrange for payment of the amount offered by the agency, or
to file its claim in our Office--for a period of more than four
months.
S3 suggests that it was the agency that failed to take any
action after sending S3 its September 15 letter. In this
connection, S3 contends that the agency failed to request a
purchase order from the firm, failed to remit payment to the
firm, and failed to provide a timetable for making the proposed
payment to S3. However, the record shows that it was S3 that
failed to take any action by, at the very least, advising the
agency that it either accepted or rejected the proposed
settlement offer. Simply stated, S3 took no action of any sort
in response to the agency’s offer for a period of more than four
months, notwithstanding that, by filing its request with our
Office, it apparently now has rejected the agency’s proposed
settlement offer. Cf. Holloway & Co., PLLC--Costs, supra.
(following agency’s proposed settlement offer, claimant
requested that agency reconsider the amount of its proposed
offer and agree to the amount originally requested by the
claimant). Under the circumstances, we conclude that S3 failed
to diligently pursue its claim. See Aalco Forwarding, Inc., et
al.--Costs, B-277241.30, Jul. 30, 1999, 99-2 CPD ¶ 36 at 5 (GAO
agreed with agency conclusion that the protester failed to
diligently pursue its claim for costs when the protester did not
respond for more than three months after the agency sought
additional supporting information for the claim). (System
Studies & Simulation, Inc.--Costs B-409375.5: May 8, 2015)
(pdf)
The agency first
argues the claimed attorneys’ hours are excessive and
duplicative because the protest issue was straightforward and
simplistic in nature and should not have required 93 hours of
attorneys’ time. We find this argument is meritless.
Our Office will examine the reasonableness of attorney hours
claimed to determine whether they exceed, in nature and amount,
what a prudent person would incur in pursuit of his or her
protest. Price Waterhouse--Claim for Costs, B-254492,
B-254492.3, July 20, 1995, 95-2 CPD ¶ 38 at 5. A recommendation
that an agency pay a protester’s costs is intended to relieve
protesters, with valid claims, of the burden of vindicating the
public interests which Congress seeks to promote; it is not
intended as a reward to prevailing protesters or as a penalty
imposed upon the government. W.S. Spotswood & Sons, Inc.--Claim
for Costs, B-236713.3, July 19, 1990, 90-2 CPD ¶ 50 at 3. Our
Office generally accepts the number of attorney hours claimed,
unless the agency identifies specific hours as excessive and
articulates a reasoned analysis as to why payment for those
hours should be disallowed. Pulau Elecs. Corp.--Costs,
B-280048.11, July 31, 2000, 2000 CPD ¶ 122 at 6. An agency
simply concluding that the hours claimed are excessive or
suggesting there may be a duplication of effort is inadequate to
justify denying a claim for protest costs. Id.
Our review of the claimed hours furnishes no basis for
concluding that they exceeded, in nature or amount, what a
prudent person would incur in pursuit of this protest, and we
find no basis to question Shaka's claim in this regard. The
record shows that Shaka submitted detailed billing statements,
which included the description of the work performed by each
attorney. The agency has not asserted that any specific charge
is inappropriate, and does not question whether the attorneys
actually worked the hours claimed. Under the circumstances, we
find the agency’s assertions that Shaka’s claimed attorney hours
were excessive and duplicative are unsupported, and find that
these arguments therefore are insufficient to justify denying or
reducing Shaka’s claim. See Pulau Elecs. Corp.--Costs, supra.
Furthermore, we do not agree with the agency that the issue
raised by the protester was a narrow, simplistic, and
uncomplicated legal issue that did not justify the hours
claimed, particularly given that this was a case of first
impression for our Office.
The agency also now argues that Shaka’s cost claim for the
attorneys’ fees incurred by Fay are not reimbursable because Fay
was not a party to the protest. This argument also has no merit.
We have addressed this specific point in TMC, Inc.--Claim for
Costs, B-230078.2, B-230079.2, Jan. 26, 1990, 90-1 CPD ¶ 111. As
in TMC, this is not a case where the costs were incurred by a
potential subcontractor acting independently of the interested
party, Shaka, the actual or prospective offeror. Rather, we find
the record shows that the costs were incurred by Fay acting in
concert with, and on behalf of Shaka, in order to provide Shaka
with legal assistance in the protest. In this regard, the record
shows that Shaka and Fay had an agreement to split the legal
costs of pursuing the protest, that the legal fees incurred by
Fay were in fact for the pursuit of Shaka’s protest, and that
Shaka will reimburse the amount paid by Fay in pursuit of this
protest when the amounts are recovered by Shaka. In these
circumstances, we believe the purpose of the statutory provision
allowing recovery of protest costs--to relieve parties with
valid claims of the burden of vindicating the public
interest--is best effectuated by finding Shaka entitled to
recover the costs incurred by Fay in concert with and on behalf
of Shaka in pursuing this protest. Id. at 3.
Thus, we recommend payment of $22,275 of Shaka’s claimed costs:
$15,450 for 47.7 hours of attorney time invoiced to Shaka at
each attorney’s full billing rate, and $6,825 for 45.5 hours of
attorney time invoiced to Fay at the $150 per hour rate.
Shaka also requests reimbursement for the costs of pursuing this
claim before our Office. Our Bid Protest Regulations, 4 C.F.R. §
21.8(f)(2), provide that we may recommend reimbursement of the
costs of pursuing a claim before our Office. See CNA Indus.
Eng’g, Inc.--Costs, B-271034.2, Nov. 20, 1997, 97-2 CPD ¶ 149 at
7. This provision is intended to encourage the agency’s
expeditious and reasonable consideration of a protester’s claim
for costs. JAFIT Enters., Inc.--Claim for Costs, B-266326.2,
B-266327.2, Mar. 31, 1997, 97-1 CPD ¶ 125 at 4. Here, given the
agency’s failure to reasonably consider Shaka’s claim, we find
that the protester may recover the reasonable costs of pursuing
its claim at our Office. (Shaka,
Inc.--Claim for Costs, B-405552.2, May 17, 2012) (pdf)
A protester
seeking to recover the costs of pursuing a protest must submit
sufficient evidence to support its monetary claim. John Peeples--Costs,
B-233167.2, Aug. 5, 1991, 91-2 CPD para. 125 at 3. The amount
claimed may be recovered to the extent that the claim is shown
to be sufficiently related to the filing and pursuit of the
protest, adequately documented, and reasonable in its nature and
amount. JAFIT Enters., Inc.--Costs, B-266326.2, B-266327.2, Mar.
31, 1997, 97-1 CPD para. 125 at 2.
The agency here objects to reimbursement of the costs related to
three of Mr. Kirkland's itemized work entries. We have reviewed
the objections and the protester's response, and we agree with
the agency's position. First, Mr. Kirkland describes a charge of
$1,134 (for work performed on March 17) as including work
related to a previously dismissed protest (B-401172, which is
not relevant here), as well as work related to the protest
associated with this claim. Since the single work entry
aggregates allowable and unallowable costs in a way such that we
cannot tell from the record what portion is unallowable, the
entire amount must be disallowed. See TRESP Assocs.,
Inc.--Costs, B-258322.8, Nov. 3, 1998, 98-2 CPD para. 108 at 4.
Likewise, since a $252 charge (for work performed on March 23)
again aggregates unallowable charges (e.g., for the preparation
of a letter for the contracting officer, which has not been
shown to have been performed in pursuit of the protest) with
allowable expenses (e.g., regarding communications about the
status of the protest), the entry must be disallowed in its
entirety. Id. Lastly, as the agency points out, a $126 work
entry (for work performed on April 28) must be denied, as it was
not in pursuit of the protest; the work instead involved
protester counsel's efforts toward possible settlement of the
protest. See Blue Rock Structures, Inc.--Costs, B-293134.2, Oct.
26, 2005, 2005 CPD para. 190 at 6.
The agency also objects to the costs for six work entries for
Mr. Billings, primarily on the basis that they involve counsel's
efforts toward settlement, and thus not pursuit, of the protest.
We agree with the objections to two of the work entries, Mr.
Billing's invoices for $160 (for work on April 28) and $80 (for
work on April 29), as the work concerns efforts toward possible
settlement of the action, and thus are not allowable costs. See
T Square Logistics Servs. Corp., Inc.--Costs, B-297790.6, June
7, 2007, 2007 CPD para. 108 at 10-11. The other four work
entries challenged by the agency (totaling $2,400), however, are
considered allowable costs, and are included in our
recommendation. The agency's assertion that these costs should
not be reimbursed is unpersuasive as there is no showing that
the costs related to settlement efforts or otherwise should not
be allowed.
The protester also generally requests reimbursement of its costs
related to the pursuit of its claim to our Office. We deny the
request. Under our Bid Protest Regulations, 4 C.F.R. sect.
21.8(f)(2) (2010), we will recommend such payment only if it is
shown that the agency failed to give reasonable consideration
to, or unreasonably delayed consideration of, the protester's
claim. See Blue Rock Structures, Inc.--Costs, supra at 7. Here,
while the agency ultimately abandoned its initial objections,
perhaps due to the additional explanation of the claim provided
by the firm in its filing to our Office, there has been no
showing that the agency failed to give reasonable consideration
to the claim. Similarly, to the extent the protester now argues
that the agency's request for proof of payment of its claimed
attorneys' fees was not legally required, and thus, the request
unreasonably delayed the agency's consideration of the claim, we
find the protester's position unpersuasive. As the agency
explains, it reasonably sought the information in order to
confirm that Baine Clark was obliged to pay the claimed
attorneys' fees; additionally, the firm did not object to the
request, pose an alternate means to further demonstrate its
obligation to pay the attorneys' fees it claimed, or immediately
respond to the agency's request for the information. Rather, the
record shows the protester added to the alleged delay by taking
several weeks to provide the requested proof of payment.
Further, the record shows that additional questions were
reasonably raised by the proof of payment submitted by the
protester, since the payment amount exceeded the amount claimed
by the protester, requiring additional time for the agency to
resolve the matter. See University of Dayton Research
Institute--Costs, B-296946.7, Oct. 23, 2006, 2006 CPD para. 155
at 4.
Accordingly, we recommend that the agency reimburse Baine Clark
a total of $24,908.34, representing $4,458.34 for Mr. Kirkland's
fees and $20,450 for Mr. Billing's fees. (Baine
Clark Company, Inc.--Costs, B-401172.4, June 7, 2010) (pdf)
Even where an
agency agrees to reimburse a protester's reasonable proposal
preparation costs, a protester seeking to recover such costs
must submit sufficient evidence to support its claim. John
Peeples--Costs, B-233167.2, Aug. 5, 1991, 91-2 CPD para. 125 at
3. At minimum, claims for reimbursement must identify and
support the amounts claimed for each individual expense
(including cost data to support the calculation of claimed
hourly rates for employees), the purpose for which each expense
was incurred, and how the expense relates to the claim.
Maintenance and Repair--Costs, B-251223.4, June 24, 1994, 94-1
CPD para. 381 at 4. Although we recognize that the requirement
for documentation may sometimes entail certain practical
difficulties, we do not consider it unreasonable to require a
protester to document in some detail the amount and purposes of
its claimed efforts. W.S. Spotswood & Sons, Inc.--Costs,
B-236713.3, July 19, 1990, 90-2 CPD para. 50 at 3. It is our
obligation to ensure that any protester seeking to recover costs
meets these minimum standards.
Here, we have reviewed the record and agree with the FCC that
DTG has failed to provide sufficient support for its claim. Even
after the FCC's specific request for the necessary
documentation, DTG failed to provide more than the vague
SinoPowell invoice as evidence of its costs. Further, DTG's
statements have raised doubts as to whether any amounts due to
SinoPowell and Yelverton Law Firm were incurred for the
preparation of the proposal. For example, in the claim for costs
filed with our Office, DTG states that SinoPowell and Yelverton
Law Firm "negotiated as their compensation for bid preparation
that they would be an integral part of implementing the $18
million project to be awarded to DTG, and would be paid for
their services on such an integrated basis, and not just for bid
preparation." Claim for Costs, Dec. 28, 2009, at 2 (emphasis in
original).
We interpret DTG's various statements to the agency and to our
Office to indicate that there is a portion of the "integrated"
costs included in its claim for $118,500 that is not
attributable to the preparation of its proposal under the
solicitation, and is therefore not properly reimbursable. Where,
as here, a protester has aggregated allowable and unallowable
costs, and provided such insufficient documentation that we
cannot tell from the record before us what portion is allowable,
the entire amount must be disallowed even though some portion of
the claim may be properly payable. TRESP Assocs., Inc.--Costs,
B-258322.8, Nov. 3, 1998, 98-2 CPD para. 108 at 4. Accordingly,
DTG's claim must be denied in full. (DTV
Transition Group, Inc.--Costs, B-401466.2, April 7, 2010) (pdf)
By correspondence
dated July 3, 2008, the protester submitted a claim for costs
totaling $130,344 to counsel for the agency. The protester
reports that by letter dated September 5, 2008, the contracting
officer rejected all but $12,930 of its claim. (The protester
did not furnish us with a copy of this correspondence.) By
letter of September 15, Holloway asked the contracting officer
to reconsider his decision; the protester furnished our Office
with a courtesy copy of this letter. In the letter's final
paragraph, Holloway noted that it was sending a copy of the
letter to our Office to place us "on notice about the
non-agreement between [the parties]." The protester asked the
contracting officer to "reconsider CMS's position and honor the
invoice that was submitted by Holloway;" in the event the
contracting officer was unwilling to reconsider his position,
the protester requested that our Office recommend the amount of
costs that the agency should pay. Holloway did not communicate
with our Office further regarding the matter until May 19, 2009,
more than 8 months later, when it submitted the instant request
for a recommendation of the amount it should be reimbursed.
Our Bid Protest Regulations contemplate prompt resolution of
protest matters, including claims for protest costs;
accordingly, we require protesters to diligently pursue such
claims. L-3 Comms. Corp., Ocean Sys. Div.--Costs, B-281784.5,
Feb. 17, 2004, 2004 CPD para. 40 at 3. Here, Holloway waited
more than 8 months after seeking reconsideration of the
contracting officer's decision regarding its claim to ask our
Office for a recommendation as to the amount of reimbursement;
moreover, the protester has furnished no evidence that it
followed up on its request to the contracting officer at any
point over the 8-month period. Under these circumstances, we
think that the protester's actions demonstrate a lack of
diligence in pursuing its claim to our Office. Because the
protester failed to diligently pursue its claim to our Office,
Holloway's request for a determination of reimbursable costs is
dismissed. (Holloway & Company,
PLLC--Costs, B-311342.5, July 6, 2009) (pdf)
Thus, ICE argues
that the legislative history of FASA indicates that Congress
intended for the $150 cap to be a “benchmark” in deciding
whether attorneys’ fees for successful small business protesters
are reasonable, and supports the agency’s view that all of the
hourly rates at issue here--especially the $705 per hour rate of
the senior partner--are unreasonable per se. While our Office
has previously addressed the “benchmark” language in FAR sect.
