HOME  |  CONTENTS  |  DISCUSSIONS  DISCUSSION ARCHIVES  |  BLOG  |  QUICK-KITs|  STATES

Loading

4 CFR 21.8 (d):  Payment of Protester's Costs

Comptroller General - Key Excerpts

New  The protester requests reimbursement of its proposal preparation costs, all of its protest-related legal fees, and the fees incurred in filing this claim for costs with GAO. The agency has agreed to reimburse the protester reasonable proposal preparation costs and the fees associated with the one meritorious challenge to the agency’s technical evaluation on which the protest was sustained, but disputes the request to reimburse the protester for the legal fees associated with pursuing this claim for reimbursement. We consider each of these elements of the claim, in turn, below.

Proposal Preparation Costs

The protester seeks to recover $48,851.68 as the reasonable costs of preparing its proposal. Claim at 2. Where our Office sustains a protest, we may recommend that the protester be reimbursed its costs of filing and pursuing a protest and preparing a proposal. 4 C.F.R. § 21.8(d). Although we normally do not recommend reimbursement of proposal preparation costs where a protester has a further opportunity for award, we may recommend reimbursement where, for instance, changed circumstances render no longer relevant a proposal that was previously submitted. See COBRO Corp., B‑287578.2, Oct. 15, 2001, 2001 CPD ¶ 181 at 8-9. Here, because the awarded lease contains no termination clause, there is no relief available to the protester except reimbursement of its costs. In these circumstances, we recommend the reimbursement of the reasonable costs of preparing the protester’s proposal. The agency has offered to reimburse the protester $47,242.00, the amount requested by the protester, less reimbursement for certain disputed travel expenditures. Agency Reply at 14.

Specifically, GSA contends that the attendance of the wife of Federal Builders’ principal at the market survey--the initial meeting at the current leased facility between the agency and the protester--was unnecessary, and the agency thus requests that we not grant the protester’s request that we recommend reimbursement of Federal Builders for her expenses. Agency Reply at 3-4. The agency notes in this regard that the wife is not an employee of Federal Builders and that the protester claims no reimbursement for her time. See Claim, Exh. 5, Letter from Agency to Federal Builders, Feb. 2, 2015 at 2. The protester asserts that the disputed amount of reimbursement, $1,609.48, is reasonable, given that the protester is not asking for the reimbursement for the expenses incurred by the attendance of other Federal Builders employees at the market survey meeting, and that the principal’s wife performed valuable services of notetaking. Protester’s Comments, Sept. 18 at 8.

We agree with the agency that the protester has not shown that the wife’s expenses are reimbursable. The manager’s wife was not an employee of the firm, and the protester has sought no reimbursement for her time spent as a note taker, thus calling into question whether her presence at the meeting was a reasonable business expense. Further, the fact that the protester has not requested reimbursement of the expenses incurred by other individuals at the meeting in no way alters the fact that the protester has not shown that the wife’s expenses were reimbursable. We therefore recommend that the agency reimburse the protester proposal preparation costs of $47,242.00, that is the level of reimbursement agreed to by the agency, and the amount requested by the protester less reimbursement for expenses related to the manager’s wife’s attendance at the market survey meeting.

Attorneys’ Fees Associated with Pursuing the Protest at GAO

The protester also requests reimbursement of all of its attorneys’ fees in this matter, totaling $231,796.64. The agency responds that the protester should be reimbursed only for the costs of pursuing the one issue on which we sustained the protest, the agency’s unreasonable conclusion that the awardee had committed to meeting the solicitation requirement that it pay Davis-Bacon wage rates for expansion of its proposed facility. Agency Reply at 4-14.

We recommend that the protester be reimbursed the cost of filing its comments on the agency report and supplemental protest, as well as all subsequent attorneys’ fees incurred. The allegation that the agency unreasonably concluded that the awardee had committed to paying Davis-Bacon wage rates--the issue on which the protest was sustained--was contained in the combined comments and supplemental protest; rather than take timely corrective action, the agency continued to defend its evaluation, causing the protester to incur unnecessary attorneys’ fees.

According to protest counsel’s invoices to Federal Builders, the protester incurred legal fees of $177,252.50 after the filing of the agency report. See Claim, Exh. 2. We therefore recommend that Federal Builders be reimbursed $177,252.50--the cost of filing the supplemental protest containing the allegation on which the protest was sustained, as well as all of the fees incurred as a result of the agency’s decision to continue the litigation rather than take corrective action. In addition, the agency has agreed that the protester is entitled to reimbursement for fees related to compliance with and admission to the protective order, and with filing a successful opposition to the agency’s request for dismissal of the protest. See Agency Comments, Sept. 24 at 5, 7. The agency calculates the fees related to the protective order at $709.60 and the protester does not dispute that calculation. See id. at 7-8. A review of invoices for June and July indicates that protest counsel billed the protester $4,960 in fees to respond to the agency’s unsuccessful motion for partial dismissal. In these circumstances, we recommend that Federal Builders be reimbursed a total of $182,922.10 in attorneys’ fees for filing and pursuing its protest at this Office.

Costs Associated with Pursuing the Claim

Pursuant to our Bid Protest Regulations, we may recommend that a contracting agency pay a protester the costs of pursuing its claim for reimbursement with our Office. 4 C.F.R. § 21.8(f)(2). This provision is intended to encourage the agency’s expeditious and reasonable consideration of a protester’s claim for costs. JAFIT Enters., Inc.--Claim for Costs, B-266326.2, B-266327.2, Mar. 31, 1997, 97-1 CPD ¶ 125 at 4. However, we will recommend payment of such costs only if it is shown that the agency failed to consider, or unreasonably delayed consideration of, the protester’s claim. Blue Rock Structures, Inc.--Costs, B‑293134.2, Oct. 26, 2005, 2005 CPD ¶ 190 at 6.

Here, the protester submitted its claim for costs to the agency on November 6, 2014; that claim included, in part, the following: line item entries for all time spent and expenses incurred by Federal Builders and its consultants in preparing and pursuing its protest; detailed monthly invoices for outside counsel, Jones Day, that identified by attorney the time spent working on the protest; support for the reasonableness of Jones Day’s hourly rates;[2] and line item entries for all time spent by Federal Builders in pursuit of the protest. Claim, Nov. 6, 2014, Exh. 2.

On the principal issue of the reasonable amount of attorneys’ fees to reimburse, the agency had all of the information necessary to make an offer of settlement to Federal Builders at the time the protester first submitted its certified claim to the agency, but the agency instead waited 10 months before making its offer. This delay is attributable to the agency. Further, the agency’s initial offer of settlement of the legal fees portion of the claim that immediately preceded the protester’s submission of its claim to this office was only $4,000. Claim, Nov. 6, 2014, Exh. 14, Letter from Agency to Federal Builders, July 24, 2015 at 7. That offer was less than two percent of the amount that the protester had requested, and was considerably less than the amount ($39,104.53) to which the agency itself agreed in the course of the subsequent negotiations to settle this claim. See Agency Comments, Sept. 24, 2015, at 10 (agreeing to reimburse protester $39,104.53 for attorneys’ fees for filing and pursing the protest and supplemental protest).

In our view, the lengthy delay in the agency’s initial offer of settlement of the legal fees and the disparity between the offer and what the agency later agreed should be reimbursed support the reasonableness of the protester’s request for reimbursement of the attorneys’ fees required to pursue the claim with this Office. We therefore recommend that the agency reimburse Federal Builders $21,577.50 for the costs of pursuing its claim with GAO. See Email from Federal Builders to GAO, Oct. 26, 2015 (containing invoices for August and September); Email from Federal Builders to GAO, Nov. 9, 2015 (containing October invoice).

Conclusion

In sum, we recommend that the agency reimburse Federal Builders a total of $259,488.52, including proposal preparation costs of $47,242.00, $182,922.10 in attorneys’ fees for filing and pursuing the protest, $7,746.92 for the time spent by Federal Builders’ manager in assisting counsel in preparing and pursuing the protest, and $21,577.50 for the costs of pursuing its claim for reimbursement.  (Federal Builders, LLC-The James R. Belk Trust--Costs B-409952.3: May 6, 2016)  (pdf)


In our view, Debcon raised a clearly meritorious challenge to the evaluation. Notwithstanding the Corps’s position in the agency report and supplemental agency report, it was contrary to regulation for the agency to rate Debcon, as a small business, merely acceptable under the small business participation plan factor where higher ratings were available. Nevertheless, the Corps argues that any misevaluation under the small business participation plan factor was not prejudicial to Debcon either because Atherton was also a small business, or because the small business participation plan evaluation “did not figure in the overall decision to award to Atherton.” Corps Opposition to Costs at 3. Our review of the record leads us to disagree. The RFP provided that the non-price factors, when combined, would be significantly more important than price in making the source selection decision, RFP amend. 1 at 4, and as noted above, Debcon’s proposal offered a lower price than Atherton’s. Although we cannot say whether the Corps would still have determined that Atherton’s proposal justified the payment of its higher price if Debcon had been evaluated properly under the small business performance plan factor, in such circumstances, we resolve doubts regarding prejudice in favor of a protester. Raytheon Co., B-409651, B-409651.2, July 9, 2014, 2014, CPD ¶ 207 at 17.

As to Debcon’s other evaluation challenges, however, the Corps presented a defensible legal position based on the factual record, so we cannot regard those issues as clearly meritorious. For example, Debcon argued that the Corps improperly imposed an unstated evaluation criterion and unreasonably evaluated the past performance factor by requiring offerors to have at least two very relevant past performance references in order to be eligible for the highest past performance rating. Our Office has held that such a requirement is reasonable, however, and need not be disclosed in the solicitation. See A&D Gen. Contracting, Inc., B‑409296, Feb. 24, 2014, 2014 CPD ¶ 71 at 5 (protest denied where evaluation required a minimum of four relevant projects to be eligible for highest past performance rating, even though requirement was not disclosed in solicitation). Since Debcon had only one very relevant project as its past performance, the Corps considered Debcon to be ineligible to receive the best past performance rating (substantial confidence). Thus, the Corps was not required to consider the project’s greater complexity or Debcon’s positive ratings for that work. Similarly, Debcon’s argument that the past performance evaluation showed unequal treatment when compared to Atherton was also not clearly meritorious. The Corps presented a defensible legal position that the evaluation of Debcon and Atherton differed because Atherton submitted multiple past performance examples, making irrelevant Debcon’s effort to compare its past performance with Atherton’s on the basis of relevance and quality.

Ultimately, Debcon presented one clearly meritorious evaluation challenge, while its other grounds of protest were either not clearly meritorious or the corrective action was prompt. Accordingly, we must consider whether the reimbursement of only a portion of the protester’s costs is proper. As a general rule a successful protester should be reimbursed the costs incurred with respect to all the issues pursued, not merely those upon which it has prevailed. Salvation Army Cmty. Corr. Program--Costs, B‑298866.3, Aug. 29, 2007, 2007 CPD ¶ 165 at 7 (recommending reimbursement of costs including those raised after receipt of agency report). In determining whether to limit the reimbursement of costs, our Office considers, among other things, whether the successful and unsuccessful arguments share a common core set of facts, are based on related legal theories, or are otherwise not readily severable. Burns & Roe Servs. Corp.--Costs, B-310828.2, Apr. 28, 2008, 2008 CPD ¶ 81 at 2-3.

In applying these principles, we have severed costs arising from allegations of misevaluation under separate evaluation factors on the basis that they are not clearly intertwined. For example, challenges to a past performance evaluation were not clearly intertwined with clearly meritorious challenges to the technical factor evaluation and the resulting tradeoff. Genesis Bus. Sys.--Costs, B-411264.11, Dec. 10, 2015, 2015 CPD ¶ 389 at 4; see also Carney, Inc.--Costs, B-408176.13, Feb. 14, 2014, 2014 CPD ¶ 82 at 5 (severing costs for alleged misevaluation of price from clearly meritorious challenge to technical capability factor evaluation); Loyal Source Gov’t Servs., LLC--Costs, B-407791.4, Feb. 14, 2014, 2014 CPD ¶ 139 at 4 (severing costs for evaluation challenges from clearly meritorious challenge to adequacy of best value tradeoff rationale). In a similar fashion, we severed the costs for challenges to the evaluation of the awardee and to the agency’s alleged failure to amend a solicitation because those issues were not clearly intertwined with a clearly meritorious allegation of unequal discussions. VSE Corp.; Univ. of Hawaii--Costs, B‑407164.11, B‑407164.12, June 23, 2014, 2014 CPD ¶ 202 at 8.

On the record here, we regard none of the protester’s challenges to the evaluation of its own proposal as intertwined with the clearly meritorious challenge to its evaluation under the small business performance plan factor. Accordingly, we do not recommend reimbursement of the costs of filing and pursuing any other issues.   (Debcon, Inc.--Costs B-412298.3: Apr 26, 2016)  (pdf)


Our Regulations provide for reimbursement, in appropriate circumstances, of reasonable proposal preparation and protest pursuit costs. 4 C.F.R. § 21.8(d). A protester seeking to recover its protest costs must submit evidence sufficient to support its claim that those costs were incurred and are properly attributable to filing and pursuing the protest. Stocker & Yale, Inc.--Claim for Costs, B-242568.3, May 18, 1993, 93-1 CPD ¶ 387 at 4. At a minimum, claims for reimbursement must identify and support the amounts claimed for each individual expense (including cost data to support the calculation of claimed hourly rates), the purpose for which that expense was incurred, and how the expense relates to the protest before our Office. International Program Group, Inc.--Claim for Costs, B‑400278.4, B‑400308.4, June 22, 2009, 2009 CPD ¶ 128 at 3. The burden is on the protester to submit sufficient evidence to support its claim; that burden is not met by general, inadequately-supported statements that particular costs have been incurred. Aztec Dev. Co.--Claim for Costs, B‑270275.2, Feb. 13, 1997, 97-1 CPD ¶ 73 at 2. Failure to file an adequately-supported claim in a timely manner will result in the loss of the protester’s right to recover costs. Wind Gap Knitwear, Inc.--Claim for Costs, B‑251411.2; B-251413.2, Aug. 30, 1995, 95-2 CPD ¶ 94 at 3 (claim that lacks detail is denied).

Although we do not doubt that the protester spent some time in preparing the protest, and responding to the agency report, we find that Slaughter has not provided adequate documentation to support this claim. In this respect, the protester states that it will “settle the claim for any amount,” Slaughter Email to GAO, Oct. 16, 2015, and the only supporting documentation provided is a calendar with the phrase “8 Hrs” written on each of the weekdays from February through June of 2015. The protester has not provided any explanation as to what efforts were performed during that time, or by whom. The claim also does not provide any cost data to support the calculation of the hourly rates for Ryan P. Slaughter. Furthermore, repeated requests by the agency for the protester to provide a more detailed accounting of its efforts did not yield any further information.

Although we recognize that the requirement for documentation may sometimes entail certain practical difficulties, we do not consider it unreasonable to require a protester to document in some detail the amount and purposes of its claimed efforts, and to establish that the claimed hourly rates reflect actual rates of compensation. John Peeples--Claim for Costs, B‑233167.2, Aug. 5, 1991, 91-2 CPD ¶ 125 at 3. Given the complete lack of documentation we cannot recommend that the Air Force reimburse the costs sought by Ryan P. Slaughter because the claim does not meet the established minimum standards. Wind Gap Knitwear, Inc.‑-Claim for Costs, supra.  (Ryan P. Slaughter--Costs B-411168.4: Dec 14, 2015)  (pdf)


DILIGENT PURSUIT

As an initial matter, the agency requests that we deny S3’s request because the firm failed to diligently pursue its claim. In this connection, the agency points out that, despite it having offered S3 an amount in settlement of its request on September 15, 2014, S3 did nothing to pursue its claim for over four months.