33.104(h)(5),[3] we have not addressed the legislative history
of FASA--where this language first appears. As discussed below,
we conclude that the legislative history does not, as ICE
argues, bar reimbursement of legal fees at the rates charged by
PCS’s outside counsel.
Our Office takes seriously--and in the words of the FASA
conference report, is “vigilant” in fulfilling--our
responsibility to evaluate the reasonableness of a successful
protester’s request for reimbursement of attorneys’ fees. In
numerous instances, our Office has agreed with agency arguments
that certain costs for successful protesters are not allowable.
For example, we have found that hours charged by outside counsel
are excessive where the number of hours billed are “far beyond
what should have been necessary to reasonably pursue the
protest.” Galen Med. Assocs., Inc.--Costs, B-288661.6, July 22,
2002, 2002 CPD para. 114 at 2. We have denied requests for
reimbursement where billing records show that multiple attorneys
performed duplicative work, and did not demonstrate a need for
such efforts. Fritz Cos., Inc.--Costs, B-246736.7, Aug. 4, 1994,
94-2 CPD para. 58 at 4-5. We have disallowed costs where the
protester does not provide adequate documentation demonstrating
the reasonableness of outside counsel’s hourly rates. TRS
Research--Costs, B-290644.2, June 10, 2003, 2003 CPD para. 112
at 4. We have denied requests for reimbursement of protest costs
where the protester has not stated that the costs sought for
reimbursement have or will be paid by the protester, regardless
of our ruling on the request. Id. at 5. We have disallowed costs
that are not reasonably related to the pursuit of the protest,
including, for example, costs associated with a request for
reconsideration. Aztec Dev. Co.--Costs, B-270275.2, Feb. 13,
1997, 97-1 CPD para. 73 at 4. Similarly, our Office has
disallowed costs in their entirety where a protester has
aggregated allowable and unallowable costs in a way that does
not allow us to identify which costs are properly reimbursable.
Blue Rock Structures, Inc.-Costs, B-293134.2, Oct. 26, 2005,
2005 CPD para. 190 at 5.
Here, we recognize that the FASA conference committee reiterated
our Office’s responsibility, imposed in 1984 by CICA, to ensure
that attorneys’ fees sought for reimbursement are reasonable. We
see no conflict between FASA’s exemption of small businesses
from a cap on attorneys’ fees, and the conference committee’s
view that the “cap placed on attorneys’ fees for businesses
other than small business constitutes a benchmark as to what
constitutes a ‘reasonable’ level for attorneys’ fees for small
businesses.” H. Rep. No. 103-712 sect. 1403 (Aug. 21, 1994), as
reprinted in 1994 U.S.C.C.A.N. 2607, 2621-22. In this regard, we
think that the conference committee report language concerning a
“benchmark” provides guidance as to the evaluation of the
reasonableness of attorneys’ fees. However, we do not view the
benchmark language as imposing an additional limitation (i.e., a
cap) on attorneys’ fees that are otherwise reasonable. Such an
interpretation would be inconsistent with the plain statutory
language of FASA which exempts small businesses from the
specific cap imposed on large businesses--and we see no evidence
that the Congress intended such a result. See Hartford
Underwriters Ins. Co. v. Union Planters Bank, N. A., 530 U.S. 1,
6, 120 S.Ct. 1942, 147 L.Ed.2d 1 (2000) (“when the statute’s
language is plain, the sole function of the courts--at least
where the disposition required by the text is not absurd--is to
enforce it according to its terms” (internal quotation marks
omitted)).
We think the benchmark language is appropriately viewed as one
of a number of factors to be considered in determining whether
attorneys’ fees are reasonable. Among these factors are: the
legal context--CICA’s creation of a fee-shifting mechanism that
provides for the reimbursement of a successful protester’s costs
of pursuing a protest and FASA’s exemption of small businesses
from the $150 per hour cap on attorney fees that applies to
large businesses; the passage of time--13 years--and the
concomitant changes in the cost of living and the level of fees
since the enactment of FASA; the customary fees charged for
similar legal work in the community where outside counsel
practices; the experience, reputation and ability of the outside
counsel; the specialized nature of government contracts law; and
the complexity of the issues in the particular protest at issue.
In summary, we have considered the difference between the rates
charged by PCS’s outside counsel and the $150 per hour cap that
applies to large businesses, particularly in light of the
conference committee’s views, and the relevant FAR provision,
concerning the cap as a benchmark for reasonableness. We
nonetheless think that, on balance, the rates charged by PCS’s
outside counsel are reasonable. Specifically, as discussed in
detail below, we find that the number of hours billed is
reasonable, and that the rates charged by PCS’s outside counsel
are consistent with those customarily charged by comparable
firms in the Washington, DC area with similar levels of
government contracts experience. We also think that the issues
in this protest were of a level of complexity that supports the
reasonableness of the rates. (Public
Communications Services, Inc.--Costs, B-400058.4, June 25,
2009) (pdf)
Based on our
review of the record, we agree with the agency that the number
of hours claimed in preparing this Phase I proposal appear
excessive, particularly considering that Celadon did not
contemporaneously record the hours specifically allocated to
this Phase I proposal or otherwise carry its burden of showing
that its claimed hours were reasonable. Where our Office has
found that the number of hours exceeded that which a prudent
person would claim, we have reduced the number of hours to
reflect a reasonable work effort, given the nature of the
particular protest. See SKJ & Assocs., Inc., B‑291533.3, July
24, 2003, 2003 CPD para. 130 at 3. Here, given the statements of
the HHS program officials as to what are reasonable hours for
preparing an SBIR proposal of this nature, and in the absence of
any better evidence, we accept as reasonable the agency’s
determination to allow 40 hours for the two employees to prepare
the proposal, and 10 hours for the president to review it.
We also accept the agency’s calculation of the rates for the
three Celadon employees who prepared the proposal. As indicated
by the agency, while Celadon supported the salaries paid its
employees, it used a flawed method to calculate its claimed
hourly labor rates based on these yearly salaries. That is to
say, Celadon’s calculations resulted in including indirect
costs, e.g.,vacation time and paid lunch, in its direct labor
rates. Celadon does not dispute this agency analysis. Thus, when
Celadon applied the fringe benefit, overhead and G&A rates to
its claimed labor rates, which should account for all of the
indirect costs, Celadon was essentially double-counting the
indirect costs included in the labor rates. This double-counting
had the effect of including profit in addition to actual costs
in Celadon’s proposed labor rates. A protester may not recover
profit on its employees’ time in filing and pursuing protests,
and, therefore, claimed rates must be based upon actual rates of
compensation, plus reasonable overhead and fringe benefits, and
not market rates that include profit as an element. W.S.
Spotswood & Sons, Inc.--Claim for Costs, supra.
In sum, we recommend that Celadon be reimbursed its proposal
preparation costs for 40 hours at $51.92 for one employee, for
40 hours at $40.86 for another employee, and for 10 hours at
$51.92 for the president. After Celadon’s claimed indirect rates
are applied to these direct labor costs, the total reasonable
proposal preparation costs, as was determined by HHS, is
calculated as $6,139. AR, Tab 26, Claim Calculation.
Celadon also claims $9,868 for its costs of pursuing the
protest, representing 101.5 hours of Celadon’s president’s time
at $67 per hour, plus applicable indirect costs. AR, Tab 2,
Celadon’s Claim. The agency only allowed 60 hours at $51.92 per
hour. AR, Tab 26, Claim Calculation. For the reasons stated
above, we accept the agency’s determination that the president
should be reimbursed at the $51.92 rate. However, the agency has
not specifically contended that the 101.5 hours charged by the
president for pursuing the protest are excessive, and based on
our review of the record, we find no basis for so concluding.
Thus, we find that Celadon should be reimbursed $7,648 for its
costs of pursuing the protest, which represents 101.5 hours of
the president’s time at $51.92 per hour, plus indirect costs at
the claimed rates.
Finally, Celadon’s claim seeks reimbursement of $8,640,
reflecting time spent on the preparation of Celadon’s cost claim
at the agency. However, while our Bid Protest Regulations
provide that we can recommend reimbursement of the costs of
pursuing a claim for protest costs at our Office, 4 C.F.R. sect.
21.8(f)(2), there is no provision providing for reimbursement of
costs of preparing and pursuing a claim at the procuring agency.
Manekin Corp.--Costs, B-249040.2, Dec. 12, 1994, 94-2 CPD para.
237 at 6. To the extent Celadon requests that it be reimbursed
the costs of pursuing its claim at our Office, we will make such
a recommendation only if it is shown that the agency
unreasonably delayed consideration of the protester’s claim or
otherwise failed to give the claim reasonable consideration.
Blue Rock Structures, Inc.--Costs, B-293134.2, Oct. 26, 2005,
2005 CPD para. 190 at 7. Here, since we have essentially agreed
with the agency’s determination of the amount of costs which
Celadon should be reimbursed and find any delay in resolving the
claim was substantially contributed to by Celadon’s actions, we
do not recommend that its costs of pursuing the claim at our
Office be reimbursed. (Celadon
Laboratories, Inc.--Costs, B-298533.2, November 7, 2008) (pdf)
As a general rule, we consider a successful protester entitled
to be reimbursed costs incurred with respect to all issues
pursued, not merely those upon which it prevails. AAR Aircraft
Servs.--Costs, B-291670.6, May 12, 2003, 2003 CPD para. 100 at
9. In our view, limiting recovery of protest costs in all cases
to only those issues on which the protester prevailed would be
inconsistent with the broad, remedial congressional purpose
behind the cost reimbursement provisions of the Competition in
Contracting Act of 1984, 31 U.S.C. sect. 3554 (c)(1)(a) (2006).
AAR Aircraft Servs.--Costs, supra; TRESP Assocs., Inc.--Costs,
B-258322.8, Nov. 3, 1998, 98-2 CPD para. 108 at 2. Nevertheless,
failing to limit the recovery of protest costs in all instances
of partial or limited success by a protester may also result in
an unjust award determination. Accordingly, in appropriate
cases, we have limited our recommendation for the award of
protest costs where a part of those costs is allocable to an
unsuccessful protest issue that is so clearly severable from the
successful issues as to essentially constitute a separate
protest. See, e.g., BAE Tech. Servs., Inc.--Costs, B-296699.3,
Aug. 11, 2006, 2006 CPD para. 122 at 3; Interface Floorings
Sys., Inc.--Claim for Attorneys’ Fees, B‑225439.5, July 29,
1987, 87‑2 CPD para. 106 at 2-3. In determining whether protest
issues are so clearly severable as to essentially constitute
separate protests, we consider, among other things, the extent
to which the issues are interrelated or intertwined--i.e., the
successful and unsuccessful arguments share a common core set of
facts, are based on related legal theories, or are otherwise not
readily severable. See Sodexho Mgmt., Inc.--Costs, B‑289605.3,
Aug. 6, 2003, 2003 CPD para.136 at 29. We previously have
found that the three issue areas raised by BRSC in its
protest--misevaluation of proposals, failure to hold meaningful
discussions, and treating offerors unequally--involve the same
core facts, and thus are intertwined for purposes of considering
whether protest costs should be reimbursed. BAE Tech. Servs.
Inc.--Costs, B-296699.3 Aug. 11, 2006 , 2006 CPD para. 122 at 3.
The agency has presented no argument or evidence that persuades
us that our view in this regard should be changed under the
facts of this case. Under these circumstances, we conclude that
the evaluation, discussions, and equal treatment issues raised
in BRSC’s protest are not severable, and that BRSC therefore
should be reimbursed its reasonable costs related to all of
these issues. BRSC is not required to separate the costs
associated with its arguments relating to the agency’s failure
to conduct meaningful discussions from the costs associated with
the other arguments raised in its protest. BRSC should submit
its claim to the agency. (Burns
and Roe Services Corporation--B-310828.2, Costs, April 28,
2008) (pdf)
We
decline to recommend that TACOM reimburse ALF for any costs. We
will recommend the amount that the agency should pay only where,
prior to coming to our Office, the protester timely pursued a
claim to the agency; that is, where the protester filed an
adequately documented claim with the agency within 60 days after
receiving our recommendation that costs be paid. See 4 C.F.R.
sect. 21.8(f)(1). The 60‑day timeframe was specifically designed
to avoid the piecemeal presentation of claims (which necessarily
results in unduly delaying their resolution), while at the same
time affording protesters an ample opportunity to submit
adequately substantiated certified claims. REEP, Inc.--Costs,
B-290665.2, July 29, 2003, 2003 CPD para. 131 at 4. To be
considered adequately documented, a claim for reimbursement of
employee compensation must include documentation establishing
the number of hours worked and the purposes of the employees’
efforts; in addition, it must demonstrate that the claimed
hourly rates reflect the employees’ actual rates of compensation
plus reasonable overhead and fringe benefits. See W.S. Spotswood
& Sons, Inc.--Claim for Costs, B-236713.3, July 19, 1990, 90-2
CPD para. 50 at 3. While we do not believe that the 60-day
timeframe should be applied in so harsh a manner that a
protester receives no reimbursement merely because its initial,
timely claim required some supplementation or elaboration, where
the timely submission is of little or no value in supporting the
claim, we will consider the claim untimely and regard it as
forfeited. REEP, Inc.--Costs, supra. We note in this connection
that a protester’s failure to file an adequately documented
claim within the 60-day period may result in forfeiture of its
right to recover costs even where the parties have continued to
negotiate after the 60-day period expired. H. G. Prop. A, L.
P.--Costs, B‑277572.8, Sept. 9, 1998, 98-2 CPD para. 62 at 2-3.