We agree with the agency that S3 failed to diligently pursue its claim. Our Bid Protest Regulations contemplate prompt resolution of protest matters, including claims for protest costs; accordingly, we require protesters to diligently pursue such claims. Holloway & Co., PLLC--Costs, B-311342.5, July 6, 2009, 2009 CPD ¶ 146 at 2-3. Here, the record shows that the agency made a final settlement offer to S3 on September 15, 2014. That offer expressly invited S3 to contact the contracting officer should the firm have any questions concerning the agency’s settlement offer. Agency Response to Cost Claim, exh. 2, Contracting Officer’s Final Decision Concerning S3’s Claim, at 4. Notwithstanding the contracting officer’s invitation to answer any questions that S3 might have concerning the agency’s settlement offer, the record shows that S3 did nothing--either to arrange for payment of the amount offered by the agency, or to file its claim in our Office--for a period of more than four months.

S3 suggests that it was the agency that failed to take any action after sending S3 its September 15 letter. In this connection, S3 contends that the agency failed to request a purchase order from the firm, failed to remit payment to the firm, and failed to provide a timetable for making the proposed payment to S3. However, the record shows that it was S3 that failed to take any action by, at the very least, advising the agency that it either accepted or rejected the proposed settlement offer. Simply stated, S3 took no action of any sort in response to the agency’s offer for a period of more than four months, notwithstanding that, by filing its request with our Office, it apparently now has rejected the agency’s proposed settlement offer. Cf. Holloway & Co., PLLC--Costs, supra. (following agency’s proposed settlement offer, claimant requested that agency reconsider the amount of its proposed offer and agree to the amount originally requested by the claimant). Under the circumstances, we conclude that S3 failed to diligently pursue its claim. See Aalco Forwarding, Inc., et al.--Costs, B-277241.30, Jul. 30, 1999, 99-2 CPD ¶ 36 at 5 (GAO agreed with agency conclusion that the protester failed to diligently pursue its claim for costs when the protester did not respond for more than three months after the agency sought additional supporting information for the claim).  (System Studies & Simulation, Inc.--Costs B-409375.5: May 8, 2015)  (pdf)


The agency first argues the claimed attorneys’ hours are excessive and duplicative because the protest issue was straightforward and simplistic in nature and should not have required 93 hours of attorneys’ time. We find this argument is meritless.

Our Office will examine the reasonableness of attorney hours claimed to determine whether they exceed, in nature and amount, what a prudent person would incur in pursuit of his or her protest. Price Waterhouse--Claim for Costs, B-254492, B-254492.3, July 20, 1995, 95-2 CPD ¶ 38 at 5. A recommendation that an agency pay a protester’s costs is intended to relieve protesters, with valid claims, of the burden of vindicating the public interests which Congress seeks to promote; it is not intended as a reward to prevailing protesters or as a penalty imposed upon the government. W.S. Spotswood & Sons, Inc.--Claim for Costs, B-236713.3, July 19, 1990, 90-2 CPD ¶ 50 at 3. Our Office generally accepts the number of attorney hours claimed, unless the agency identifies specific hours as excessive and articulates a reasoned analysis as to why payment for those hours should be disallowed. Pulau Elecs. Corp.--Costs, B-280048.11, July 31, 2000, 2000 CPD ¶ 122 at 6. An agency simply concluding that the hours claimed are excessive or suggesting there may be a duplication of effort is inadequate to justify denying a claim for protest costs. Id.

Our review of the claimed hours furnishes no basis for concluding that they exceeded, in nature or amount, what a prudent person would incur in pursuit of this protest, and we find no basis to question Shaka's claim in this regard. The record shows that Shaka submitted detailed billing statements, which included the description of the work performed by each attorney. The agency has not asserted that any specific charge is inappropriate, and does not question whether the attorneys actually worked the hours claimed. Under the circumstances, we find the agency’s assertions that Shaka’s claimed attorney hours were excessive and duplicative are unsupported, and find that these arguments therefore are insufficient to justify denying or reducing Shaka’s claim. See Pulau Elecs. Corp.--Costs, supra. Furthermore, we do not agree with the agency that the issue raised by the protester was a narrow, simplistic, and uncomplicated legal issue that did not justify the hours claimed, particularly given that this was a case of first impression for our Office.

The agency also now argues that Shaka’s cost claim for the attorneys’ fees incurred by Fay are not reimbursable because Fay was not a party to the protest. This argument also has no merit.

We have addressed this specific point in TMC, Inc.--Claim for Costs, B-230078.2, B-230079.2, Jan. 26, 1990, 90-1 CPD ¶ 111. As in TMC, this is not a case where the costs were incurred by a potential subcontractor acting independently of the interested party, Shaka, the actual or prospective offeror. Rather, we find the record shows that the costs were incurred by Fay acting in concert with, and on behalf of Shaka, in order to provide Shaka with legal assistance in the protest. In this regard, the record shows that Shaka and Fay had an agreement to split the legal costs of pursuing the protest, that the legal fees incurred by Fay were in fact for the pursuit of Shaka’s protest, and that Shaka will reimburse the amount paid by Fay in pursuit of this protest when the amounts are recovered by Shaka. In these circumstances, we believe the purpose of the statutory provision allowing recovery of protest costs--to relieve parties with valid claims of the burden of vindicating the public interest--is best effectuated by finding Shaka entitled to recover the costs incurred by Fay in concert with and on behalf of Shaka in pursuing this protest. Id. at 3.

Thus, we recommend payment of $22,275 of Shaka’s claimed costs: $15,450 for 47.7 hours of attorney time invoiced to Shaka at each attorney’s full billing rate, and $6,825 for 45.5 hours of attorney time invoiced to Fay at the $150 per hour rate.

Shaka also requests reimbursement for the costs of pursuing this claim before our Office. Our Bid Protest Regulations, 4 C.F.R. § 21.8(f)(2), provide that we may recommend reimbursement of the costs of pursuing a claim before our Office. See CNA Indus. Eng’g, Inc.--Costs, B-271034.2, Nov. 20, 1997, 97-2 CPD ¶ 149 at 7. This provision is intended to encourage the agency’s expeditious and reasonable consideration of a protester’s claim for costs. JAFIT Enters., Inc.--Claim for Costs, B-266326.2, B-266327.2, Mar. 31, 1997, 97-1 CPD ¶ 125 at 4. Here, given the agency’s failure to reasonably consider Shaka’s claim, we find that the protester may recover the reasonable costs of pursuing its claim at our Office.  (Shaka, Inc.--Claim for Costs, B-405552.2, May 17, 2012)  (pdf)
 


A protester seeking to recover the costs of pursuing a protest must submit sufficient evidence to support its monetary claim. John Peeples--Costs, B-233167.2, Aug. 5, 1991, 91-2 CPD para. 125 at 3. The amount claimed may be recovered to the extent that the claim is shown to be sufficiently related to the filing and pursuit of the protest, adequately documented, and reasonable in its nature and amount. JAFIT Enters., Inc.--Costs, B-266326.2, B-266327.2, Mar. 31, 1997, 97-1 CPD para. 125 at 2.

The agency here objects to reimbursement of the costs related to three of Mr. Kirkland's itemized work entries. We have reviewed the objections and the protester's response, and we agree with the agency's position. First, Mr. Kirkland describes a charge of $1,134 (for work performed on March 17) as including work related to a previously dismissed protest (B-401172, which is not relevant here), as well as work related to the protest associated with this claim. Since the single work entry aggregates allowable and unallowable costs in a way such that we cannot tell from the record what portion is unallowable, the entire amount must be disallowed. See TRESP Assocs., Inc.--Costs, B-258322.8, Nov. 3, 1998, 98-2 CPD para. 108 at 4. Likewise, since a $252 charge (for work performed on March 23) again aggregates unallowable charges (e.g., for the preparation of a letter for the contracting officer, which has not been shown to have been performed in pursuit of the protest) with allowable expenses (e.g., regarding communications about the status of the protest), the entry must be disallowed in its entirety. Id. Lastly, as the agency points out, a $126 work entry (for work performed on April 28) must be denied, as it was not in pursuit of the protest; the work instead involved protester counsel's efforts toward possible settlement of the protest. See Blue Rock Structures, Inc.--Costs, B-293134.2, Oct. 26, 2005, 2005 CPD para. 190 at 6.

The agency also objects to the costs for six work entries for Mr. Billings, primarily on the basis that they involve counsel's efforts toward settlement, and thus not pursuit, of the protest. We agree with the objections to two of the work entries, Mr. Billing's invoices for $160 (for work on April 28) and $80 (for work on April 29), as the work concerns efforts toward possible settlement of the action, and thus are not allowable costs. See T Square Logistics Servs. Corp., Inc.--Costs, B-297790.6, June 7, 2007, 2007 CPD para. 108 at 10-11. The other four work entries challenged by the agency (totaling $2,400), however, are considered allowable costs, and are included in our recommendation. The agency's assertion that these costs should not be reimbursed is unpersuasive as there is no showing that the costs related to settlement efforts or otherwise should not be allowed.

The protester also generally requests reimbursement of its costs related to the pursuit of its claim to our Office. We deny the request. Under our Bid Protest Regulations, 4 C.F.R. sect. 21.8(f)(2) (2010), we will recommend such payment only if it is shown that the agency failed to give reasonable consideration to, or unreasonably delayed consideration of, the protester's claim. See Blue Rock Structures, Inc.--Costs, supra at 7. Here, while the agency ultimately abandoned its initial objections, perhaps due to the additional explanation of the claim provided by the firm in its filing to our Office, there has been no showing that the agency failed to give reasonable consideration to the claim. Similarly, to the extent the protester now argues that the agency's request for proof of payment of its claimed attorneys' fees was not legally required, and thus, the request unreasonably delayed the agency's consideration of the claim, we find the protester's position unpersuasive. As the agency explains, it reasonably sought the information in order to confirm that Baine Clark was obliged to pay the claimed attorneys' fees; additionally, the firm did not object to the request, pose an alternate means to further demonstrate its obligation to pay the attorneys' fees it claimed, or immediately respond to the agency's request for the information. Rather, the record shows the protester added to the alleged delay by taking several weeks to provide the requested proof of payment. Further, the record shows that additional questions were reasonably raised by the proof of payment submitted by the protester, since the payment amount exceeded the amount claimed by the protester, requiring additional time for the agency to resolve the matter. See University of Dayton Research Institute--Costs, B-296946.7, Oct. 23, 2006, 2006 CPD para. 155 at 4.

Accordingly, we recommend that the agency reimburse Baine Clark a total of $24,908.34, representing $4,458.34 for Mr. Kirkland's fees and $20,450 for Mr. Billing's fees.  (Baine Clark Company, Inc.--Costs, B-401172.4, June 7, 2010) (pdf)


Even where an agency agrees to reimburse a protester's reasonable proposal preparation costs, a protester seeking to recover such costs must submit sufficient evidence to support its claim. John Peeples--Costs, B-233167.2, Aug. 5, 1991, 91-2 CPD para. 125 at 3. At minimum, claims for reimbursement must identify and support the amounts claimed for each individual expense (including cost data to support the calculation of claimed hourly rates for employees), the purpose for which each expense was incurred, and how the expense relates to the claim. Maintenance and Repair--Costs, B-251223.4, June 24, 1994, 94-1 CPD para. 381 at 4. Although we recognize that the requirement for documentation may sometimes entail certain practical difficulties, we do not consider it unreasonable to require a protester to document in some detail the amount and purposes of its claimed efforts. W.S. Spotswood & Sons, Inc.--Costs, B-236713.3, July 19, 1990, 90-2 CPD para. 50 at 3. It is our obligation to ensure that any protester seeking to recover costs meets these minimum standards.

Here, we have reviewed the record and agree with the FCC that DTG has failed to provide sufficient support for its claim. Even after the FCC's specific request for the necessary documentation, DTG failed to provide more than the vague SinoPowell invoice as evidence of its costs. Further, DTG's statements have raised doubts as to whether any amounts due to SinoPowell and Yelverton Law Firm were incurred for the preparation of the proposal. For example, in the claim for costs filed with our Office, DTG states that SinoPowell and Yelverton Law Firm "negotiated as their compensation for bid preparation that they would be an integral part of implementing the $18 million project to be awarded to DTG, and would be paid for their services on such an integrated basis, and not just for bid preparation." Claim for Costs, Dec. 28, 2009, at 2 (emphasis in original).

We interpret DTG's various statements to the agency and to our Office to indicate that there is a portion of the "integrated" costs included in its claim for $118,500 that is not attributable to the preparation of its proposal under the solicitation, and is therefore not properly reimbursable. Where, as here, a protester has aggregated allowable and unallowable costs, and provided such insufficient documentation that we cannot tell from the record before us what portion is allowable, the entire amount must be disallowed even though some portion of the claim may be properly payable. TRESP Assocs., Inc.--Costs, B-258322.8, Nov. 3, 1998, 98-2 CPD para. 108 at 4. Accordingly, DTG's claim must be denied in full.  (DTV Transition Group, Inc.--Costs, B-401466.2, April 7, 2010) (pdf)
 


By correspondence dated July 3, 2008, the protester submitted a claim for costs totaling $130,344 to counsel for the agency. The protester reports that by letter dated September 5, 2008, the contracting officer rejected all but $12,930 of its claim. (The protester did not furnish us with a copy of this correspondence.) By letter of September 15, Holloway asked the contracting officer to reconsider his decision; the protester furnished our Office with a courtesy copy of this letter. In the letter's final paragraph, Holloway noted that it was sending a copy of the letter to our Office to place us "on notice about the non-agreement between [the parties]." The protester asked the contracting officer to "reconsider CMS's position and honor the invoice that was submitted by Holloway;" in the event the contracting officer was unwilling to reconsider his position, the protester requested that our Office recommend the amount of costs that the agency should pay. Holloway did not communicate with our Office further regarding the matter until May 19, 2009, more than 8 months later, when it submitted the instant request for a recommendation of the amount it should be reimbursed.

Our Bid Protest Regulations contemplate prompt resolution of protest matters, including claims for protest costs; accordingly, we require protesters to diligently pursue such claims. L-3 Comms. Corp., Ocean Sys. Div.--Costs, B-281784.5, Feb. 17, 2004, 2004 CPD para. 40 at 3. Here, Holloway waited more than 8 months after seeking reconsideration of the contracting officer's decision regarding its claim to ask our Office for a recommendation as to the amount of reimbursement; moreover, the protester has furnished no evidence that it followed up on its request to the contracting officer at any point over the 8-month period. Under these circumstances, we think that the protester's actions demonstrate a lack of diligence in pursuing its claim to our Office. Because the protester failed to diligently pursue its claim to our Office, Holloway's request for a determination of reimbursable costs is dismissed.  (Holloway & Company, PLLC--Costs, B-311342.5, July 6, 2009)  (pdf)


Thus, ICE argues that the legislative history of FASA indicates that Congress intended for the $150 cap to be a “benchmark” in deciding whether attorneys’ fees for successful small business protesters are reasonable, and supports the agency’s view that all of the hourly rates at issue here--especially the $705 per hour rate of the senior partner--are unreasonable per se. While our Office has previously addressed the “benchmark” language in FAR sect. 33.104(h)(5),[3] we have not addressed the legislative history of FASA--where this language first appears. As discussed below, we conclude that the legislative history does not, as ICE argues, bar reimbursement of legal fees at the rates charged by PCS’s outside counsel.

Our Office takes seriously--and in the words of the FASA conference report, is “vigilant” in fulfilling--our responsibility to evaluate the reasonableness of a successful protester’s request for reimbursement of attorneys’ fees. In numerous instances, our Office has agreed with agency arguments that certain costs for successful protesters are not allowable. For example, we have found that hours charged by outside counsel are excessive where the number of hours billed are “far beyond what should have been necessary to reasonably pursue the protest.” Galen Med. Assocs., Inc.--Costs, B-288661.6, July 22, 2002, 2002 CPD para. 114 at 2. We have denied requests for reimbursement where billing records show that multiple attorneys performed duplicative work, and did not demonstrate a need for such efforts. Fritz Cos., Inc.--Costs, B-246736.7, Aug. 4, 1994, 94-2 CPD para. 58 at 4-5. We have disallowed costs where the protester does not provide adequate documentation demonstrating the reasonableness of outside counsel’s hourly rates. TRS Research--Costs, B-290644.2, June 10, 2003, 2003 CPD para. 112 at 4. We have denied requests for reimbursement of protest costs where the protester has not stated that the costs sought for reimbursement have or will be paid by the protester, regardless of our ruling on the request. Id. at 5. We have disallowed costs that are not reasonably related to the pursuit of the protest, including, for example, costs associated with a request for reconsideration. Aztec Dev. Co.--Costs, B-270275.2, Feb. 13, 1997, 97-1 CPD para. 73 at 4. Similarly, our Office has disallowed costs in their entirety where a protester has aggregated allowable and unallowable costs in a way that does not allow us to identify which costs are properly reimbursable. Blue Rock Structures, Inc.-Costs, B-293134.2, Oct. 26, 2005, 2005 CPD para. 190 at 5.

Here, we recognize that the FASA conference committee reiterated our Office’s responsibility, imposed in 1984 by CICA, to ensure that attorneys’ fees sought for reimbursement are reasonable. We see no conflict between FASA’s exemption of small businesses from a cap on attorneys’ fees, and the conference committee’s view that the “cap placed on attorneys’ fees for businesses other than small business constitutes a benchmark as to what constitutes a ‘reasonable’ level for attorneys’ fees for small businesses.” H. Rep. No. 103-712 sect. 1403 (Aug. 21, 1994), as reprinted in 1994 U.S.C.C.A.N. 2607, 2621-22. In this regard, we think that the conference committee report language concerning a “benchmark” provides guidance as to the evaluation of the reasonableness of attorneys’ fees. However, we do not view the benchmark language as imposing an additional limitation (i.e., a cap) on attorneys’ fees that are otherwise reasonable. Such an interpretation would be inconsistent with the plain statutory language of FASA which exempts small businesses from the specific cap imposed on large businesses--and we see no evidence that the Congress intended such a result. See Hartford Underwriters Ins. Co. v. Union Planters Bank, N. A., 530 U.S. 1, 6, 120 S.Ct. 1942, 147 L.Ed.2d 1 (2000) (“when the statute’s language is plain, the sole function of the courts--at least where the disposition required by the text is not absurd--is to enforce it according to its terms” (internal quotation marks omitted)).

We think the benchmark language is appropriately viewed as one of a number of factors to be considered in determining whether attorneys’ fees are reasonable. Among these factors are: the legal context--CICA’s creation of a fee-shifting mechanism that provides for the reimbursement of a successful protester’s costs of pursuing a protest and FASA’s exemption of small businesses from the $150 per hour cap on attorney fees that applies to large businesses; the passage of time--13 years--and the concomitant changes in the cost of living and the level of fees since the enactment of FASA; the customary fees charged for similar legal work in the community where outside counsel practices; the experience, reputation and ability of the outside counsel; the specialized nature of government contracts law; and the complexity of the issues in the particular protest at issue.

In summary, we have considered the difference between the rates charged by PCS’s outside counsel and the $150 per hour cap that applies to large businesses, particularly in light of the conference committee’s views, and the relevant FAR provision, concerning the cap as a benchmark for reasonableness. We nonetheless think that, on balance, the rates charged by PCS’s outside counsel are reasonable. Specifically, as discussed in detail below, we find that the number of hours billed is reasonable, and that the rates charged by PCS’s outside counsel are consistent with those customarily charged by comparable firms in the Washington, DC area with similar levels of government contracts experience. We also think that the issues in this protest were of a level of complexity that supports the reasonableness of the rates. (Public Communications Services, Inc.--Costs, B-400058.4, June 25, 2009) (pdf)


Based on our review of the record, we agree with the agency that the number of hours claimed in preparing this Phase I proposal appear excessive, particularly considering that Celadon did not contemporaneously record the hours specifically allocated to this Phase I proposal or otherwise carry its burden of showing that its claimed hours were reasonable. Where our Office has found that the number of hours exceeded that which a prudent person would claim, we have reduced the number of hours to reflect a reasonable work effort, given the nature of the particular protest. See SKJ & Assocs., Inc., B‑291533.3, July 24, 2003, 2003 CPD para. 130 at 3. Here, given the statements of the HHS program officials as to what are reasonable hours for preparing an SBIR proposal of this nature, and in the absence of any better evidence, we accept as reasonable the agency’s determination to allow 40 hours for the two employees to prepare the proposal, and 10 hours for the president to review it.

We also accept the agency’s calculation of the rates for the three Celadon employees who prepared the proposal. As indicated by the agency, while Celadon supported the salaries paid its employees, it used a flawed method to calculate its claimed hourly labor rates based on these yearly salaries. That is to say, Celadon’s calculations resulted in including indirect costs, e.g.,vacation time and paid lunch, in its direct labor rates. Celadon does not dispute this agency analysis. Thus, when Celadon applied the fringe benefit, overhead and G&A rates to its claimed labor rates, which should account for all of the indirect costs, Celadon was essentially double-counting the indirect costs included in the labor rates. This double-counting had the effect of including profit in addition to actual costs in Celadon’s proposed labor rates. A protester may not recover profit on its employees’ time in filing and pursuing protests, and, therefore, claimed rates must be based upon actual rates of compensation, plus reasonable overhead and fringe benefits, and not market rates that include profit as an element. W.S. Spotswood & Sons, Inc.--Claim for Costs, supra.

In sum, we recommend that Celadon be reimbursed its proposal preparation costs for 40 hours at $51.92 for one employee, for 40 hours at $40.86 for another employee, and for 10 hours at $51.92 for the president. After Celadon’s claimed indirect rates are applied to these direct labor costs, the total reasonable proposal preparation costs, as was determined by HHS, is calculated as $6,139. AR, Tab 26, Claim Calculation.

Celadon also claims $9,868 for its costs of pursuing the protest, representing 101.5 hours of Celadon’s president’s time at $67 per hour, plus applicable indirect costs. AR, Tab 2, Celadon’s Claim. The agency only allowed 60 hours at $51.92 per hour. AR, Tab 26, Claim Calculation. For the reasons stated above, we accept the agency’s determination that the president should be reimbursed at the $51.92 rate. However, the agency has not specifically contended that the 101.5 hours charged by the president for pursuing the protest are excessive, and based on our review of the record, we find no basis for so concluding. Thus, we find that Celadon should be reimbursed $7,648 for its costs of pursuing the protest, which represents 101.5 hours of the president’s time at $51.92 per hour, plus indirect costs at the claimed rates.

Finally, Celadon’s claim seeks reimbursement of $8,640, reflecting time spent on the preparation of Celadon’s cost claim at the agency. However, while our Bid Protest Regulations provide that we can recommend reimbursement of the costs of pursuing a claim for protest costs at our Office, 4 C.F.R. sect. 21.8(f)(2), there is no provision providing for reimbursement of costs of preparing and pursuing a claim at the procuring agency. Manekin Corp.--Costs, B-249040.2, Dec. 12, 1994, 94-2 CPD para. 237 at 6. To the extent Celadon requests that it be reimbursed the costs of pursuing its claim at our Office, we will make such a recommendation only if it is shown that the agency unreasonably delayed consideration of the protester’s claim or otherwise failed to give the claim reasonable consideration. Blue Rock Structures, Inc.--Costs, B-293134.2, Oct. 26, 2005, 2005 CPD para. 190 at 7. Here, since we have essentially agreed with the agency’s determination of the amount of costs which Celadon should be reimbursed and find any delay in resolving the claim was substantially contributed to by Celadon’s actions, we do not recommend that its costs of pursuing the claim at our Office be reimbursed.  (Celadon Laboratories, Inc.--Costs, B-298533.2, November 7, 2008) (pdf)


As a general rule, we consider a successful protester entitled to be reimbursed costs incurred with respect to all issues pursued, not merely those upon which it prevails. AAR Aircraft Servs.--Costs, B-291670.6, May 12, 2003, 2003 CPD para. 100 at 9. In our view, limiting recovery of protest costs in all cases to only those issues on which the protester prevailed would be inconsistent with the broad, remedial congressional purpose behind the cost reimbursement provisions of the Competition in Contracting Act of 1984, 31 U.S.C. sect. 3554 (c)(1)(a) (2006). AAR Aircraft Servs.--Costs, supra; TRESP Assocs., Inc.--Costs, B-258322.8, Nov. 3, 1998, 98-2 CPD para. 108 at 2. Nevertheless, failing to limit the recovery of protest costs in all instances of partial or limited success by a protester may also result in an unjust award determination. Accordingly, in appropriate cases, we have limited our recommendation for the award of protest costs where a part of those costs is allocable to an unsuccessful protest issue that is so clearly severable from the successful issues as to essentially constitute a separate protest. See, e.g., BAE Tech. Servs., Inc.--Costs, B-296699.3, Aug. 11, 2006, 2006 CPD para. 122 at 3; Interface Floorings Sys., Inc.--Claim for Attorneys’ Fees, B‑225439.5, July 29, 1987, 87‑2 CPD para. 106 at 2-3. In determining whether protest issues are so clearly severable as to essentially constitute separate protests, we consider, among other things, the extent to which the issues are interrelated or intertwined--i.e., the successful and unsuccessful arguments share a common core set of facts, are based on related legal theories, or are otherwise not readily severable. See Sodexho Mgmt., Inc.--Costs, B‑289605.3, Aug. 6, 2003, 2003 CPD para.136 at 29.  We previously have found that the three issue areas raised by BRSC in its protest--misevaluation of proposals, failure to hold meaningful discussions, and treating offerors unequally--involve the same core facts, and thus are intertwined for purposes of considering whether protest costs should be reimbursed. BAE Tech. Servs. Inc.--Costs, B-296699.3 Aug. 11, 2006 , 2006 CPD para. 122 at 3. The agency has presented no argument or evidence that persuades us that our view in this regard should be changed under the facts of this case. Under these circumstances, we conclude that the evaluation, discussions, and equal treatment issues raised in BRSC’s protest are not severable, and that BRSC therefore should be reimbursed its reasonable costs related to all of these issues. BRSC is not required to separate the costs associated with its arguments relating to the agency’s failure to conduct meaningful discussions from the costs associated with the other arguments raised in its protest. BRSC should submit its claim to the agency.  (Burns and Roe Services Corporation--B-310828.2, Costs, April 28, 2008)  (pdf)


We decline to recommend that TACOM reimburse ALF for any costs. We will recommend the amount that the agency should pay only where, prior to coming to our Office, the protester timely pursued a claim to the agency; that is, where the protester filed an adequately documented claim with the agency within 60 days after receiving our recommendation that costs be paid. See 4 C.F.R. sect. 21.8(f)(1). The 60‑day timeframe was specifically designed to avoid the piecemeal presentation of claims (which necessarily results in unduly delaying their resolution), while at the same time affording protesters an ample opportunity to submit adequately substantiated certified claims. REEP, Inc.--Costs, B-290665.2, July 29, 2003, 2003 CPD para. 131 at 4. To be considered adequately documented, a claim for reimbursement of employee compensation must include documentation establishing the number of hours worked and the purposes of the employees’ efforts; in addition, it must demonstrate that the claimed hourly rates reflect the employees’ actual rates of compensation plus reasonable overhead and fringe benefits. See W.S. Spotswood & Sons, Inc.--Claim for Costs, B-236713.3, July 19, 1990, 90-2 CPD para. 50 at 3. While we do not believe that the 60-day timeframe should be applied in so harsh a manner that a protester receives no reimbursement merely because its initial, timely claim required some supplementation or elaboration, where the timely submission is of little or no value in supporting the claim, we will consider the claim untimely and regard it as forfeited. REEP, Inc.--Costs, supra. We note in this connection that a protester’s failure to file an adequately documented claim within the 60-day period may result in forfeiture of its right to recover costs even where the parties have continued to negotiate after the 60-day period expired. H. G. Prop. A, L. P.--Costs, B‑277572.8, Sept. 9, 1998, 98-2 CPD para. 62 at 2-3. Here, ALF’s initial, timely submission to the agency was so deficient as to be of basically no value in supporting its claim. As previously noted, the submission failed to furnish any detail regarding the claimed employee hours or supporting the claimed rates of compensation; in addition, it failed to include any documentation demonstrating ALF’s obligation to compensate the consultant. Moreover, even when given the opportunity to supplement its submission to the agency, ALF never sought to overcome the second deficiency; that is, it never furnished the agency with documentation supporting its claimed rates of employee compensation--and, indeed, ultimately submitted documentation to our Office that clearly demonstrated that the initially claimed rates were substantially overstated. In addition, we are not persuaded that prior to seeking a recommendation regarding cost recovery from our Office, the protester made a reasonable attempt to reach an agreement with the agency, as contemplated by our Regulations. As noted above, it was not until the protester sought a recommendation from our Office that it for the first time furnished documentation substantiating its claimed rates of employee compensation. By failing to furnish such documentation to the agency, ALF effectively eliminated the possibility of the two parties arriving at an agreement. We do not think that it is appropriate to permit a protester to seek a recommendation regarding cost recovery from our Office where it has not previously made a reasonable effort to reach an agreement with the agency.  (Al Long Ford--Costs, B-297807.2, October 18, 2007) (pdf)


Under the Competition in Contracting Act (CICA), when our Office finds that an agency’s procurement activities fail to comply with the requirements of statute or regulation, we are given discretionary authority to recommend the reimbursement of proposal preparation costs. Specifically, CICA states: “If the Comptroller General determines that . . . the award of a contract does not comply with a statute or regulation, the Comptroller General may recommend that the Federal agency conducting the procurement pay to an appropriate interested party the costs of . . . bid and proposal preparation.” 31. U.S.C. sect. 3554(c)(1) (2000) (italics added).  Here, as discussed above, Lockheed Martin has already received the agreed-upon compensation for its performance of the fixed-price CAD contract, under which its technical solution for the SDD contract was evaluated. Further, Lockheed Martin will have an opportunity to compete for the phase II requirements that were deleted from the solicitation. Finally, it is clear that, following deletion of the phase II requirements, Lockheed Martin continued to compete for the modified phase I requirements; its protest, which we sustained, challenged the basis for the changes to those requirements--not the source selection process following the changes.  Based on our consideration of the record as a whole, we decline to exercise our discretionary authority to recommend reimbursement of Lockheed Martin’s proposal preparation costs. (Lockheed Martin Corporation--Costs, B-295402.2, November 1, 2005) (pdf)


We have previously reasoned that the justification for an upward fee adjustment is self-evident if the claimant alleges that the cost of living has increased, as measured by the Department of Labor’s Consumer Price Index (CPI). Sodexho Mgmt., Inc.--Costs, B-­289605.3, Aug. 6, 2003, 2003 CPD para. 136 at 41. In this regard, we have declined to impose a requirement that a claimant do more than request an adjustment and present a basis upon which the adjustment should be calculated. Id.; see Brickwood Contractors, Inc. v. United States, 49 Fed. Cl. 148, 164 (2001); California Marine Cleaning Servs., Inc. v. United States, 43 Fed. Cl. 724 (1999). Where a claimant meets this standard, and an agency does not articulate any objection, we will grant a claimant’s request for a recommendation in favor of a cost of living adjustment to the fee cap. Sodexho Mgmt., Inc.--Costs, supra. In support of its claim for attorneys’ fees above the $150 level, Inter-Con provided a detailed explanation of its calculation of the rates and included a printout of the “All Urban Consumers” CPI for the San Francisco-Oakland-San Jose, California area. Inter‑Con Claim Letters, dated April 8 and 26, 2005. Use of the “All Urban Consumers” CPI for a specific area is consistent with our decision in Sodexho. See Sodexho Mgmt., Inc.--Costs, supra, at 43 n.33. In requesting our recommendation, DOS agrees that the protester’s “request appears to be consistent with the standards followed in [Sodexho],” and provides no specific objection to the higher fees. DOS Letter, June 3, 2005. We have reviewed Inter-Con’s calculation in support of the higher requested fees, and find that they appear properly supported and reasonable. Accordingly, we recommend that DOS pay the higher attorneys’ fees claimed. (Department of State--Costs, B-295352.5, August 18, 2005) (pdf)