Here, ALF’s initial, timely submission to the agency was so
deficient as to be of basically no value in supporting its
claim. As previously noted, the submission failed to furnish any
detail regarding the claimed employee hours or supporting the
claimed rates of compensation; in addition, it failed to include
any documentation demonstrating ALF’s obligation to compensate
the consultant. Moreover, even when given the opportunity to
supplement its submission to the agency, ALF never sought to
overcome the second deficiency; that is, it never furnished the
agency with documentation supporting its claimed rates of
employee compensation--and, indeed, ultimately submitted
documentation to our Office that clearly demonstrated that the
initially claimed rates were substantially overstated. In
addition, we are not persuaded that prior to seeking a
recommendation regarding cost recovery from our Office, the
protester made a reasonable attempt to reach an agreement with
the agency, as contemplated by our Regulations. As noted above,
it was not until the protester sought a recommendation from our
Office that it for the first time furnished documentation
substantiating its claimed rates of employee compensation. By
failing to furnish such documentation to the agency, ALF
effectively eliminated the possibility of the two parties
arriving at an agreement. We do not think that it is appropriate
to permit a protester to seek a recommendation regarding cost
recovery from our Office where it has not previously made a
reasonable effort to reach an agreement with the agency. (Al
Long Ford--Costs, B-297807.2, October 18, 2007) (pdf)
Under the Competition in Contracting Act (CICA), when our
Office finds that an agency’s procurement activities fail to
comply with the requirements of statute or regulation, we are
given discretionary authority to recommend the reimbursement of
proposal preparation costs. Specifically, CICA states: “If the
Comptroller General determines that . . . the award of a
contract does not comply with a statute or regulation, the
Comptroller General may recommend that the Federal agency
conducting the procurement pay to an appropriate interested
party the costs of . . . bid and proposal preparation.” 31.
U.S.C. sect. 3554(c)(1) (2000) (italics added). Here, as
discussed above, Lockheed Martin has already received the
agreed-upon compensation for its performance of the fixed-price
CAD contract, under which its technical solution for the SDD
contract was evaluated. Further, Lockheed Martin will have an
opportunity to compete for the phase II requirements that were
deleted from the solicitation. Finally, it is clear that,
following deletion of the phase II requirements, Lockheed Martin
continued to compete for the modified phase I requirements; its
protest, which we sustained, challenged the basis for the
changes to those requirements--not the source selection process
following the changes. Based on our consideration of the
record as a whole, we decline to exercise our discretionary
authority to recommend reimbursement of Lockheed Martin’s
proposal preparation costs. (Lockheed
Martin Corporation--Costs, B-295402.2, November 1, 2005) (pdf)
We have previously reasoned that the justification for an
upward fee adjustment is self-evident if the claimant alleges
that the cost of living has increased, as measured by the
Department of Labor’s Consumer Price Index (CPI). Sodexho Mgmt.,
Inc.--Costs, B-289605.3, Aug. 6, 2003, 2003 CPD para. 136 at
41. In this regard, we have declined to impose a requirement
that a claimant do more than request an adjustment and present a
basis upon which the adjustment should be calculated. Id.; see
Brickwood Contractors, Inc. v. United States, 49 Fed. Cl. 148,
164 (2001); California Marine Cleaning Servs., Inc. v. United
States, 43 Fed. Cl. 724 (1999). Where a claimant meets this
standard, and an agency does not articulate any objection, we
will grant a claimant’s request for a recommendation in favor of
a cost of living adjustment to the fee cap. Sodexho Mgmt.,
Inc.--Costs, supra. In support of its claim for attorneys’ fees
above the $150 level, Inter-Con provided a detailed explanation
of its calculation of the rates and included a printout of the
“All Urban Consumers” CPI for the San Francisco-Oakland-San
Jose, California area. Inter‑Con Claim Letters, dated April 8
and 26, 2005. Use of the “All Urban Consumers” CPI for a
specific area is consistent with our decision in Sodexho. See
Sodexho Mgmt., Inc.--Costs, supra, at 43 n.33. In requesting our
recommendation, DOS agrees that the protester’s “request appears
to be consistent with the standards followed in [Sodexho],” and
provides no specific objection to the higher fees. DOS Letter,
June 3, 2005. We have reviewed Inter-Con’s calculation in
support of the higher requested fees, and find that they appear
properly supported and reasonable. Accordingly, we recommend
that DOS pay the higher attorneys’ fees claimed. (Department
of State--Costs, B-295352.5, August 18, 2005) (pdf)
CourtSmart incurred $153,971.25 for its attorney's
services at an hourly rate of $475. SSA generally alleges that
the rate is above the reasonable rate charged for these
services. In response, CourtSmart submitted information from a
2002 national billing rate survey. Specifically, CourtSmart
identified the ranges of hourly billing rates for partners and
for associates from 19 firms in the Washington, D.C. area, as
published in the January 2003 edition of Legal Times. The hourly
rates for partners reported by these firms ranged from $185 to
$750. CourtSmart Submission (Oct. 1, 2004) at 2, encl. 4. The
highest rates for partners for all but two of these firms were
in excess of $500. CourtSmart states that a breakdown of billing
rates by specific practice area was not available. CourtSmart's
attorney states that he has 30 years of experience in federal
procurement law in the Washington, D.C. area, and has the
expertise, reputation and ability commensurate with partners at
the high end of the billing rate range. CourtSmart asserts that,
since the $475 rate billed by its attorney is within the range
billed by firms in the community, the hourly rate is reasonable.
SSA has not challenged the applicability of the survey for the
purpose of determining the reasonableness of the attorney's
hourly rate billed here. SSA has also not challenged the
asserted expertise, reputation and ability of the attorney.
Here, the work was performed by the attorney from November 2003
through February 2004, which is within approximately 1 year of
the billing rate survey. Although the survey does not provide
hourly rate information for attorneys practicing in federal
procurement law or related areas of practice, SSA does not
challenge the relevance of the information submitted. On this
record, we find the attorney's billed hourly rate of $475 was
reasonable. See KPMG Peat Marwick, LLP--Costs , supra, at 5-6;
Bay Tankers, Inc.--Costs , supra . Therefore, we find
$153,971.25 ( i.e. , 324.15 hours x $475 per hour) that
CourtSmart claims for attorney's fees is reasonable and
recoverable. (CourtSmart Digital
Systems, Inc.--Costs, B-292995.7, March 18, 2005) (pdf)
Furthermore, even if SBA were to issue a formal size
determination, that determination would not have any
retroactive effect on Brechan's size for purposes of its
initial protest, as the effect of such a determination
after the award of a contract is prospective. See , e.g. ,
FAR 19.302(j); Planned Sys. Int'l, Inc. , B-292319.7, Feb.
24, 2004, 2004 CPD 43 at 3 (adverse SBA decision issued
after award does not require cancellation of the award);
Dawkins Gen. Contractors & Supply, Inc , B243613,
B-243613.11, Sept. 21,1992, 92-2 CPD 190 at 3 (adverse SBA
size determinations apply prospectively only). Although
Brechan's request presents the somewhat unusual
circumstance of an agency's challenge to the size status
of an unsuccessful offeror after award has been made, in
the context of a recompetition in which the offeror is not
participating and solely for the purpose of challenging
entitlement to protest costs, we believe that our cases
and SBA regulations do not provide for a retroactive
challenge to Brechan's standing. Accordingly, we conclude
that there is no basis to challenge Brechan's status as a
small business for purposes of this request. Based on the
record, Brechan's request for a recommendation that it be
reimbursed the reasonable costs of filing and pursuing its
protest is granted. Further, in light of the discussion
above, we conclude that Brechan is a small business for
purposes of filing its claim for costs with the agency. (Brechan
Enterprises, Inc.--Costs, B-294046.2, November 4,
2004) (pdf)
We
find that reimbursement is warranted. The promptness
standard applicable to protests cannot be applied to the
agency's request for reconsideration because the request
itself caused the protester to expend unnecessary time and
resources to obtain relief, a key consideration in our
deciding whether reimbursement of a protester's costs is
appropriate. See AAR Aircraft Servs.--Costs , B-291670.6,
May 12, 2003, 2003 CPD 100 at 5. It is reasonable for a
firm whose protest has been sustained by our Office to
feel compelled to respond to the agency's request for
reconsideration. Here, the agency caused the protester to
incur costs opposing a request for reconsideration that
was devoid of merit. In this regard, parties filing
requests for reconsideration are required to submit a
detailed statement of the factual and legal grounds upon
which reversal or modification is deemed warranted,
specifying any errors of law made or information not
previously considered. Bid Protest Regulations, 4 C.F.R.
21.14(a). DHS's reconsideration request did not meet this
standard. (Security Consultants
Group, Inc.--Costs, B-293344.6, November 4, 2004) (pdf)
Neither our regulations nor our prior decisions recognize
an exception to the 60-day filing requirement based simply
on the fact of a request for reconsideration having been
filed. While our Office has indicated that we may consider
an untimely claim for good cause, we have construed the
term to mean that some compelling reason beyond the
control of the protester prevented the protester from
timely filing the claim. Continental Maritime of San
Diego, Inc.-Costs , B-249858.5, Dec. 17, 1993, 93-2 CPD 323
at 2; Test Sys. Assocs., Inc.-Costs , May 3, 1993, 93-1 CPD
351 at 2. Here, there is no evidence that Keeton could not
have filed within the required time period a documented,
substantiated claim for the costs of filing and pursuing
the protest that we had sustained. Not only did Keeton's
request for reconsideration not prevent the protester from
timely filing its claim, the request for reconsideration
did not even call into question the basis upon which we
sustained the protest and thus our recommendation of
protest costs. Moreover, we note that when Keeton received
our decision denying its request for reconsideration on
March 31, Keeton still had 33 days within which to file its
cost claim. Keeton has offered no explanation as to why it
did not have sufficient time after receiving our decision
denying its request for reconsideration to complete and
timely file its claim with the agency. In these
circumstances, we decline to recommend that the agency pay
the claimed costs. (Keeton
Corrections, Inc.—Costs, B-293348.3, October 25, 2004)
(pdf)
Based on our review of the record, we find no basis to
object to the reasonableness of the agency’s determination
that CAMS should be reimbursed $3,946.30 for its total
claimed costs of filing and pursuing its protest. However,
we do not recommend that CAMS be reimbursed for the costs
of pursuing its claim at the agency, because those costs
are not associated with proceedings before our Office. See
SKJ & Assocs.--Costs, B-291533.3, July 24, 2003, 2003 CPD
¶ 130 at 4. We also deny CAMS’s costs for pursuing this
claim before our Office. Our Bid Protest Regulations, 4
C.F.R. § 21.6(f)(2) (2003), provide that we may recommend
that a protester be reimbursed the costs of pursuing its
claim before our Office. Since we recommend that CAMS be
reimbursed the amount the agency determined is due,
however, we find no basis to recommend that CAMS be
reimbursed for the costs of pursuing the claim at our
Office. (CAMS, Inc.--Costs,
B-292546.2, March 22, 2004) (pdf)
Our Bid Protest Regulations, 4 C.F.R. § 21.8(f)(1) (2003),
require protesters to file claims for protest costs within
60 days of receiving our recommendation that such costs be
paid. This 60-day timeframe was specifically designed to
avoid the piecemeal presentation of claims (which
necessarily results in unduly delaying their resolution),
while at the same time affording protesters an ample
opportunity to submit adequately substantiated, certified
claims. HG Properties A, L.P.--Costs, B-277572.8, Sept. 9,
1998, 98-2 CPD ¶ 62 at 2. A protester's failure to file an
adequately documented claim within this 60-day period
results in forfeiture of its right to recover costs,
irrespective of whether the parties may have continued to
negotiate after the 60-day period expired. Id. at 2-3. In
this latter connection, a protester seeking to recover its
protest costs must submit evidence sufficient to support
its claim that those costs were incurred and are properly
attributable to filing and pursuing the protest. Stocker &
Yale, Inc.--Claim for Costs, B-242568.3, May 18, 1993,
93-1 CPD ¶ 387 at 4. Although we recognize that the
requirement for documentation may sometimes entail certain
practical difficulties, we do not consider it unreasonable
to require a protester to document in some detail the
amount and purposes of its employees' and attorneys'
efforts and to establish that the claimed hourly rates
reflect the employees' actual rates of compensation plus
reasonable overhead and fringe benefits. W.S. Spotswood &
Sons, Inc.--Claim for Costs, B-236713.3, July 19, 1990,
90-2 CPD ¶ 50 at 3. We do not believe that the 60-day
timeframe should be applied in so harsh a manner that a
protester receives no reimbursement merely because its
initial, timely, claim required some supplementation or
elaboration. Nonetheless, where the timely submission is
of little or no value in supporting the claim, we believe
that the claim should be rejected as untimely. (REEP,
Inc.--Costs, B-290665.2, July 29, 2003) (pdf)
Our review of the record confirms the reasonableness of
the agency's conclusion that the protester has not
adequately documented its protest costs. Despite the
passage of many months and several requests from the
agency to do so, the protester has not submitted any
documentation to show that the $425 hourly rate claimed by
TRS counsel is representative of that charged for similar
services in the Philadelphia area, where he practices law.
(TRS Research--Costs,
B-290644.2, June 10, 2003)
Our Bid Protest Regulations provide that where the
contracting agency decides to take corrective action in
response to a protest, we may recommend that the protester
be reimbursed the costs of filing and pursuing its
protest, including reasonable attorneys' fees. 4
C.F.R. §
21.8(e) (2003). This does not mean that costs should be
reimbursed in every case in which an agency decides to
take corrective action; rather, a protest should be
reimbursed its costs where an agency unduly delayed its
decision to take corrective action in the face of a
clearly meritorious protest. Griner's-A-One Pipeline Servs.,
Inc.--Entitlement to Costs, B-255078.3, July 22, 1994,
94-2 CPD ¶ 41. Thus, as a prerequisite to our
recommending that costs be reimbursed where a protest has
been settled by corrective action, not only must the
protest have been meritorious, but it also must have been
clearly meritorious, i.e., not a close question. J.F.
Taylor, Inc.--Entitlement to Costs, B-266039.3, July 5,
1996, 96-2 CPD ¶ 5 at 3; Baxter Healthcare
Corp.--Entitlement to Costs, B-259811.3, Oct. 16, 1995,
95-2 CPE ¶ 174 at 4-5; GVC Cos.--Entitlement to Costs,
B-254670.4, May 3, 1994, 94-1 CPD ¶ 292 at 3. A protest is
"clearly meritorious" when a reasonable agency inquiry
into the protester's allegations would show facts
disclosing the absence of a defensible legal position.