CourtSmart incurred $153,971.25 for its attorney's services at an hourly rate of $475. SSA generally alleges that the rate is above the reasonable rate charged for these services. In response, CourtSmart submitted information from a 2002 national billing rate survey. Specifically, CourtSmart identified the ranges of hourly billing rates for partners and for associates from 19 firms in the Washington, D.C. area, as published in the January 2003 edition of Legal Times. The hourly rates for partners reported by these firms ranged from $185 to $750. CourtSmart Submission (Oct. 1, 2004) at 2, encl. 4. The highest rates for partners for all but two of these firms were in excess of $500. CourtSmart states that a breakdown of billing rates by specific practice area was not available. CourtSmart's attorney states that he has 30 years of experience in federal procurement law in the Washington, D.C. area, and has the expertise, reputation and ability commensurate with partners at the high end of the billing rate range. CourtSmart asserts that, since the $475 rate billed by its attorney is within the range billed by firms in the community, the hourly rate is reasonable. SSA has not challenged the applicability of the survey for the purpose of determining the reasonableness of the attorney's hourly rate billed here. SSA has also not challenged the asserted expertise, reputation and ability of the attorney. Here, the work was performed by the attorney from November 2003 through February 2004, which is within approximately 1 year of the billing rate survey. Although the survey does not provide hourly rate information for attorneys practicing in federal procurement law or related areas of practice, SSA does not challenge the relevance of the information submitted. On this record, we find the attorney's billed hourly rate of $475 was reasonable. See KPMG Peat Marwick, LLP--Costs , supra, at 5-6; Bay Tankers, Inc.--Costs , supra . Therefore, we find $153,971.25 ( i.e. , 324.15 hours x $475 per hour) that CourtSmart claims for attorney's fees is reasonable and recoverable. (CourtSmart Digital Systems, Inc.--Costs, B-292995.7, March 18, 2005) (pdf)


Furthermore, even if SBA were to issue a formal size determination, that determination would not have any retroactive effect on Brechan's size for purposes of its initial protest, as the effect of such a determination after the award of a contract is prospective. See , e.g. , FAR 19.302(j); Planned Sys. Int'l, Inc. , B-292319.7, Feb. 24, 2004, 2004 CPD 43 at 3 (adverse SBA decision issued after award does not require cancellation of the award); Dawkins Gen. Contractors & Supply, Inc , B243613, B-243613.11, Sept. 21,1992, 92-2 CPD 190 at 3 (adverse SBA size determinations apply prospectively only). Although Brechan's request presents the somewhat unusual circumstance of an agency's challenge to the size status of an unsuccessful offeror after award has been made, in the context of a recompetition in which the offeror is not participating and solely for the purpose of challenging entitlement to protest costs, we believe that our cases and SBA regulations do not provide for a retroactive challenge to Brechan's standing. Accordingly, we conclude that there is no basis to challenge Brechan's status as a small business for purposes of this request. Based on the record, Brechan's request for a recommendation that it be reimbursed the reasonable costs of filing and pursuing its protest is granted. Further, in light of the discussion above, we conclude that Brechan is a small business for purposes of filing its claim for costs with the agency. (Brechan Enterprises, Inc.--Costs, B-294046.2, November 4, 2004) (pdf)


We find that reimbursement is warranted. The promptness standard applicable to protests cannot be applied to the agency's request for reconsideration because the request itself caused the protester to expend unnecessary time and resources to obtain relief, a key consideration in our deciding whether reimbursement of a protester's costs is appropriate. See AAR Aircraft Servs.--Costs , B-291670.6, May 12, 2003, 2003 CPD 100 at 5. It is reasonable for a firm whose protest has been sustained by our Office to feel compelled to respond to the agency's request for reconsideration. Here, the agency caused the protester to incur costs opposing a request for reconsideration that was devoid of merit. In this regard, parties filing requests for reconsideration are required to submit a detailed statement of the factual and legal grounds upon which reversal or modification is deemed warranted, specifying any errors of law made or information not previously considered. Bid Protest Regulations, 4 C.F.R. 21.14(a). DHS's reconsideration request did not meet this standard. (Security Consultants Group, Inc.--Costs, B-293344.6, November 4, 2004) (pdf)


Neither our regulations nor our prior decisions recognize an exception to the 60-day filing requirement based simply on the fact of a request for reconsideration having been filed. While our Office has indicated that we may consider an untimely claim for good cause, we have construed the term to mean that some compelling reason beyond the control of the protester prevented the protester from timely filing the claim. Continental Maritime of San Diego, Inc.-Costs , B-249858.5, Dec. 17, 1993, 93-2 CPD 323 at 2; Test Sys. Assocs., Inc.-Costs , May 3, 1993, 93-1 CPD 351 at 2. Here, there is no evidence that Keeton could not have filed within the required time period a documented, substantiated claim for the costs of filing and pursuing the protest that we had sustained. Not only did Keeton's request for reconsideration not prevent the protester from timely filing its claim, the request for reconsideration did not even call into question the basis upon which we sustained the protest and thus our recommendation of protest costs. Moreover, we note that when Keeton received our decision denying its request for reconsideration on March 31, Keeton still had 33 days within which to file its cost claim. Keeton has offered no explanation as to why it did not have sufficient time after receiving our decision denying its request for reconsideration to complete and timely file its claim with the agency. In these circumstances, we decline to recommend that the agency pay the claimed costs. (Keeton Corrections, Inc.—Costs, B-293348.3, October 25, 2004) (pdf)


Based on our review of the record, we find no basis to object to the reasonableness of the agency’s determination that CAMS should be reimbursed $3,946.30 for its total claimed costs of filing and pursuing its protest. However, we do not recommend that CAMS be reimbursed for the costs of pursuing its claim at the agency, because those costs are not associated with proceedings before our Office. See SKJ & Assocs.--Costs, B-291533.3, July 24, 2003, 2003 CPD ¶ 130 at 4. We also deny CAMS’s costs for pursuing this claim before our Office. Our Bid Protest Regulations, 4 C.F.R. § 21.6(f)(2) (2003), provide that we may recommend that a protester be reimbursed the costs of pursuing its claim before our Office. Since we recommend that CAMS be reimbursed the amount the agency determined is due, however, we find no basis to recommend that CAMS be reimbursed for the costs of pursuing the claim at our Office. (CAMS, Inc.--Costs, B-292546.2, March 22, 2004) (pdf)


Our Bid Protest Regulations, 4 C.F.R. § 21.8(f)(1) (2003), require protesters to file claims for protest costs within 60 days of receiving our recommendation that such costs be paid. This 60-day timeframe was specifically designed to avoid the piecemeal presentation of claims (which necessarily results in unduly delaying their resolution), while at the same time affording protesters an ample opportunity to submit adequately substantiated, certified claims. HG Properties A, L.P.--Costs, B-277572.8, Sept. 9, 1998, 98-2 CPD ¶ 62 at 2. A protester's failure to file an adequately documented claim within this 60-day period results in forfeiture of its right to recover costs, irrespective of whether the parties may have continued to negotiate after the 60-day period expired. Id. at 2-3. In this latter connection, a protester seeking to recover its protest costs must submit evidence sufficient to support its claim that those costs were incurred and are properly attributable to filing and pursuing the protest. Stocker & Yale, Inc.--Claim for Costs, B-242568.3, May 18, 1993, 93-1 CPD ¶ 387 at 4. Although we recognize that the requirement for documentation may sometimes entail certain practical difficulties, we do not consider it unreasonable to require a protester to document in some detail the amount and purposes of its employees' and attorneys' efforts and to establish that the claimed hourly rates reflect the employees' actual rates of compensation plus reasonable overhead and fringe benefits. W.S. Spotswood & Sons, Inc.--Claim for Costs, B-236713.3, July 19, 1990, 90-2 CPD ¶ 50 at 3. We do not believe that the 60-day timeframe should be applied in so harsh a manner that a protester receives no reimbursement merely because its initial, timely, claim required some supplementation or elaboration. Nonetheless, where the timely submission is of little or no value in supporting the claim, we believe that the claim should be rejected as untimely.  (REEP, Inc.--Costs, B-290665.2, July 29, 2003)  (pdf)


Our review of the record confirms the reasonableness of the agency's conclusion that the protester has not adequately documented its protest costs. Despite the passage of many months and several requests from the agency to do so, the protester has not submitted any documentation to show that the $425 hourly rate claimed by TRS counsel is representative of that charged for similar services in the Philadelphia area, where he practices law.  (TRS Research--Costs, B-290644.2, June 10, 2003)


Our Bid Protest Regulations provide that where the contracting agency decides to take corrective action in response to a protest, we may recommend that the protester be reimbursed the costs of filing and pursuing its protest, including reasonable attorneys' fees.  4 C.F.R. § 21.8(e) (2003). This does not mean that costs should be reimbursed in every case in which an agency decides to take corrective action; rather, a protest should be reimbursed its costs where an agency unduly delayed its decision to take corrective action in the face of a clearly meritorious protest. Griner's-A-One Pipeline Servs., Inc.--Entitlement to Costs, B-255078.3, July 22, 1994, 94-2 CPD ¶ 41.  Thus, as a prerequisite to our recommending that costs be reimbursed where a protest has been settled by corrective action, not only must the protest have been meritorious, but it also must have been clearly meritorious, i.e., not a close question. J.F. Taylor, Inc.--Entitlement to Costs, B-266039.3, July 5, 1996, 96-2 CPD ¶ 5 at 3; Baxter Healthcare Corp.--Entitlement to Costs, B-259811.3, Oct. 16, 1995, 95-2 CPE ¶ 174 at 4-5; GVC Cos.--Entitlement to Costs, B-254670.4, May 3, 1994, 94-1 CPD ¶ 292 at 3. A protest is "clearly meritorious" when a reasonable agency inquiry into the protester's allegations would show facts disclosing the absence of a defensible legal position.  Department of the Army--Recon., B-270860.5, July 18, 1996, 96-2 CPD ¶ 23 at 3. The mere fact that an agency decides to take corrective action does not establish that a statute or regulation clearly has been violated. Spar Applied Sys.--Declaration of Entitlement, B-276030.2, Sept. 12, 1997, 97-2 CPD ¶ 70 at 5.  Here, we conclude that it is not appropriate to recommend that East Penn recover its protest costs because East Penn's protest was not clearly meritorious.  (East Penn Manufacturing Company, Inc.--Costs, B-291503.4, April 10, 2003)  (txt version)


In view of the cancellation of the RFP, which has deprived ATS of an opportunity to compete for the scope of services contemplated in the solicitation at issue in the protest, ATS requests that we modify our earlier recommendation to allow ATS to be reimbursed the costs of preparing its proposal. The Army has no objections to ATS's request. Under these circumstances, we modify our recommendation to provide that ATS should be reimbursed the costs of preparing its proposal under the canceled solicitation. [1] 31 U.S.C. sect. 3554(c)(1), 4 C.F.R. sect. 21.8(d)(2) (2001).  (Aberdeen Technical Services--Modification of Recommendation, B-283727.3, August 22, 2001)  (pdf)


Request for recommendation that agency reimburse protester for the costs it incurred in pursuing an administrative appeal of the agency's initial cost comparison decision under Office of Management and Budget Circular No. A-76 is denied because GAO's authority to recommend reimbursement of protest costs does not extend to costs incurred by a protester in litigating in another forum.  (Rice Services, Ltd.--Costs, B-284997.2, May 18, 2001)


Our Office generally accepts the number of attorney hours claimed, unless the agency identifies specific hours as excessive and articulates a reasoned analysis as to why payment for those hours should be disallowed. Data Based Decisions, Inc.--Claim for Costs, B-232663.3, Dec. 11, 1989, 89-2 CPD para. 538 at 3. Simply concluding that the hours claimed are excessive or suggest duplication of effort is inadequate to justify denying a claim for protest costs. Princeton Gamma-Tech, Inc.--Claim for Costs, B-228052.5, Apr. 24, 1989, 89-1 CPD para. 401 at 4. We will examine the reasonableness of the attorney hours claimed to determine whether they exceed, in nature and amount, what a prudent person would incur in pursuit of his or her protest. Price Waterhouse--Claim for Costs, B-254492.3, July 20, 1995, 95-2 CPD para. 38 at 5.  (Pulau Electronics Corporation--Costs, B-280048.11, July 31, 2000)  (pdf)


We next turn to the Navy's contention that it should not be required to reimburse DRS for its protest costs because the agency acted in good faith in relying on GSA's representations. As we stated in our prior decision, we have no basis to conclude, nor do we think, that the Navy acted in less than complete good faith in placing this order. DRS Precision Echo, Inc., supra, at 3. In addition, our prior decision did not intend to suggest that the Navy acted in bad faith in defending DRS's protest. Instead, the decision reflected only a limited concern about the continued defense of this purchase given GSA's inability over a period of several months to produce any evidence that a contract slated to expire had not done so. Id. Nonetheless, despite the Navy's claims of good faith, and despite any concern by our Office that the Navy may have unnecessarily prolonged the dispute, the decision whether to recommend an award of costs bears no relationship to whether the agency acted in good faith; rather, as stated above, costs are awarded to relieve protesters of the financial burden of the public service they perform. General Servs. Admin.--Recon., B-239569.2, Feb.13, 1991, 91-1 CPD para. 163 at 3.  (Department of the Navy--Modification of Remedy, B-284080.3, May 24, 2000)


As a general rule, we recommend that a prevailing protester be reimbursed the costs incurred with respect to all issues pursued, not merely those upon which it prevails. Omni Analysis; Department of the Navy--Recon., B-233372.2, B-233372.3, July 24, 1989, 89-2 CPD para. 73 at 3-4. However, our Office will limit its recommendation regarding a successful protester's recovery of protest costs when a part of the costs is allocable to a losing protest issue that is so clearly severable as to constitute a separate protest. Price Waterhouse--Claim for Costs, B-254492.3, July 20, 1995, 95-2 CPD para. 38 at 3-4.  (TRW, Inc.--Costs, B-282459.3, August 4, 1999) (pdf)


We will not consider requests for a recommendation for reimbursement of costs where the protester fails to document its claim to the contracting agency. See Custom Prod. Mfg., Inc.--Recon., B-235431.8, July 21, 1995, 95-2 CPD para. 40 at 3. Where, as here, attorneys' fees are sought to be recovered, evidence from the attorneys involved must be submitted, including, for instance, copies of bills from the attorneys listing the dates the services were performed and the hours billed to the protester. Custom Prod. Mfg., Inc.--Costs, B-235431.7, May 9, 1995, 95-1 CPD para. 236 at 3. We have reviewed the documentation submitted by the protesters' attorneys here, which consists of the abstracts of attorneys' fees and expenses for each pleading or document that dealt with the partial set-aside issue, and we find this evidence insufficient to support the protesters' claim.  (A-1 Movers of America, Inc. et al.--Costs, B-277241.31, August 2, 1999)  (pdf)


A protester seeking to recover the costs of pursuing its protest must submit sufficient evidence to support its monetary claim. The amount claimed may be recovered to the extent that the claim is adequately documented and is shown to be reasonable; a claim is reasonable, if, in its nature and amount, it does not exceed that which would be incurred by a prudent person in the pursuit of a protest. E&R, Inc.--Claim for Costs, B-255868.2, May 30, 1996, 96-1 CPD para. 264 at 2; Data Based Decisions, Inc.--Claim for Costs, B-232663.3, Dec. 11, 1989, 89-2 CPD para. 538 at 2-3.  (Chant Engineering Co., Inc.--Costs, B-274871.4, April 28, 1999)  (pdf)