Department of the Army--Recon., B-270860.5, July 18, 1996,
96-2 CPD ¶ 23 at 3. The mere fact that an agency decides
to take corrective action does not establish that a
statute or regulation clearly has been violated. Spar
Applied Sys.--Declaration of Entitlement, B-276030.2,
Sept. 12, 1997, 97-2 CPD ¶ 70 at 5. Here, we
conclude that it is not appropriate to recommend that East
Penn recover its protest costs because East Penn's protest
was not clearly meritorious. (East
Penn Manufacturing Company, Inc.--Costs, B-291503.4,
April 10, 2003) (txt
version)
In view of
the cancellation of the RFP, which has deprived ATS of
an opportunity to compete for the scope of services
contemplated in the solicitation at issue in the
protest, ATS requests that we modify our earlier
recommendation to allow ATS to be reimbursed the costs
of preparing its proposal. The Army has no objections to
ATS's request. Under these circumstances, we modify our
recommendation to provide that ATS should be reimbursed
the costs of preparing its proposal under the canceled
solicitation. [1] 31 U.S.C. sect. 3554(c)(1), 4 C.F.R.
sect. 21.8(d)(2) (2001). (Aberdeen
Technical Services--Modification of Recommendation,
B-283727.3, August 22, 2001) (pdf)
Request for
recommendation that agency reimburse protester for the
costs it incurred in pursuing an administrative appeal
of the agency's initial cost comparison decision under
Office of Management and Budget Circular No. A-76 is
denied because GAO's authority to recommend
reimbursement of protest costs does not extend to costs
incurred by a protester in litigating in another forum.
(Rice
Services, Ltd.--Costs, B-284997.2, May 18, 2001)
Our Office generally
accepts the number of attorney hours claimed, unless the
agency identifies specific hours as excessive and
articulates a reasoned analysis as to why payment for
those hours should be disallowed. Data Based Decisions,
Inc.--Claim for Costs, B-232663.3, Dec. 11, 1989, 89-2
CPD para. 538 at 3. Simply concluding that the hours
claimed are excessive or suggest duplication of effort
is inadequate to justify denying a claim for protest
costs. Princeton Gamma-Tech, Inc.--Claim for Costs,
B-228052.5, Apr. 24, 1989, 89-1 CPD para. 401 at 4. We
will examine the reasonableness of the attorney hours
claimed to determine whether they exceed, in nature and
amount, what a prudent person would incur in pursuit of
his or her protest. Price Waterhouse--Claim for Costs,
B-254492.3, July 20, 1995, 95-2 CPD para. 38 at 5.
(Pulau
Electronics Corporation--Costs, B-280048.11, July
31, 2000) (pdf)
We next turn to the
Navy's contention that it should not be required to
reimburse DRS for its protest costs because the agency
acted in good faith in relying on GSA's representations.
As we stated in our prior decision, we have no basis to
conclude, nor do we think, that the Navy acted in less
than complete good faith in placing this order. DRS
Precision Echo, Inc., supra, at 3. In addition, our
prior decision did not intend to suggest that the Navy
acted in bad faith in defending DRS's protest. Instead,
the decision reflected only a limited concern about the
continued defense of this purchase given GSA's inability
over a period of several months to produce any evidence
that a contract slated to expire had not done so. Id.
Nonetheless, despite the Navy's claims of good faith,
and despite any concern by our Office that the Navy may
have unnecessarily prolonged the dispute, the decision
whether to recommend an award of costs bears no
relationship to whether the agency acted in good faith;
rather, as stated above, costs are awarded to relieve
protesters of the financial burden of the public service
they perform. General Servs. Admin.--Recon., B-239569.2,
Feb.13, 1991, 91-1 CPD para. 163 at 3. (Department
of the Navy--Modification of Remedy, B-284080.3, May
24, 2000)
As a general rule, we
recommend that a prevailing protester be reimbursed the
costs incurred with respect to all issues pursued, not
merely those upon which it prevails. Omni Analysis;
Department of the Navy--Recon., B-233372.2, B-233372.3,
July 24, 1989, 89-2 CPD para. 73 at 3-4. However, our
Office will limit its recommendation regarding a
successful protester's recovery of protest costs when a
part of the costs is allocable to a losing protest issue
that is so clearly severable as to constitute a separate
protest. Price Waterhouse--Claim for Costs, B-254492.3,
July 20, 1995, 95-2 CPD para. 38 at 3-4. (TRW,
Inc.--Costs, B-282459.3, August 4, 1999) (pdf)
We will not consider
requests for a recommendation for reimbursement of costs
where the protester fails to document its claim to the
contracting agency. See Custom Prod. Mfg., Inc.--Recon.,
B-235431.8, July 21, 1995, 95-2 CPD para. 40 at 3.
Where, as here, attorneys' fees are sought to be
recovered, evidence from the attorneys involved must be
submitted, including, for instance, copies of bills from
the attorneys listing the dates the services were
performed and the hours billed to the protester. Custom
Prod. Mfg., Inc.--Costs, B-235431.7, May 9, 1995, 95-1
CPD para. 236 at 3. We have reviewed the documentation
submitted by the protesters' attorneys here, which
consists of the abstracts of attorneys' fees and
expenses for each pleading or document that dealt with
the partial set-aside issue, and we find this evidence
insufficient to support the protesters' claim. (A-1
Movers of America, Inc. et al.--Costs, B-277241.31,
August 2, 1999) (pdf)
A protester seeking to
recover the costs of pursuing its protest must submit
sufficient evidence to support its monetary claim. The
amount claimed may be recovered to the extent that the
claim is adequately documented and is shown to be
reasonable; a claim is reasonable, if, in its nature and
amount, it does not exceed that which would be incurred
by a prudent person in the pursuit of a protest.
E&R, Inc.--Claim for Costs, B-255868.2, May 30,
1996, 96-1 CPD para. 264 at 2; Data Based Decisions,
Inc.--Claim for Costs, B-232663.3, Dec. 11, 1989, 89-2
CPD para. 538 at 2-3. (Chant
Engineering Co., Inc.--Costs, B-274871.4, April 28,
1999) (pdf)
|
|
Comptroller General - Listing of Decisions |
For
the Government |
For
the Protester |
Ryan P. Slaughter--Costs B-411168.4: Dec 14, 2015
(pdf) |
New
Federal Builders, LLC-The James
R. Belk Trust--Costs B-409952.3: May 6, 2016 (pdf) |
System Studies & Simulation,
Inc.--Costs B-409375.5: May 8, 2015 (pdf) |
Debcon, Inc.--Costs B-412298.3:
Apr 26, 2016 (pdf) |
Baine Clark Company, Inc.--Costs,
B-401172.4, June 7, 2010 (pdf) |
Shaka, Inc.--Claim for Costs,
B-405552.2, May 17, 2012 (pdf) |
DTV Transition Group, Inc.--Costs,
B-401466.2, April 7, 2010 (pdf) |
Public Communications Services, Inc.--Costs,
B-400058.4, June 25, 2009 (pdf) |
Holloway & Company, PLLC--Costs,
B-311342.5, July 6, 2009 (pdf) |
Burns and Roe Services Corporation--B-310828.2,
Costs, April 28, 2008) (pdf) |
Celadon Laboratories, Inc.--Costs,
B-298533.2, November 7, 2008 (pdf) |
CourtSmart Digital Systems,
Inc.--Costs, B-292995.7, March 18, 2005 (pdf) |
Al Long Ford--Costs,
B-297807.2, October 18, 2007 (pdf) |
Security Consultants Group,
Inc.--Costs, B-293344.6, November 4, 2004 (pdf) |
Lockheed Martin
Corporation--Costs, B-295402.2, November 1, 2005 (pdf) |
Brechan Enterprises, Inc.--Costs,
B-294046.2, November 4, 2004 (pdf) |
Department of State--Costs,
B-295352.5, August 18, 2005 (pdf) |
|
Keeton Corrections, Inc.—Costs,
B-293348.3, October 25, 2004 (pdf) |
|
e-LYNXX Corporation--Costs,
B-292761.2, August 12, 2004 |
|
CAMS, Inc.--Costs,
B-292546.2, March 22, 2004 (pdf) |
|
REEP, Inc.--Costs,
B-290665.2, July 29, 2003 (pdf) |
|
SKJ & Associates, Inc.--Costs,
B-291533.3, July 24, 2003 (pdf) |
|
TRS Research--Costs,
B-290644.2, June 10, 2003 (pdf) |
|
East Penn Manufacturing Company, Inc.--Costs, B-291503.4,
April 10, 2003) (txt
version) |
|
M&S Farms, Inc.--Costs,
B-290599.3, April 8, 2003 (pdf) |
|
QuanTech, Inc.--Costs, B-291226.3, March 17, 2003 (pdf)
(txt
version) |
|
Priority
One Services, Inc.--Costs, B-288836.5, November 8, 2002
(pdf) |
|
Galen
Medical Associates, Inc. -- Costs, B-288661.6, July 22,
2002 (pdf) |
|
Parmatic
Filter Corporation--Costs, B-285288.5, August 27, 2001 (pdf) |
|
Aberdeen
Technical Services--Modification of Recommendation,
B-283727.3, August 22, 2001 (pdf) |
|
Rice
Services, Ltd.--Costs, B-284997.2, May 18, 2001 (PDF
Version) |
|
Pulau
Electronics Corporation--Costs, B-280048.11, July 31,
2000 (pdf) |
|
Department
of the Navy--Modification of Remedy, B-284080.3, May 24,
2000 (pdf) |
|
Dual
Inc.--Costs, B-280719.3, April 28, 2000 (pdf) |
|
Aberdeen
Technical Services, B-283727.2, February 22, 2000 |
|
TRW,
Inc.--Costs, B-282459.3, August 4, 1999 (pdf) |
|
A-1
Movers of America, Inc. et al.--Costs, B-277241.31, August
2, 1999 (pdf) |
|
Aalco
Forwarding, Inc., et al.--Costs, B-277241.30, July 30, 1999
(pdf) |
|
Chant
Engineering Co., Inc.--Costs, B-274871.4, April 28, 1999 |
|
U. S. Court of Federal Claims
- Key Excerpts |
As permitted by the applicable statute granting jurisdiction over bid protests, the
Court “may award any relief that the court considers proper, including declaratory and
injunctive relief except that any monetary relief shall be limited to bid preparation and
proposal costs.” 28 U.S.C. § 1491(b)(2); see also Gentex Corp. v. United States, 58 Fed.
Cl. 634, 656 (2003).
A disappointed bidder may recover bid preparation and proposal costs if the
following conditions are satisfied: (1) the agency committed a prejudicial error in
conducting a procurement; (2) the error caused the protester to incur unnecessary bid
preparation and proposal costs; and (3) the protester shows that the costs it seeks to recover
were reasonable and allocable. Reema Consulting Servs., Inc. v. United States, 107 Fed.
Cl. 519, 532 (2012).
A. The Agency Committed Prejudicial Error in Conducting the Procurement
A successful protester is entitled to bid preparation costs where an agency conducted
a procurement in violation of an applicable statute prejudicing the offeror. CSE Const. Co.
United States, 58 Fed. Cl. 230, 263 (2003). Defendant does not contest that HUD violated
federal procurement laws resulting in prejudicial error. Rather, Defendant argues that
Plaintiffs are not entitled to bid preparation costs because HUD did not conduct a
procurement, and therefore Plaintiffs cannot recover costs under the applicable statute.
Def.’s Resp. 8 (citing 48 C.F.R. 31.20-18(a)). Contrary to Defendant’s assertion, the
Federal Circuit found that the “PBACCs [were] procurement contracts and not cooperative
agreements[,]” and were subject to federal procurement laws permitting recovery of bid
preparation costs. CMS Cont. Mgmt. Servs., 745 F.3d at 1385-86.
B. The Error Caused Protesters to Incur Unnecessary Bid Preparation and
Proposal Costs
Defendant contends that Plaintiffs did not incur unnecessary bid preparation costs
because “Plaintiffs will presumably have the opportunity to resubmit prior proposals” in
response to a new procurement, and allowing both injunctive and monetary relief provides
a double recovery not permitted under 28 U.S.C. § 1491(b)(2). Def.’s Resp. 9-10. This
argument assumes that making the [Performance-Based Annual Contribution
Contracts] PBACCs FAR-compliant will not substantially change
the information an offeror must submit in its proposals. For the reasons stated below, this
outcome seems highly unlikely.
Defendant concedes that compliance with federal procurement law will “require
numerous, significant programmatic changes not only to the structure of the competition
awarding the [PBACCs] but also to the entire administration of the program.” AR 3 (HUD
Memorandum, [Performance-Based Contract Administrator] “PBCA [Notice of Funding
Availability] NOFA Status, Post-GAO Recommendations”). Indeed, HUD has
not yet re-initiated a FAR-compliant procurement. Instead, it has continued the “contracts
awarded between 1999 and 2005 to [P]laintiffs and others. . . . HUD plans to continue this
practice for the foreseeable future as it restructures the program to be consistent with
[federal procurement regulations].” Dkt. No. 121 (Def.’s April 27, 2015 Status Rep. 1).
HUD is continuing this restructuring without a clear timeline for issuing a new
procurement. Importantly, during oral argument on September 21, 2015, counsel for the
Government was unable to provide information on when HUD would complete its
restructuring, further attenuating the likelihood of an upcoming procurement.
Realistically, it may be years before HUD issues any new procurement.
The Government’s argument that monetary relief is improper because Plaintiffs will
be able to resubmit their proposals amounting to a double recovery is similarly
unpersuasive. Assuming HUD re-initiates a procurement, Plaintiffs will need to revise
their three-year-old proposals containing state-specific legal opinions to respond to the
“numerous, significant” changes HUD will need to make to comply with federal
procurement laws. AR 3. Given the substantial anticipated changes to the PBACCs, the
Court agrees with Plaintiffs that their bid proposal and preparation costs have been wasted.
See, e.g., Beta Analytics Int’l v. United States, 75 Fed. Cl. 155, 159 (2007) (awarding bid
proposal costs where re-evaluation of proposals was not practical). Moreover, HUD
essentially caused the incurrence of the proposal preparation costs by requiring offerors to
go forward with their proposals while the protests were pending at the GAO. If HUD had
agreed to wait until the GAO decided the protests, the proposal preparation costs could
have been avoided.
Further, the Court agrees with Plaintiffs that it is within the Court’s discretion to
grant both injunctive and monetary relief. The plain language of 28 U.S.C. § 1491(b)(2)
permits the Court to award relief that it considers proper, including bid and proposal costs
as well as injunctive relief. See 28 U.S.C. § 1491 (b)(2). The statute does not have a
restriction that if the Court grants injunctive relief, monetary damages are not available.
Accord MVM, Inc. v. United States, 47 Fed. Cl. 361, 366 (2000).
Defendant also asserts that Plaintiffs who did not specifically request bid
preparation costs in their complaints may not recover such costs. Def.’s Resp. 5. However,
Plaintiffs requested that the Court “[g]rant such other and further relief the court determines
just and appropriate,” see, e.g., dkt. no. 1 (CMS Compl. 12), which this Court has found
sufficient for granting bid and proposal costs. See CSE Const. Co., 58 Fed. Cl. at 263. All
of the Plaintiffs asserted their claims for proposal preparation costs at various times so that
Defendant well understood that these costs were at issue.
C. Recovery of Reasonable and Allocable Costs
Contrary to the Government’s argument, it is within this Court’s discretion to
determine that Plaintiffs are entitled to bid preparation and proposal costs before ruling on
the amount of costs that may be recovered. See e.g., Idea Int’l, Inc. v. United States, 74
Fed. Cl. 129, 143 (2006) (awarding proposal costs and requiring the parties to submit a
joint stipulation as to costs). Recognizing the competitive nature of Plaintiffs’ relationships
with one other, the Court must devise a procedure that preserves the confidentiality of the
individual cost claims. This goal can be accomplished if Plaintiffs individually submit
proposal preparation claims to the Department of Justice attorney of record who will
convey them to HUD for review. Plaintiffs shall submit their claims to the Department of
Justice within 30 days, on or before October 29, 2015. The Court will expect these claims
to be resolved voluntarily before December 31, 2015. If the claims are not resolved by
December 31, 2015, Defendant shall file a status report with the Court by January 8, 2016
indicating when the cost resolution process will be completed. The Court will enter final
judgment upon being advised that all of Plaintiffs’ cost claims have been resolved and paid.
(CMS Contract Mgmt. Servs. et
al v. U. S., Nos. 12-852C, 12-853C, 12-862C, 12-864C, &
12-869C, September 29, 2015) (pdf)
II.
The court turns first to
plaintiffs’ motions for attorney’s fees. As a threshold
matter, this court must determine whether the position of the
United States in this case was substantially justified. The
Equal Access to Justice Act (EAJA), 28 U.S.C. § 2412(d)(1)(A),
states, in pertinent part, that “a court shall award to a
prevailing party other than the United States fees and other
expenses, . . . unless the court finds that the position of
the United States was substantially justified or that special
circumstances make an award unjust.” Defendant bears the
burden of proving that its position was substantially
justified. See Helfer v. West, 174 F.3d 1332, 1336 (Fed. Cir.
1999); Doty v. United States, 71 F.3d 384, 385 (Fed. Cir.
1995); Abramson v. United States, 45 Fed. Cl. 149, 152 (1999).
It must show that its position throughout the dispute was
“‘justified in substance or in the main’ – that is, justified
to a degree that could satisfy a reasonable person.” Pierce v.
Underwood, 487 U.S. 552, 565 (1988); see also Chiu v. United
States, 948 F.2d 711, 715 (Fed. Cir. 1991). Such an inquiry
focuses not only on the position taken by the Justice
Department before this court, but also on the agency’s
prelitigation conduct. See Comm’r of I.N.S. v. Jean, 496 U.S.
154, 159 (1990); Hubbard v. United States, 480 F.3d 1327, 1332
(Fed. Cir. 2007); Smith v. Principi, 343 F.3d 1358, 1361-62
(Fed. Cir. 2003).
The Supreme Court has
instructed that the Government’s “position can be justified
even though it is not correct,” requiring that that position
have a “reasonable basis in law and fact.” Pierce, 487 U.S.
566 n.2; see also Norris v. S.E.C., 695 F.3d 1261, 1265 (Fed.
Cir. 2012). The courts have been particularly hesitant to
impose attorney’s fees in matters of first impression. See
White v. Nicholson, 412 F.3d 1314, 1316 (Fed. Cir. 2005);
Luciano Pisoni Fabbrica Accessori Instrumenti Musicali v.
United States, 837 F.2d 465, 467 (Fed. Cir. 1988); Gava v.
United States, 699 F.2d 1367, 1371 (Fed. Cir. 1983); see also
Marcus v. Shalala, 17 F.3d 1033, 1037 (7th Cir. 1994). Indeed,
the legislative history of EAJA makes clear that the governing
standard allows defendant to advance “‘in good faith . . .
novel but credible . . . interpretations of the law.’” Russell
v. Nat’l Mediation Bd., 775 F.2d 1284, 1290 (5th Cir. 1985)
(quoting H.R. Rep. No. 80-1418 at 11 (1980)); see also Renee
v. Duncan, 686 F.3d 1002, 1017 (9th Cir. 2012).
The instant case
presented a matter of first impression to this court. The
factual situation here was somewhat unique, requiring the
court, inter alia, to order defendant to file, as part of the
administrative record, the contracts and procedures governing
its mail servers. Although this court found that the agency’s
actions were contrary to the Federal Acquisition Regulations,
and arbitrary and capricious, there was little decisional
guidance that previously would have signaled this conclusion.
Defendant advanced arguments in support of the actions taken
below that relied on prior decisions of this court and the
General Accountability Office. See, e.g., Conscoop-Consorzia
v. United States, 62 Fed. Cl. 219, 239-40 (2004); Sea Box,
Inc., 2002 C.P.D. ¶ 181 (2002). Although the court concluded
that, based upon the language of the regulations, those
decisions were wrong (or in the case of Conscoop-Consorzia at
least distinguishable), it cannot say that defendant’s
reliance on these prior opinions was not substantially
justified. See Devine v. Sutermeister, 733 F.2d 892, 895 (Fed.
Cir. 1984) (“[T]he justification for the government’s
litigating position must be measured against the law as it
existed . . . , and not against the new law enunciated by the
court in its opinion.”); see also Watterson Constr. Co. v.
United States, 106 Fed. Cl. 609, 618 (2012). In these
circumstances, the court concludes that the position of the
United States in this litigation was substantially justified
and that an award of attorney’s fees is, therefore,
inappropriate.
III.
Only CenterScope seeks
bid preparation and proposal costs.
Following the court’s
April 22, 2013, order, the Clerk entered judgment pursuant to
RCFC 58. Defendant argues that this case is now “closed” and
asserts that the court does not have jurisdiction under 28
U.S.C. § 1491(b)(2) to determine whether CenterScope is
entitled to monetary relief. Contrary to defendant’s claims,
the entry of a permanent injunction in a case, whether
succeeded vel non by the Clerk’s filing of a judgment under
RCFC 58, does not deprive this court of further jurisdiction
over the case. The continuing responsibility of this court
over its decrees “is a necessary concomitant of the
prospective operation of equitable relief,” 11A Charles Alan
Wright, Arthur R. Miller & Mary Kay Kane, Federal Practice and
Procedure, § 2961 (2014), and has its roots in the power of
courts to modify decrees “as events may shape the need.”
United States v. Swift & Co., 286 U.S. 106, 114 (1932). In the
court’s view, nothing about the Clerk’s pro forma entry of a
judgment under RCFC 58, prevents this court from revisiting
its decree in a bid protest case to address subsequent events.
See RCFC 60, 65; see also CNA Corp. v. United States, 83 Fed.
Cl. 1, 5-6 (2008) (discussing this court’s ability to award
bid preparation and proposal costs after the entry of a
judgment under RCFC 58). A contrary ruling might encourage an
agency to play a procurement version of thimblerig –
indicating that a new procurement was anticipated, only to
proceed otherwise after the time for bid preparation and
proposal costs has run.
The problem with
CenterScope’s request for costs is not jurisdictional, then,
but rather the fact that CenterScope has not met its
evidentiary burden. “Bid preparation and proposal costs can be
awarded by courts as an appropriate way to try to compensate,
at least in part, a victim of unjust government action during
the procurement process.” CNA Corp., 83 Fed. Cl. at 11. Those
costs are recoverable only if three conditions are satisfied:
(i) the agency has committed a prejudicial error in conducting
the procurement; (ii) that error caused the protester to incur
unnecessarily bid preparation and proposal costs; and (iii)
the costs to be recovered are both reasonable and allocable,
i.e., incurred specifically for the contract in question.
Reema Consulting Servs., Inc. v. United States, 107 Fed. Cl.
519, 532 (2012) (citing cases); see also Caddell Constr. Co.,
Inc. v. United States, 111 Fed. Cl. 49, 119 (2013). The second
prong of this analysis, with its causation requirement, does
not permit a protester to recover compensation if the costs
wasted on the initial procurement become necessary in a second
procurement. See Reema, 107 Fed. Cl. at 532; CNA, 107 Fed. Cl.
at 11.
In the case sub judice,
CenterScope initially claimed that it was entitled to bid
preparation and proposal costs because USAID decided to cancel
the first procurement. In its motion, it indicated that “[i]f
the Agency would not have cancelled the procurement, [CenterScope’s]
bid preparation and proposal costs would not have been
unnecessarily incurred.” However, plaintiff continued to seek
those costs even after the agency, as it had previously
indicated it would do, initiated a second procurement covering
essentially the same subject matter as the first (enjoined)
procurement. CenterScope claimed that it could not submit a
proposal in response to this second RFP because it could not
certify that it was a small business under the NAICS code that
is the subject of the procurement. However, it provided no
factual support for this claim – and defendant supplied
evidence to refute this claim.
Because CenterScope has
failed to show that it could not participate in the second
procurement, the court finds that it has not shown that the
error previously documented caused it to incur unnecessarily
bid preparation and proposal costs. Rather, it would appear
that CenterScope, had it chosen, could have used materials
prepared for the first procurement in the second. Accordingly,
those costs were not rendered unnecessary by the agency’s
prior error. At the least, CenterScope has not shown
otherwise. As such, the court finds that CenterScope is not
entitled to recover bid preparation and proposals costs in
this action. Compare Bannum, Inc. v. United States, 56 Fed. Cl.
453, 462 (2003) (“If plaintiff becomes a disappointed offeror
because another vendor is awarded the contract or if the
solicitation is cancelled, it could be entitled to bid
preparation costs if it could show in those circumstances that
the government action was illegal and that it was prejudiced
by the illegality.”).
Based on the foregoing,
the court hereby DENIES plaintiffs’ motions for attorney’s
fees and DENIES CenterScope’s motion for bid preparation and
proposal costs. (Insight
Systems Corp. and CenterScope Technologies, Inc., Nos.
12-863C and 12-883C, May 12, 2014) (pdf)
Plaintiff makes two claims in this
regard. First, it asserts that [Edgewood Chemical Biological
Center] ECBC acted contrary to the relevant regulations in
awarding the contract to an offeror that did not qualify as a
small business within the NAICS code involved. Second, it
contends that ECBC applied the evaluation criteria in the RFP
inconsistently, in rating Reema’s and SMRC’s proposals
differently.
Plaintiff’s first
assertion would be more tenable if the governing regulations
required ECBC to confirm SMRC’s eligibility prior to making an
award. They do not. To be sure, under those regulations, an
agency generally determines a business’ size status as of the
date the offeror submits its initial offer. 48 C.F.R. §
19.301-1(a). That determination, however, is based on the
offeror’s “self-certification that it is small to the
contracting activity.” Enter. Info. Servs., Inc., 2010 CPD ¶
213, at 2 (2010). Thus, under the regulations, the offeror
must represent “that it is a small business concern in
connection with a specific solicitation,” which representation
it may make “if it meets the definition of a small business
concern applicable to the solicitation and has not been
determined by the Small Business Administration (SBA) to be
other than a small business.” 48 C.F.R. § 19.301-1(a); see
also 48 C.F.R. § 52.204-8(d) (discussing representations and
certifications). Under the Federal Acquisition Regulation
(FAR), the contracting officer “shall accept an offeror’s
representation . . . that it is a small business unless (1)
another offeror or interested party challenges the concern’s
small business representation or (2) the contracting officer
has a reason to question the representation.” 48 C.F.R. §
19.301-1(b). Under this regulation, the CO here thus was
required to accept SMRC’s representations regarding its size
unless one of the two exceptions to that rule was triggered.
And, as will be seen, neither of those exceptions were
triggered.
By the time the CO
received Reema’s size protest, she had already awarded the
contract to SMRC. Nothing in the regulations requires a
contracting officer to suspend or terminate a contract based
upon the filing of a size protest. See 13 C.F.R. § 121.1009.
On December 29, 2011, the SBA issued a size determination
concluding that SMRC was not small for the procurement at
issue and was, therefore, ineligible for the award. The
regulations provide that if a contracting officer receives a
determination that the awardee is not an eligible small
business for the procurement in question, and “no OHA appeal
has been filed, the contracting officer shall terminate the
award.” Id. at § 121.1009(g)(2)(i). Here, however, a timely
OHA appeal was filed, which, under the regulations, gave the
CO discretion to determine “whether performance can be
suspended until an appellate decision is rendered.” Id. at §
121.1009(g)(2)(ii). And, the CO, exercising this authority,
determined that the contract should proceed. The OHA then
affirmed the size determination finding, requiring the CO,
under the regulations discussed above, to “either terminate
the contract or not exercise the next option.” Id. at §
121.1009(g)(2)(iii).
Reema, however, asserts
that the CO had reason to question SMRC’s representations
about its size and should have referred the matter to the SBA
pursuant to 48 C.F.R. § 19.301-1(b). But, this claim proves
too much. Plaintiff points to nothing in SMRC’s proposal that
should have triggered an inquiry. Rather, it argues that the
CO should have questioned SMRC’s status because the awardee
failed to list NAICS code 541620, Environmental Consulting
Services, on its profile in the Central Contractor
Registration (CCR) system previously maintained by the General
Services Administration (GSA). This claim is a red herring for
several reasons.