Comptroller General  - Listing of Decisions

For the Government For the Protester
Ryan P. Slaughter--Costs B-411168.4: Dec 14, 2015  (pdf) New Federal Builders, LLC-The James R. Belk Trust--Costs B-409952.3: May 6, 2016  (pdf)
System Studies & Simulation, Inc.--Costs B-409375.5: May 8, 2015  (pdf) Debcon, Inc.--Costs B-412298.3: Apr 26, 2016  (pdf)
Baine Clark Company, Inc.--Costs, B-401172.4, June 7, 2010 (pdf) Shaka, Inc.--Claim for Costs, B-405552.2, May 17, 2012  (pdf)
DTV Transition Group, Inc.--Costs, B-401466.2, April 7, 2010 (pdf) Public Communications Services, Inc.--Costs, B-400058.4, June 25, 2009 (pdf)
Holloway & Company, PLLC--Costs, B-311342.5, July 6, 2009  (pdf) Burns and Roe Services Corporation--B-310828.2, Costs, April 28, 2008)  (pdf)
Celadon Laboratories, Inc.--Costs, B-298533.2, November 7, 2008 (pdf) CourtSmart Digital Systems, Inc.--Costs, B-292995.7, March 18, 2005 (pdf)
Al Long Ford--Costs, B-297807.2, October 18, 2007 (pdf) Security Consultants Group, Inc.--Costs, B-293344.6, November 4, 2004 (pdf)
Lockheed Martin Corporation--Costs, B-295402.2, November 1, 2005 (pdf) Brechan Enterprises, Inc.--Costs, B-294046.2, November 4, 2004 (pdf)
Department of State--Costs, B-295352.5, August 18, 2005 (pdf)  
Keeton Corrections, Inc.—Costs, B-293348.3, October 25, 2004 (pdf)  
e-LYNXX Corporation--Costs, B-292761.2, August 12, 2004  
CAMS, Inc.--Costs, B-292546.2, March 22, 2004 (pdf)  
REEP, Inc.--Costs, B-290665.2, July 29, 2003  (pdf)  
SKJ & Associates, Inc.--Costs, B-291533.3, July 24, 2003 (pdf)  
TRS Research--Costs, B-290644.2, June 10, 2003 (pdf)  
East Penn Manufacturing Company, Inc.--Costs, B-291503.4, April 10, 2003)  (txt version)  
M&S Farms, Inc.--Costs, B-290599.3, April 8, 2003  (pdf)  
QuanTech, Inc.--Costs, B-291226.3, March 17, 2003 (pdf)  (txt version)  
Priority One Services, Inc.--Costs, B-288836.5, November 8, 2002  (pdf)  
Galen Medical Associates, Inc. -- Costs, B-288661.6, July 22, 2002  (pdf)  
Parmatic Filter Corporation--Costs, B-285288.5, August 27, 2001 (pdf)  
Aberdeen Technical Services--Modification of Recommendation, B-283727.3, August 22, 2001  (pdf)  
Rice Services, Ltd.--Costs, B-284997.2, May 18, 2001  (PDF Version)  
Pulau Electronics Corporation--Costs, B-280048.11, July 31, 2000  (pdf)  
Department of the Navy--Modification of Remedy, B-284080.3, May 24, 2000  (pdf)  
Dual Inc.--Costs, B-280719.3, April 28, 2000 (pdf)  
Aberdeen Technical Services, B-283727.2, February 22, 2000  
TRW, Inc.--Costs, B-282459.3, August 4, 1999 (pdf)  
A-1 Movers of America, Inc. et al.--Costs, B-277241.31, August 2, 1999 (pdf)  
Aalco Forwarding, Inc., et al.--Costs, B-277241.30, July 30, 1999 (pdf)  
Chant Engineering Co., Inc.--Costs, B-274871.4, April 28, 1999  

U. S. Court of Federal Claims - Key Excerpts

As permitted by the applicable statute granting jurisdiction over bid protests, the Court “may award any relief that the court considers proper, including declaratory and injunctive relief except that any monetary relief shall be limited to bid preparation and proposal costs.” 28 U.S.C. § 1491(b)(2); see also Gentex Corp. v. United States, 58 Fed. Cl. 634, 656 (2003).

A disappointed bidder may recover bid preparation and proposal costs if the following conditions are satisfied: (1) the agency committed a prejudicial error in conducting a procurement; (2) the error caused the protester to incur unnecessary bid preparation and proposal costs; and (3) the protester shows that the costs it seeks to recover were reasonable and allocable. Reema Consulting Servs., Inc. v. United States, 107 Fed. Cl. 519, 532 (2012).

A. The Agency Committed Prejudicial Error in Conducting the Procurement

A successful protester is entitled to bid preparation costs where an agency conducted a procurement in violation of an applicable statute prejudicing the offeror. CSE Const. Co. United States, 58 Fed. Cl. 230, 263 (2003). Defendant does not contest that HUD violated federal procurement laws resulting in prejudicial error. Rather, Defendant argues that Plaintiffs are not entitled to bid preparation costs because HUD did not conduct a procurement, and therefore Plaintiffs cannot recover costs under the applicable statute. Def.’s Resp. 8 (citing 48 C.F.R. 31.20-18(a)). Contrary to Defendant’s assertion, the Federal Circuit found that the “PBACCs [were] procurement contracts and not cooperative agreements[,]” and were subject to federal procurement laws permitting recovery of bid preparation costs. CMS Cont. Mgmt. Servs., 745 F.3d at 1385-86.

B. The Error Caused Protesters to Incur Unnecessary Bid Preparation and Proposal Costs

Defendant contends that Plaintiffs did not incur unnecessary bid preparation costs because “Plaintiffs will presumably have the opportunity to resubmit prior proposals” in response to a new procurement, and allowing both injunctive and monetary relief provides a double recovery not permitted under 28 U.S.C. § 1491(b)(2). Def.’s Resp. 9-10. This argument assumes that making the [Performance-Based Annual Contribution Contracts] PBACCs FAR-compliant will not substantially change the information an offeror must submit in its proposals. For the reasons stated below, this outcome seems highly unlikely.

Defendant concedes that compliance with federal procurement law will “require numerous, significant programmatic changes not only to the structure of the competition awarding the [PBACCs] but also to the entire administration of the program.” AR 3 (HUD Memorandum, [Performance-Based Contract Administrator] “PBCA [Notice of Funding Availability] NOFA Status, Post-GAO Recommendations”). Indeed, HUD has not yet re-initiated a FAR-compliant procurement. Instead, it has continued the “contracts awarded between 1999 and 2005 to [P]laintiffs and others. . . . HUD plans to continue this practice for the foreseeable future as it restructures the program to be consistent with [federal procurement regulations].” Dkt. No. 121 (Def.’s April 27, 2015 Status Rep. 1). HUD is continuing this restructuring without a clear timeline for issuing a new procurement. Importantly, during oral argument on September 21, 2015, counsel for the Government was unable to provide information on when HUD would complete its restructuring, further attenuating the likelihood of an upcoming procurement. Realistically, it may be years before HUD issues any new procurement.

The Government’s argument that monetary relief is improper because Plaintiffs will be able to resubmit their proposals amounting to a double recovery is similarly unpersuasive. Assuming HUD re-initiates a procurement, Plaintiffs will need to revise their three-year-old proposals containing state-specific legal opinions to respond to the “numerous, significant” changes HUD will need to make to comply with federal procurement laws. AR 3. Given the substantial anticipated changes to the PBACCs, the Court agrees with Plaintiffs that their bid proposal and preparation costs have been wasted. See, e.g., Beta Analytics Int’l v. United States, 75 Fed. Cl. 155, 159 (2007) (awarding bid proposal costs where re-evaluation of proposals was not practical). Moreover, HUD essentially caused the incurrence of the proposal preparation costs by requiring offerors to go forward with their proposals while the protests were pending at the GAO. If HUD had agreed to wait until the GAO decided the protests, the proposal preparation costs could have been avoided.

Further, the Court agrees with Plaintiffs that it is within the Court’s discretion to grant both injunctive and monetary relief. The plain language of 28 U.S.C. § 1491(b)(2) permits the Court to award relief that it considers proper, including bid and proposal costs as well as injunctive relief. See 28 U.S.C. § 1491 (b)(2). The statute does not have a restriction that if the Court grants injunctive relief, monetary damages are not available. Accord MVM, Inc. v. United States, 47 Fed. Cl. 361, 366 (2000).

Defendant also asserts that Plaintiffs who did not specifically request bid preparation costs in their complaints may not recover such costs. Def.’s Resp. 5. However, Plaintiffs requested that the Court “[g]rant such other and further relief the court determines just and appropriate,” see, e.g., dkt. no. 1 (CMS Compl. 12), which this Court has found sufficient for granting bid and proposal costs. See CSE Const. Co., 58 Fed. Cl. at 263. All of the Plaintiffs asserted their claims for proposal preparation costs at various times so that Defendant well understood that these costs were at issue.

C. Recovery of Reasonable and Allocable Costs

Contrary to the Government’s argument, it is within this Court’s discretion to determine that Plaintiffs are entitled to bid preparation and proposal costs before ruling on the amount of costs that may be recovered. See e.g., Idea Int’l, Inc. v. United States, 74 Fed. Cl. 129, 143 (2006) (awarding proposal costs and requiring the parties to submit a joint stipulation as to costs). Recognizing the competitive nature of Plaintiffs’ relationships with one other, the Court must devise a procedure that preserves the confidentiality of the individual cost claims. This goal can be accomplished if Plaintiffs individually submit proposal preparation claims to the Department of Justice attorney of record who will convey them to HUD for review. Plaintiffs shall submit their claims to the Department of Justice within 30 days, on or before October 29, 2015. The Court will expect these claims to be resolved voluntarily before December 31, 2015. If the claims are not resolved by December 31, 2015, Defendant shall file a status report with the Court by January 8, 2016 indicating when the cost resolution process will be completed. The Court will enter final judgment upon being advised that all of Plaintiffs’ cost claims have been resolved and paid.  (CMS Contract Mgmt. Servs. et al v. U. S., Nos. 12-852C, 12-853C, 12-862C, 12-864C, & 12-869C, September 29, 2015)  (pdf)


II.

The court turns first to plaintiffs’ motions for attorney’s fees. As a threshold matter, this court must determine whether the position of the United States in this case was substantially justified. The Equal Access to Justice Act (EAJA), 28 U.S.C. § 2412(d)(1)(A), states, in pertinent part, that “a court shall award to a prevailing party other than the United States fees and other expenses, . . . unless the court finds that the position of the United States was substantially justified or that special circumstances make an award unjust.” Defendant bears the burden of proving that its position was substantially justified. See Helfer v. West, 174 F.3d 1332, 1336 (Fed. Cir. 1999); Doty v. United States, 71 F.3d 384, 385 (Fed. Cir. 1995); Abramson v. United States, 45 Fed. Cl. 149, 152 (1999). It must show that its position throughout the dispute was “‘justified in substance or in the main’ – that is, justified to a degree that could satisfy a reasonable person.” Pierce v. Underwood, 487 U.S. 552, 565 (1988); see also Chiu v. United States, 948 F.2d 711, 715 (Fed. Cir. 1991). Such an inquiry focuses not only on the position taken by the Justice Department before this court, but also on the agency’s prelitigation conduct. See Comm’r of I.N.S. v. Jean, 496 U.S. 154, 159 (1990); Hubbard v. United States, 480 F.3d 1327, 1332 (Fed. Cir. 2007); Smith v. Principi, 343 F.3d 1358, 1361-62 (Fed. Cir. 2003).

The Supreme Court has instructed that the Government’s “position can be justified even though it is not correct,” requiring that that position have a “reasonable basis in law and fact.” Pierce, 487 U.S. 566 n.2; see also Norris v. S.E.C., 695 F.3d 1261, 1265 (Fed. Cir. 2012). The courts have been particularly hesitant to impose attorney’s fees in matters of first impression. See White v. Nicholson, 412 F.3d 1314, 1316 (Fed. Cir. 2005); Luciano Pisoni Fabbrica Accessori Instrumenti Musicali v. United States, 837 F.2d 465, 467 (Fed. Cir. 1988); Gava v. United States, 699 F.2d 1367, 1371 (Fed. Cir. 1983); see also Marcus v. Shalala, 17 F.3d 1033, 1037 (7th Cir. 1994). Indeed, the legislative history of EAJA makes clear that the governing standard allows defendant to advance “‘in good faith . . . novel but credible . . . interpretations of the law.’” Russell v. Nat’l Mediation Bd., 775 F.2d 1284, 1290 (5th Cir. 1985) (quoting H.R. Rep. No. 80-1418 at 11 (1980)); see also Renee v. Duncan, 686 F.3d 1002, 1017 (9th Cir. 2012).

The instant case presented a matter of first impression to this court. The factual situation here was somewhat unique, requiring the court, inter alia, to order defendant to file, as part of the administrative record, the contracts and procedures governing its mail servers. Although this court found that the agency’s actions were contrary to the Federal Acquisition Regulations, and arbitrary and capricious, there was little decisional guidance that previously would have signaled this conclusion. Defendant advanced arguments in support of the actions taken below that relied on prior decisions of this court and the General Accountability Office. See, e.g., Conscoop-Consorzia v. United States, 62 Fed. Cl. 219, 239-40 (2004); Sea Box, Inc., 2002 C.P.D. ¶ 181 (2002). Although the court concluded that, based upon the language of the regulations, those decisions were wrong (or in the case of Conscoop-Consorzia at least distinguishable), it cannot say that defendant’s reliance on these prior opinions was not substantially justified. See Devine v. Sutermeister, 733 F.2d 892, 895 (Fed. Cir. 1984) (“[T]he justification for the government’s litigating position must be measured against the law as it existed . . . , and not against the new law enunciated by the court in its opinion.”); see also Watterson Constr. Co. v. United States, 106 Fed. Cl. 609, 618 (2012). In these circumstances, the court concludes that the position of the United States in this litigation was substantially justified and that an award of attorney’s fees is, therefore, inappropriate.

III.

Only CenterScope seeks bid preparation and proposal costs.

Following the court’s April 22, 2013, order, the Clerk entered judgment pursuant to RCFC 58. Defendant argues that this case is now “closed” and asserts that the court does not have jurisdiction under 28 U.S.C. § 1491(b)(2) to determine whether CenterScope is entitled to monetary relief. Contrary to defendant’s claims, the entry of a permanent injunction in a case, whether succeeded vel non by the Clerk’s filing of a judgment under RCFC 58, does not deprive this court of further jurisdiction over the case. The continuing responsibility of this court over its decrees “is a necessary concomitant of the prospective operation of equitable relief,” 11A Charles Alan Wright, Arthur R. Miller & Mary Kay Kane, Federal Practice and Procedure, § 2961 (2014), and has its roots in the power of courts to modify decrees “as events may shape the need.” United States v. Swift & Co., 286 U.S. 106, 114 (1932). In the court’s view, nothing about the Clerk’s pro forma entry of a judgment under RCFC 58, prevents this court from revisiting its decree in a bid protest case to address subsequent events. See RCFC 60, 65; see also CNA Corp. v. United States, 83 Fed. Cl. 1, 5-6 (2008) (discussing this court’s ability to award bid preparation and proposal costs after the entry of a judgment under RCFC 58). A contrary ruling might encourage an agency to play a procurement version of thimblerig – indicating that a new procurement was anticipated, only to proceed otherwise after the time for bid preparation and proposal costs has run.