For one thing, the
regulations that governed that system did not oblige SMRC to
list itself as qualifying under any particular NAICS code in
order to be eligible to make an offer. Nor did they suggest
that the CO was obliged to examine SMRC’s CCR listing prior to
making an award. Rather, it appears that the CCR system was
designed primarily to assist government agencies in performing
market research and in administering contracts post-award. See
48 C.F.R. §13.102; see also Shirlington Limousine & Transp.,
Inc. v. United States, 77 Fed. Cl. 157, 160 n.5 (2007). There
is no indication that the system was also to be used in
examining proposals. Indeed, the regulations did not require
small businesses to register before making an offer, but only
required them to do so immediately prior to receiving an
award. 48 C.F.R. § 52.204-7(b)(1) (“[b]y submission of an
offer, the offeror acknowledges the requirement that a
prospective awardee shall be registered in the CCR database
prior to award”); see also Nilson Van & Storage, Inc. v.
United States, 99 Fed. Cl. 408, 416-17 (2011); JGB Enters.,
Inc. v. United States, 63 Fed. Cl. 319, 322 (2004).
Accordingly, there is utterly no reason to believe that SMRC’s
failure to list any particular information in its CCR profile
should have engendered suspicions regarding its size status.
As such, the court must conclude that the CO acted reasonably
under the circumstances, which is all that is required. See
Reliable Builders, Inc., 2010 CPD ¶ 260, at 5 (2010);
Synergetics, Inc., 2007 CPD ¶ 168, at 2 (2007).
Plaintiff next claims it
is entitled to bid preparation and proposal costs because ECBC
improperly evaluated its proposal. But, the court need not
resolve this dispute – or address whether the agency afforded
SMRC benefits that were unwarranted – because, as it turns
out, there is a fatal flaw in plaintiff’s claim for damages.
“Bid preparation and
proposal costs can be awarded by courts as an appropriate way
to try to compensate, at least in part, a victim of unjust
government action during the procurement process.” CNA Corp.
v. United States, 83 Fed. Cl. 1, 11 (2008). Such costs are
recoverable only if three conditions are satisfied: (i) the
agency has committed a prejudicial error in conducting the
procurement; (ii) that error caused the protester to incur
unnecessarily bid preparation and proposal costs; and (iii)
the costs to be recovered are both reasonable and allocable,
i.e., incurred specifically for the contract in question.
Though often not discussed explicitly in cases, the second
prong of this three-part test is designed “to place the
plaintiff in the position he or she would have occupied but
for defendant’s wrong.” Ala. Aircraft Indus., 85 Fed. Cl. at
565; see also CNA Corp., 83 Fed. Cl. at 11 (bid preparation
and proposal costs permissible where such costs would not have
been unnecessarily incurred “but for the arbitrarily and
capriciously issued . . . decision”). Reflecting this view,
where defendant’s wrongful action requires a protester to
submit a second proposal, this court has allowed the recovery
of bid preparation and proposal costs for a first proposal as
a way to provide the protester a complete remedy. But, this
same second prong, with its causation requirement, can
disqualify a protester from receiving compensation if it would
have incurred additional bid preparation and proposal costs
even if the agency had not committed an error.
In the case sub judice,
plaintiff cannot show that the bid preparation and proposal
costs it incurred in creating its first proposal were rendered
unnecessary by the arbitrary, capricious, or otherwise
erroneous actions committed by ECBC. Rather, the situation in
which plaintiff finds itself – unable to receive an award on
its earlier proposal and compelled to seek an award, if at
all, via a new one – stems not from agency misfeasance, but
from the way the regulations deal with the timing of the size
determination made by the SBA. In particular, plaintiff’s
plight, such as it is, derives from the fact that the drafters
of those regulations decided to allow agencies to proceed with
certain contracts pending the ultimate resolution of the size
protest. And, of course, that is what happened here.
Only in the meekest terms
does plaintiff yet argue that ECBC should award it the
contract in question, rather than conduct a reprocurement. Its
hesitation is well-founded as there are statutory and
practical impediments that prevent ECBC from reevaulating the
first set of proposals, none the least of which is the fact
that they are now three years old. (And, it goes almost
without saying, this court is in no position to order such an
award). It follows, a fortiori, that if plaintiff must prepare
a second offer if it hopes to receive the award in question,
and must do so regardless of whether ECBC evaluated its first
offer properly vel non, it cannot obtain bid preparation and
proposal costs for that first proposal. Those costs were not
rendered a ‘“needless expense”’ by defendant’s erroneous
conduct, CNA Corp., 83 Fed. Cl. at 9 (quoting Heyer Prods. Co.
v. United States, 135 Ct. Cl. 63, 71 (1956)), but rather were
lost due to the proper application of the procedural
regulations implementing the size standards.
Accordingly, plaintiff
has failed to satisfy the second prong of the requirements for
receiving bid preparation and proposal costs, to wit, that a
prejudicial error committed by the agency be the cause of its
incurring unnecessarily the bid preparation and proposal costs
it seeks. Therefore, the costs it seeks are not recoverable.
(Reema Consulting Services, Inc., v.
U. S., No. 12-402C, November 26, 2012) (pdf)
The Government bears the
burden of showing that its position was substantially justified.
See Infiniti Info. Solutions, LLC. v. United States, 94 Fed. Cl.
740, 748 (2010) (citing White v. Nicholson, 412 F.3d 1314, 1315
(Fed. Cir. 2005)). The substantial justification inquiry
determines whether the Government’s position was “‘justified in
substance or in the main’ –that is, justified to the degree that
would satisfy a reasonable person.” Pierce v. Underwood, 487
U.S. 552, 565 (1988) (citations omitted). The Government’s
overall position “both prior to and during the litigation” must
have a reasonable basis in both law and fact. United Partition
Sys., 95 Fed. Cl. at 50 (citing Chiu v. United States, 948 F.2d
711, 715 (Fed. Cir. 1991) and Blakley v. United States, 593 F.3d
1337, 1341 (Fed. Cir. 2010)). The key inquiry is “not what the
law now is, but what the Government was substantially justified
in believing it to have been.” Loomis v. United States, 74 Fed.
Cl. 350, 355 (2006) (quoting Pierce, 487 U.S. at 561). The Court
must determine whether the Government was reasonable in bringing
about and continuing the litigation at hand.
The mere fact that the
Government did not prevail is not dispositive of the substantial
justification inquiry. Schock v. United States, 254 F.3d 1, 5
(1st Cir. 2001). Whether one court agreed or disagreed with the
Government does not establish whether the Government’s position
was not substantiality justified, although “a string of court
decisions going either way can be indicative.” Id. (citing
Pierce, 487 U.S. at 568).
Defendant essentially
presented two arguments in the underlying litigation to show why
DGR’s judicial bid protest should fail: (1) DGR waived its right
to bring suit in this Court by not filing its action prior to
the closing date for receipt of proposals; and (2) under the
Small Business Act and applicable regulations, as interpreted by
at least three executive agencies, the Air Force was not
required to give priority to HUBZone small business concerns.
The Court will address both of these arguments below.
1. Waiver of Right
to Bring Suit in This Court
As explained in the prior
opinion, DGR Associates, 94 Fed. Cl. at 200-04, the Court found
Defendant’s waiver argument to be patently unreasonable. When
DGR first saw that the Air Force’s solicitation did not include
a preference for eligible HUBZone offerors, DGR challenged the
solicitation, first by letter to the contracting officer, and
then by filing a formal agency-level protest. DGR took both of
these actions prior to the closing date for receipt of
proposals. The Court noted that DGR’s letter and agency protest
were “in compliance with [Federal Acquisition Regulation (FAR)],
48 C.F.R. § 33.103,” and that by taking these actions, DGR was
“adhering to the federal government’s stated policy of
attempting to resolve protests at the contracting officer and
agency level.” Id. at 202.
When the Air Force denied
DGR’s agency-level protest, DGR timely initiated a protest at
the Government Accountability Office (GAO) within ten days of
adverse agency action. By this time, proposals had been
submitted, and the Air Force had decided to proceed with the
procurement. DGR prevailed in its GAO protest, DGR Associates,
Inc., B-402494, 2010 CPD ¶ 115 (Comp. Gen. May 14, 2010), but
the Air Force declined to follow GAO’s decision. The GAO awarded
DGR its fees and costs of pursuing the protest, but the Air
Force refused to consider DGR’s request. Thereafter, DGR filed
suit in this Court, only to be faced with Defendant’s argument
that DGR waived its right to sue by failing to commence an
action before the closing date for receipt of proposals, citing
Blue & Gold Fleet L.P. v. United States, 492 F.3d 1308 (Fed.
Cir. 2007).
In denying Defendant’s
waiver defense, the Court stated that DGR “diligently pursued
its solicitation challenge,” and “[a]t each step, . . . followed
applicable FAR and GAO protest procedures.” DGR Associates, 94
Fed. Cl. at 202. The Court observed that Defendant’s waiver
argument “would be directly at odds with government policy to
seek resolution of protests within the agency.” Id. at 203.
Following Defendant’s argument “would have parties running into
the Court of Federal Claims to challenge solicitation errors,
instead of pursuing other available avenues of relief.” Id. The
Court ultimately ruled:
The correct
interpretation of Blue & Gold Fleet is that, if a party has
challenged a solicitation impropriety before the close of the
bidding process, the party is not precluded from later filing
its protest at the Court of Federal Claims. A party must do
something before the closing date to preserve its rights, and
must thereafter pursue its position in a timely manner.
Id. The Court noted the
gross inequity of Defendant’s argument as it would apply to DGR:
The Court hardly can
conceive of a greater injustice than to say to DGR “even
though you followed applicable protest procedures and
prevailed at the GAO, now you are out of luck because you
failed to file a judicial action in the Court of Federal
Claims before the close of the bidding process.”
Id. The Court continued by
stating “Defendant’s added insult to DGR would be that ‘the Air
Force has decided not to follow the GAO’s decision in your
favor, and there is nothing you can do to prevent it.’” Id. By
any measure, Defendant’s waiver argument was patently
unreasonable, and not substantially justified.
2. Statutory
Preference for the HUBZone Small Business Program
Defendant’s second
argument, that under the Small Business Act and implementing
regulations, the Air Force was not required to give priority to
HUBZone small business concerns, contradicted the plain meaning
of the Small Business Act. Defendant asserts that the
interpretation of the statute was a novel issue, and thus its
position was substantially justified. (Def.’s Resp. 19-20, Jan.
6, 2011.) However, the Court concludes otherwise, that the
interpretation of the HUBZone statutory language was not novel.
Due to the unambiguous wording of the statute, and the existing
case law precedent, Defendant’s position in the underlying
litigation was not reasonable.
When DGR filed suit in this
Court for declaratory and injunctive relief on June 28, 2010,
multiple courts and the GAO uniformly had held that the Small
Business Act was unambiguous, and that the HUBZone program
should be given a preference over other small business programs.
Contract Mgmt., Inc. v. Rumsfeld, 434 F.3d 1145, 1147 (9th Cir.
2006) (“The HUBZone Program, by contrast, commands in
unequivocal terms that a contract opportunity be designated as a
HUBZone set-aside when certain criteria are met.”); Contract
Mgmt., Inc. v. Rumsfeld, 291 F.Supp.2d 1166, 1174 (D.Haw. 2003)
(“Congress has used clear language to mandate, ‘notwithstanding
any other provision of law,’ the award of contract opportunities
on the basis of competition restricted to qualified HUBZone
small business concerns when certain, specific criteria are
met.”); Mission Critical Solutions v. United States, 91 Fed. Cl.
386, 402-03 (2010) (“[T]he statutory language is mandatory and
that the plain meaning of the HUBZone statute requires a
contract opportunity to be competed among qualified HUBZone
small business concerns whenever the specified criteria are met,
notwithstanding other provisions of law – including those found
within the Small Business Act itself.”); Small Business
Administration Reconsideration, B-401057.2, 2009 CPD ¶ 148 at 6
(Comp. Gen. July 6, 2009) (“[B]oth the appellate court and
district court ultimately concluded, in no uncertain terms, that
the HUBZone statute mandates a set-aside, while the statutory
language authorizing the 8(a) program is discretionary.”);
Mission Critical Solutions, B-401057, 2009 CPD ¶ 193 at 3 (Comp.
Gen. May 4, 2009) (“We do not think that SBA's regulatory
implementation of the HUBZone and 8(a) statutes is reasonable
since it fails to give effect to the mandatory language of the
HUBZone statute.”). Confronted with this line of unwavering
authorities, the Court does not find it reasonable that
Defendant would continue to litigate this issue.
Furthermore, Defendant’s
position did not have a reasonable basis in law, as the HUBZone
statutory language was unambiguous. The GAO “read the plain
language of the HUBZone statute as requiring an agency to set
aside an acquisition for competition restricted to qualified
HUBZone small business concerns where it has a reasonable
expectation” that the two pre-conditions of the HUBZone statute
would be satisfied. DGR Associates Inc., B-402494, 2010 CPD ¶
115 (Comp. Gen. May 14, 2010). If the Air Force simply had
elected to follow the GAO’s decision, DGR’s lawsuit would not
have been necessary. However, the Air Force rejected the GAO’s
decision, forcing DGR to pursue further litigation in this
Court. Given the clear statutory language, Defendant was
unreasonable in putting DGR to additional effort and expense.
The Court’s analysis of the Small Business Act’s HUBZone program
found no room for debate. DGR Associates, 94 Fed. Cl. at 208 (“[T]he
Court finds the plain language of the HUBZone provision to
establish the priority of the HUBZone program over the 8(a)
program.”). The Court examined the legislative history to see
whether a “clear intent contrary to the plain meaning exists.”
Id. (citation omitted). The legislative history was
unpersuasive, offering no explanation of why the Senate omitted
the parity provision from the HUBZone program, making the
Defendant’s reasoning as to Congress’s intent “purely
speculative.” Id. at 209. Due to the plain language of the
statute and the lack of any contrary Congressional intent
expressed in the legislative history, Defendant’s position was
unreasonable.
For all of the foregoing
reasons, the Court concludes for purposes of DGR’s attorneys’
fees application that Defendant’s arguments in the underlying
litigation were not substantially justified. 28 U.S.C. §
2412(d)(1)(A). (DGR
Associates, Inc. v. U. S. and General Trades and Services, Inc.,
No. 10-396C, February 15, 2011) (pdf) (Reversed by
the Court of Appeals for the Federal Circuit in DGR
Associates, Inc., v. U. S. and General Trades and Services, Inc.,
No. 2011-5880, August 2, 2012 (pdf) (See below)
A. Permissibility of Awarding
Both Injunctive Relief and Bid Preparation and Proposal Costs
In arguing that this court cannot “award both full injunctive
relief and bid preparation and
proposal costs,” Def.’s Resp. at 6, the government looks chiefly
to the law as it existed prior to
the modification of the Tucker Act by the ADRA. Under that law,
the government contends that
“a successful protestor could receive either equitable or
monetary relief, but not both.” Def.’s
Resp. at 6-7. The government maintains that the ADRA of 1996 was
not intended “to alter the
remedies available to a successful protester.” Def.’s Resp. at
7. Additionally, the government
argues that if the court has the ability to grant both
injunctive and monetary relief, it should not
do so in the instant case because allowing Alabama Aircraft to
recover bid preparation and
proposal costs would violate the principle that a remedy should
not put a plaintiff “in a better
position than if no breach had occurred.” Def.’s Resp. at 11.