The problem with CenterScope’s request for costs is not jurisdictional, then, but rather the fact that CenterScope has not met its evidentiary burden. “Bid preparation and proposal costs can be awarded by courts as an appropriate way to try to compensate, at least in part, a victim of unjust government action during the procurement process.” CNA Corp., 83 Fed. Cl. at 11. Those costs are recoverable only if three conditions are satisfied: (i) the agency has committed a prejudicial error in conducting the procurement; (ii) that error caused the protester to incur unnecessarily bid preparation and proposal costs; and (iii) the costs to be recovered are both reasonable and allocable, i.e., incurred specifically for the contract in question. Reema Consulting Servs., Inc. v. United States, 107 Fed. Cl. 519, 532 (2012) (citing cases); see also Caddell Constr. Co., Inc. v. United States, 111 Fed. Cl. 49, 119 (2013). The second prong of this analysis, with its causation requirement, does not permit a protester to recover compensation if the costs wasted on the initial procurement become necessary in a second procurement. See Reema, 107 Fed. Cl. at 532; CNA, 107 Fed. Cl. at 11.

In the case sub judice, CenterScope initially claimed that it was entitled to bid preparation and proposal costs because USAID decided to cancel the first procurement. In its motion, it indicated that “[i]f the Agency would not have cancelled the procurement, [CenterScope’s] bid preparation and proposal costs would not have been unnecessarily incurred.” However, plaintiff continued to seek those costs even after the agency, as it had previously indicated it would do, initiated a second procurement covering essentially the same subject matter as the first (enjoined) procurement. CenterScope claimed that it could not submit a proposal in response to this second RFP because it could not certify that it was a small business under the NAICS code that is the subject of the procurement. However, it provided no factual support for this claim – and defendant supplied evidence to refute this claim.

Because CenterScope has failed to show that it could not participate in the second procurement, the court finds that it has not shown that the error previously documented caused it to incur unnecessarily bid preparation and proposal costs. Rather, it would appear that CenterScope, had it chosen, could have used materials prepared for the first procurement in the second. Accordingly, those costs were not rendered unnecessary by the agency’s prior error. At the least, CenterScope has not shown otherwise. As such, the court finds that CenterScope is not entitled to recover bid preparation and proposals costs in this action. Compare Bannum, Inc. v. United States, 56 Fed. Cl. 453, 462 (2003) (“If plaintiff becomes a disappointed offeror because another vendor is awarded the contract or if the solicitation is cancelled, it could be entitled to bid preparation costs if it could show in those circumstances that the government action was illegal and that it was prejudiced by the illegality.”).

Based on the foregoing, the court hereby DENIES plaintiffs’ motions for attorney’s fees and DENIES CenterScope’s motion for bid preparation and proposal costs.  (Insight Systems Corp. and CenterScope Technologies, Inc., Nos. 12-863C and 12-883C, May 12, 2014)  (pdf)


Plaintiff makes two claims in this regard. First, it asserts that [Edgewood Chemical Biological Center] ECBC acted contrary to the relevant regulations in awarding the contract to an offeror that did not qualify as a small business within the NAICS code involved. Second, it contends that ECBC applied the evaluation criteria in the RFP inconsistently, in rating Reema’s and SMRC’s proposals differently.

Plaintiff’s first assertion would be more tenable if the governing regulations required ECBC to confirm SMRC’s eligibility prior to making an award. They do not. To be sure, under those regulations, an agency generally determines a business’ size status as of the date the offeror submits its initial offer. 48 C.F.R. § 19.301-1(a). That determination, however, is based on the offeror’s “self-certification that it is small to the contracting activity.” Enter. Info. Servs., Inc., 2010 CPD ¶ 213, at 2 (2010). Thus, under the regulations, the offeror must represent “that it is a small business concern in connection with a specific solicitation,” which representation it may make “if it meets the definition of a small business concern applicable to the solicitation and has not been determined by the Small Business Administration (SBA) to be other than a small business.” 48 C.F.R. § 19.301-1(a); see also 48 C.F.R. § 52.204-8(d) (discussing representations and certifications). Under the Federal Acquisition Regulation (FAR), the contracting officer “shall accept an offeror’s representation . . . that it is a small business unless (1) another offeror or interested party challenges the concern’s small business representation or (2) the contracting officer has a reason to question the representation.” 48 C.F.R. § 19.301-1(b). Under this regulation, the CO here thus was required to accept SMRC’s representations regarding its size unless one of the two exceptions to that rule was triggered. And, as will be seen, neither of those exceptions were triggered.

By the time the CO received Reema’s size protest, she had already awarded the contract to SMRC. Nothing in the regulations requires a contracting officer to suspend or terminate a contract based upon the filing of a size protest. See 13 C.F.R. § 121.1009. On December 29, 2011, the SBA issued a size determination concluding that SMRC was not small for the procurement at issue and was, therefore, ineligible for the award. The regulations provide that if a contracting officer receives a determination that the awardee is not an eligible small business for the procurement in question, and “no OHA appeal has been filed, the contracting officer shall terminate the award.” Id. at § 121.1009(g)(2)(i). Here, however, a timely OHA appeal was filed, which, under the regulations, gave the CO discretion to determine “whether performance can be suspended until an appellate decision is rendered.” Id. at § 121.1009(g)(2)(ii). And, the CO, exercising this authority, determined that the contract should proceed. The OHA then affirmed the size determination finding, requiring the CO, under the regulations discussed above, to “either terminate the contract or not exercise the next option.” Id. at § 121.1009(g)(2)(iii).

Reema, however, asserts that the CO had reason to question SMRC’s representations about its size and should have referred the matter to the SBA pursuant to 48 C.F.R. § 19.301-1(b). But, this claim proves too much. Plaintiff points to nothing in SMRC’s proposal that should have triggered an inquiry. Rather, it argues that the CO should have questioned SMRC’s status because the awardee failed to list NAICS code 541620, Environmental Consulting Services, on its profile in the Central Contractor Registration (CCR) system previously maintained by the General Services Administration (GSA). This claim is a red herring for several reasons.

For one thing, the regulations that governed that system did not oblige SMRC to list itself as qualifying under any particular NAICS code in order to be eligible to make an offer. Nor did they suggest that the CO was obliged to examine SMRC’s CCR listing prior to making an award. Rather, it appears that the CCR system was designed primarily to assist government agencies in performing market research and in administering contracts post-award. See 48 C.F.R. §13.102; see also Shirlington Limousine & Transp., Inc. v. United States, 77 Fed. Cl. 157, 160 n.5 (2007). There is no indication that the system was also to be used in examining proposals. Indeed, the regulations did not require small businesses to register before making an offer, but only required them to do so immediately prior to receiving an award. 48 C.F.R. § 52.204-7(b)(1) (“[b]y submission of an offer, the offeror acknowledges the requirement that a prospective awardee shall be registered in the CCR database prior to award”); see also Nilson Van & Storage, Inc. v. United States, 99 Fed. Cl. 408, 416-17 (2011); JGB Enters., Inc. v. United States, 63 Fed. Cl. 319, 322 (2004). Accordingly, there is utterly no reason to believe that SMRC’s failure to list any particular information in its CCR profile should have engendered suspicions regarding its size status. As such, the court must conclude that the CO acted reasonably under the circumstances, which is all that is required. See Reliable Builders, Inc., 2010 CPD ¶ 260, at 5 (2010); Synergetics, Inc., 2007 CPD ¶ 168, at 2 (2007).

Plaintiff next claims it is entitled to bid preparation and proposal costs because ECBC improperly evaluated its proposal. But, the court need not resolve this dispute – or address whether the agency afforded SMRC benefits that were unwarranted – because, as it turns out, there is a fatal flaw in plaintiff’s claim for damages.

“Bid preparation and proposal costs can be awarded by courts as an appropriate way to try to compensate, at least in part, a victim of unjust government action during the procurement process.” CNA Corp. v. United States, 83 Fed. Cl. 1, 11 (2008). Such costs are recoverable only if three conditions are satisfied: (i) the agency has committed a prejudicial error in conducting the procurement; (ii) that error caused the protester to incur unnecessarily bid preparation and proposal costs; and (iii) the costs to be recovered are both reasonable and allocable, i.e., incurred specifically for the contract in question. Though often not discussed explicitly in cases, the second prong of this three-part test is designed “to place the plaintiff in the position he or she would have occupied but for defendant’s wrong.” Ala. Aircraft Indus., 85 Fed. Cl. at 565; see also CNA Corp., 83 Fed. Cl. at 11 (bid preparation and proposal costs permissible where such costs would not have been unnecessarily incurred “but for the arbitrarily and capriciously issued . . . decision”). Reflecting this view, where defendant’s wrongful action requires a protester to submit a second proposal, this court has allowed the recovery of bid preparation and proposal costs for a first proposal as a way to provide the protester a complete remedy. But, this same second prong, with its causation requirement, can disqualify a protester from receiving compensation if it would have incurred additional bid preparation and proposal costs even if the agency had not committed an error.

In the case sub judice, plaintiff cannot show that the bid preparation and proposal costs it incurred in creating its first proposal were rendered unnecessary by the arbitrary, capricious, or otherwise erroneous actions committed by ECBC. Rather, the situation in which plaintiff finds itself – unable to receive an award on its earlier proposal and compelled to seek an award, if at all, via a new one – stems not from agency misfeasance, but from the way the regulations deal with the timing of the size determination made by the SBA. In particular, plaintiff’s plight, such as it is, derives from the fact that the drafters of those regulations decided to allow agencies to proceed with certain contracts pending the ultimate resolution of the size protest. And, of course, that is what happened here.

Only in the meekest terms does plaintiff yet argue that ECBC should award it the contract in question, rather than conduct a reprocurement. Its hesitation is well-founded as there are statutory and practical impediments that prevent ECBC from reevaulating the first set of proposals, none the least of which is the fact that they are now three years old. (And, it goes almost without saying, this court is in no position to order such an award). It follows, a fortiori, that if plaintiff must prepare a second offer if it hopes to receive the award in question, and must do so regardless of whether ECBC evaluated its first offer properly vel non, it cannot obtain bid preparation and proposal costs for that first proposal. Those costs were not rendered a ‘“needless expense”’ by defendant’s erroneous conduct, CNA Corp., 83 Fed. Cl. at 9 (quoting Heyer Prods. Co. v. United States, 135 Ct. Cl. 63, 71 (1956)), but rather were lost due to the proper application of the procedural regulations implementing the size standards.

Accordingly, plaintiff has failed to satisfy the second prong of the requirements for receiving bid preparation and proposal costs, to wit, that a prejudicial error committed by the agency be the cause of its incurring unnecessarily the bid preparation and proposal costs it seeks. Therefore, the costs it seeks are not recoverable.  (Reema Consulting Services, Inc., v. U. S., No. 12-402C, November 26, 2012)  (pdf)


The Government bears the burden of showing that its position was substantially justified. See Infiniti Info. Solutions, LLC. v. United States, 94 Fed. Cl. 740, 748 (2010) (citing White v. Nicholson, 412 F.3d 1314, 1315 (Fed. Cir. 2005)). The substantial justification inquiry determines whether the Government’s position was “‘justified in substance or in the main’ –that is, justified to the degree that would satisfy a reasonable person.” Pierce v. Underwood, 487 U.S. 552, 565 (1988) (citations omitted). The Government’s overall position “both prior to and during the litigation” must have a reasonable basis in both law and fact. United Partition Sys., 95 Fed. Cl. at 50 (citing Chiu v. United States, 948 F.2d 711, 715 (Fed. Cir. 1991) and Blakley v. United States, 593 F.3d 1337, 1341 (Fed. Cir. 2010)). The key inquiry is “not what the law now is, but what the Government was substantially justified in believing it to have been.” Loomis v. United States, 74 Fed. Cl. 350, 355 (2006) (quoting Pierce, 487 U.S. at 561). The Court must determine whether the Government was reasonable in bringing about and continuing the litigation at hand.

The mere fact that the Government did not prevail is not dispositive of the substantial justification inquiry. Schock v. United States, 254 F.3d 1, 5 (1st Cir. 2001). Whether one court agreed or disagreed with the Government does not establish whether the Government’s position was not substantiality justified, although “a string of court decisions going either way can be indicative.” Id. (citing Pierce, 487 U.S. at 568).

Defendant essentially presented two arguments in the underlying litigation to show why DGR’s judicial bid protest should fail: (1) DGR waived its right to bring suit in this Court by not filing its action prior to the closing date for receipt of proposals; and (2) under the Small Business Act and applicable regulations, as interpreted by at least three executive agencies, the Air Force was not required to give priority to HUBZone small business concerns. The Court will address both of these arguments below.

1. Waiver of Right to Bring Suit in This Court

As explained in the prior opinion, DGR Associates, 94 Fed. Cl. at 200-04, the Court found Defendant’s waiver argument to be patently unreasonable. When DGR first saw that the Air Force’s solicitation did not include a preference for eligible HUBZone offerors, DGR challenged the solicitation, first by letter to the contracting officer, and then by filing a formal agency-level protest. DGR took both of these actions prior to the closing date for receipt of proposals. The Court noted that DGR’s letter and agency protest were “in compliance with [Federal Acquisition Regulation (FAR)], 48 C.F.R. § 33.103,” and that by taking these actions, DGR was “adhering to the federal government’s stated policy of attempting to resolve protests at the contracting officer and agency level.” Id. at 202.

When the Air Force denied DGR’s agency-level protest, DGR timely initiated a protest at the Government Accountability Office (GAO) within ten days of adverse agency action. By this time, proposals had been submitted, and the Air Force had decided to proceed with the procurement. DGR prevailed in its GAO protest, DGR Associates, Inc., B-402494, 2010 CPD ¶ 115 (Comp. Gen. May 14, 2010), but the Air Force declined to follow GAO’s decision. The GAO awarded DGR its fees and costs of pursuing the protest, but the Air Force refused to consider DGR’s request. Thereafter, DGR filed suit in this Court, only to be faced with Defendant’s argument that DGR waived its right to sue by failing to commence an action before the closing date for receipt of proposals, citing Blue & Gold Fleet L.P. v. United States, 492 F.3d 1308 (Fed. Cir. 2007).

In denying Defendant’s waiver defense, the Court stated that DGR “diligently pursued its solicitation challenge,” and “[a]t each step, . . . followed applicable FAR and GAO protest procedures.” DGR Associates, 94 Fed. Cl. at 202. The Court observed that Defendant’s waiver argument “would be directly at odds with government policy to seek resolution of protests within the agency.” Id. at 203. Following Defendant’s argument “would have parties running into the Court of Federal Claims to challenge solicitation errors, instead of pursuing other available avenues of relief.” Id. The Court ultimately ruled:

The correct interpretation of Blue & Gold Fleet is that, if a party has challenged a solicitation impropriety before the close of the bidding process, the party is not precluded from later filing its protest at the Court of Federal Claims. A party must do something before the closing date to preserve its rights, and must thereafter pursue its position in a timely manner.

Id. The Court noted the gross inequity of Defendant’s argument as it would apply to DGR:

The Court hardly can conceive of a greater injustice than to say to DGR “even though you followed applicable protest procedures and prevailed at the GAO, now you are out of luck because you failed to file a judicial action in the Court of Federal Claims before the close of the bidding process.”

Id. The Court continued by stating “Defendant’s added insult to DGR would be that ‘the Air Force has decided not to follow the GAO’s decision in your favor, and there is nothing you can do to prevent it.’” Id. By any measure, Defendant’s waiver argument was patently unreasonable, and not substantially justified.

2. Statutory Preference for the HUBZone Small Business Program

Defendant’s second argument, that under the Small Business Act and implementing regulations, the Air Force was not required to give priority to HUBZone small business concerns, contradicted the plain meaning of the Small Business Act. Defendant asserts that the interpretation of the statute was a novel issue, and thus its position was substantially justified. (Def.’s Resp. 19-20, Jan. 6, 2011.) However, the Court concludes otherwise, that the interpretation of the HUBZone statutory language was not novel. Due to the unambiguous wording of the statute, and the existing case law precedent, Defendant’s position in the underlying litigation was not reasonable.