(at p. 5 of decision)
(sections deleted)
Therefore, it would not amount
to an impermissible double recovery for Alabama
Aircraft to receive bid preparation and proposal costs in
addition to the injunctive relief the court
previously awarded.
The foremost principle in
fashioning a remedy is to endeavor to place the plaintiff in the
position he or she would have occupied but for defendant’s
wrong. See, e.g., Glendale Federal
Bank, FSB v. United States, 239 F.3d 1374, 1380 (Fed. Cir.
2001). In this case, an award of bid
preparation and proposal costs is necessary to place Alabama
Aircraft in its rightful position.
Here, without defendant’s errors, Alabama Aircraft would have
had to submit only one proposal.
Due to those errors, Alabama Aircraft is now required to pay for
and submit another proposal in a
continuing effort to obtain an award of a contract for
maintenance work on the KC-135 PDM
Stratotanker. An award of bid preparation and proposed costs is
fully appropriate to provide a
complete remedy for Alabama Aircraft.
CONCLUSION
For the foregoing
reasons, Alabama Aircraft is entitled to receive bid preparation
and
proposal costs consisting of $289,887.31 for burdened labor
costs, $13,133.52 for internal
expenses, and $700,267.40 for consultants’ fees and expenses.
The clerk shall enter judgment
for plaintiff in the total amount of $1,003,288.23. (Alabama
Aircraft Industries, Inc. - Birmingham, v. U.S., No.
08-470C, Reissued February 3, 2009) (pdf)
Under the EAJA, an award of reasonable attorneys’ fees may be
made to a qualifying
party who prevails in an action by or against the United States,
provided that certain criteria are
met. 28 U.S.C. § 2412(d)(1)(A).2 Eligibility for such an award
requires that: (1) the claimant be
a “prevailing party;” (2) the government’s position was not
“substantially justified;” (3) no
“special circumstances make an award unjust;” and (4) any fee
application be submitted to the
court within 30 days of final judgment in the action and be
supported by an itemized statement.
Id. § 2412(d)(1)(A), (B); see Commissioner, INS v. Jean, 496
U.S. 154, 158 (1990); Loomis v.
United States, 74 Fed. Cl. 350, 353 (2006); Lion Raisins, Inc.
v. United States, 57 Fed. Cl. 505
(2003); see also Knowledge Connections, Inc. v. United States,
76 Fed. Cl. 612, 614-15 (2007).
(sections deleted)
The burden of establishing substantial justification rests upon
the government. See White
v. Nicholson, 412 F.3d 1314, 1315 (Fed. Cir. 2005); Hillensbeck
v. United States, 74 Fed. Cl.
477, 479-80 (2006); Lion Raisins, 57 Fed. Cl. at 512. In
Pierce
v. Underwood, 487 U.S. 552,
565 (1998), the Supreme Court described substantial
justification as meaning “not ‘justified to a
high degree,’ but rather ‘justified in substance or in the
main’– that is, justified to a degree that
could satisfy a reasonable person.” In determining substantial
justification, the court must “look
at the entirety of the government’s conduct [both prior to and
during litigation] and make a
judgment call whether the government’s overall position had a
reasonable basis in both law and
fact.” Chiu v. United States, 948 F.2d 711, 715 (Fed. Cir.
1991); see also Doty v. United States,
71 F.3d 384, 386 (Fed. Cir. 1995) (“[T]he term ‘position of the
United States’ [in the EAJA]
refers to the government’s position throughout the dispute,
including not only its litigating
position but also the agency’s administrative position.”).
The key inquiry is “not what the law now is, but what the
government was substantially
justified in believing it to have been.” Loomis, 74 Fed. Cl. at
355 (quoting Underwood, 487 U.S.
at 561). The government’s position may therefore be found to be
substantially justified even
though the court previously overturned the government’s actions.
Id.; see also Scarborough v. Principi, 541 U.S. 401, 415 (2004) (“Congress did not . . . want
the ‘substantially justified’
standard to ‘be read to raise a presumption that the [g]overnment
position was not substantially
justified simply because it lost the case.’”); RAMCOR Servs.
Group, Inc. v. United States, 185
F.3d 1286, 1290 (Fed. Cir. 1999) (“Although INS had lost the
underlying action, that outcome
does not alone show that its position had no substantial
justification.”). Of course, “[t]o be
‘substantially justified’ means . . . more than merely
undeserving of sanctions for frivolousness.”
Underwood, 487 U.S. at 566.
The government argues that its position in the underlying
litigation was justified because
there was “significant GAO precedent” supporting the Contracting
Officer’s issuance of
Solicitation Amendments 9 and 12 to extend the closing dates for Presidential’s proposal
revisions nunc pro tunc. Def.’s Opp’n at 4 (citing Micromass,
Inc., B-278869, Mar. 24, 1998,
98-1 CPD ¶ 93; Ivey Mech. Co., Comp. Gen. Dec. B-272764, 96-2 CPD ¶ 83, Aug. 23, 1996;
Fort Biscuit Co., B-247319, May 12, 1992, 92-1 CPD ¶ 440;
Institute for Advanced Safety
Studies-Recon., B-221330.2, July 25, 1986, 86-2 CPD ¶ 110). The
government posits that its
reliance on these GAO opinions “was reasonable and substantially
justified” because the
Contracting Officer in the instant case was “faced with
circumstances essentially the same” as
those existing in the GAO cases and issued the amendments to
enhance competition, consistent
with those decisions. Id. The government also puts forward GAO’s
decision in Geo-Seis
Helicopters, Inc., B-299175, B-299175.2, Mar. 5, 2007, as a
basis for support. The government
argues that, having prevailed before GAO, ‘“the [g]overnment’s
defense of a case arising from an
administrative decision is reasonable where it is not clear that
the administrative decision was
erroneous.’” Def.’s Opp’n at 4-5 (quoting Trone v. United
States, 3 Cl. Ct. 690, 693 (1983), and
citing Engles v. United States, 2 Cl. Ct. 166 (1983), and Stolpe
v. United States, 36 Fed. Cl. 259,
266 (1996)).
The government’s reliance on the set of decisions by GAO is
problematic. The court
specifically disavowed and refused to follow those precedents.
See Geo-Seis, 77 Fed. Cl. at 645
n.28. More importantly, the government’s argument based on the
GAO precedents sidesteps the
basis for the court’s decision on the merits. The court looked
directly to the provisions of the
FAR that governed the procurement and held that “[t]he plain
language of FAR § 52.215-
1(c)(3)(ii)(A) precluded the Sealift Command’s consideration of
Presidential’s revised
proposals.” Geo-Seis, 77 Fed. Cl. at 645.3 After examining the
regulatory history of revisions
made to the FAR in 1997, id. at 642-45, the court concluded that
those revisions expressly
rejected the position taken by the Contracting Officer in the
challenged procurement, i.e., that she
could issue a post-deadline amendment to the solicitation
allowing a late proposal where doing
so was “in the best interest of the [g]overnment.” Id. at 637
(quoting AR 342 (Mem. to file from
Stangler and Kimm (Mar. 22, 2006))). Proposed revisions to the
FAR in 1996 would have
allowed just that sort of discretion on the part of a
contracting officer, id. at 642 (citing and
quoting Federal Acquisition Regulation; Part 15 Rewrite–Phase I,
61 Fed. Reg. 48,380, 48,380-
81 (Sept. 12, 1996)), but those proposed revisions were not
adopted on the ground that they gave
too much discretion to a contracting officer. Id. at 643 (citing
and quoting Federal Acquisition
Regulation; Part 15 Rewrite; Contracting by Negotiation and
Competitive Range Determination,
62 Fed. Reg. 51,224 (Sept. 30, 1997)). Thus, the FAR, not GAO
and not the court, established
the parameters for the Contracting Officer’s action. “[T]he FAR
Councils [the Civilian Agency
Acquisition Council and the Defense Acquisition Regulations
Council] specifically addressed th[e attendant] policy issues in the 1997 reconsideration of the
FAR, and th[e] court should not undercut that resolution by a
contrary decision in this case.” Id. at 646. In short,
even if the line of GAO decisions had some basis prior to the
1997 revisions to the FAR, which itself is a dubious
proposition, those decisions could not have retained any
vitality after those revisions.
The government’s position will not be found to be reasonable or
substantially justified
when explicit, unambiguous regulations directly contradict that
position. See Hillensbeck, 74
Fed. Cl. at 481 (government’s position conflicted with
unambiguous statutory definition and
regulations); Loomis, 74 Fed. Cl. at 355 (military failed to
comply with its own regulations). The
government argues that Hillensbeck is “readily distinguishable”
from the instant case because the
agency here did not “rel[y] upon an internal agency
interpretation of a statute,” but, rather, “[the]
M[ilitary] S[ealift] C[ommand] relied upon a line of protest
decisions from the GAO . . . [which
is] statutorily mandated to render such decisions.” Def.’s Opp’n
at 6. The proffered distinction
is not meaningful. The actions of the Sealift Command’s
Contracting Officer contravened the
FAR, and the GAO precedents could not excuse that deviation from
legal requirements. In short,
“there is no justification for the government’s position when
clear, unambiguous regulations
directly contradict that position.” Filtration Dev. Co. v.
United States, 63 Fed. Cl. 612, 621
(2005).
Accordingly, the government has not met its burden of proving
that its position was
substantially justified. Geo-Seis’ claim satisfies the
requirements of the EAJA.
(sections deleted)
The clerk shall enter judgment for plaintiff in the total amount
of
$101,915.26. (Geo-Seis
Helicopters, Inc., v. U. S. and Presidential Airways, Inc.,
07-155C, Reissued October 31, 2007) (pdf)
The Court of Claims recognized in Severin v. United States that
if a contractor proved that “in the performance of [its]
contract with the Government [it] became liable to [its]
subcontractor for the damages which the latter suffered, . . .
[this] might well constitute actual damages” recoverable by the
contractor, even though the contractor has not yet paid the
subcontractor. 99 Ct. Cl. 435, 443 (1943). In the absence of
such proof, however, the Court of Claims made clear that a
contractor is precluded from recovering in its claim for damages
those losses suffered by its subcontractor. Id. at 443-44.
Notwithstanding an opportunity to supplement its initially
submitted documentary evidence to support its claim for bid
proposal and preparation costs, plaintiff has declined even to
submit corroborating declarations from its subcontractors
regarding the respective payment obligations between plaintiff
and the subcontractors. The Court of Claims recognized in
Severin that, in the absence of proof of a contractor’s
liability to a subcontractor, a contractor is precluded from
recovering in its claim for damages those losses suffered by its
subcontractor. 99 Ct. Cl. at 443-44. The court finds that
plaintiff has failed to carry its burden of proof in this case
and DENIES, as part of plaintiff’s claim for bid proposal and
preparation costs, the recovery of those expenses incurred by
plaintiff’s subcontractors in connection with the bid
preparation at issue here.
In this case, plaintiff has submitted no evidence regarding its
directly incurred bid preparation costs. Notwithstanding the
court’s order directing plaintiff to provide specific
documentary evidence in support of its claim, plaintiff has
declined to expend the effort to prove its claim. Plaintiff
states that “to spend significant amounts of money on Italian
lawyers and accountants to verify and further substantiate it
case . . . [would] not be prudent from a business standpoint
considering the amount of time and energy and money already
spent in pursuing this case.” Pl.’s Claim Supp. at 3. The court,
however, fails to see why it would have been necessary to hire
“Italian lawyers and accountants” to provide such basic evidence
as tax or payroll records. In the absence of any evidence of the
bid preparation costs directly incurred by plaintiff,
plaintiff’s claim is wholly unsupported and legally
insufficient. Accordingly,the court DENIES plaintiff’s claim for
its directly incurred bid preparation and proposal costs. (Impressa
Construzioni Geom. Domenico Garufi v. U. S., No. 99-400C,
c/w 01-708C, June 30, 2004) (pdf)
Where, as here, a teaming agreement or subcontract “expressly
negates any liability of the prime contractor to the
subcontractor,” the prime may not recover those costs. Donovan
Constr. Co.v. United States, 138 Ct. Cl. 97, 99 (1957), cert.
denied, 355 U.S. 826 (construing United States v.Blair, 321 U.S.
730, 737 (1944)). As our appellate authority held:
Quite logically where the subcontract absolves the prime
contractor from liability to his subcontractor there can be no
derivative liability of the Government to the subcontractor
even where the Government would otherwise be culpable, for
actual damage to the prime is a prerequisite to recovery
either for himself or for those subordinate to him.
Gardner Displays Co. v. United States, 346 F.2d 585, 586-87 (Ct.
Cl. 1965).
Because Plaintiff’s teaming agreements with ILC Dover and CUBRC
clearly indicate that Plaintiff was under no obligation to
compensate its teammates for their B&P costs, Gentex may not
recover those costs on their behalf in this action. Gentex’s
post hoc agreement to reimburse their B&P costs if it recovers
them in this action does not create an obligation or liability
sufficient to imbue Gentex with the requisite actual injury
necessary for standing. Absent such obligation, the Court would
be allowing a plaintiff to raise another entity’s legal rights
and recover the damages of nonparties in disregard of
traditional threshold requirements of standing. Allen, 468 U.S.
at 751.
Plaintiff has asked that a 15% markup, or “profit,” be included
in its bid preparation and proposal costs. However, because
profit is not a cost incurred in the bid preparation and
proposal process, the Court denies recovery. (Gentex
Corporation v. U. S., No. 03-728C, June 10, 2004, June 18,
2004) (pdf)
Balancing the hardships between the government and WPS on the
one hand and PGBA on the other, the Court determines that
adequate justification does not exist to set aside the contract
and require a new round of solicitation. This procurement has
already lasted nearly one and one half years, from the issuance
of the RFP in September 2002 to the anticipated work
commencement date of April 1, 2004, and WPS avers that it has
expended significant resources preparing for implementation.