When DGR filed suit in this Court for declaratory and injunctive relief on June 28, 2010, multiple courts and the GAO uniformly had held that the Small Business Act was unambiguous, and that the HUBZone program should be given a preference over other small business programs. Contract Mgmt., Inc. v. Rumsfeld, 434 F.3d 1145, 1147 (9th Cir. 2006) (“The HUBZone Program, by contrast, commands in unequivocal terms that a contract opportunity be designated as a HUBZone set-aside when certain criteria are met.”); Contract Mgmt., Inc. v. Rumsfeld, 291 F.Supp.2d 1166, 1174 (D.Haw. 2003) (“Congress has used clear language to mandate, ‘notwithstanding any other provision of law,’ the award of contract opportunities on the basis of competition restricted to qualified HUBZone small business concerns when certain, specific criteria are met.”); Mission Critical Solutions v. United States, 91 Fed. Cl. 386, 402-03 (2010) (“[T]he statutory language is mandatory and that the plain meaning of the HUBZone statute requires a contract opportunity to be competed among qualified HUBZone small business concerns whenever the specified criteria are met, notwithstanding other provisions of law – including those found within the Small Business Act itself.”); Small Business Administration Reconsideration, B-401057.2, 2009 CPD ¶ 148 at 6 (Comp. Gen. July 6, 2009) (“[B]oth the appellate court and district court ultimately concluded, in no uncertain terms, that the HUBZone statute mandates a set-aside, while the statutory language authorizing the 8(a) program is discretionary.”); Mission Critical Solutions, B-401057, 2009 CPD ¶ 193 at 3 (Comp. Gen. May 4, 2009) (“We do not think that SBA's regulatory implementation of the HUBZone and 8(a) statutes is reasonable since it fails to give effect to the mandatory language of the HUBZone statute.”). Confronted with this line of unwavering authorities, the Court does not find it reasonable that Defendant would continue to litigate this issue.

Furthermore, Defendant’s position did not have a reasonable basis in law, as the HUBZone statutory language was unambiguous. The GAO “read the plain language of the HUBZone statute as requiring an agency to set aside an acquisition for competition restricted to qualified HUBZone small business concerns where it has a reasonable expectation” that the two pre-conditions of the HUBZone statute would be satisfied. DGR Associates Inc., B-402494, 2010 CPD ¶ 115 (Comp. Gen. May 14, 2010). If the Air Force simply had elected to follow the GAO’s decision, DGR’s lawsuit would not have been necessary. However, the Air Force rejected the GAO’s decision, forcing DGR to pursue further litigation in this Court. Given the clear statutory language, Defendant was unreasonable in putting DGR to additional effort and expense. The Court’s analysis of the Small Business Act’s HUBZone program found no room for debate. DGR Associates, 94 Fed. Cl. at 208 (“[T]he Court finds the plain language of the HUBZone provision to establish the priority of the HUBZone program over the 8(a) program.”). The Court examined the legislative history to see whether a “clear intent contrary to the plain meaning exists.” Id. (citation omitted). The legislative history was unpersuasive, offering no explanation of why the Senate omitted the parity provision from the HUBZone program, making the Defendant’s reasoning as to Congress’s intent “purely speculative.” Id. at 209. Due to the plain language of the statute and the lack of any contrary Congressional intent expressed in the legislative history, Defendant’s position was unreasonable.

For all of the foregoing reasons, the Court concludes for purposes of DGR’s attorneys’ fees application that Defendant’s arguments in the underlying litigation were not substantially justified. 28 U.S.C. § 2412(d)(1)(A).  (DGR Associates, Inc. v. U. S. and General Trades and Services, Inc., No. 10-396C, February 15, 2011)  (pdf)  (Reversed by the Court of Appeals for the Federal Circuit in DGR Associates, Inc., v. U. S. and General Trades and Services, Inc., No. 2011-5880, August 2, 2012  (pdf)  (See below)


A. Permissibility of Awarding Both Injunctive Relief and Bid Preparation and Proposal Costs

In arguing that this court cannot “award both full injunctive relief and bid preparation and proposal costs,” Def.’s Resp. at 6, the government looks chiefly to the law as it existed prior to the modification of the Tucker Act by the ADRA. Under that law, the government contends that “a successful protestor could receive either equitable or monetary relief, but not both.” Def.’s Resp. at 6-7. The government maintains that the ADRA of 1996 was not intended “to alter the remedies available to a successful protester.” Def.’s Resp. at 7. Additionally, the government argues that if the court has the ability to grant both injunctive and monetary relief, it should not do so in the instant case because allowing Alabama Aircraft to recover bid preparation and proposal costs would violate the principle that a remedy should not put a plaintiff “in a better position than if no breach had occurred.” Def.’s Resp. at 11.  (at p. 5 of decision)

(sections deleted)

Therefore, it would not amount to an impermissible double recovery for Alabama Aircraft to receive bid preparation and proposal costs in addition to the injunctive relief the court previously awarded.

The foremost principle in fashioning a remedy is to endeavor to place the plaintiff in the position he or she would have occupied but for defendant’s wrong. See, e.g., Glendale Federal Bank, FSB v. United States, 239 F.3d 1374, 1380 (Fed. Cir. 2001). In this case, an award of bid preparation and proposal costs is necessary to place Alabama Aircraft in its rightful position. Here, without defendant’s errors, Alabama Aircraft would have had to submit only one proposal. Due to those errors, Alabama Aircraft is now required to pay for and submit another proposal in a continuing effort to obtain an award of a contract for maintenance work on the KC-135 PDM Stratotanker. An award of bid preparation and proposed costs is fully appropriate to provide a complete remedy for Alabama Aircraft.

CONCLUSION

For the foregoing reasons, Alabama Aircraft is entitled to receive bid preparation and proposal costs consisting of $289,887.31 for burdened labor costs, $13,133.52 for internal expenses, and $700,267.40 for consultants’ fees and expenses. The clerk shall enter judgment for plaintiff in the total amount of $1,003,288.23.  (Alabama Aircraft Industries, Inc. - Birmingham, v. U.S., No. 08-470C, Reissued February 3, 2009) (pdf)


Under the EAJA, an award of reasonable attorneys’ fees may be made to a qualifying party who prevails in an action by or against the United States, provided that certain criteria are met. 28 U.S.C. § 2412(d)(1)(A).2 Eligibility for such an award requires that: (1) the claimant be a “prevailing party;” (2) the government’s position was not “substantially justified;” (3) no “special circumstances make an award unjust;” and (4) any fee application be submitted to the court within 30 days of final judgment in the action and be supported by an itemized statement. Id. § 2412(d)(1)(A), (B); see Commissioner, INS v. Jean, 496 U.S. 154, 158 (1990); Loomis v. United States, 74 Fed. Cl. 350, 353 (2006); Lion Raisins, Inc. v. United States, 57 Fed. Cl. 505 (2003); see also Knowledge Connections, Inc. v. United States, 76 Fed. Cl. 612, 614-15 (2007).

(sections deleted)

The burden of establishing substantial justification rests upon the government. See White v. Nicholson, 412 F.3d 1314, 1315 (Fed. Cir. 2005); Hillensbeck v. United States, 74 Fed. Cl. 477, 479-80 (2006); Lion Raisins, 57 Fed. Cl. at 512. In Pierce v. Underwood, 487 U.S. 552, 565 (1998), the Supreme Court described substantial justification as meaning “not ‘justified to a high degree,’ but rather ‘justified in substance or in the main’– that is, justified to a degree that could satisfy a reasonable person.” In determining substantial justification, the court must “look at the entirety of the government’s conduct [both prior to and during litigation] and make a judgment call whether the government’s overall position had a reasonable basis in both law and fact.” Chiu v. United States, 948 F.2d 711, 715 (Fed. Cir. 1991); see also Doty v. United States, 71 F.3d 384, 386 (Fed. Cir. 1995) (“[T]he term ‘position of the United States’ [in the EAJA] refers to the government’s position throughout the dispute, including not only its litigating position but also the agency’s administrative position.”).

The key inquiry is “not what the law now is, but what the government was substantially justified in believing it to have been.” Loomis, 74 Fed. Cl. at 355 (quoting Underwood, 487 U.S. at 561). The government’s position may therefore be found to be substantially justified even though the court previously overturned the government’s actions. Id.; see also Scarborough v. Principi, 541 U.S. 401, 415 (2004) (“Congress did not . . . want the ‘substantially justified’ standard to ‘be read to raise a presumption that the [g]overnment position was not substantially justified simply because it lost the case.’”); RAMCOR Servs. Group, Inc. v. United States, 185 F.3d 1286, 1290 (Fed. Cir. 1999) (“Although INS had lost the underlying action, that outcome does not alone show that its position had no substantial justification.”). Of course, “[t]o be ‘substantially justified’ means . . . more than merely undeserving of sanctions for frivolousness.” Underwood, 487 U.S. at 566.

The government argues that its position in the underlying litigation was justified because there was “significant GAO precedent” supporting the Contracting Officer’s issuance of Solicitation Amendments 9 and 12 to extend the closing dates for Presidential’s proposal revisions nunc pro tunc. Def.’s Opp’n at 4 (citing Micromass, Inc., B-278869, Mar. 24, 1998, 98-1 CPD ¶ 93; Ivey Mech. Co., Comp. Gen. Dec. B-272764, 96-2 CPD ¶ 83, Aug. 23, 1996; Fort Biscuit Co., B-247319, May 12, 1992, 92-1 CPD ¶ 440; Institute for Advanced Safety Studies-Recon., B-221330.2, July 25, 1986, 86-2 CPD ¶ 110). The government posits that its reliance on these GAO opinions “was reasonable and substantially justified” because the Contracting Officer in the instant case was “faced with circumstances essentially the same” as those existing in the GAO cases and issued the amendments to enhance competition, consistent with those decisions. Id. The government also puts forward GAO’s decision in Geo-Seis Helicopters, Inc., B-299175, B-299175.2, Mar. 5, 2007, as a basis for support. The government argues that, having prevailed before GAO, ‘“the [g]overnment’s defense of a case arising from an administrative decision is reasonable where it is not clear that the administrative decision was erroneous.’” Def.’s Opp’n at 4-5 (quoting Trone v. United States, 3 Cl. Ct. 690, 693 (1983), and citing Engles v. United States, 2 Cl. Ct. 166 (1983), and Stolpe v. United States, 36 Fed. Cl. 259, 266 (1996)).

The government’s reliance on the set of decisions by GAO is problematic. The court specifically disavowed and refused to follow those precedents. See Geo-Seis, 77 Fed. Cl. at 645 n.28. More importantly, the government’s argument based on the GAO precedents sidesteps the basis for the court’s decision on the merits. The court looked directly to the provisions of the FAR that governed the procurement and held that “[t]he plain language of FAR § 52.215- 1(c)(3)(ii)(A) precluded the Sealift Command’s consideration of Presidential’s revised proposals.” Geo-Seis, 77 Fed. Cl. at 645.3 After examining the regulatory history of revisions made to the FAR in 1997, id. at 642-45, the court concluded that those revisions expressly rejected the position taken by the Contracting Officer in the challenged procurement, i.e., that she could issue a post-deadline amendment to the solicitation allowing a late proposal where doing so was “in the best interest of the [g]overnment.” Id. at 637 (quoting AR 342 (Mem. to file from Stangler and Kimm (Mar. 22, 2006))). Proposed revisions to the FAR in 1996 would have allowed just that sort of discretion on the part of a contracting officer, id. at 642 (citing and quoting Federal Acquisition Regulation; Part 15 Rewrite–Phase I, 61 Fed. Reg. 48,380, 48,380- 81 (Sept. 12, 1996)), but those proposed revisions were not adopted on the ground that they gave too much discretion to a contracting officer. Id. at 643 (citing and quoting Federal Acquisition Regulation; Part 15 Rewrite; Contracting by Negotiation and Competitive Range Determination, 62 Fed. Reg. 51,224 (Sept. 30, 1997)). Thus, the FAR, not GAO and not the court, established the parameters for the Contracting Officer’s action. “[T]he FAR Councils [the Civilian Agency Acquisition Council and the Defense Acquisition Regulations Council] specifically addressed th[e attendant] policy issues in the 1997 reconsideration of the FAR, and th[e] court should not undercut that resolution by a contrary decision in this case.” Id. at 646. In short, even if the line of GAO decisions had some basis prior to the 1997 revisions to the FAR, which itself is a dubious proposition, those decisions could not have retained any vitality after those revisions.

The government’s position will not be found to be reasonable or substantially justified when explicit, unambiguous regulations directly contradict that position. See Hillensbeck, 74 Fed. Cl. at 481 (government’s position conflicted with unambiguous statutory definition and regulations); Loomis, 74 Fed. Cl. at 355 (military failed to comply with its own regulations). The government argues that Hillensbeck is “readily distinguishable” from the instant case because the agency here did not “rel[y] upon an internal agency interpretation of a statute,” but, rather, “[the] M[ilitary] S[ealift] C[ommand] relied upon a line of protest decisions from the GAO . . . [which is] statutorily mandated to render such decisions.” Def.’s Opp’n at 6. The proffered distinction is not meaningful. The actions of the Sealift Command’s Contracting Officer contravened the FAR, and the GAO precedents could not excuse that deviation from legal requirements. In short, “there is no justification for the government’s position when clear, unambiguous regulations directly contradict that position.” Filtration Dev. Co. v. United States, 63 Fed. Cl. 612, 621 (2005). Accordingly, the government has not met its burden of proving that its position was substantially justified. Geo-Seis’ claim satisfies the requirements of the EAJA.

(sections deleted)

The clerk shall enter judgment for plaintiff in the total amount of $101,915.26.  (Geo-Seis Helicopters, Inc., v. U. S. and Presidential Airways, Inc., 07-155C, Reissued October 31, 2007) (pdf)


The Court of Claims recognized in Severin v. United States that if a contractor proved that “in the performance of [its] contract with the Government [it] became liable to [its] subcontractor for the damages which the latter suffered, . . . [this] might well constitute actual damages” recoverable by the contractor, even though the contractor has not yet paid the subcontractor. 99 Ct. Cl. 435, 443 (1943). In the absence of such proof, however, the Court of Claims made clear that a contractor is precluded from recovering in its claim for damages those losses suffered by its subcontractor. Id. at 443-44. Notwithstanding an opportunity to supplement its initially submitted documentary evidence to support its claim for bid proposal and preparation costs, plaintiff has declined even to submit corroborating declarations from its subcontractors regarding the respective payment obligations between plaintiff and the subcontractors. The Court of Claims recognized in Severin that, in the absence of proof of a contractor’s liability to a subcontractor, a contractor is precluded from recovering in its claim for damages those losses suffered by its subcontractor. 99 Ct. Cl. at 443-44. The court finds that plaintiff has failed to carry its burden of proof in this case and DENIES, as part of plaintiff’s claim for bid proposal and preparation costs, the recovery of those expenses incurred by plaintiff’s subcontractors in connection with the bid preparation at issue here.

In this case, plaintiff has submitted no evidence regarding its directly incurred bid preparation costs. Notwithstanding the court’s order directing plaintiff to provide specific documentary evidence in support of its claim, plaintiff has declined to expend the effort to prove its claim. Plaintiff states that “to spend significant amounts of money on Italian lawyers and accountants to verify and further substantiate it case . . . [would] not be prudent from a business standpoint considering the amount of time and energy and money already spent in pursuing this case.” Pl.’s Claim Supp. at 3. The court, however, fails to see why it would have been necessary to hire “Italian lawyers and accountants” to provide such basic evidence as tax or payroll records. In the absence of any evidence of the bid preparation costs directly incurred by plaintiff, plaintiff’s claim is wholly unsupported and legally insufficient. Accordingly,the court DENIES plaintiff’s claim for its directly incurred bid preparation and proposal costs. (Impressa Construzioni Geom. Domenico Garufi v. U. S., No. 99-400C, c/w 01-708C, June 30, 2004) (pdf)


Where, as here, a teaming agreement or subcontract “expressly negates any liability of the prime contractor to the subcontractor,” the prime may not recover those costs. Donovan Constr. Co.v. United States, 138 Ct. Cl. 97, 99 (1957), cert. denied, 355 U.S. 826 (construing United States v.Blair, 321 U.S. 730, 737 (1944)). As our appellate authority held:

Quite logically where the subcontract absolves the prime contractor from liability to his subcontractor there can be no derivative liability of the Government to the subcontractor even where the Government would otherwise be culpable, for actual damage to the prime is a prerequisite to recovery either for himself or for those subordinate to him.

Gardner Displays Co. v. United States, 346 F.2d 585, 586-87 (Ct. Cl. 1965).

Because Plaintiff’s teaming agreements with ILC Dover and CUBRC clearly indicate that Plaintiff was under no obligation to compensate its teammates for their B&P costs, Gentex may not recover those costs on their behalf in this action. Gentex’s post hoc agreement to reimburse their B&P costs if it recovers them in this action does not create an obligation or liability sufficient to imbue Gentex with the requisite actual injury necessary for standing. Absent such obligation, the Court would be allowing a plaintiff to raise another entity’s legal rights and recover the damages of nonparties in disregard of traditional threshold requirements of standing. Allen, 468 U.S. at 751.

Plaintiff has asked that a 15% markup, or “profit,” be included in its bid preparation and proposal costs. However, because profit is not a cost incurred in the bid preparation and proposal process, the Court denies recovery. (Gentex Corporation v. U. S., No. 03-728C, June 10, 2004, June 18, 2004) (pdf)


Balancing the hardships between the government and WPS on the one hand and PGBA on the other, the Court determines that adequate justification does not exist to set aside the contract and require a new round of solicitation. This procurement has already lasted nearly one and one half years, from the issuance of the RFP in September 2002 to the anticipated work commencement date of April 1, 2004, and WPS avers that it has expended significant resources preparing for implementation. Interv.-Def.’s Opp. at 63; Interv.-Def.’s Reply at 24. Revoking the contract and requiring a new solicitation would likely engender an additional delay of at least the same length. In light of these considerations, the Court determines that the balance of 30 hardships weighs in favor of denying PGBA’s request for declaratory relief. In a bid protest case, 28 U.S.C. § 1491(b)(2) provides that “[t]o afford relief in such an action, the court[] may award any relief that the court considers proper, including declaratory and injunctive relief except that any monetary relief shall be limited to bid preparation and proposal costs.” In the circumstances of this case, the Court has determined that PGBA is entitled to recover its reasonable costs incurred in preparing its proposal for the TDEFIC solicitation. “[A]losing competitor may recover the costs of preparing its unsuccessful proposal if it can establish that the Government’s consideration of the proposal submitted was arbitrary or capricious or in violation of applicable statute or regulation.” Gentex Corp., 58 Fed. Cl. at 656 (citing CSE Constr. Co. v. United States, 58 Fed. Cl. 230, 262- 3 (2003); 28 U.S.C. § 1491(b)(2)). In light of the errors discussed above and because PGBA was prejudiced by such errors, PGBA may recover its bid preparation and proposal costs. The amount of such recovery shall be determined through further proceedings in this action. (PGBA, LLC,v. U. S. (Defendant) and Wisconsin Physicians Service Insurance Corporation (Intervening-Defendant); No. 03-2773C, March 31, 2004, Reissued April 22, 2004.) (pdf)

U. S. Court of Federal Claims - Listing of Decisions

For the Government For the Protester
Insight Systems Corp. and CenterScope Technologies, Inc., Nos. 12-863C and 12-883C, May 12, 2014  (pdf) CMS Contract Mgmt. Servs. et al v. U. S., Nos. 12-852C, 12-853C, 12-862C, 12-864C, & 12-869C, September 29, 2015  (pdf)
Reema Consulting Services, Inc., v. U. S., No. 12-402C, November 26, 2012  (pdf) DGR Associates, Inc. v. U. S. and General Trades and Services, Inc., No. 10-396C, February 15, 2011  (pdf)  (Reversed by the Court of Appeals for the Federal Circuit in DGR Associates, Inc., v. U. S. and General Trades and Services, Inc., No. 2011-5880, August 2, 2012  (pdf)  (See below)
Impressa Construzioni Geom. Domenico Garufi v. U. S., No. 99-400C, c/w 01-708C, June 30, 2004 (pdf) Alabama Aircraft Industries, Inc. - Birmingham, v. U.S., No. 08-470C, Reissued February 3, 2009 (pdf)
Gentex Corporation v. U. S., No. 03-728C, June 10, 2004, June 18, 2004 (pdf) Geo-Seis Helicopters, Inc., v. U. S. and Presidential Airways, Inc., 07-155C, Reissued October 31, 2007 (pdf)
Lion Raisins, Inc, Nos. 01-322C & 01-536C, March 20, 2002 PGBA, LLC,v. U. S. (Defendant) and Wisconsin Physicians Service Insurance Corporation (Intervening-Defendant); No. 03-2773C, March 31, 2004, Reissued April 22, 2004 (pdf)
  Lion Raisins, Inc, Nos. 01-322C & 01-536C, June 10, 2002

U. S. Court of Appeals for the Federal Circuit

II. DISCUSSION

On appeal, IDEA argues that the [Court of Federal Claims] CFC erroneously decided that there is “no recovery when no bid was submitted” and that the “‘act of submitting a bid’ is always essential. Appellant’s Br. 11–12. IDEA contends that it should receive “just and proper reimbursement for its presolicitation bid preparation costs” because the Air Force refused to allow any bids for the sole-source bridge contract. Id. at 13. IDEA further insists that the number of hours it is requesting for reimbursement is very modest and there is independent evidence supporting its claims. Although it never prepared a draft proposal, IDEA insists that its pre-solicitation actions were recoverable and reasonable, including: (1) pre-drafting elements to go in the proposal, including “ABOUT CMAS” and “ABOUT IDEA” sections; (2) contacts with the contracting office; and (3) checking for the bid posting online. Joint Appendix (“J.A.”) 68–72. According to IDEA, moreover, the CFC was wrong in valuing Crain’s labor at $0/hour and that there were a number of possible acceptable rates the CFC could have adopted. Finally, IDEA asserts that the CFC wrongly rejected its claim for attorney fees under the EAJA because the Air Force clearly broke the law and the EAJA is designed to protect companies like IDEA.

The government responds that the burden is on the protestor to adequately demonstrate reasonable and recoverable costs in a bid protest case. According to the government, the CFC correctly concluded that IDEA was not entitled to bid preparation costs because it did not submit or prepare a proposal. The government contends that the CFC also correctly concluded that all of IDEA’s costs were not properly characterized as bid preparation and proposal costs. Because the CFC is not a court of equity, the government asserts that CFC correctly found that there is no basis in law for IDEA’s monetary claims. According to the government, moreover, the CFC properly concluded that all of IDEA’s costs are unsupported, not reasonable, and excessive. Finally, the government argues that, based on binding precedent, the CFC properly rejected IDEA’s EAJA claim.

We review the CFC’s decisions de novo for errors of law and for clear error for findings of fact. Ind. Mich. Power Co. v. United States, 422 F.3d 1369, 1373 (Fed. Cir. 2005).

A. Bid Preparation and Proposal Costs

By statute, if a party is successful in a bid protest case, “the [CFC] may award any relief that the court considers proper, including declaratory and injunctive relief except that any monetary relief shall be limited to bid preparation and proposal costs.” 28 U.S.C. § 1491(b)(2) (emphasis added). Although § 1492(b)(2) does not define bid preparation and proposal costs, courts often turn to the Federal Acquisition Regulation (“FAR”) provisions for guidance in interpreting the statute. See Coflexip & Servs., Inc. v. United States, 961 F.2d 951, 953 (Fed. Cir. 1992) (referring to the federal regulations to define proposal preparation costs).

The pertinent FAR provision states in relevant part: “Bid and proposal (B&P) costs means the costs incurred in preparing, submitting, and supporting bids and proposals (whether or not solicited) on potential Government or non- Government contracts.” 48 C.F.R. § 31.205-18(a) (2012).

We agree with the CFC that IDEA is not entitled to recover any costs because IDEA did not submit or prepare a bid proposal.1 The statute clearly limits monetary relief available to “bid preparation and proposal costs,” 28 U.S.C. § 1491(b)(2). It is undisputed that IDEA never submitted a proposal, whether solicited or unsolicited. The CFC further found that IDEA did not even allege that it prepared a draft proposal. We see no clear error in this finding. Although IDEA argues that it drafted materials about CMAS and IDEA that it intended to put in the proposal, a review of those materials indicates that they were clearly used in an email to the Air Force before any bid was posted. See J.A. 68–72.

IDEA’s equitable argument is unpersuasive because the plain language of the statute states that “any monetary relief shall be limited to bid preparation and proposal costs.” 28 U.S.C. § 1491(b)(2) (emphasis added). Furthermore, IDEA’s assertion that the number of hours it claims is very modest misses the point. Monetary relief, no matter how “modest,” is not available except for bid preparation and proposal costs.

Because we conclude that IDEA cannot recover any costs when it did not submit or prepare a bid proposal, we affirm the CFC’s decision to deny IDEA’s claim for costs in its entirety.

B. IDEA’s EAJA Claim

The EAJA provides that “a court may award fees and expenses of attorneys . . . to the prevailing party in any civil action brought by or against the United States or any agency or any official of the United States acting in his or her official capacity in any court having jurisdiction of such action.” 28 U.S.C. § 2412(b) (emphasis added). In Farrar v. Hobby, 506 U.S. 103 (1992), the Supreme Court defined “prevailing party”: “a plaintiff ‘prevails’ when actual relief on the merits of his claim materially alters the legal relationship between the parties by modifying the defendant’s behavior in a way that directly benefits the plaintiff.” 506 U.S. at 111–12. We have generally adopted this meaning of prevailing party in “all cases in which Congress has authorized an award of fees to a ‘prevailing party.’” Singer v. Office of Senate Sergeant at Arms, 173 F.3d 837 (Fed. Cir. 1999) (quoting Hensley v. Eckerhart, 461 U.S. 424, 433 (1983)).

In this case, the CFC correctly rejected IDEA’s claim for EAJA because IDEA was not a prevailing party entitled to recovery of attorney fees. IDEA did not receive an injunction and recovered no money damages. Therefore, IDEA did not receive any actual relief that “materially alters the legal relationship between the parties.” Farrar, 506 U.S. at 111–12.

Because IDEA is not a prevailing party, we conclude that the CFC properly denied recovery of attorney’s fees under 28 U.S.C. § 2412(b).  (Innovation Development Enterprises of America, Inc. v. U. S., No. 2014-5070, January 12, 2015)  (pdf)


The [Equal Access to Justice Act] EAJA provides that, when a timely application is filed, an eligible prevailing party shall be awarded attorneys’ fees and other expenses incurred by that party in any civil action brought by or against the United States “unless the court finds that the position of the United States was substantially justified . . . .” 28 U.S.C. § 2412(d)(1)(A).

(sections deleted)

In the underlying bid protest, the Government argued that the Small Business Act and the SBA’s implementing regulations did not require the Air Force to give priority to HUBZone small business concerns. DGR, 97 Fed. Cl. at 218. The Court of Federal Claims rejected the Government’s position because in the court’s view the Government’s interpretation of the Act “contradicted the plain meaning of the Small Business Act.” Id. at 219. In the subsequent EAJA action, the Government argued that its position in the bid protest litigation nevertheless was substantially justified because “interpretation of the statute was a novel issue . . . .” Id. The Court of Federal Claims rejected the Government’s justification argument, holding that “the unambiguous wording of the statute, and the existing case law precedent” rendered the Government’s merits-based argument in the underlying litigation “not reasonable.” Id.

We cannot agree. While the Government’s position must be “more than merely undeserving of sanctions for frivolousness,” it is sufficient for purposes of establishing substantial justification that there was a “genuine dispute” such that “reasonable people could differ as to [the appropriateness of the contested action].” Pierce, 487 U.S. at 565-66 (alteration in original) (citation omitted). At the time DGR initiated the underlying bid protest, presumptively reasonable people in all three branches of the Government had reached differing conclusions as to whether the Small Business Act permitted participating agencies to place the HUBZone and 8(a) programs on an equal footing.

Of the various Government agencies to opine on the matter, the Small Business Administration, the Department of Justice, the Office of Management and Budget, and the Department of Defense all considered the SBA’s parity regulations to be consistent with the Act. The opposite conclusion had been reached by the Government Accountability Office in four separate decisions in three separate bid protests.

Even the Federal courts were split on the matter. Although the Court of Federal Claims in Mission Critical had concluded that the SBA’s parity regulations were inconsistent with the plain meaning of the Act, the District Court for the District of Hawaii had rejected a challenge to the regulations on the grounds that the regulations “sufficiently promote the congressional objective of parity between the HUBZone and 8(a) programs.” Contract Mgmt., 291 F. Supp. 2d at 1177.

Thus, at the time DGR filed its bid protest in the Court of Federal Claims, there was a genuine dispute among all three branches of Government as to whether the Air Force was required to give priority to the HUBZone program over the 8(a) program.

That alone should be sufficient reason to conclude that the Department of Justice’s merits-based argument in the underlying litigation was, if not actually correct, at least sufficiently grounded in law to be substantially justified under the relatively low threshold standard described above. There is more. Though the Congressional resolution of this issue came after the litigation in the Court of Federal Claims, there had been an earlier indication of the Congress’ view of the matter. Following the GAO’s Mission Critical decision, the Senate proposed amending the Act to clarify that when a contract could be awarded pursuant to more than one small business program, Federal agencies have discretion as to which program to apply. See H.R. 2647, 111th Cong. § 838 (July 23, 2009) (Engrossed amendment Senate). While the amendment was under consideration in the House, the Department of Justice issued its 2009 memorandum in reaction to the GAO’s Mission Critical decision.

One and a half months later, the Senate receded, noting “that the Department of Justice has concluded that no change to the Small Business Act is required to ensure that contracting officers . . . have discretion whether or not to award contracts pursuant to the HUBZone program,” and “direct[ing] the Secretary of Defense to continue to administer the HUBZone program in a manner consistent with the Department of Justice opinion.” H.R. Rep. No. 111-288, at 789 (2009).

In view of this clear statement from Congress affirming the SBA regulations at issue, it is difficult for us to conclude that the Government was not substantially justified in believing that the Small Business Act permitted participating agencies to place the HUBZone and 8(a) programs on an equal footing. We conclude, therefore, that the Court of Federal Claims made a clear error of judgment in weighing the factors relevant to the question of whether the Government’s merits-based argument was substantially justified.  (DGR Associates, Inc., v. U. S. and General Trades and Services, Inc., No. 2011-5880, August 2, 2012)  (pdf)  (Reversed Court of Federal Claims opinion in DGR Associates, Inc. v. U. S. and General Trades and Services, Inc., No. 10-396C, February 15, 2011  (pdf))  (See above)

U. S. Court of Appeals for the Federal Circuit

For the Government For the Protester
Innovation Development Enterprises of America, Inc. v. U. S., No. 2014-5070, January 12, 2015  (pdf)  
DGR Associates, Inc., v. U. S. and General Trades and Services, Inc., No. 2011-5880, August 2, 2012  (pdf)  (Reversed Court of Federal Claims opinion in DGR Associates, Inc. v. U. S. and General Trades and Services, Inc., No. 10-396C, February 15, 2011  (pdf))  (See above)  
Legal

Protests

Bona Fide Needs Rule
Public Laws
Legislation
Courts & Boards


Rules & Tools
Workforce
Reading

Small Business
 

   
 
 

ABOUT  l CONTACT