Interv.-Def.’s Opp. at 63; Interv.-Def.’s Reply at 24. Revoking
the contract and requiring a new solicitation would likely
engender an additional delay of at least the same length. In
light of these considerations, the Court determines that the
balance of 30 hardships weighs in favor of denying PGBA’s
request for declaratory relief. In a bid protest case, 28 U.S.C.
§ 1491(b)(2) provides that “[t]o afford relief in such an
action, the court[] may award any relief that the court
considers proper, including declaratory and injunctive relief
except that any monetary relief shall be limited to bid
preparation and proposal costs.” In the circumstances of this
case, the Court has determined that PGBA is entitled to recover
its reasonable costs incurred in preparing its proposal for the
TDEFIC solicitation. “[A]losing competitor may recover the costs
of preparing its unsuccessful proposal if it can establish that
the Government’s consideration of the proposal submitted was
arbitrary or capricious or in violation of applicable statute or
regulation.” Gentex Corp., 58 Fed. Cl. at 656 (citing CSE Constr.
Co. v. United States, 58 Fed. Cl. 230, 262- 3 (2003); 28 U.S.C.
§ 1491(b)(2)). In light of the errors discussed above and
because PGBA was prejudiced by such errors, PGBA may recover its
bid preparation and proposal costs. The amount of such recovery
shall be determined through further proceedings in this action.
(PGBA, LLC,v. U. S. (Defendant) and
Wisconsin Physicians Service Insurance Corporation
(Intervening-Defendant); No. 03-2773C, March 31, 2004,
Reissued April 22, 2004.) (pdf) |
|
U. S. Court of Federal Claims
-
Listing of Decisions |
For
the Government |
For
the Protester |
Insight Systems Corp. and
CenterScope Technologies, Inc., Nos. 12-863C and 12-883C,
May 12, 2014 (pdf) |
CMS Contract Mgmt. Servs. et al
v. U. S., Nos. 12-852C, 12-853C, 12-862C, 12-864C, &
12-869C, September 29, 2015 (pdf) |
Reema Consulting Services, Inc., v. U.
S., No. 12-402C, November 26, 2012 (pdf) |
DGR
Associates, Inc. v. U. S. and General Trades and Services, Inc.,
No. 10-396C, February 15, 2011 (pdf) (Reversed by
the Court of Appeals for the Federal Circuit in DGR
Associates, Inc., v. U. S. and General Trades and Services, Inc.,
No. 2011-5880, August 2, 2012 (pdf) (See below) |
Impressa Construzioni Geom. Domenico
Garufi v. U. S., No. 99-400C, c/w 01-708C, June 30, 2004 (pdf) |
Alabama Aircraft Industries,
Inc. - Birmingham, v. U.S., No. 08-470C, Reissued February
3, 2009 (pdf) |
Gentex Corporation v. U. S., No.
03-728C, June 10, 2004, June 18, 2004 (pdf) |
Geo-Seis Helicopters, Inc., v. U. S. and
Presidential Airways, Inc., 07-155C, Reissued October 31, 2007 (pdf) |
Lion
Raisins, Inc, Nos. 01-322C & 01-536C, March 20, 2002 |
PGBA, LLC,v. U. S. (Defendant) and
Wisconsin Physicians Service Insurance Corporation
(Intervening-Defendant); No. 03-2773C, March 31, 2004,
Reissued April 22, 2004 (pdf) |
|
Lion
Raisins, Inc, Nos. 01-322C & 01-536C, June 10, 2002 |
U. S. Court of Appeals for the Federal
Circuit |
II. DISCUSSION
On appeal, IDEA argues that the
[Court of Federal Claims] CFC erroneously
decided that there is “no recovery when no bid was submitted”
and that the “‘act of submitting a bid’ is always
essential. Appellant’s Br. 11–12. IDEA contends that it
should receive “just and proper reimbursement for its presolicitation
bid preparation costs” because the Air Force
refused to allow any bids for the sole-source bridge contract.
Id. at 13. IDEA further insists that the number of
hours it is requesting for reimbursement is very modest
and there is independent evidence supporting its claims.
Although it never prepared a draft proposal, IDEA insists
that its pre-solicitation actions were recoverable and
reasonable, including: (1) pre-drafting elements to go in
the proposal, including “ABOUT CMAS” and “ABOUT
IDEA” sections; (2) contacts with the contracting office;
and (3) checking for the bid posting online. Joint Appendix
(“J.A.”) 68–72. According to IDEA, moreover, the CFC
was wrong in valuing Crain’s labor at $0/hour and that
there were a number of possible acceptable rates the CFC
could have adopted. Finally, IDEA asserts that the CFC
wrongly rejected its claim for attorney fees under the
EAJA because the Air Force clearly broke the law and the
EAJA is designed to protect companies like IDEA.
The government responds that the burden is on the
protestor to adequately demonstrate reasonable and recoverable costs in a bid protest case. According to the
government, the CFC correctly concluded that IDEA was
not entitled to bid preparation costs because it did not
submit or prepare a proposal. The government contends
that the CFC also correctly concluded that all of IDEA’s
costs were not properly characterized as bid preparation
and proposal costs. Because the CFC is not a court of
equity, the government asserts that CFC correctly found
that there is no basis in law for IDEA’s monetary claims.
According to the government, moreover, the CFC properly
concluded that all of IDEA’s costs are unsupported, not
reasonable, and excessive. Finally, the government
argues that, based on binding precedent, the CFC properly
rejected IDEA’s EAJA claim.
We review the
CFC’s decisions de novo for errors of law and for clear error
for findings of fact. Ind. Mich. Power Co. v. United States, 422
F.3d 1369, 1373 (Fed. Cir. 2005).
A. Bid
Preparation and Proposal Costs
By statute, if a party is successful in a bid protest
case, “the [CFC] may award any relief that the court
considers proper, including declaratory and injunctive
relief except that any monetary relief shall be limited to
bid preparation and proposal costs.” 28 U.S.C.
§ 1491(b)(2) (emphasis added). Although § 1492(b)(2) does
not define bid preparation and proposal costs, courts often
turn to the Federal Acquisition Regulation (“FAR”) provisions
for guidance in interpreting the statute. See Coflexip
& Servs., Inc. v. United States, 961 F.2d 951, 953 (Fed.
Cir. 1992) (referring to the federal regulations to define
proposal preparation costs).
The pertinent FAR provision states in relevant part:
“Bid and proposal (B&P) costs means the costs incurred in
preparing, submitting, and supporting bids and proposals
(whether or not solicited) on potential Government or non-
Government contracts.” 48 C.F.R. § 31.205-18(a) (2012).
We agree with the CFC that IDEA is not entitled to
recover any costs because IDEA did not submit or prepare
a bid proposal.1 The statute clearly limits monetary relief
available to “bid preparation and proposal costs,” 28 U.S.C. § 1491(b)(2). It is undisputed that IDEA never
submitted a proposal, whether solicited or unsolicited.
The CFC further found that IDEA did not even allege that
it prepared a draft proposal. We see no clear error in this
finding. Although IDEA argues that it drafted materials
about CMAS and IDEA that it intended to put in the
proposal, a review of those materials indicates that they
were clearly used in an email to the Air Force before any
bid was posted. See J.A. 68–72.
IDEA’s equitable argument is unpersuasive because
the plain language of the statute states that “any monetary
relief shall be limited to bid preparation and proposal
costs.” 28 U.S.C. § 1491(b)(2) (emphasis added). Furthermore,
IDEA’s assertion that the number of hours it
claims is very modest misses the point. Monetary relief,
no matter how “modest,” is not available except for bid
preparation and proposal costs.
Because we conclude that IDEA cannot recover any
costs when it did not submit or prepare a bid proposal, we
affirm the CFC’s decision to deny IDEA’s claim for costs
in its entirety.
B. IDEA’s EAJA Claim
The EAJA provides that “a court may award fees and
expenses of attorneys . . . to the prevailing party in any
civil action brought by or against the United States or any
agency or any official of the United States acting in his or
her official capacity in any court having jurisdiction of such action.” 28 U.S.C. § 2412(b) (emphasis added). In
Farrar v. Hobby, 506 U.S. 103 (1992), the Supreme Court
defined “prevailing party”: “a plaintiff ‘prevails’ when
actual relief on the merits of his claim materially alters
the legal relationship between the parties by modifying
the defendant’s behavior in a way that directly benefits
the plaintiff.” 506 U.S. at 111–12. We have generally
adopted this meaning of prevailing party in “all cases in
which Congress has authorized an award of fees to a
‘prevailing party.’” Singer v. Office of Senate Sergeant at
Arms, 173 F.3d 837 (Fed. Cir. 1999) (quoting Hensley v.
Eckerhart, 461 U.S. 424, 433 (1983)).
In this case, the CFC correctly rejected IDEA’s claim
for EAJA because IDEA was not a prevailing party entitled
to recovery of attorney fees. IDEA did not receive an
injunction and recovered no money damages. Therefore,
IDEA did not receive any actual relief that “materially
alters the legal relationship between the parties.” Farrar,
506 U.S. at 111–12.
Because IDEA is not a prevailing party, we conclude
that the CFC properly denied recovery of attorney’s fees
under 28 U.S.C. § 2412(b). (Innovation
Development Enterprises of America, Inc. v. U. S., No.
2014-5070, January 12, 2015) (pdf)
The [Equal Access to Justice Act] EAJA provides that, when a timely
application is filed, an eligible prevailing party shall be
awarded attorneys’ fees and other expenses incurred by that
party in any civil action brought by or against the United
States “unless the court finds that the position of the United
States was substantially justified . . . .” 28 U.S.C. §
2412(d)(1)(A).
(sections deleted)
In the underlying bid protest, the Government argued that the
Small Business Act and the SBA’s implementing regulations did
not require the Air Force to give priority to HUBZone small
business concerns. DGR, 97 Fed. Cl. at 218. The Court of Federal
Claims rejected the Government’s position because in the court’s
view the Government’s interpretation of the Act “contradicted
the plain meaning of the Small Business Act.” Id. at 219. In the
subsequent EAJA action, the Government argued that its position
in the bid protest litigation nevertheless was substantially
justified because “interpretation of the statute was a novel
issue . . . .” Id. The Court of Federal Claims rejected the
Government’s justification argument, holding that “the
unambiguous wording of the statute, and the existing case law
precedent” rendered the Government’s merits-based argument in
the underlying litigation “not reasonable.” Id.
We cannot agree. While the Government’s position must be “more
than merely undeserving of sanctions for frivolousness,” it is
sufficient for purposes of establishing substantial
justification that there was a “genuine dispute” such that
“reasonable people could differ as to [the appropriateness of
the contested action].” Pierce, 487 U.S. at 565-66 (alteration
in original) (citation omitted). At the time DGR initiated the
underlying bid protest, presumptively reasonable people in all
three branches of the Government had reached differing
conclusions as to whether the Small Business Act permitted
participating agencies to place the HUBZone and 8(a) programs on
an equal footing.
Of the various Government agencies to opine on the matter, the
Small Business Administration, the Department of Justice, the
Office of Management and Budget, and the Department of Defense
all considered the SBA’s parity regulations to be consistent
with the Act. The opposite conclusion had been reached by the
Government Accountability Office in four separate decisions in
three separate bid protests.
Even the
Federal courts were split on the matter. Although the Court of
Federal Claims in Mission Critical had concluded that the SBA’s
parity regulations were inconsistent with the plain meaning of
the Act, the District Court for the District of Hawaii had
rejected a challenge to the regulations on the grounds that the
regulations “sufficiently promote the congressional objective of
parity between the HUBZone and 8(a) programs.” Contract Mgmt.,
291 F. Supp. 2d at 1177.
Thus, at
the time DGR filed its bid protest in the Court of Federal
Claims, there was a genuine dispute among all three branches of
Government as to whether the Air Force was required to give
priority to the HUBZone program over the 8(a) program.
That alone
should be sufficient reason to conclude that the Department of
Justice’s merits-based argument in the underlying litigation
was, if not actually correct, at least sufficiently grounded in
law to be substantially justified under the relatively low
threshold standard described above. There is more. Though the
Congressional resolution of this issue came after the litigation
in the Court of Federal Claims, there had been an earlier
indication of the Congress’ view of the matter. Following the
GAO’s Mission Critical decision, the Senate proposed amending
the Act to clarify that when a contract could be awarded
pursuant to more than one small business program, Federal
agencies have discretion as to which program to apply. See H.R.
2647, 111th Cong. § 838 (July 23, 2009) (Engrossed amendment
Senate). While the amendment was under consideration in the
House, the Department of Justice issued its 2009 memorandum in
reaction to the GAO’s Mission Critical decision.
One and a
half months later, the Senate receded, noting “that the
Department of Justice has concluded that no change to the Small
Business Act is required to ensure that contracting officers . .
. have discretion whether or not to award contracts pursuant to
the HUBZone program,” and “direct[ing] the Secretary of Defense
to continue to administer the HUBZone program in a manner
consistent with the Department of Justice opinion.” H.R. Rep.
No. 111-288, at 789 (2009).
In view of
this clear statement from Congress affirming the SBA regulations
at issue, it is difficult for us to conclude that the Government
was not substantially justified in believing that the Small
Business Act permitted participating agencies to place the
HUBZone and 8(a) programs on an equal footing. We conclude,
therefore, that the Court of Federal Claims made a clear error
of judgment in weighing the factors relevant to the question of
whether the Government’s merits-based argument was substantially
justified. (DGR Associates,
Inc., v. U. S. and General Trades and Services, Inc., No.
2011-5880, August 2, 2012) (pdf) (Reversed Court of
Federal Claims opinion in
DGR Associates, Inc. v. U. S.
and General Trades and Services, Inc., No. 10-396C, February
15, 2011 (pdf)) (See above) |
|
U. S. Court of Appeals for the Federal Circuit |
For
the Government |
For
the Protester |
Innovation Development Enterprises
of America, Inc. v. U. S., No. 2014-5070, January 12, 2015
(pdf) |
|
DGR
Associates, Inc., v. U. S. and General Trades and Services, Inc.,
No. 2011-5880, August 2, 2012 (pdf) (Reversed Court
of Federal Claims opinion in
DGR Associates, Inc. v. U. S.
and General Trades and Services, Inc., No. 10-396C, February
15, 2011 (pdf)) (See above) |
|
|
|